Documente Academic
Documente Profesional
Documente Cultură
MIDAS Material
Tutorial
3-Span Continuous Prestressed Post-Tensioned Box
Girder Bridge
00
3-Span Continuous Prestressed Box Girder Bridge
In this tutorial we will learn the following things;
- How to generate PSC box section.
- How to define construction stages for the given construction sequence of the bridge.
- How to simulate boundary conditions and assign static and prestress load in midas Civil.
- How to interpret the tendon losses, forces, stresses represented by midas Civil.
-How to carry out design for PSC box girder as per IRC:112-2011.
post tensioned box girder to be constructed in three construction stages using fully supported method.
125m
40m 8m 37m 8m 32m
Longitudinal View
- The behavior of the bridge under Static loads, Prestress loads, temperature loads and Moving loads
are examined.
Step
40
45
40
Mid Section
0.44
0.44
0.71
0.26
0.71
0.26
0.268
0.268
0.94
0.2
0.94
0.45
0.2
0.45
1.032 1.4 1.032
1.032 1.4 1.032
End Section
Diaphragm Section
1.9m
Fixed Pier
0. 3m 3m 13.5m
5
Longitudinal Section Near End Span
13.5m 3m 3m 1m 3m 3m 16m
Units
Invoke midas Civil
1 Open New File
2 Select the Unit System [ kN, m]
3 Save as ‘3-Span PSC Box Girder’
2
.
Properties 2
1 Go to “Properties”
Name> Tendon
Type of Design: Steel
Steel Standard: IS(S)
DB: Fe540 5
5 Click on OK
2 Go to “Properties” 3
3 (Creep/Shrinkage)”
4 Click on “Add” to define properties
6 7
Note: To get the creep & shrinkage strains, the value of relative humidity is to be considered as 70%, Notational size of member, h as
1000mm and Age of concrete at the beginning of shrinkage as 3 days. Later, the h value would be automatically updated for
composite sections
2
1 Go to “Properties”
2 Click on “Comp. Strength”
3 Click on “Add” to define properties
6 Click on OK
5 6
8 Click on “Close”
1
Model Generation – Defining Tapered Box Girder Sections
2
1 Go to “Properties”
2 Click on “Section Properties”
3 Click on “Add..”
3
4 Click on tab “Tapered”
5 Define Pier Cap Tapering section:
Name > Pcap-Left
Section Type > Solid Rectangle
Section – i: H>2m, B>1.5m
Section – j: H>1.25m, B>1.5m
Select y Axis Variation as “Linear”
Select z Axis Variation as “Linear”
6 Click “Change Offset”
Select Offset : Center- Top 6
Click on “OK” 7
7
Click on “Apply”
Similarly Define Pier-Cap Right
Tapering :
Name > Pcap-Right
Section Type > Solid Rectangle
Section – i: H>1.25m, B>1.5m
Section – j: H>2m, B>1.5m
Select y Axis Variation as “Linear”
Select z Axis Variation as “Linear”
Click “Change Offset”
Note: To define prismatic sections in midas Civil, go to Models > Properties > Section > Value and here enter the section properties directly
Select Offset : Center- Top instead of section dimensions. To know how sectional properties are calculated go to Help > Contents > Start > Model > Properties >
Click on “OK” Section > Section Properties
& again Click on “OK”
1 Go to “Properties”
2 Click on “Section Properties”
3 Click on “Add..”
3
4 Click on tab “DB/User”
5 Define Pier:
Name > Pier‘
Section Type > Solid Rectangle
Select “User”
H > 1.5m, B > 1.5m
6
Click on “OK”
Note: To define prismatic sections in midas Civil, go to Models > Properties > Section > Value and here enter the section properties directly
instead of section dimensions. To know how sectional properties are calculated go to Help > Contents > Start > Model > Properties >
Section > Section Properties
Nodes 2
Elements 2
1 Click on “Node/Elements”
2 Click on “Extrude”
3 Go to “Tree Menu” 4
1 Click on “Node/Element”
2 Click on “Translate Node”
3 Select nodes numbers 2, 43, 89 & 130
by entering them in the nodes
selection box as shown. 4
3
Go to “Tree Menu”
4 Mode “Copy”
Translation “Equal Distance”
Dx,dy,dx: “0,-1.9,-3”
2 Click on “Node/Element” 2
3
3 Click on “Translate Node”
4 Click on Select Single button
4
5 Select nodes as shown
Go to “Tree Menu”
6 Mode “Copy”
Translation “Unequal Distance”
Axis: “Y”
Distance: “3.8”
7 7
Click “Apply”
& Click “Close”
Note: Here, translational distance of 3.8m is the transverse distance between the two bearings.
