Documente Academic
Documente Profesional
Documente Cultură
1/22/05
12 API 510/4 ASME VIII/2 ASME V/1 ASME IX/1 API 578
Question 1: A vessel made of P-3 material was found to have a crack and the
excavation depth after removal was measured to be 0.875 inch deep.
Which of the following can be used to avoid postweld heat treatment?
Preheat at 275 F or higher temperature and maintain interpass
a. temperature 450 F.
use controlled-deposition welding method with a shielded metal arc
b. welding process with a weld procedure specification developed and
qualified for the application.
Use controlled-deposition, temper-bead or half-bead technique with a
c. SMAW or GTAW process and weld procedure specification developed
and qualified for the application.
Preheat a 275 F or higher temperature and maintain interpass
d. temperature between 300 F and 600 F after procedure approval by the
authorized vessel inspector.
ASME VIII UG99
2: A retired vessel is replaced by one that is constructed from SA-516 Gr. 70
material to the 2001 Edition of ASME, Section VIII, Division 1. The design
conditions are 200 psig at 300 F. The operating pressure is 170 psig, and
the minimum design metal temperature is 20 F. The appropriate post-
fabrication hydrostatic test pressure is:
a. 255 psig.
b. 220 psig.
c. 260 psig.
d. 300 psig.
Section API 510 Section 6.2
3: When risk-based inspections (RBI), the assessment of the likelihood of a
pressure vessel failure; the likelihood assessment must be based on all
forms of degradation that could reasonably be expected to affect a vessel in
any particular service. The likelihood of failure assessment should be:
a. an essential variable.
a nonessential variable provided the nominal electrode is not changed by
b. more than one size.
d. a nonessential variable.
API 578
a. 88 psig
b. 177 psig
c. 155 psig
d. 208 psig
ASME Section V Article 2 T 282.2B
11: If the density of the radiograph anywhere through the area of interest
varies by more than minus 15% or plus 30% from the density through the
body of the hole IQI within the minimum/maximum allowable density
ranges specified in Section V, then an additional IQI shall be used for each
exceptional area and the radiograph retaken. However, when shims are
used with hole type IQIs:
API 510 5
API 510 6.3
16: Corrosion under insulation becomes a consideration in planning an external
inspection when a carbon steel vessel is operated continuously:
a. 207 psig
b. 171 psig
c. 193 psig
d. 165 psig
19: A vessel that was fabricated of P-1 material with wall thickness of 2 inches,
has experienced localized corrosion to below its minimum required
thickness. When weld metal buildup is required to restore the corroded
area, which of the following methods can be used to avoid postweld heat
treatment?
a. Controlled-deposition welding.
b. FCAW welding.
c. Preheat to 250 F.
d. Automated-deposition welding.
Question 21: A vessel was designed to the 2001 Edition of the ASME Section VIII,
Division 1 Code. The ID of the seamless head is 48 inches. The
design pressure is 500 psig and the design temperature is 300 F. The
vessel seams have been radiographically inspected per UW-51. The
vessel material is SA 516 Grade 70. The corrosion allowable is 0.125
inch. The minimum required thickness of the 2:1 elliptical head per
the code of construction is:
a. 0.820 inch.
b. 0.610 inch.
c. 0.730 inch.
d. 0.940 inch.
a. until the Manufacturer's Data Report has been signed by the inspector.
c. for 5 years.
until receipt of the Manufacturer's Data Report has been acknowledged by
d. the owner/user.
API 510 6.2
24: When using risk-based inspection (RBI) to increase the 10-yr inspection
limit described in Section 6.4 of API 510, RBI assessment shall be reviewed
and approved by:
d. Brittle fracture.