PREGUNTA N°1

DATOS:

EXP. TEC M1 M2
MENSUAL May-17 Nov-17 Mar-18 Apr-18
UI39= 195.78 201.33 203.75 205.96

CDP 100% - 9.67% = 0.90330


POSTOR 3,124,262.89 / 90.33% = 3,458,721.23

SUMA ALZADA
POSTOR ENTIDAD
PRESUPUESTO VALOR REF.
COSTO DIRECTO 3,124,262.89 3,458,721.23
COSTO INDIRECTO
GASTOS GENERALES (CD) 29% 906,036.24 1,003,029.16
G. FIJOS(GG) 15% 135,905.44 150,454.37
G. VARIABLES (GG) 85% 770,130.80 852,574.78
UTILIDAD (CD) 11% 343,668.92 380,459.34
COSTO TOTAL (S/IGV) 4,373,968.05 4,842,209.73
IMPUESTO IGV 18% 787,314.25 871,597.75
GRAN TOTAL 5,161,282.29 5,713,807.48

DATOS NECESARIO:

FECHA DE AMPLIACION N° DE DIAS


PLAZOAMPLIADOS: 3/24/2018 4/25/2018 33 PLAZO TOTAL:

Fr=MC/VR 0.90330 GGV 852,574.78 IP

MGG=#dias ampl.x ggv(base) x Ip


plazo(dias) Io

MGG= 139,430.06 S/IGV


IGV= 18%

MGG= 164,527.47 C/IGV


FECHAS N° DE DIAS
PLAZO TOTAL: 11/25/2017 6/22/2018 210

203.75 IO 195.78
PREGUNTA N°2

PARA UNA OBRA QUE SE GANO CON EL 3.75% MAS, CON UN PLAZO QUE INICIABA EL 13 SEP. 15 Y DEBIA CULMINAR EL 2
ENCONTRAR UN MANTO PARACAS NO CONTEMPLADO EN EL PLANO, SE GENERO UNA PARALIZACION NO ATRIBUIBLE AL
LA RUTA CRITICA , CON LO CUAL, LA ENTIDAD LE RECONOCIO UNA AMPLIACION EN DIAS, DESDE EL 11 ENR. 16 AL 17 FEB
ESTRUCTURA DE PRESUPUESTO A PRECIO UNITARIOS, HALLAR SU MAYOR GASTO GENERAL CON IGV (FACTURA), POR EL T
RECONOCIDO. SI:

DATOS:

EXP. TEC M1 M2
MENSUAL Oct-18 Apr-19 Aug-19 Sep-19
UI39= 199.63 205.18 207.6 209.81

CDP 100% + 1.97% = 1.01970


ENTIDAD 2,456,852.14 * 101.97% = 2,505,252.13

PRECIOS UNITARIOS
POSTOR ENTIDAD
PRESUPUESTO VALOR REF.
COSTO DIRECTO 2,505,252.13 2,456,852.14
COSTO INDIRECTO
GASTOS GENERALES (CD) 28% 701,470.60 687,918.60
G. FIJOS(GG) 11% 77,161.77 75,671.05
G. VARIABLES (GG) 89% 624,308.83 612,247.55
UTILIDAD (CD) 13% 325,682.78 319,390.78
COSTO TOTAL (S/IGV) 3,532,405.50 3,464,161.52
IMPUESTO IGV 18% 635,832.99 623,549.07
GRAN TOTAL 4,168,238.49 4,087,710.59

DATOS NECESARIO:

FECHA DE AMPLIACION N° DE DIAS


PLAZOAMPLIADOS: 8/7/2019 9/28/2019 53

Fr=MC/VR 1.01970 GGV 624308.83

MGG=#dias ampl.x ggv(oferta) x Ip


plazo(dias) Io

MGG= 152,253.91 S/IGV


IGV= 18%
MGG= 179,659.61 C/IGV
13 SEP. 15 Y DEBIA CULMINAR EL 25 ABR. 16, PERO AL
A PARALIZACION NO ATRIBUIBLE AL CONTRATISTA , AFECTANDO
AS, DESDE EL 11 ENR. 16 AL 17 FEB. 16 SI TIENE UNA
ERAL CON IGV (FACTURA), POR EL TIEMPO AMPLIADO Y

FECHAS N° DE DIAS
PLAZO TOTAL: 4/18/2019 11/29/2019 226

IP 207.60 IO 199.63
PREGUNTA N°3

DATOS:

CDP 100% - 3.85% = 0.96150


POSTOR 6,588,337.76 / 96.15% = ###

PRECIOS UNITARIOS
POSTOR ENTIDAD VALOR
PRESUPUESTO REF.
COSTO DIRECTO 6,588,337.76 6,852,145.36
COSTO INDIRECTO
GASTOS GENERALES (CD) 32% 2,108,268.08 2,192,686.51
UTILIDAD (CD) 13% 856,483.91 890,778.90
COSTO TOTAL (S/IGV) 9,553,089.75 9,935,610.77
IMPUESTO IGV 18% 1,719,556.16 1,788,409.94
GRAN TOTAL 11,272,645.91 11,724,020.70