2 Click on “Node/Element” 2
3
3 Click on “Translate Node”
4 Click on Select Single button
4
5 Select encircled nodes as shown
Go to “Tree Menu”
6 Mode “Copy”
Translation “Unequal Distance”
Axis: “Z”
Distance: “-0.1”
7
Click “Apply” 5 7
2 Click on “Node/Element”
3 Click on “Translate Nodes” button
4 Click on Select Single button
5
5 Select encircled nodes as shown
6 Click on “Activate” button to
separately view the selected nodes.
7 Click on the Side View button to 9
switch to side-view
8 Select encircled node as shown
Go to “Tree Menu”
7
9 Mode “Copy”
Translation “Unequal Distance” 8
Axis: “Y”
Distance: “-0.6”
10 Click “Apply”
12
& Click “Close”
11
Click on “Activate ALL” button. 10
12 Click on the arrow as shown to the Note: Here, Bearing centerline to pier-cap end projection is considered as 0.6m
view isometric view
Pier-Cap Node 2
9
Click on “Apply” 6
Click on “Close”
2 Click on “Node/Element”
3 Click on “Delete Elements” button
4 Click on Select Single button
5 Select encircled nodes/elements as 5
shown
6 Click on “Activate” button to
separately view the selected items.
7 Click on the Side View button to
7
switch to side-view
8 Select the elements as shown
Go to “Tree Menu”
9 Uncheck the option “with Free Nodes”
8
10 Click “Apply”
& Click “Close”
11 Click on “Activate ALL” button.
9
10
9 Click on “Apply”
Click on “Close”
shown
6 Go to “Tree Menu”
7 Mode “Copy”
7
Translation “Unequal Distance” 5
Axis: “X”
Distance: “45”
8 Check the options “Intersect Node,
Intersect Element, Copy Node
Attributes & Copy Element
Attributes”
9 Click “Apply”
& Click “Close”
8
Go to “Tree Menu”
2 Click on “Works”
3 Select the elements as highlighted.
On selection the selected element
4
number list will be updated
as “11 12 52 53 98 99 139
140” 3 3
Go to “Tree Menu”
2 Click on “Works”
3 Select the elements as highlighted.
On selection the selected element 4
3
3
Go to “Tree Menu”
2 Click on “Works”
3 Select the elements as highlighted.
On selection the selected element
4
number list will be updated
as “46to48 92to94 133to135”
4 Drag and Drop Mid-Sup over the 3
model window
Go to “Tree Menu”
2 Click on “Works”
3 Select the elements as highlighted.
On selection the selected element
number list will be updated 4
Go to “Tree Menu”
2 Click on “Works”
3 Select the elements as highlighted.
On selection the selected element
number list will be updated 4
as “7to10”
4 Drag and Drop Pcap-Left over the
3
model window
3 Click on “Properties”
4 Click on “Tapered Group”
Go to “Tree Menu”
5 6
Generating Tapered Groups:
Set z-Axis as Linear
Set y-Axis as Linear
shown
5
Go to Tree menu
5 Element Type: “Frame”
Select Equal Distance
Number of Divisions x: 2
6 Click “Apply”
Click “Close”
Note: Here, the elements are being divided to create the construction joint nodes
6 which are located at 8m to the right of centerlines of intermediate piers/supports.
1 Click on “Properties”
2 Click on “Change Property” button
3 Select all Superstructure elements
Go to Tree menu
4 Click “Apply”
Click “Close”
3
4
Note: Here, the elements are being divided to create the construction joint nodes
which are located at 8m to the right of centerlines of intermediate piers/supports.
1 3
Defining Group
Note: 1) Structure groups are especially dedicated to Construction Stage analysis (of a sequential bridge construction) where each part of
the total structure erected in each stage needs to be identified as a different structure from those of other stages.
2) Boundary groups are especially dedicated to Construction Stage analysis (of a sequential bridge construction) where each part of
the total structure erected in each stage may retain different boundary conditions from those of other stages.
3) Load groups are especially dedicated to Construction Stage analysis (of a sequential bridge construction) where each part of the
total structure erected in each stage may be subjected to different loadings.
A1 P1
Construction Joint
A1 P1 P2
front view.
