Sunteți pe pagina 1din 25

Tunnelling and Underground Space Technology 58 (2016) 49–73

Contents lists available at ScienceDirect

Tunnelling and Underground Space Technology


journal homepage: www.elsevier.com/locate/tust

An investigation into efficient drainage layouts for the stabilization


of tunnel faces in homogeneous ground
Sara Zingg ⇑, Georg Anagnostou
ETH Zurich, Switzerland

a r t i c l e i n f o a b s t r a c t

Article history: This paper investigates the effectiveness of various advance drainage schemes with respect to face stabil-
Received 26 February 2015 ity. The latter is analysed through limit equilibrium computations taking account of the modified seepage
Received in revised form 10 March 2016 flow conditions prevailing in the ground after the implementation of drainage measures. The seepage
Accepted 17 April 2016
forces are determined numerically through steady-state, three-dimensional seepage flow analysis which
takes account of the characteristics of a given drainage scheme. A suite of computations was carried out
to quantify the effects of the geometric parameters for the drainage layout, i.e. the number, length, spac-
Keywords:
ing and location of drainage boreholes or the diameter and location of the pilot tunnel used for drainage.
Advance drainage
Face stability
The computational results provide useful indications about optimum drainage arrangement with regard
Limit equilibrium to face stability. A dimensionless formulation of the required support pressure (or the required cohesion
Seepage of the ground, respectively) is developed in order to produce dimensionless design nomograms, which
Subaqueous tunnel can provide a quick assessment of face stability in cases involving partial or complete pore pressure relief
in advance of excavation.
Ó 2016 Elsevier Ltd. All rights reserved.

1. Introduction have been presented by Zingg and Anagnostou (2012, 2013) and
Zingg et al. (2013).
Water adversely affects the stability and deformation of under- Drainage measures comprise horizontal or inclined boreholes
ground structures; advance drainage improves face stability by that are drilled either directly from the face (Fig. 1a) or from lateral
reducing the pore water pressure and hydraulic head gradient in niches or enlarged cross-sections (Fig. 1b). Deep below the water
the vicinity of the tunnel face (Anagnostou and Zingg, 2013). The table, the equipment has to be protected against high water pres-
favourable effect of advance drainage on face stability is well sure by means of so called ‘‘preventers”. The installation of advance
known from tunnelling experience (e.g. Nilsen, 1999, 2011, drainage boreholes from the tunnel face interferes with tunnel
Nilsen and Palmström, 2001; Wang et al., 2004; Fulcher et al., excavation and support installation. In addition, technical equip-
2008; Sellner et al., 2008). Although there are many publications ment and procedures limit the length of the drainage boreholes
addressing face stability in water bearing ground (e.g. Pellet and thus the time available for pore pressure relief, which is a crit-
et al., 1993; Anagnostou and Kovári, 1996; de Buhan et al., 1999; ical factor in low permeability grounds. Advance drainage from
Broere, 2001; Vermeer et al., 2002; Droniuc et al., 2004; Lee and niches (Fig. 1b) in combination with directional drilling (allowing
Nam, 2001; Fellner and Gärber, 2004; Höfle and Fillibeck, 2007; for longer boreholes) remedies these problems. Another option is
Ströhle and Vermeer, 2009; Perazzelli et al., 2014), few research to employ a pre-existing underground opening, such as a pilot tun-
works deal specifically with the effect of advance drainage mea- nel inside or outside the cross-section of the main tunnel
sures on face stability (Lee et al., 2003; Anagnostou et al., 2010). (Fig. 1c and d) or – in the case of twin tunnels – the tube con-
This paper extends the face stability model of Anagnostou and structed first (Fig. 1e). The drainage action of a pre-existing under-
Kovári (1996) to include pore pressure relief due to advance drai- ground opening can be enhanced by drilling sufficiently long radial
nage. In addition, it analyses and presents design nomograms for boreholes, i.e. extending beyond the axis of the main tunnel
the most common drainage layouts (Fig. 1). Preliminary results (Fig. 1d). Such drainage curtains are of course essential for pore
pressure relief where the lining of the pre-existing opening is
⇑ Corresponding author at: ETH Zurich, Chair of Underground Construction, P.O. watertight (e.g. a TBM-driven safety gallery with a sealed segmental
Box 133, Stefano-Franscini Platz 5, 8093 Zurich, Switzerland. lining).
E-mail address: sara.zingg@igt.baug.ethz.ch (S. Zingg).

http://dx.doi.org/10.1016/j.tust.2016.04.004
0886-7798/Ó 2016 Elsevier Ltd. All rights reserved.
50 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Notation

adr distance of drainage curtains sx support pressure for wedge angle x


c effective cohesion of the ground T distance of the upper boundary of the seepage flow do-
clim,d limiting cohesion main to the tunnel crown
clim,s limiting cohesion TI shear resistance of the inclined slip plane of the wedge
D tunnel diameter TV shear resistance of the two lateral slip planes of the
D0 side length of equivalent square tunnel cross-section wedge
db diameter of grouted borehole V volume of the wedge
ddr diameter of drainage boreholes V0 effective vertical force of prism
dp diameter of pilot tunnel Wk seepage forces acting on the wedge
ed coefficient x1 horizontal coordinate parallel to the tunnel axis
es coefficient x2 horizontal coordinate perpendicular to the tunnel axis
F0–F3 coefficients provided by nomograms x3 vertical coordinate
f(. . .) function of . . .
G0 submerged weight of the wedge Greek symbols
H depth of cover a coefficient
Hw elevation of water table b coefficient
h hydraulic head c0 submerged unit weight of the ground
hav average piezometric head over prism cross-section cd dry unit weight of the ground
h0 depth of the tunnel axis underneath the water table cw unit weight of water
I1, I3, Is coefficients for the contribution of seepage flow dd coefficient
ldr length of drainage boreholes ds coefficient
L centre distance kw coefficient of lateral stress in wedge
Lh horizontal centre distance kp coefficient of lateral stress in prism
Lv vertical centre distance nk normalized coordinate
n number of drainage boreholes f integration variable
N0 effective normal force on the slip pane of the wedge r0 v silo pressure acting upon the wedge
nb bolt density r0 vd contribution of the ground above the water table to the
Nc value of Ncx at xcr silo pressure
Nc value of Ncx at xcr r0 vT silo pressure at the elevation of the water table
Nh value of Nhx at xcr r0 ve contribution of the ground underneath the water table
Ncx cohesion influence coefficient for wedge angle x to the silo pressure under hydraulic equilibrium
Nc x weight influence coefficient for wedge angle x r0 vs contribution of the seepage flow to the silo pressure
Nhx seepage flow influence coefficient for wedge angle x sm bond strength
nk unit normal vector u angle of effective internal friction of the ground
r ratio of volume to circumferential area of the prism v ratio of idealized square tunnel cross-section side length
rdr distance of boreholes from tunnel axis to tunnel diameter
S integration area x angle between face and inclined slip plane
s effective face support pressure xcr critical angle x
Sx support force for wedge angle x

