Sunteți pe pagina 1din 1

PROJECT : STARGOLD SHOP-HOUSE POIPET (4.

2X16)
SCOP WORKS: PILECAP
STARTING DATE: 11/22/2019
TODAY: 12/7/2019

DAILY SITE PROGRESS REPORTS


No Items Unit Quantity Done (%) Marks
STAGE 01 FOR PILECAPE
PIPECAP
01 PC-01 pcs 5
Exvation 5.00 100%
Prepaired for Level 5.00 100%
Cut pilehead 5.00 100%
Leand Concrete 5.00 100%
Cute and tire Rebar 5.00 100%
Installation Rebar 5.00 100%
Formwork fabricate 5.00 100%
Installation Formworks 5.00 100%
Casting Concrete 5.00 100%
02 PC-01a pcs 2
Exvation 2.00 100%
Prepaired for Level 2.00 100%
Cut pilehead 2.00 100%
Leand Concrete 2.00 100%
Cute and tire Rebar 2.00 100%
Installation Rebar 2.00 100%
Formwork fabricate 2.00 100%
Installation Formworks 2.00 100%
Casting Concrete 2.00 100%
03 PC-02 pcs 28
Exvation 28.00 100%
Prepaired for Level 28.00 100%
Cut pilehead 28.00 100%
Leand Concrete 28.00 100%
Cute and tire Rebar 28.00 100%
Installation Rebar 28.00 100%
Formwork fabricate 28.00 100%
Installation Formworks 28.00 100%
Casting Concrete 28.00 100%

STAGE 02 FOR PILECAPE


PIPECAP
04 PC-01 pcs 6
Exvation 6.00 100%
Prepaired for Level 6.00 100%
Cut pilehead 6.00 100%
Leand Concrete 4.00 67%
Cute and tire Rebar 0%
Installation Rebar 3.00 50%
Formwork fabricate 3.00 50%
Installation Formworks 3.00 50%
Casting Concrete 3.00 50%
05 PC-02 pcs 24
Exvation 24.00 100%
Prepaired for Level 12.00 50%
Cut pilehead 12.00 50%
Leand Concrete 12.00 50%
Cute and tire Rebar 7.00 29%
Installation Rebar 12.00 50%
Formwork fabricate 12.00 50%
Installation Formworks 12.00 50%
Casting Concrete 12.00 50%

06 Fencing and worker house house 19


Steel Frame 16.00 67%
Zn Wall - 0%