Documente Academic
Documente Profesional
Documente Cultură
J. KRISTIL A. ABARRI
Complainant,
Respondents.
x-------------------------x
POSITION PAPER
THE PARTIES
1. The complainant J. KRISTIL A. ABARRI, is of legal age, Filipino, and married with
residence at 1110 Ubos Pundok Basak Pardo, Cebu City. She may be served
summons and other processes through the address of undersigned office at Unit
9, Albulario Bldg. 2, General Maxilo Ave., Cebu City;
STATEMENT OF FACTS
3. The complainant filed this case against herein respondents for a claim for full
refund of equity and damages as provided for in Sec. 23 of P.D. 957.
1|Page
4. The respondent is engaged in the business of selling real property development
such as but not limited to house and lot inside a residential subdivision;
6. Under the Contract to Sell, respondent obligated itself to deliver a brand new 2-
storey house, model name APRIL, in favor of Complainant to be constructed in a
certain parcel of land known as Lot No. 3, block No. 4, with lot area of Sixty (60)
Square Meters1;
7. The total consideration or purchase price od the subject house and lot as stated
on the contract is Two Million Four Hundred Eighty Thousand Pesos (Php
2,480,000.00) while the equity payment period availed by complainant was 30
months;
9. Such amount accounts for the 36-month worth of equity payments as seen in a
Statement of Accounts covering equity payments which corresponds to the equity
amount necessary for the commencement of the house construction per
provision found in par. 4 f the Contract to Sell, to wit:
10. Sometime on May 2018, the complainant personally visited the construction site
and discovered that the house had not yet even started 3;
11. On May 21, 2018, the complainant, through undersigned, sent a demant letter to
respondent seeking full refund of the Php 509,000.00 she paid for the equity 4;
1
Annex A
2
Annex B
3
Annex C
4
Annex D
2|Page
12. Complainant sought the intervention of the HLURB to mediate for any possible
settlement. However, Respondent refused to heed the demand for refund 5;
13. Respondent answered the demand letter stated that the complainant is not
entitled for refund because the counting of the date to start construction has not
yet arrived. According to respondent, commencement of the construction should
be counted from the time the full payment is made. Further, the commencement
is not only dependent to the full payment of the complainant but as well as
whether the adjacent units in the row or cluster of units are already qualified for
construction6;
14. The complainant allowed respondent additional time to comply with its
construction obligation based on how Monares interpreted the Contract to Sell;
15. On May 2019, the complainant visited the construction site and to her dismay, the
situation remains the same7;
16. For failure of respondent to file their answer within the reglementary period
despite proper service of summons, this Honorable Office ordered complainant to
submit her verified position paper and draft decision.
ISSUES
18. Whether or not respondent’s continued failure to begin construction entitled the
complainant to full refund as provided for in Sec. 23 of P.D. 957;
19.
DISCUSSION
20.
PRAYER
1) Fully REFUND the complainant the amount of Php 509,500.00 with damages;
2) Pay for attorney’s fees in amount of Php 30,000.00 and cost of suit;
5
Annex D
6
Annex E
7
Annex F
3|Page
Other reliefs just and quitable under the premises are likewide prayed for.
Resectfully submitted this __________ at Cebu City, Philippines.
4|Page