The effectiveness of advance drainage may be limited by several allowing a quick estimate to be made of the necessary face support
factors: the technically feasible geometric layouts of drainage mea- pressure in the presence of drainage measures. The practical
sures often provide only partial pore pressure relief; in a highly applicability of the nomograms is illustrated in Section 5, making
permeable ground, the capacity of the drainage boreholes and reference to two tunnelling projects.
the design of their casings may also limit pore pressure relief; on
the other hand, in a low-permeability ground, pore pressure relief 2. Computational model
by advance drainage may take a prohibitively long time to work; in
a heterogeneous ground, consisting of alternating aquifers and Face stability is analysed after Anagnostou and Kovári (1996),
aquitards, some drainage boreholes may be ineffective; and, which considered a failure mechanism consisting of a wedge and
finally, environmental constraints with respect to the drawdown a prism (Fig. 2), and determined the seepage forces by means of
of the water table or the magnitude of settlements may impose numerical, steady state seepage flow analyses assuming Darcy’s
limits on the amount of admissible pore pressure relief. law, and introduced these into the equilibrium equations. There
Solely homogeneous ground is considered next, keeping in are only two differences to the model of Anagnostou and Kovári
mind the above-mentioned potential limitations. The permeability (1996): (i) The latter takes the ratio of horizontal to vertical stres-
is considered sufficiently high for the necessary drainage time not ses which governs the frictional part of the shear resistance at the
to be a limiting factor. This condition is fulfilled where ground per- vertical slip planes of the failure mechanism to kp = 0.8 for the
meability is higher than about 108 m/s (Anagnostou and Kovári, prism and kw = 0.4 for the wedge. Here, slightly higher values are
1996; Anagnostou et al., 2010). In addition, uncased drainage bore- considered (1.0 and 0.5, respectively), based on recent results in
holes of sufficient hydraulic capacity are considered. Anagnostou (2012). (ii) For the determination of the seepage
After outlining the computational model (Section 2), basic forces, Anagnostou and Kovári (1996) considered the hydraulic
aspects of the different drainage layouts in Fig. 1 are discussed in head field that prevails when drainage occurs only through the
Section 3 through comparative analyses of a cylindrical tunnel tunnel face. Here, the effect of advance drainage measures
(Fig. 2). Section 4 presents dimensionless design nomograms (Fig. 1) on the hydraulic head field is taken into account.
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 51

(k = 107 m/s), a large cover (T = 250 m) and a thin lining (tlin = 0.2
m), the threshold lining permeability amounts to about 1011 m/s.
Well applied shotcrete exhibits a lower permeability (1012 m/s,
Franzen and Celestino, 2002) and can, therefore, be considered as
practically impermeable. Low-quality shotcrete may exhibit a
higher permeability (in the order of 1010 m/s; Celestino et al.,
2001) and allow for some additional drainage and pore pressure
relief. This is particularly true for a perforated shotcrete lining or
an open shield. In such cases, the no-flow boundary condition rep-
resents a simplification on the safe side.
The numerical seepage flow analyses were performed with the
finite element code COMSOLÒ.

2.2. Support pressure

The support pressure that is needed in order to stabilize a speci-


fic wedge (characterized by the angle x; Fig. 2) for given drainage
measures can be expressed as follows (see Appendix A):

sx ¼ Ncx c0 D  Ncx c þ Nhx cw h0 ; ð1Þ

where c, h0, c0 and cw denote the cohesion, the depth of the tunnel
axis underneath the water table (Fig. 2), the submerged unit weight
of the ground and the unit weight of the water, respectively. Ncx,
Ncx and Nhx are dimensionless coefficients, which depend on the
numerically computed hydraulic head field (and thus on the drai-
nage layout), the friction angle u, the normalized cohesion c/c0 D,
the ratio of dry unit weight cd to c0 , the normalized overburden H/
D, the normalized in situ head cwh0/c0 D and the angle x between
the tunnel face and the inclined slip surface of the wedge (hereafter
referred to as ‘‘wedge angle”).
The critical wedge angle xcr, i.e. the angle that results in the
maximum support pressure s, is determined iteratively by repeat-
ing the computation for different values of x.

3. Comparative analyses

3.1. Introduction

We consider the example of a 100 m deep subaqueous cylindri-


cal tunnel (Fig. 4). The assumed parameters are given in Table 1.
The effectiveness of each drainage scheme (Fig. 1) is evaluated in
Fig. 1. Drainage via: (a) boreholes from the tunnel face; (b) boreholes from a niche
terms of the face support pressure s that is needed for stability.
or from a locally enlarged cross-section; (c) a co-axial pilot tunnel; (d) boreholes
from an external pilot tunnel; (e) the first tube of a twin tunnel. For the purposes of comparison we first consider the following
two borderline cases (Section 3.2): (i) no drainage measures, i.e.
pore pressure relief only due to the natural drainage action of
2.1. Seepage flow analyses the open tunnel face; (ii) ideal drainage, i.e. complete pore pressure
relief in the ground ahead of the tunnel face. These two borderline
The seepage flow domain extends either up to the ground sur- cases bound the range of face support pressures that would be
face H (subaqueous tunnels) or up to the groundwater table Hw. needed in combination with non-ideal, real world advance drai-
The upper boundary of the numerical model is thus located at dis- nage. They thus serve as reference cases for an evaluation of the
tance T = min(H, Hw) above the tunnel crown. The hydraulic head effectiveness of the various drainage layouts in Fig. 1.
at the far-field boundaries is taken equal to the initial hydraulic Subsequently (in Section 3.3), we show the effect of the num-
head h0, which is equal to the elevation of the water table above ber, length and location of drainage boreholes drilled either
the tunnel axis. The water table is assumed to remain constant in directly from the tunnel face (Fig. 1a) or from lateral niches or
spite of the drainage action of the tunnel. This assumption is true enlarged cross-sections (Fig. 1b). Sections 3.4 and 3.5 deal with
in the case of sufficient groundwater recharge from the surface the drainage action of a pilot tunnel (located inside or outside
and conservative in the case of a draw-down. the cross-section of the main tunnel) or of the first tube of a twin
The tunnel face and the walls of the drainage boreholes are tunnel, respectively. Finally, Section 3.6 investigates drainage
taken as seepage faces under atmospheric pressure, while the tun- curtains (Fig. 1d).
nel boundary is considered impervious up to the face (no-flow
boundary condition, Fig. 3). Investigations by Wongsaroj (2005) 3.2. Reference cases
indicated that seepage flow through the lining can be neglected
if the lining permeability is lower than 0.1 ktlin/T, where k and tlin Fig. 5a shows the support pressure needed for face stability in a
denote the ground permeability and the lining thickness, respec- cohesionless ground as a function of the wedge angle x in the case
tively (cf. also Mair, 2008). Even if with a low permeability ground of ideal drainage (lower curve) and in the absence of drainage
52 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 2. Failure mechanism (after Anagnostou and Kovári, 1996): (a) cross-section, (b) longitudinal section and (c) axonometric projection.

Table 1
Parameters for the comparative analyses.

Problem layout
Depth of cover H 100 m
Elevation of water table Hw 130 m
Tunnel diameter D 10 m
Ground
Effective cohesion c 0–400 kPa
Angle of eff. internal friction u 30°
Submerged unit weight c0 12 kN/m3
Unit weight water cw 10 kN/m3
Shear resistance of the vertical slip surfaces
Coefficient of lateral stress in wedge kw 0.5
Coefficient of lateral stress in prism kp 1.0
Drainage boreholes
Diameter ddr 0.1 m
Length ldr 0.5–30 m
Number n 0–12
Fig. 3. Example of spatial discretisation and hydraulic boundary conditions for Distance from tunnel axis rdr 1.5–11 m
advance drainage according to Fig. 1a.
Drainage via a pilot tunnel or another tunnel
Diameter of coaxial pilot tunnel dp 0.5–5 m
Diameter of adjacent tunnel dp 1–10 m
Vertical centre distance Lv 14–92 m
Horizontal centre distance Lh 14–90 m
Distance of drainage curtains adr 4–20 m

inevitably leads to some pore pressure relief in the ground ahead


of the face.
The practical significance of these results becomes evident
when we consider the fact that face support pressures of more than
200 kPa cannot be managed in conventional tunnelling, even with
heavy face bolt reinforcement (Anagnostou and Serafeimidis,
2007). In the present example, ground improvement by grouting
Fig. 4. Problem setup for the comparative analyses.
or freezing would be indispensable in the absence of drainage mea-
sures. In the case of complete pore pressure relief by advance drai-
measures (upper curve). In the first case, the pore pressure in the nage, the face would still need support, but this would be
wedge is atmospheric; seepage forces have to be taken into technically feasible considering the relatively moderate support
account only for the overlying prism. In the second case, the wedge pressure of about 100 kPa that is required.
is acted upon by seepage forces which are directed towards The required support pressure (for the critical wedge) decreases
the tunnel face, thus leading not only to a considerably higher with increasing cohesion of the ground (Fig. 5b). In the case of
necessary support pressure (s = 770 vs. 100 kPa), but also a more complete pore pressure relief, cohesion of just 45 kPa would be
extended unstable region (critical wedge angle xcr = 63° vs. 30°). sufficient for the tunnel face to remain stable without support
It is, nevertheless, remarkable that even in the absence of drainage (point A). Without drainage measures the cohesion required for
measures the necessary support pressure is considerably lower an unsupported face increases to 330 kPa (point B); even with
than the initial hydrostatic pressure (s = 770 vs. 1400 kPa). This is heavy bolt reinforcements (s = 180 kPa), the ground would need a
due to the natural drainage action of the tunnel heading, which cohesion of at least 240 kPa (point C).
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 53

Fig. 5. (a) Required support pressure s as a function of the angle x for a cohesionless ground with ideal advance drainage (lower curve) and without advance drainage (upper
curve); (b) required support pressure s for the critical wedge as a function of the cohesion c (parameters according to Fig. 4 and Table 1).

the reference pressure; marginal utility diminishes with further


boreholes. In a weak rock exhibiting a cohesion of 150 kPa, 6 bore-
holes would suffice for face stability (point D in Fig. 8). Trading the
feasible pore pressure relief against the drilling effort, 4–6 drainage
boreholes can be recommended as an efficient face stabilization
measure in homogeneous ground. (In a heterogeneous ground, a
larger number of drainage boreholes may be needed to reach all
Fig. 6. Locations of the most effective drainage boreholes. water-bearing ground layers.)
Taking these results into account, we next discuss the effect of
borehole length ldr for the case of 6 boreholes (Fig. 9). The required
3.3. Drainage via boreholes from the tunnel face or niches support pressure decreases rapidly with increasing borehole length
ldr until the latter reaches about 15 m (point A in Fig. 9), i.e. until
We consider horizontal boreholes of uniform diameter the boreholes extend sufficiently ahead of the largest critical
(ddr = 10 cm) and investigate successively the effect of their num- wedge (remember that in the absence of drainage the critical angle
ber n, length ldr and distance rdr from the tunnel axis (Fig. 1a and b). xcr is equal to about 63°). Longer boreholes provide no benefit,
The effect of the number of boreholes is investigated assuming because they cause pore pressure relief far ahead of the tunnel face
that they are 30 m long and located at rdr = 3.8 m. Fig. 6 shows the (in a zone that is anyway non-critical for face stability). In the pre-
borehole locations considered for every number n of boreholes. sent example (10 m diameter tunnel), 30 m long boreholes (a tech-
Comparative computations for other arrangements showed that nically feasible length) every 15 m (one and a half tunnel
the exact location of the boreholes is of secondary importance diameters) would be a sensible choice. Longer boreholes would
for the necessary support pressure, provided that at least two bore- be advantageous in medium to low permeability ground because
holes are located in the upper third of the tunnel face (Zingg and they provide a longer drainage period in advance of excavation.
Anagnostou, 2012; see also later Fig. 10). The other boreholes can However, they may present execution difficulties due to instabili-
either be arranged in the upper section or distributed evenly over ties or deformations in the borehole walls, friction when using
the face. casings or drilling accuracy.
Fig. 7 shows the distribution of the hydraulic head along the Finally, we investigate whether there is any optimisation poten-
x1-axis ahead of the tunnel face and along the x3-axis above the tial with respect to the distance rdr of the boreholes from the tunnel
tunnel for 2–12 boreholes (dashed lines) as well as for the refer- centre. We consider six, 30 m long drainage boreholes located at
ence case without drainage boreholes (solid line). It is remarkable distances of 1.5–11 m from the tunnel centre (the distances rdr >
that just 2–4 boreholes result in considerable pore pressure relief, D/2 = 5 m apply to boreholes drilled from niches), which are
particularly ahead of the tunnel face (x1-axis in Fig. 7). Advance located either at the upper part of the cross-section or laterally
drainage decreases the hydraulic head gradients close to the face in groups of three (see inset in Fig. 10, l.h.s. and r.h.s cross-
(they occur only at a greater distance), which leads to narrower section, respectively). Fig. 10 shows the required support pressure
critical wedges and a substantial reduction in the required support s as a function of rdr for these two arrangements (solid and dashed
pressure (Fig. 8). In a cohesionless ground, advance drainage with lines, respectively). As the dashed and solid lines are very close
just two boreholes decreases the required support pressure to together but all curves exhibit a minimum at rdr = 5–7 m, the con-
about 60% of the reference pressure, i.e. the pressure required in clusion is that the drainage boreholes should be arranged close to
the absence of boreholes (compare points A and B in Fig. 8). The the periphery of the tunnel cross-section, while draining from a
addition of four more drainage boreholes (point C in Fig. 8) leads niche above the roof or from a lateral niche does not make any
to a further reduction in the support pressure to about 40% of difference.
54 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 7. Distribution of the hydraulic head h above (l.h.s.) and ahead of (r.h.s) the tunnel face (parameters according to Fig. 4 and Table 1).

Fig. 8. Required support pressure s as a function of the number of drainage


boreholes n (borehole locations see Fig. 6; parameters according to Fig. 4 and Fig. 9. Required support pressure s as a function of the borehole length ldr (borehole
Table 1). locations see inset; parameters according to Fig. 4 and Table 1).
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 55

thereof were considered (mechanisms I, II and III in the inset in


Fig. 11). Mechanism III proved to be decisive. The pore pressure
relief from the pilot tunnel has a significant stabilizing effect. For
example, face stability in a weak rock exhibiting a cohesion c of
150 kPa would require a very high support pressure of about
400 kPa in the absence of drainage measures (point A in Fig. 11).
A 3 m diameter pilot tunnel would, however, provide sufficient
pore pressure relief in advance of profile enlargement for the face
to be stable without support (point B in Fig. 11).
The drainage effect of a pilot tunnel outside the cross-section of
the main tunnel (Fig. 12) is, as might be expected, less pronounced
than that of a coaxial pilot tunnel. It is still remarkable, however,
considering the relatively long distance from the main tunnel
(27 m in the example in Fig. 12). A 3 m diameter pilot tunnel
causes a reduction in the required support pressure by 34–80%
depending on the cohesion of the ground (compare points at
dp = 0 with points at dp = 3 m in Fig. 12). In the case of a weak rock
exhibiting cohesion of 150–200 kPa, for example, the necessary
face support pressure can be reduced to a technically feasible level
of 50–150 kPa by pre-constructing a pilot tunnel of 3–4 m
diameter.
According to Figs. 11 and 12, the drainage effect of a pilot tunnel
is considerable even if its diameter is very small (as is the case with
micro-tunnelling). The form of the s(dp) curves also shows that the
benefit of excavating a larger diameter pilot tunnel is relatively
small. In addition, the stability of the face in a larger diameter pilot
tunnel may itself be problematic. (For small tunnel diameters, drai-
nage measures alone often suffice for stability, even in ground of
low cohesion, cf. Zingg and Anagnostou, 2013.) From the point of
view of face stability, a pilot tunnel of small diameter is therefore
Fig. 10. Required support pressure s as a function of the borehole location rdr clearly preferable.
(borehole locations see inset; parameters according to Fig. 4 and Table 1).

3.4. Drainage action of a pilot tunnel 3.5. Drainage action of the first tube of a twin tunnel

We consider first a pilot tunnel that is coaxial with the main The solid curves in Fig. 13 show the support pressure s required
tunnel. Fig. 11 shows the required face support pressure s as a for face stability of the second tube as a function of its distance L
function of the diameter dp of the pilot tunnel for different values from the first tube. The crosses apply to the tube constructed first.
of the cohesion c. In order to determine the required face support The advance drainage of the ground due to the first tube has a
pressure, failure mechanisms involving the entire face or parts marked effect on the face stability of the second tube even if the

Fig. 11. Required support pressure s as a function of the pilot tunnel diameter dp (inset: the considered failure mechanisms after Zingg et al. (2013); parameters according to
Fig. 4 and Table 1).
56 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 12. Required support pressure s as a function of the diameter dp of an external


pilot tunnel (parameters according to Fig. 4 and Table 1).

distance of the two tubes is relatively large (L = 50–70 m; compare


solid lines with crosses in Fig. 13).
For a typical spacing of Lh = 30 m, the drainage action of the first
tube leads to a reduction in the necessary face support pressure in
the second tube of 44–77% depending on the cohesion of the
ground. The construction of the second tube is, therefore, consider-
ably easier than that of the first tube. Consider, for example, a twin
tunnel in weak rock exhibiting a cohesion c of 200 kPa. Face stabi-
lization in the first tube would require a barely feasible support Fig. 13. Required support pressure s as a function of the centre distance L of two
pressure of more than 200 kPa (point B in Fig. 13), or, alternatively, twin tunnels (parameters according to Fig. 4 and Table 1).
advance drainage by means of boreholes from the face, ground
improvement by grouting or combinations thereof. In the second
tube, however, the face would be stable without any support s
lining) and a permeable lining (e.g. a shotcrete lining with pore
(point C in Fig. 13).
pressure relief holes). In the first case, drainage occurs solely via
It should be noted that the decisive parameter for the drainage
the face of the main tunnel and via the radial boreholes. In the sec-
action of the first tube is the distance L, irrespective of the vertical
ond case, pore pressure relief also occurs due to drainage through
or horizontal offset of the two tubes. This is illustrated by the
the pilot tunnel walls.
dashed lines in Fig. 13, which applies to the theoretical case of ver-
The computations were carried out for 1, 2, 4 or 6 boreholes per
tically arranged tunnel tubes with zero horizontal offset.
curtain; the benefit of a larger number of boreholes per curtain is
marginal (cf. Section 3.3). For any specific number of boreholes
3.6. Effect of drainage curtains from a pilot tunnel per curtain, computations for different borehole arrangements in
the plane of the tunnel cross-section were carried out to identify
Taking into account the results of the previous sections, we con- the one with the lowest necessary support pressure (Zingg et al.,
sider a pilot tunnel of 3 m diameter. The geometric parameters for 2013). The table in Fig. 14 shows the optimum borehole
drainage curtains are: their spacing adr, the number n and the loca- arrangements.
tion of the boreholes of each curtain (Fig. 14). The length and the The diagrams in Fig. 15 apply to the case of a single tunnel
diameter of the boreholes are taken equal to 30 m and 10 cm, (Fig. 14a) and show the distribution of the hydraulic head in the
respectively. Both the case of a single tunnel (Fig. 14a) and that axial direction ahead of the tunnel face for 1, 2, 4 or 6 boreholes
of a twin tunnel will be considered (Fig. 14b). The horizontal and per curtain (diagrams from the top down) and a sealed (l.h.s. dia-
vertical offsets of the pilot tunnel are taken equal to 20 m and grams) or draining (r.h.s. diagrams) pilot tunnel lining. The curves
10 m, respectively, which mean that the drainage curtains reach in every diagram apply to curtain spacings adr = 4–20 m (Fig. 14).
the entire cross section of the main tunnel(s). The diagrams also show for comparison the head distribution
The numerical investigations were carried out for two different without drainage curtains (upper line in every diagram). The
pilot tunnel linings: an impermeable lining (e.g. a sealed segmental hydraulic head is lower in the case of a draining pilot tunnel lining
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 57

Fig. 14. Location of the most effective boreholes (dr1  dr6) of the drainage curtain (after Zingg et al., 2013).

(r.h.s. diagrams), exhibits local minima at the locations of the drai- the following equation, which is sufficiently accurate for practical
nage curtains and decreases with decreasing curtain spacing and design purposes:
with increasing number of boreholes per curtain. It is remarkable  
that just 2 boreholes per curtain spaced at 10 m intervals in
s c c c w h0
¼ F 0  F 1 0 þ F 2  F 3 0 ; ð2Þ
the longitudinal direction suffice to reduce the hydraulic head to c0 D cD c D c0 D
45–60% of its initial value in the vicinity of the face (see red curves
where the dimensionless coefficients F0 to F3 depend only on the
in Fig. 15b and f). Considering the high cost but limited additional
friction angle u and the drainage layout. The coefficients were
benefit of very closely spaced curtains, a spacing of 10 m (i.e. one
determined by means of a comprehensive parametric study and
tunnel diameter) represents a reasonable choice. Fig. 16 shows
can be depicted from the design nomograms of Figs. 17–23. Each
the required support pressure s for this spacing as a function of
figure applies to a different drainage layout; Table 2 provides an
the cohesion c for curtains consisting of 1, 2, 4 or 6 boreholes for
overview. Details of the development of the design Eq. (2), the
an impermeable (Fig. 16a) and a permeable (Fig. 16b) pilot tunnel
determination of the coefficients F0 to F3 and the applicability limits
lining, a single tunnel (black lines) and a twin tunnel (red1 lines).
of the presented nomograms are given in Appendix B.
The difference between single and twin tunnels is small (e.g. for
c = 0: 3–12% for an impermeable, 3–7% for a permeable pilot tunnel
lining). 4.1. Applicability limits of the nomograms
In order to illustrate the significance of these results from the
practical engineering point of view, consider a single tunnel cross- The nomograms assume that T = min(H, Hw) > 5D. This condi-
ing weak rock exhibiting a cohesion of 100–150 kPa. In the absence tion is fulfilled by subaqueous tunnels (Hw > H) with an overburden
of drainage measures, the required support pressure would be H of minimum 5D and by mountain tunnels (Hw < H) at a depth Hw
400–500 kPa (point A in Fig. 16a). This value, which is unfeasible of minimum 5D underneath the water table. For T/D < 5 the nomo-
in conventional tunnelling, can be reduced to a manageable level grams underestimate the support pressure. This can be compen-
(of about 100 kPa) by drainage curtains consisting of 2–4 boreholes sated roughly by increasing the coefficient F2 by 20%. Of course,
each (points B and C, Fig. 16a). In combination with a permeable the nomograms are not applicable where there is no seepage flow.
pilot tunnel lining (Fig. 16b), the drainage curtains would even The nomograms provide an estimate of the required support
allow an unsupported face, and this in spite of the combination pressure that is slightly on the safe side for the practically relevant
of weak ground with high in situ hydrostatic pressure. ranges of cohesion and support pressure (c/c0 D P 0.2, 0 6
s/c0 D 6 4) and up to very high hydraulic heads (cwh0/c0 D 6 30).
The nomograms were developed for a normalized borehole
4. Design equation diameter ddr/D = 0.01, which is typical for usual borehole and traf-
fic tunnel diameters, but they are sufficiently accurate in the range
Provided that the upper boundary of the seepage flow domain is ddr/D = 0.005–0.020, i.e. for most practical purposes.
not too close to the tunnel crown (specifically, that min(H, Hw)
> 5D), the required face support pressure can be approximated by 4.2. Use of the nomograms

1
For interpretation of color in Figs. 15, 16, 26, B2 and B3, the reader is referred to The use of the nomograms is straightforward: choose the appli-
the web version of this article. cable nomogram according to the intended drainage scheme
58 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 15. Axial distribution of the hydraulic head h ahead of the face of the main tunnel (borehole locations according to table in Fig. 14, parameters according to Figs. 2 and 4
and Table 1).
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 59

Fig. 16. Required support pressure s as a function of cohesion c for n = 0–6 drainage boreholes per curtain: (a) impermeable, (b) permeable pilot tunnel lining (borehole
locations according to inset, parameters according to Fig. 4 and Table 1).