1
2
Go to “Tree Menu”
2 1
3
5
Click “ Close”
3
5
Rigid Links 1 3
5 3
Rigid Links 1 3
5 3
Note: The elastic links stiffness in different directions are provided to simulate the layout of
bearings as given on Page8
3-Span Continuous Prestressed Box Girder Bridge 47
Step
4
1 Click on the arrow as shown to switch
to the isometric view
2 Click “Boundary”
3 Click “Elastic Link…”
Go to “Tree Menu”
4 Go to “Boundary” tab
Select Boundary Group Name “Sub”
Enter “SDx”> 1e+8 kN/m
“SDy”> 1e+8 kN/m
“SDz”> 100 kN/m
Check “Copy Elastic Link”
1
Select Axis “X”
Enter Distances: “84.75,39.75”
Click in input box “2 Nodes:”
Click Highlighted Node “1”
and then Click Highlighted
5 Node “2”
Click “ Close” 5 2
Note: The elastic links stiffness in different directions are provided to simulate the layout of
bearings as given on Page 8
3-Span Continuous Prestressed Box Girder Bridge 48
Step
5 Click “ Close”
Note: The elastic links stiffness in different directions are provided to simulate the layout of
bearings as given on Page 8
3-Span Continuous Prestressed Box Girder Bridge 49
Step
Fixed Supports 1 3
5 Click “Apply”
Click “Close”
Note: The elastic links stiffness in different directions are provided to simulate the layout of
bearings as given on Page 8
3-Span Continuous Prestressed Box Girder Bridge 50
Step
Load Cases 2
1 Go to “Load” tab
2 Click “Static Load Cases”
3 Define Static Load Cases
Name : “Self Weight”
Type : “Construction Stage Load(CS)”
Click “Add”
3
Name : “SIDL-WC”
Type : “Construction Stage Load(CS)”
Click “Add”
Name : “SDL-CB”
Type : “Construction Stage Load(CS)”
Click “Add”
Name : “Prestress”
Type : “Construction Stage Load(CS)”
Click “Add”
2
Static Loads – Self Weight
Assigning Self Weight
1 Go to “Load” tab
2 Click “Self Weight…”
3 Go to “Tree Menu”
Go to “Load” 3
4 Click “Add”
Click “Close”
3 Go to “Tree Menu”
Go to “Load”
Select Load Case Name “SIDL-WC”
Select Load Group Name “SIDL”
Select Load Type “Uniform Loads”
X
Select Load Direction “Global Z”
Enter w “-16.5” KN/m
In “Model View” window select all
Superstructure elements x
4
Click “Apply”
Click “Close”
Change “Eccentricity”
Enter Distance I-End “4.25”m
3 Click “Temp/Prestress”
4 Click “Tendon Property”
6
5 Click “Add”
6 Enter Tendon Name “Tendon” 5
Select Tendon Type “Internal(Post-
Tension”
Select Material “Tendon”
Click “…” in the dialog box for Total
Tendon Area
Select Strand Diameter “15.2mm(0.6”)”
Enter Number of Strands “19”
7
Click “OK”
Enter Duct Diameter “110”mm
Select Relaxation Coefficient “India
(IRC:112-2011) – Low”
Enter Ultimate Strength “1860”
Enter Yield Strength “1581”
Enter Curvature Friction Factor “0.17”
Enter Wobble Friction Factor as
“2e-6”/mm
Enter Anchorage Slip Begin : “6”
Enter Anchorage Slip End : “6”
Select Bond Type “Bonded”
Click “OK”
7 Click “Close”
1 Go to “Load” tab
2 Click “Temp/Prestress” 4
7
Rotation as “11.31” instead of “-11.31”
Click “Close” Note: An insertion point is used as a point of reference for the tendon profile in the Global
*Select respective cable coordinates and Coordinate System (GCS). Only one profile is needed for a precast beam in spite of the
paste it in input table. number of elements (four in this example) that we are using to model it.
1 Go to “Load” tab
2 Click “Temp/Prestress” 4
1 Go to “Load” tab
2 Click “Temp/Prestress” 4
1 Go to “Load” tab
2 Click “Temp/Prestress” 4
1 Go to “Load” tab
2 Click “Temp/Prestress” 4
1 Go to “Load” tab
2 Click “Temp/Prestress” 3
4 Click “Add”
5 Click “Close”
4
Go to “Tree Menu”
1 Go to “Works” pane 2
1 Go to “Load” tab
2 Click “Temp/Prestress”
3 Click “Element Temp.”
4 Select all superstructure elements. 4
5 Go to “Tree menu”
6 Click “Close”
1 Go to “Load” tab
2 Click “Temp/Prestress”
4
3 Click “Beam Section Temp.”
4 Select all superstructure elements.
5 Go to “Tree menu”
Select Load Case name as “Positive
Temp. Grad.”
