ID Task Task Name Duration Start Finish September 2017

Mode 19 21 23 25 27 29 31 02 04 06 08 10 12 14
1 Material Mobilization 2 days? Wed 30/08/17 Fri 01/09/17
2 Cable Conductor 2 days? Wed 30/08/17 Fri 01/09/17
3 1/C-300MM2, NYY, 0.6/1KV 0 days Fri 01/09/17 Fri 01/09/17 01/09
4 1/C-120MM2, NYA, 0.6KV 0 days Fri 01/09/17 Fri 01/09/17 01/09
5 1/C-70MM2, NYA, 0.6KV 0 days Wed 30/08/17Wed 30/08/17 30/08
6 5/C-25MM2, NYY, 0.6/1KV 0 days Wed 30/08/17Wed 30/08/17 30/08
7 NFA2x-T – 3x35 + 1x25 + 16, 0.6/1KV 0 days Fri 01/09/17 Fri 01/09/17 01/09
8 Cable Ladder & Accesoires 0 days Wed 30/08/17 Wed 30/08/17 30/08
9 Aerial Cable Hardware 0 days Fri 01/09/17 Fri 01/09/17 01/09
10 Grounding & Termination 0 days Fri 01/09/17 Fri 01/09/17 01/09
11 Part - 1 (Welding shed Eastern & Western) 16 days Tue 22/08/17Tue 12/09/17
12 Welding shed West & East repair 1 day Tue 22/08/17Tue 22/08/17
13 Install disconnecting switch panel seawall 1 day Wed 30/08/17Wed 30/08/17
14 Install Cable Ladder to Welding shed West & East 2 days Wed 30/08/17Thu 31/08/17
15 Install Cable Ladder 62-SB-803 to 62-LP-811 1 day Fri 01/09/17 Fri 01/09/17
16 Install Cable Ladder 62-SB-803 to GE182;GE183 1 day Fri 01/09/17 Fri 01/09/17
17 Install Cable 62-SB-803 to 62-LP-811 1 day Mon 04/09/17Mon 04/09/17
18 Install Cable 62-SB-803 to 62-LP-812 1 day Mon 04/09/17Mon 04/09/17
19 Install Cable 62-PB-811 to 62-WR-001 1 day Tue 05/09/17Tue 05/09/17
20 Install Cable 62-PB-812 to 62-WR-002 1 day Tue 05/09/17Tue 05/09/17
21 Install Cable 62-SB-803 to 62-WR-003 1 day Wed 06/09/17Wed 06/09/17
22 Install Cable 62-SB-803 to 62-WR-004 1 day Wed 06/09/17Wed 06/09/17
23 Main Genset mobilization & energization 1 day Fri 08/09/17 Fri 08/09/17
24 Welding Machine mobilization & energization (test) 2 days Mon 11/09/17Tue 12/09/17
25 Part - 2 (Offices Tailing Project) 4 days Tue 22/08/17Fri 25/08/17
26 Install Cable GE180 to 62-LP-813 1 day Tue 22/08/17Tue 22/08/17
27 Office repair 2 days Tue 22/08/17Wed 23/08/17
28 Office Genset mobilization & energization 1 day Fri 25/08/17 Fri 25/08/17
29 Part - 3 (Toilets) 3 days Tue 22/08/17Thu 24/08/17
30 Old Toilet repair 2 days Tue 22/08/17Wed 23/08/17
31 New Toilet Install 2 days Wed 23/08/17Thu 24/08/17
32 Part - 4 (Waiting Room - Shelter) 1 day Fri 25/08/17 Fri 25/08/17
33 Install Lamp & Cables 1 day Fri 25/08/17 Fri 25/08/17
34 Part - 5 (Lighting) 4 days Wed 30/08/17 Mon 04/09/17
35 Install panel 62-LP-813;814;815;816;817;818 1 day Fri 01/09/17 Fri 01/09/17
36 Install Undergorund Cable 62-PB-814 to 62-LP-816 1 day Wed 30/08/17Wed 30/08/17
37 Install Undergorund Cable 62-PB-814 to 62-LP-813 1 day Thu 31/08/17Thu 31/08/17
38 Install Aerial Cable 62-LP-813 to 62-LP-814 1 day Fri 01/09/17 Fri 01/09/17
39 Install Aerial Cable 62-LP-814 to 62-LP-815 1 day Fri 01/09/17 Fri 01/09/17
40 Install Aerial Cable 62-LP-815 to 62-PB-815 1 day Fri 01/09/17 Fri 01/09/17
41 Install Aerial Cable 62-LP-816 to 62-LP-817 1 day Mon 04/09/17Mon 04/09/17
42 Install Aerial Cable 62-LP-817 to 62-LP-818 1 day Mon 04/09/17Mon 04/09/17
Task Project Summary Manual Task Start-only Deadline

Project: Project Schedule Tailing Split Inactive Task Duration-only Finish-only Progress
Date: Thu 24/08/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone