JOB PROCEDURE

FOR
CONCRETING
INDEX

1.0 PURPOSE

2.0 SCOPE

3.0 CONTROLLING SPECIFICATIONS

4.0 MATERIALS

5.0 PROCEDURES

6.0 INSPECTIONS
PURPOSE:
The purpose of this procedure is for supervision of concreting works at site and to
ensure that proper quality control is made at site.

SCOPE:
This procedure covers supervision and method of record keeping for all concreting
works at all structures.

CONTROLLING SPECIFICATION
IS: 456 and approved construction drawings.

MATERIALS
Fine & Coarse Aggregate
Procured materials for site work will be tested for all the properties as stipulated in
IS: 383 and to check its suitability. These materials will be free from injurious
amounts of alkalis, vegetable matter, and other deleterious substances.
The grading of aggregates will conform to table 2,4 & 5 of IS: 383 After assessing
the properties of the aggregates, a suitable mix proportion for different grades of
concrete will be tested in lab and the same will be got approved by the Engineer in
charge. Grading of aggregates shall be checked weekly for their conformity with
mix design grading. Each type and grade of aggregate will be stored separately on
hard firm ground.
Cement:
Unless otherwise specified cement will be ordinary Portland cement conforming to
IS: 269 and IS: 8112. Cement will be stored in godowns at site to protect from
dampness and will be made easily accessible for proper inspection and accounting.
Cement mobilized for the work shall have MTC, or otherwise, it should be tested in
a reputed lab as per the relevant IS specifications.

Steel
Tor steel reinforcement for cement concrete works will confirm to high yield strength
deformed steel bars of Grade Fe 415 and IS: 1786 and relevant parts of IS: 456
and co-related with MTC (Manufacturer's test certificate). MTC which will be
produced for all types of reinforcement steel and for all the consignments coming
to site and in the case of absence of MTC, the same shall be tested in an approved
lab as per the relevant IS code and sampling procedure. All reinforcement bars will
be clean and free from dirt, oil, paints, grease, mill scales, and loose rust. Bar
bending schedule will be prepared before cutting.
Form Work
Formwork will be of commercial plywood or steel plates. The shuttering will be
supported on battens and props of pipes cross-braced together. The surface of
shuttering in contact with concrete will be given a coating of shuttering oil. Removal
of shuttering will be as per IS 456. The completed form- work shall be inspected as
per QA/QC plans.
Water
The water used for site work will be clean and free from harmful chemicals and
organic material. To ascertain the same, a sample of water will be tested in any of
the reputed laboratories prior to the commencement of work and later on in case if
any visible change is found. The water shall be in general confirmed to the
requirement of IS: 456.

PROCEDURE:
All concreting works will confirm to the latest editions of IS specifications. The
grading, design of mix, sampling, and strength testing of concrete will be as per IS:
456 and other relevant codes mentioned therein.
A. Plain Cement Concrete:
For all PCC works, the concrete will be mixed in an approved mechanical mixer.
The coarse and fine aggregates will be measured in approved measuring boxes or
in weigh batcher. For volume batching the mass of aggregates to be used will be
divided by the bulk density of the aggregates to get the mix proportion. Compaction
of lean concrete will be done manually using rammers. PCC for flooring etc shall be
consolidated using vibrators. Form work for PCC will be done using battens I
wooden planks as and where required.
B. Reinforced Cement Concrete:
For all the RCC works, concrete shall be produced in Batching Plant. Batching of
concrete ingredients shall be by weigh batcher only. Nominal mix concrete by mixer
machine as an alternate shall be produced only in case of exigency or smaller
quantities not viable with batching plant. The Engineer in charge shall be informed
about the concreting program well in advance. Availability and arrangement of
necessary materials and equipments shall be checked before calling for inspection.
All information pertaining to a particular concrete pour shall be incorporated in Pour
Cards and the pouring shall commence only after due review of relevant QA
documents. Coarse aggregate, fine aggregate and water sample used for
concreting shall be checked in case of change of source.
Requisite concreting ingredients shall be mixed in approved batching plant. The
mixing time shall not be less than 2 minutes for a mixer drum of 0.75cum. capacity
and 2.5 minutes for a mixer drum of capacity more than 0.75cum. Concrete shall
not be dropped from a height of more than 1.5m and shall be laid in position in
horizontal layers and shall be compacted using mechanical vibrators. The whole
process shall be completed before initial setting takes place.
Whenever a construction joint to be provided in a monolithic structure, bonding
grooves will be formed in the concrete already laid and the surface will be
roughened, cleaned and given a wash of neat cement slurry before laying new
concrete as laid down in clause 12.4.1 of IS:456. The concrete will be cured for a
minimum period of 07 days from the day of casting. Bending, binding, lapping and
placing reinforcement in position will be done as per IS: 456, IS: 2052 and other
relevant codes.
Bars will be cleaned of rust, scales, grease, oil, and any other foreign matter before
placing in position. Unless otherwise specified, minimum cover, spacing, and bond
length will be as per IS: 456.

C. Monolithic reinforced cement concrete:


If the design requirement of any structure is monolithic, then the pouring shall be
done continuously to avoid formation of any cold joints. Curing will be done for a
minimum period of 07 days from the day of casting.
INSPECTION
Sampling and strength testing of concrete cubes shall be in accordance to IS: 456
and other relevant codes mentioned therein.
A. Sampling frequency for concrete produced by conventional methods.
CONCRETE QUNATITY (cum.) CONCRETE CUBES SAMPLE
(SET OF 6 CUBES)
01-05 1
06-15 2
16-30 3
31-50 4
51 & above 4+ one additional for each 50 cum.