Change Section Type to PSC/Composite
Select “Element” option for Material
Keep Ref. as “Top” Positive Temperature Reverse Temperature
For B check “Section” Option Differences Differences
Enter H1 as 0 mm
Enter H2 as 150 mm
Enter T1 as 17.8 [C]
h1 h1
Enter T2 as 4 [C]
Click on Add
Change Parameters:
Enter H1 as 150 mm
Enter H2 as 400 mm h2 h2
Enter T1 as 4 [C]
Enter T2 as 0 [C]
Click on Add
Change Parameters:
h3
Enter H1 as 2850 mm
h3
Enter H2 as 3000 mm h4
Enter T1 as 0 [C]
Enter T2 as 2.1 [C] For the given depth of box girder
Click on Add
h1 = 0.15m h1 = h4 = 0.25m 6
6 Click “Apply” h2 = 0.25m h2 = h3 = 0.25m
h3 = 0.15m
Click “Close”
If temperature units are in degree Fahrenheit, one can change to degree Celsius from Tools Unit System
1 Go to “Load” tab
2 Click “Temp/Prestress”
3 Click “Beam Section Temp.”
4 Select all superstructure elements. 4
5 Go to “Tree menu”
Select Load Case name as “Negative
Temp. Grad.”
Change Section Type to PSC/Composite
Select “Element” option for Material
Keep Ref. as “Top”
For B check “Section” Option
Enter H1 as 0 mm
Enter H2 as 250 mm
Enter T1 as -10.3 [C]
Enter T2 as -0.7 [C]
Click on Add
Change Parameters:
Enter H1 as 250 mm Change Parameters:
Enter H2 as 500 mm Enter H1 as 2750 mm
Enter T1 as -0.7 [C] Enter H2 as 3000 mm
Enter T2 as 0 [C] Enter T1 as -0.8 [C]
Click on Add Enter T2 as -6.6 [C]
Change Parameters:
Enter H1 as 2500 mm 6
Enter H2 as 2750 mm Click “Apply”
Enter T1 as 0 [C] Click “Close”
Enter T2 as -0.8 [C]
Click on Add
6
Note: An insertion point is used as a point of reference for the tendon profile in the Global Coordinate System (GCS).
Only one profile is needed for a precast beam in spite of the number of elements (four in this example) that we are
using to model it.
2 Go to “Load” tab 3 6
3
1 Go to “Load” of Main Menu
2
2 Click “Moving Load”
3 Click “Vehicles”
4
Click “Add Standard”
4
5
Select Standard Name “IRC:6-2000 5
Standard Load”
6 Select Vehicular Load Type “Class A” 6
7 Click “Apply” 9
8 Click “OK”
9 Click “Close”
8 7
Load Combination 3
1 Go to “Load” tab 2
Click on “->”
Click “OK”
7
9 Click “OK”
9
Note: To take into account of the wheel spacing and minimum clearance for different vehicles, the Auto Live Load Combination
option can be unchecked and manually different moving load combinations can be created for the vehicles as per IRC 6:2000.
Load Combination 3
1 Go to “Load” tab 2
Click on “->”
Click “OK”
7
9 Click “OK”
9
Note: To take into account of the wheel spacing and minimum clearance for different vehicles, the Auto Live Load Combination
option can be unchecked and manually different moving load combinations can be created for the vehicles as per IRC 6:2000.
Each construction stage is identified with First Span is stressed & Launched with structure group age of 21
CS 1 7
activated (or deactivated) element, days.
boundary and load groups. Each stage
retains a unique element group, a
boundary group and a load group, forming Second Span with structure group age of 21 days is stitched to the
an interim independent structure. The CS 2 7
constructed stage1 structure and stressed.
stage information that was difficult to
define in Wizard can now be added or
modified using this function. Last span with structure group age of 21 days is stitched to the
CS 3 7
constructed stage2 structure and stressed.
Note:
The results of all prior construction stages are
accumulated and applied to the current stage. Once
activated elements, boundary conditions and loads
CS4 10000 Casting of Crash Barrier and Wearing Course.
remain active until they are deactivated. When an
element is removed, the internal forces are internally
imposed to the contiguous remaining elements in
the opposite directions.