(Figs. 17–23); read out the values of the coefficients F0 to F3; and experienced during construction through the so-called rauwacke
calculate the required support pressure s by means of design Eq. formation (Theiler et al., 2013). The latter consists of cellular dolo-
(2). Safety factors can easily be taken into account by using mite, a weak rock exhibiting a porous, sponge-like structure with
reduced shear strength parameters (c, tanu) or a higher hydraulic pore dimensions in the range of millimetres. Close to the boundary
head h0. with the next geological unit, the rauwacke formation contains a
Consider, for example, the problem of Section 3 (Fig. 4) with 6 network of what are probably tubular cavities with fine-grained
axial drainage boreholes drilled from the face (ddr/D = 0.01, ldr/ infillings. The locally almost cohesionless ground in combination
D = 3) and the ground parameters u = 30°, c = 100 kPa, c0 = 12 kN/ with the high water table (initially about 120 m above the align-
m3 and cw = 10 kN/m3. The applicable nomograms are given in ment) resulted in instabilities with several instances of material
Fig. 18. For u = 30° and n = 6, the coefficients are: F0 = 0.15, inrush and tunnel flooding. Overcoming the rauwacke formation,
F1 = 1.9, F2 = 0.21 and F3 = 0.007. Inserting these values in Eq. (2) which was only 110 m long, caused a delay of 11 months in
results in a support pressure of 104 kPa. construction.
The design Eq. (2) can be used in an inverse way to estimate the On account of the previous tunnelling experience, the rauwacke
critical cohesion c (i.e. the cohesion that would render face support formation is also expected to be challenging in the construction of
measures unnecessary). Solving Eq. (2) with respect to c for s = 0 Albula II. According to recent geological investigations, the infill-
results in a critical cohesion of 152 kPa for the example considered. ings of the voids appear – when drained – to be ‘‘a stiff to weak,
If the cohesion is higher than this value, then advance drainage strongly silty sand with some gravel”, but under seepage condi-
would suffice for face stability. tions become flowing slurry (Sieber et al., 2014). Advance drainage
therefore represents a construction option, alone or in combination
with ground improvement by grouting or freezing, provided of
5. Application examples course that the environmental impact of drainage can be accepted.
In the following paragraphs, we investigate the effectiveness of
5.1. Albula tunnel some possible drainage schemes with respect to the stabilization of
the tunnel face by using the design Eq. (2). For this purpose, the
The planned Albula II railway tunnel will run at an axial dis- egg-shaped cross-section of the planned tunnel is approximated
tance of 30 m parallel to the historic Albula I tunnel, a UNESCO by a circular cross-section of same area (44 m2, diameter 7.5 m).
engineering landmark built about 110 years ago in Switzerland The shear strength parameters for the ground depend on
(Fig. 24). Albula I became famous because of the difficulties the degree of disintegration and on the fraction of voids with soft
60 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 17. Nomograms for the coefficients F0 to F3 in the case of drainage via boreholes from the tunnel face (ldr/D = 1.5; variable: number n of boreholes).

infillings. The friction angle u of the rauwacke is in the range of with an inclined slip surface forming an angle of 45°  u/2 = 32.5°
25–30°, while the cohesion amounts to 5–10 kPa for the infillings to the vertical direction (Fig. 25). Where the bolts are sufficiently
and to 500–1000 kPa for the rock (Sieber et al., 2014). The compu- long, the limiting factor for the support force offered by the rein-
tations were carried out assuming overall values representing a forcement is the anchorage length of the bolts inside the wedge
weakly consolidated rauwacke formation with a high fraction of (Anagnostou and Serafeimidis, 2007). For the wedge under consid-
infillings (u = 25°, c = 50 kPa). According to recent measurements, eration, the average anchorage length amounts to about 2.1 m. Tak-
the current piezometric head is about 50 m above the tunnel. ing the diameter db of the grouted bolt boreholes equal to 0.1 m and
Due to the drainage action of Albula I, this value is probably lower the bond strength sm of the grout–ground interface equal to maxi-
than the undisturbed head that prevailed before its construction mum 150–200 kPa, the support pressure offered by the reinforce-
(estimated to 120 m). ment amounts at most to nb  p  db  sm = 100–130 kPa, which is
Table 3 shows the coefficients F0 to F3 as well as the support considerably lower than the necessary support pressure.
pressure s after Eq. (2). Without drainage measures the necessary According to rows 2–4 of Table 3, which apply to the case of
support pressure amounts to 191 kPa (Table 3, row 1). Such high advance drainage via 2–6 boreholes from the tunnel face, four drai-
support pressure is barely feasible with face bolts: Consider, for nage boreholes, each a minimum of 11 m long, would be sufficient
example, a dense face reinforcement consisting of fully grouted to reduce the necessary support pressure to an acceptable level. A
bolts spaced at 1 m (i.e., a bolt density nb of 1 bolt/m2) and a wedge considerable reduction in the necessary support pressure could
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 61

Fig. 18. Nomograms for the coefficients F0 to F3 in the case of drainage via boreholes from the tunnel face (ldr/D = 3; variable: number n of boreholes).

also be achieved by first excavating a 3 m diameter coaxial tunnel geometry underlying the nomograms (smaller tunnel spacing,
(Table 3, row 5). Stabilization of the pilot tunnel’s face would, nev- symmetrically arranged drainage curtains). This was confirmed
ertheless, require advance drainage by at least 8 boreholes by a numerical seepage flow analysis that was carried-out consid-
(Table 3, row 6). ering the actual geometry (Fig. 26). According to Table 3, row 7,
Alternatively, drainage of the ground ahead of the excavation drainage curtains (spaced at 7.5 m and each consisting of six bore-
face of Albula II tunnel could be carried-out by means of about holes) are sufficient for face stability. This solution would thus not
30 m long boreholes from the existing Albula I tunnel (Table 3, only avoid the interference between excavation and drainage work,
row 7). As the latter is lined by a stonework arch, the necessary but also render unnecessary any other stabilization measures. On
support pressure can be estimated with the coefficients F0 to F3 the other hand, the execution of drainage work from the existing
according to Fig. 22 (permeable lining). In the present case, we tunnel would impose constraints on railway operations.
used Fig. 23, which applies to an impermeable lining, because
the drainage effect of the existing tunnel is taken into account by 5.2. Lake Mead Intake No. 3 Tunnel
considering the current piezometric head (50 m) instead of the ini-
tial, undisturbed head. It should be noted that the support pressure The Lake Mead Intake Tunnel No. 3 belongs to Las Vegas’ water
computation with the nomograms in Fig. 23 is sufficiently accurate supply scheme. It is 4.7 km long and has a diameter of 7.22 m.
in spite of the differences between the actual geometry and the Tunnel excavation was recently completed using a convertible
62 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 19. Nomograms for the coefficients F0 to F3 in the case of drainage via boreholes from the tunnel face (n = 6; variable: borehole location rdr/D).