B. Sampling frequency for RMC / Batching Plant supplied concrete. (Proposed)


CONCRETE QUNATITY (cum.) CONCRETE CUBES SAMPLE
(SET OF 6 CUBES)
001-030 1

030-060 2

060-100 3

100 & above 3+ one additional for each 50 cum.


INSPECTION & TEST PLAN
Sr. Inspection Activity Inspection agency
No. Type of
Contractor PMC Record
1 Material Acceptance
-Cement & Steet WC S
-Aggregate
2 Design Mix WC HP
3 Layout , lines, Levels, and
plumb in form work WC S
4 Supports/ Staying/ bracing WC S
5 Reinforcement, Inserts, Pipe
sleeves, Concealed
Electrical conduits, Fan WC S
6 hooks, Dowels, Cover for WC S
7 reinforcement
8 Pockets and Openings WC S
9 Expansion joints if any WC S
10 Check for water slopes WC W
11 Pour card
Concreting, W/C ratio, WC S
12 Consolidating, finishing. WC S
13 Casting of Cubes WC S
14 Curing WC RW
15 Testing of Work cubes WC S
16 De-shuttering WC S
Finishing

Legend: HP - Hold Point W - Witness Point


RW- Rivew of Contractor's Documents
S - Surveillance Inspection by Owner IPMC
WC- 100% Examination by Contractor
CEMENT TEST REPORT

Report No :
Brand/grade : Date Of Sampling :
Date of receipt : Date Of Testing :
Quantity received : Week No. :

S.No. TYPE OF TEST RESULT AS PER IS: 8112 REMARKS


OBTAINED

1 Consistency (%)

2 Setting Time Should not be


a) Initial less than 30 min.

b) Final Should not be


less than 300 min.

3 Compressive a) 3 days –
strength (n/mm2) 23(min.)
b) 7 days-
33(min.)
c) 28 days-
43(min.)

The above sample is found suitable for concrete work.

STEEL RECEIPT NOTE


Date :
Job no.: Report No :

Sl.no. Description Quantity Inv/ DC MTC Visual Remarks


no. no inspection

Contractor PMC
BAR BENDING SCHEDULE

Report No. : ________________ Page No. __________________


Name of work ________________ Job No. __________________
Drawn By _________________ Drawing No. __________________
Checked By _________________ Date __________________

Sl. Location Bar Size No. No. Total Total Shape


No Mark & of Per number length
Type Sets sets

COMPRESSIVE STRENGTH TEST OF CONCRETE CUBE


Report no. : Date:
Grade of concrete: location : Cement type:
Slump: Max. Size of aggregate:
W/c ratio: Pour card no. :

Compressiv
Load gauge reading
Cube identification

e
Type of structure

Wt of cube (kg)
Date of casting

Date of testing

Strengt5h(k
Size of cube

Load (kg)

Remarks

g/c m2)
(days)

(cm2)
Area
(cm)
Age

(kn)
no.

Tested Checked
POUR- CARD
Consultant :

Report no. : Date:


A – PROGRAMME FOR CONCRETING

Unit & Location :


Drawing Ref : Grade of Concrete :
Type of Structure : W/C Ratio :
Co Ordinates – X/Y : Levels :
Approx. Qty of Concrete to be poured :
Machinery proposed to be used:
1. Batching plant :
2. Concrete Mixer :
3. Vibrators : Time Intending To Pour:
4. Pumps : Concrete – Start :
5. Hoist : Completion :
Observations:
I. Shuttering: II. Reinforcement:
II. Inserts / anchor bolts: IV. Pocket Opening:
V. Quality of coarse aggregate: VI. Quality of Water;
VII. Quality of fine aggregate: VIII. Type of Cement Used:
Extra reinforcement:
* Laps : Lighting Arrangement :
* Separators : Safe Arrangement :
* Chairs : Any Other :
Deviation from drawing if any :
Provision for Construction joint / expansion joints:
Clearance:
The above structure / work has been checked and found ready for Concreting.

B- OBSERVATION DURING CONCRETING


1. Actual time to start of pouring concrete:
2. Actual time of completion:
3. Slump:
4. No of cubes taken: ID Mark of Cubes:
5. Total cement consumption:
6. No of engineers / supervisors deployed:
7. Comments if any:

Contractor PMC
SIEVE ANALYSIS OF COARSE AGGREGATE
Report no:

Source: M1:__________________ Date:

M2:__________________

Sr. Sieve Wt. % Wt. Cumulative % Cumulative % Limit


No. Size Retained in Ret. retained Passing as per
Gms IS:
383
1 40mm 100
2 20mm 95-
100
3 12.5mm -
4 10mm 25-55
5 4.75mm 0-10
6 2.36mm -
TOTAL

REMARKS

SIEVE ANALYSIS OF FINE AGGREGATE

Report no. : Date:


Source :
Sr. No. Sieve Size Wt. % Wt. Cumulative Cumulative
Retaine Ret. % %Passing Zone 2 Zone 3
d in Retained
Gms
1. 10mm 100 100
2. 4.75mm 90-100 90-100
3. 2.36mm 75-100 85-100
4. 1.18mm 55-90 75-100
5. 600 micron 35-59 60-79
6. 150 micron 8-30 12-40
7. PAN 0-10 0-10
8.

TOTAL

REMARKS