Rate Analysis
Rate analysis
• How do I estimate the cost of a given
unit of work?
– Determine the cost of materials
– Determine Labour costs
– Determine costs of equipment
– Determine overhead charges
• “Schedules of rates” such as DSR
provide a useful set of guidelines
Rate Analysis for Concrete
• What is the cost of 10 cu.m of RCC
1:2:4, given that cement costs Rs. 240
per bag, sand costs Rs. 120 per cu.m
and aggregate costs Rs. 165 per cu.m?
Some basic facts
• Sand
• Cost of sand at quarry = Rs. 120 per cu.m
• Transportation charges for 5 cu.m truck = 35x20 = Rs. 700
• Transportation charges pre cu.m = 700/5 = Rs. 140
• Handling charges – Rs.5 per cu.m
• Cost of Sand at Project Site = Rs. 265 per cu.m
• Cost of 20 mm Aggregate
• Cost of sand at quarry = Rs. 140 per cu.m
• Transportation charges for 5 cu.m truck = 40x20 = Rs. 800
• Transportation charges pre cu.m = 800/5 = Rs. 160
• Handling charges – Rs.7 per cu.m
• Cost of Sand at Project Site = Rs. 307 per cu.m
Data for 10 cu.m of RCC 1:1.5:3