hybrid TBM capable of boring in open mode or in closed mode as a zone subparallel to the tunnel (Anagnostou, 2014). The fault, con-
slurry shield (McDonald and Burger, 2009). The ground consists of sisting of almost cohesionless material, made it necessary to oper-
metamorphic and tertiary sedimentary rocks (conglomerates, ate in closed mode at 14 bar for several hundred metres. Attempts
breccias, sandstones, siltstones and mudstones of very variable to bring the slurry pressure below the hydrostatic pressure
quality) with several fault zones probably recharged directly from resulted in extremely high, barely manageable quantities of water
the lake (Fig. 27). The maximum hydrostatic pressure amounts to inflow (up to 1100 m3/h, Nicola et al., 2014). Advance drainage
about 14 bar. Due to the lack of experience with closed-mode oper- under such conditions was ineffective.
ation under such high pressures and the very poor local ground The sedimentary rocks exhibited a medium-low permeability
quality, it was necessary to design face stabilisation measures such (106–1010 m/s) and proved sufficiently stable at least in short
as advance drainage and pre-excavation grouting that would allow term. The TBM was operated mainly in open mode in combination
for open mode operation. with 3 boreholes drilled through the cutter head for advance prob-
In the first part of the alignment through metamorphic rocks, ing and drainage. The boreholes were 30–45 m long and over-
considerable difficulties were encountered due to the unfavourable lapped by 10 m. In order to ensure stability during longer
combination of high water pressure, extremely high rock perme- standstills (of more than two days), 2–3 additional boreholes of
ability (104–105 m/s) and the presence of an unexpected fault at least 10 m were drilled.
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 63

Fig. 20. Nomograms for the coefficients F0 to F3 in the case of drainage via a co-axial pilot tunnel (variable: normalized pilot tunnel diameter dp/D).

The advance drainage in the Lake Mead tunnel has considerably numerical seepage flow analysis taking account of the additional
widened the feasibility range of open mode TBM drives and atmo- seepage face around the shield); (c) from the tunnel face and from
spheric interventions in the working chamber for inspection and four advance drainage boreholes (based on the nomograms in
maintenance. Related studies can be found elsewhere Fig. 18); (d) from the tunnel face, the shield area and four advance
(Anagnostou et al., 2010, 2014). Here, we focus on one peculiarity drainage boreholes (based on a numerical seepage flow analysis
of shielded TBMs in order to show a limitation of the proposed taking account of the additional seepage face around the shield
design nomograms. In a shielded TBM, water inflows occur not as well as the exact locations, length and diameter of the boreholes
only from the tunnel face and the drainage boreholes, but also from according to the inset in Fig. 28).
the rock around the shield. The shield of the Lake Mead TBM is Without the boreholes, drainage through the additional seepage
14.87 m long, which means that the total area of the seepage face face around the shield reduces the necessary support pressure by
is 337 m2 larger than the tunnel face (41 m2). As larger seepage about 200 kPa or, for the given support pressure, the necessary
face areas obviously favour pore pressure relief, the question arises cohesion by about 100 kPa (compare a to b in Fig. 28). In the case
as to how much the nomograms (which assume no flow through of advance drainage by 4 boreholes, disregarding the drainage in
the tunnel periphery) underestimate stability in such cases. the shield area overestimates the necessary support pressure and
Fig. 28 shows the relationship between the necessary support cohesion by about 125 kPa and 60 kPa, respectively (compare c
pressure s and the cohesion c for the following drainage cases: to d in Fig. 28). This example shows that the nomograms should
(a) from the tunnel face only (based on the nomograms in be used with care where the seepage flow conditions are very
Fig. 18); (b) from the tunnel face and the shield area (based on a different from the ones assumed by the nomograms.
64 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 21. Nomograms for the coefficients F0 to F3 in the case of drainage via the first tube of a twin tunnel (variable: centre distance Lh/D).

6. Conclusions

Table 2 Advance drainage greatly improves tunnel face stability


Drainage layouts and belonging design nomograms. because it reduces pore pressures and their gradients in the ground
Drainage layout Nomogram ahead of the face. This study quantifies the effects of various
None (only drainage action of the tunnel face) Fig. 17 (n = 0)
advance drainage schemes by means of limit equilibrium computa-
Axis-parallel, short boreholes through the tunnel Fig. 17 tions which take account of the steady-state, three-dimensional
face (ldr/D = 1.5) seepage flow conditions prevailing in a homogenously permeable
Axis-parallel, long boreholes through the tunnel Fig. 18 ground.
face (ldr/D = 3)
Four to six drainage boreholes (from the tunnel face or a niche)
Axis-parallel boreholes from niches Fig. 19
Co-axial pilot tunnel Fig. 20 with a minimum length of one and a half tunnel diameters will
First tube of twin tunnel Fig. 21 generally be enough to reduce the necessary face support pressure
External pilot tunnel with permeable lining Fig. 22 (n = 0) significantly or even to render support unnecessary. The marginal
Radial boreholes from external pilot tunnel with Fig. 22 utility of advance drainage diminishes for more or longer bore-
permeable lining
Radial boreholes from external pilot tunnel with Fig. 23
holes. The boreholes are more effective if they are located in the
impermeable lining upper part and close to the periphery of the tunnel cross section,
but their exact positioning (roof or lateral) is not so important.
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 65

Table 3
Coefficients F0 to F3 and resulting support pressure s for the application example Albula.

Drainage layout F0 F1 F2 F3 s [kPa]


1 None (Fig. 17, n = 0) 0.134 2.241 0.552 0.014 191
2 2 axis-parallel boreholes through the face (Fig. 17, n = 2, ldr = 11.3 m) 0.154 2.145 0.377 0.016 103
3 4 axis-parallel boreholes through the face (Fig. 17, n = 4, ldr = 11.3 m) 0.189 2.218 0.292 0.016 57
4 6 axis-parallel boreholes through the face (Fig. 17, n = 6, ldr = 11.3 m) 0.199 2.251 0.268 0.013 43
5 Co-axial pilot tunnel of 3 m diameter (Fig. 20) 0.177 2.231 0.244 0.001 20
6 Face of 3 m diameter pilot tunnel dp (Fig. 17, n = 8, ldr = 1.5dp = 4.5 m) 0.216 2.331 0.232 0.008 4
7 Drainage curtains spaced at 7.5 m, each having 6 boreholes, executed from Albula I (Fig. 23) 0.190 2.391 0.191 0.005 0

Fig. 22. Nomograms for the coefficients F0 to F3 in the case of drainage via drainage curtains from an external pilot tunnel with permeable boundary (variable: number n of
drainage boreholes).
66 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Fig. 23. Nomograms for the coefficients F0 to F3 in the case of drainage via drainage curtains from an external pilot tunnel with impermeable boundary (variable: number n of
drainage boreholes).