Analysis Data
3
1 Go to “Load” of Main Menu 2
Note: Age reflects the effects of creep and shrinkage on the elements. The Age
represents the time elapsed from the time of concrete casting prior to the start of
the current construction stage being defined. That is, the Age is the maturity of the 10
element groups at the start of the current stage being defined. The Age typically
represents the time span from the time of concrete casting to the time of removal
of formwork for horizontal members such as slabs.
3 Select “Deformed”
4 Click “Add”
3
5 Click “OK” 2
16 Click “OK”
3-Span Continuous Prestressed Box Girder Bridge 75
Step
8 Click “Add”
6
6 Select “PS2-3” under Group List
7 Select Active Day as “0.06”
8 Click “Add”
16 Click “OK”
3-Span Continuous Prestressed Box Girder Bridge 77
Step
8 Click “Add”
16 Click “OK”
3-Span Continuous Prestressed Box Girder Bridge 79
Step
on Page71
2 Enter Name “CS4”
5
Select Active Day “First”
6 Click “Add”
7 Click “OK”
1 Go to “Analysis” tab
2 Click “Moving Load”
3 Enter Number/Line Elements: 3
4 Select Analysis Results Frame 3
1
Go to “Analysis” tab
2 Click “Construction Stage”
3 Click “Add”
4 Enter Load Case Name as “SIDL-WC”
Select Load Type for C.S as “Dead
Load of Wearing Surfaces and
Utilities”
From List of Load Case, Select “SIDL
WC” and Click “->”
Click “OK”
3
5
Repeat Steps 3 & 4 with Load for load 4
case SIDl-CB, Select Load Type for C.S
as “Dead Load of Components and
Attachments”
6
5 Change Beam Section Property
Changes to “Constant”
Check “Save Output of Current Stage”
6 Click “OK”
6
5
Note:
In case the diameter of rebars is not in terms
of P(dia), then change the rebar material code
from Tools Preferences Design
7
Concrete Rebar Material Code Select
IS(RC) & Click OK
6
1
Run Analysis 2
1 Go to “Analysis” tab
2 Click “Perform Analysis”
Load Combinations
Load Combination
Service LL Service Temp
Temp Temp Grad Temp Overall MVL ULS
Leading Leading
Temperature Rise(ST) 1 - - - - - -
Temperature fall(ST) 1 - - - - - -
Positive temp Grad(ST) - 1 - - - - -
Negative temp Grad(ST) - 1 - - - - -
Temp(CBC) - - 1 - - -
Load Cases & Factor
Temp Grad(CBC) - - 1 - - -
70R(MV) - - - 1 - - -
Cl.A(MV) - - - 1 - - -
Dead Load(CS) - - - - 1 1 1.35
SIDL-WC(CS) - - - - 1 1 1.75
SIDL-CB(CS) - - - - 1 1 1.35
Erection Load 3(CS) - - - - 1 1 1
Tendon Primary(CS) - - - - 0.9 0.9 1
Tendon Secondary(CS) - - - - 0.9 0.9 1
Creep Secondary(CS) - - - - 1 1 1
Shrinkage Secondary(CS) - - - - 1 1 1
MVL(CBC) - - - - 1 0.75 1.5
Temp Overall(CBC) - - - - 0.6 1 -
Combinations
1 Click on “Results” Tab
2 Click on “Stresses” “Beam Stresses
Diagram”
Go to Tree Menu 3
1
Defining Design Parameters
2
1 Go to “PSC” tab
2 Select “IRC 112-2011”
3 Click “Parameters”
4 Select Prestressing Strand type:
Strands
5 Click “Select All”
4
6 Click “OK”
1 Go to “PSC” tab
2 Select “PSC Design Material”
3 Click on Material Name “M50”
4 Under Concrete Material Selection
3
Select Code: IS(RC)
Select Grade: M50
4
5 Under Rebar Selection
Select Code: IS(RC)
Select Grade of Main Rebar: Fe500
5
1 Go to “PSC” tab 3
2
1 Go to “PSC” tab
2 Select “Serviceability Load
Combination Type”
3 Select Serviceability load
3 X
combinations “Service LL
Leading” & “Service Temp
Leading”
4 Select -> button to move the selected
combinations under
Characteristic combinations.
4
5 Click “OK”
6
Click “Perform Design”
7 Click “Excel Report” to get the design 5