5/12/20119

BBGM Gua Musang.

Phase – 1. (End of December 2019)

- Shop lot. (Ground floor)


- Hotel. (1st, 2nd and 3rd)

Phase – 2. (End of January)

- Apartments. (4th floor)


- Apartments. (5th floor)
- Rooftop. (6th floor)

Phase – 3. (__________)

- Hypermarket.

Note- Phase – 1.

1) EXTERNAL.
1.1) Building.
- Plastering. (Defects)
- Painting. (Defects)
- Windows. (Defects) (Testing) if any?
1.2) Infra.
- Parameter Drainage cover. (Outstanding)
- Road curves. (If any) to check drawings.
- Drainage. (If any) to check drawings.
- Road works. (Outstanding)
- Street lighting. (If any). To check drawings.
- Feeder Piller. (If any)

2) INTERNAL. (Ground floor)


2.1) Architectural.
- Wall plastering. (Outstanding and Defect) if any?
- Wall painting. (Outstanding and Defect) if any?
- Floor Screeding. ( Outstanding and Defect) if any?
- Floor tiling. (Outstanding and Defect) if any?
- Windows. (Outstanding, Defect and testing) if any?
- Ceiling. (Outstanding and Defects) is any?
- Painting. (Outstanding and Defect) if any?
- Door finishes. (Outstanding and Defect) if any?
- Ironmongery. (Outstanding, Defect and keys)big any?
- Toilet fittings. (Outstanding, Defect and testing) if any)
- Cleaning. (Defects).
2.2) M&E
- Electrical. (Outstanding, testing and defect) if any?
- Fire Fighting. (Outstanding, testing and Defect) if any?
- CCTV. (Outstanding, testing and defect) if any?
- Air-conditioning system. (Outstanding, testing and defect) if any?

3) INTERNAL. (1st floor)


3.1) Architectural.
- Wall plastering. (Outstanding and Defect)
- Wall painting. (Outstanding, Defect, and Testing)
- Floor screeding. (Outstanding, Defect and Testing)
- Floor tiling. (Outstanding, Defect, and Testing)
- Windows. (Outstanding, Defect and Testing)
- Ceiling. (Outstanding, Defects and Testing)
- Painting. (Outstanding and Defect)
- Door finishes. (Outstanding and Defect)
- Ironmongery. (Outstanding, defects and keys)
- Toilet fittings. (Outstanding, defects and testing)
- Cleaning. (Defects).

3.2) M&E.
- Electrical. (Outstanding, Defects and testing).
- Fire Fighting. (Outstanding, Defects and testing)
- CCTV. (Outstanding, defect and testing).
- Air-conditioning. (Outstanding, defects and testing).

4) INTERNAL. (2ND Floor)

4.1) Architecture.

- Wall plastering. (Outstanding and Defects)


- Wall painting. (Outstanding and Defects).
- Floor screeding. (Outstanding and Defects).
- Floor tiling. (Outstanding and Defects).
- Windows. (Outstanding, Defects).
- Ceiling. (Outstanding and Defects and testing).
- Painting. (Outstanding and Defects).
- Door finishes. (Outstanding and Defects).
- Ironmongery. (Outstanding, Defects and keys).
- Toilet fittings. (Outstanding, Defects and testing).
- Cleaning. (Defects).
-
4.2) M&E.

- Electrical. (Outstanding, defects and testing)


- Fire Fighting. (Outstanding, defects and testing)
- CCTV. (Outstanding, defects and testing).
- Air-conditioning. (Outstanding, defects and testing).
-

5) INTERNAL. (3rd floor).

5.1) Architecture.

- Wall plastering. (Outstanding and Defects).


- Wall painting. (Outstanding and Defects).
- Floor screeding. (Outstanding and Defects).
- Floor tiling. (Outstanding and ).
- Windows. (Outstanding and Defects and testing)
- Ceiling. (Outstanding and Defects).
- Painting. (Outstanding and Defects).
- Door. (Outstanding and defects).
- Ironmongery. (Outstanding, defects and keys).
- Toilet fittings. (Outstanding, defects and testing).
- Cleaning. (Defects)

5.2) M&E.

- Electrical. (Outstanding, defects and testing).


- Fire Fighting. (Outstanding, defects and testing).
- CCTV. (Outstanding, defects and testing).
- Air-conditioning. (Outstanding, defects and testing).

Note: PHASE- 2. (APPOINTMENT AND ROOF TOP)

1) 5TH Floor. (Apartments)


1.1) Internal. (Architecture)
- Wall plastering. (Outstanding and defects)
- Wall plastering. (Outstanding and defects).
- Floor screeding. (Outstanding and defects).
- Floor tiling. (Outstanding and defects).
- Windows. (Outstanding and defects)
- Ceiling. (Outstanding and defects)
- Painting. (Outstanding and defects).
- Door. (Outstanding and defects).
- Ironmongery. (Outstanding, defects and keys)
- Toilet fittings. (Outstanding, defects and testing)
- Cleaning. (Defects)
1.2) M&E.

- Electrical. (Outstanding, defects, fittings and testing)


- Fire Fighting. (Outstanding, defects, fittings and testing).
- CCTV. (Outstanding, defects, fittings and testing).
- Air-conditioning. (Outstanding, defects, fittings and testing).

2) 6th floor. (Apartments).

2.1) Internal. (Architecture).

- Wall plastering. (Outstanding and defects).


- Wall painting. (Outstanding and defects).
- Floor screeding. (Outstanding and defects).
- Floor tiling. (Outstanding and defects).
- Windows. (Outstanding and defects).
- Ceiling. (Outstanding and defects).
- Painting. (Outstanding and defects).
- Doors. (Outstanding and defects).
- Ironmongery. (Outstanding, defects and keys).
- Toilet fittings. (Outstandin defects and testing)
- Cleaning. (Defects).

2.2) M&E.

- Electrical.
- Fire Fighting.
- CCTV.
- Air-conditioning.
- 3) Roof Top.

3.1) Architecture.

- Wall plastering.
- Wall Painting.
- Floor screeding.
- Floor tiling.
- Windows.
- Ceiling.
- Painting.
- Door.
- Ironmongery.
- Toilet fittings.
- Cleaning.
3.2) M&E.

- Electrical.
- Fire Fighting.
- CCTV.
- Air-conditioning.