DATOS:

MONTO DE OBRA 9,553,089.75 S/IGV

PLAZO ATRASO MULTA (S/IGV)


9/26/2018 6/12/2019 1/14/2019 3/21/2019 1,056,321.58
INICIO FINAL INICIO FINAL

PLAZO

FECHA DE OBRA N° DE DIAS


PLAZOAMPLIADOS: 9/26/2018 6/12/2019 260

MULTA

FECHA DE ATRASO N° DE DIAS


PLAZOAMPLIADOS: 1/14/2019 3/21/2019 67

a)MULTA POR DIA

P1día= 0.10 x MC P1día= 24,495.10 MULTA= #DIAS x P1d


F x Plazo
b) CALCULAR EL 10% DEL MONTO DEL CONTRATO

MC x 10%=
955,308.98

c) CUAL ES EL MONTO QUE SE DEBE PAGAR

MULTA CONTRATISTA= ###


MULTA SUPERVISION= ###
MULTA MAXIMA (10% MC)= 955,308.98

MULTA C/IGV ENTIDAD


1,936,582.76 RESPUESTA
MULTA= #DIAS x P1día MULTA S/IGV ###
PREGUNTA N°4

DATOS:

POSTOR 100% + 3.61% = 1.03610


CDP 4,412,365.70 * 103.61% = 4,571,652.10

MD= 6,583,179.03 AD= 559570.217257

PRECIOS UNITARIOS
POSTOR ENTIDAD VALOR
PRESUPUESTO REF.
COSTO DIRECTO 4,571,652.10 4,412,365.70
COSTO INDIRECTO
GASTOS GENERALES (CD) 31% 1,417,212.15 1,367,833.37
UTILIDAD (CD) 13% 594,314.77 573,607.54
COSTO TOTAL (S/IGV) 6,583,179.03 6,353,806.61
IMPUESTO IGV 18% 1,184,972.22 1,143,685.19
GRAN TOTAL 7,768,151.25 7,497,491.80

Fr=MC/VR 1.03610

M AD. EFEC. M1 M2 M3 M4
MES Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19
%AV 19% 25% 29% 27%
K M Ad Efe 1,207,223.26 1,588,451.65 1,842,603.92 1,715,527.78
FR 1.0361 1.0361 1.0361 1.0361
MC 1,250,804.02 1,645,794.76 1,909,121.92 1,777,458.34
1.28 1.284 1.281 1.283 1.282 1.285

VALORIZACION

MES= DICIEMBRE MES= ENERO


V1= 1,250,804.02 V2= 1,645,794.76
R1= V1*(Kmes ant.-1) R2= V2*(Kmes ant.-1)
R1= 355,228.34 R2= 462,468.33

REINTEGRO

RI1= V1*(Kmes ant.-Kmes)


R1= -3,752.41
REGULARIZACION DE REAJUSTE

a)INTERES CAUZADO POR MORA

Dec-17 Jan-18 Feb-18


31 31 2 64
31 31 28

DATO BUSCADO EN PAGINA DE INTERNET http://www.sbs.gob.pe/app/pp/EstadisticasSAEEPortal/Paginas/TIL

F MAX. PAGO Dec-17 31 TIL= 7.31171


F REAL DE PAGO Feb-18 2 TIL= 7.32775

INTERES LEGAL= 4,600.64


V
M
(a) VALORIZACION MES
reajuste +
reintegro +
regu. - reaj +
Ded Ad Efec -
Ded Ad Mat -
(b) Valorización bruta (vb)
AMORTIZACIONES
Por Adel Directo -
Por Adel Materiales -
( c) Total Amortizaciones
MONTO NETO A FACTURAR
Valoriz Neta (b)-( c) +
Impuesto IGV (18%)
Monto a Facturar

100%
6,353,806.61
1.0361
6,583,179.03

MES= FEBRERO MES= MARZO


V3= 1,909,121.92 V4= 1,777,458.34
R3= V3*(Kmes ant.-1) R4= V4*(Kmes ant.-1)
R3= 540,281.50 R4= 501,243.25

RI2= V2*(Kmes ant.-Kmes) R3= V3*(Kmes ant.-Kmes)


R2= 3,291.59 R3= -1,909.12
RR1= V1*(Kmes ant.-Kmes) RR2= V2*(Kmes ant.-Kmes)
R1= 2,501.61 R2= -1,645.79

ticasSAEEPortal/Paginas/TILegalEfectiva.aspx
VAL-01 VAL-02 VAL-03 VAL-04

1,250,804.02 1,645,794.76 1,909,121.92 1,777,458.34


355,228.34 462,468.33 540,281.50 501,243.25
-3,752.41 3,291.59 -1,909.12
2,501.61 -1,645.79
332.24 109.29 380.33 236.07

1,605,700.11 2,104,401.38 2,454,816.29 2,274,910.60

125,080.40 164,579.48 190,912.19 177,745.83

125,080.40 164,579.48 190,912.19 177,745.83