The drainage effect of a pilot tunnel (located either inside or options rapidly, thus providing a very valuable design aid. The
outside the main tunnel cross-section) is also considerable. Even coefficients that appear in this equation depend on the friction
a very small diameter coaxial pilot tunnel brings so much pore angle and the geometric parameters for the drainage layout. They
pressure relief that the face of the main tunnel may be stable with- can be depicted using the dimensionless nomograms worked out
out additional auxiliary measures. Sparsely arranged drainage cur- by analysing the computational results of a comprehensive para-
tains (e.g. spaced at about one diameter intervals along the tunnel metric study incorporating a wide parameter range and several
and consisting of two to four drainage boreholes each) improve the advance drainage schemes.
drainage effectiveness of adjacent tunnels.
In the case of twin tunnels, the drainage action of the first tube Acknowledgements
is important with respect to face stability of the second tube, even
if the distance of the two tubes is relatively large (4–7 tunnel This paper evolved within the framework of the research
diameters). project ‘‘Static effects, feasibility and execution of drainages in
A design equation has been developed which makes it possible tunnelling”. The support given to this project by the Swiss Tun-
to assess the stabilizing effect of drainage and study the various nelling Society (STS) and the Federal Road Office of Switzerland
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 67

Fig. 24. Problem layout of application example Albula.

Fig. 26. Axonometric projection of the hydraulic head field of application example
(FEDRO) is greatly appreciated. The authors thank the reviewers for Albula in the presence of drainage curtains.

their valuable comments.

Appendix A. Support pressure

The mechanism considered approximates the circular tunnel


face by a square having the same centre point and an equal area,
i.e. its side length D0 = vD, where v = 0.5p0.5 = 0.89 (Fig. 2). Over-
scores denote normalized variables. Cohesion and all pressures
are normalized by c0 D, where c0 denotes the submerged unit
weight of the ground. Lengths are normalized by the tunnel diam-
eter D, with the exception of h0 (= 0.5D + Hw), which is normalized
as follows: h  0 ¼ c ð0:5 þ H
 w Þ=c0 .
w Fig. 27. Geological profile of the Lake Mead Intake No 3 tunnel (after Feroz et al.,
2007).
A.1. Limit equilibrium

The required support force Sx for a given angle x is obtained by N0 ¼ ðG0 þ V 0  W 3 Þ sin x þ ðSx þ W 1 Þ cos x; ð5Þ
considering the limit equilibrium of the wedge. The latter is acted
upon by the following forces: its submerged weight G0 (= 0.5c0 v3D3 T I þ T V ¼ ðG0 þ V 0  W 3 Þ cos x  ðSx þ W 1 Þ sin x: ð6Þ
tanx); the vertical load V0 of the prism (= v2D2rv0 tanx, where r0 v 0
Eliminating TI and N from the last three equations leads to the fol-
denotes the effective silo pressure); the resultant seepage forces
lowing expression for the required support force:
W1 and W3; the unknown support force Sx; the unknown effective
normal force N0 on the inclined slip plane; the shear resistance TV of W 3 þ G0 þ V 0 T V þ ðvDÞ2 c= cos x
the two lateral vertical slip planes of the wedge, which according Sx ¼ W 1 þ  : ð7Þ
tanðu þ xÞ ðtan u þ tan xÞ cos x
to Anagnostou and Kovári (1994) reads as follows for kw = 0.5:

T V ¼ ðvDÞ2 tan xðc þ tan uðvDc0 =6 þ r0v =3ÞÞ; ð3Þ A.2. Seepage forces
and the shear resistance TI of the inclined slip plane of the wedge
By making use of Gauss’ theorem, the seepage forces Wk acting
according to the Mohr-Coulomb failure criterion:
upon the wedge can be calculated by means of surface integrals:
T I ¼ ðvDÞ2 c= cos x þ N0 tan u: ð4Þ Z Z
@h
Wk ¼  cw dV ¼ cw nk hdS; ð8Þ
The equilibrium conditions normal and parallel to the sliding V @xk S
direction are:
where h denotes the hydraulic head field; nk is the unit normal vec-
tor of the wedge surface; and cw is the unit weight of the water.
Taking into account that n1 = 0 over the boundaries KON, LMP and
MNOP (Fig. 2c), n1 = 1 over KNML, n1 = cosx over KLPO, n3 = 0 over
KON, LMP and KNML, n3 = 1 over NOPM and n3 = sinx over KLPO,
the resultant seepage forces in the axial and vertical directions (W1
and W3, respectively) read as follows (W2 = 0 due to symmetry):

W 1 ¼ cw h0 D2 cos xI1 ; ð9Þ

W 3 ¼ cw h0 D2 ðI3  I1 sin xÞ; ð10Þ


Fig. 25. Estimate of the support pressure provided by face reinforcement: (a) actual
tunnel cross-section; (b) equivalent square cross-section; (c) geometry of the where h0 is the depth of the tunnel axis underneath the water table
wedge in longitudinal section. (h0 = D/2 + Hw) and Ik represents dimensionless coefficients:
68 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

Table B1
Geotechnical conditions considered in working out the design nomograms.

Problem layout
a
Depth of cover H/D 10
Hydraulic head cwh0/c0 D 0–25.5
b

Ground
Effective cohesion c/c0 D 0–4
c

Angle of effective internal friction u 15–40°


Submerged unit weight c0 /cw 1.2
d

e
Dry unit weight cd/cw 1.7

Coefficients of lateral stress


Wedge kw 0.5
Prism kp 1.0

a
The results are applicable for T/D > 5 (Section 4, Appendix B).
b
The results are applicable for 0.5 6 cwh0/c0 D 6 35 (Fig. B2).
c
The results are applicable for c/c0 D P 0.2 (Section 3.2, Appendix B).
d
The results are sufficiently accurate for 1 6 c0 /cw 6 1.8.
e
This parameter is irrelevant for T/D > 5 (Appendix B).

r  c
r 0v e ¼ ð1  es Þ; ð14Þ
tan u
where
tan u 
es ¼ e r ðTþ0:5ð1 vÞÞ
; ð15Þ
r is the ratio of the area to the circumference of the horizontal cross-
section of the prism,

r ¼ 0:5vD tan xð1 þ tan xÞ1 ; ð16Þ


and T denotes the height of the prism part underneath the water
table:
T ¼ minðH; Hw Þ: ð17Þ
The second r.h.s. term of Eq. (13) takes into account that the
ground above the water table exerts the load

Fig. 28. Lake Mead Intake No 3 tunnel, Ch. 12+60 (point A): Support pressure s as a d  c
r c
r 0v T ¼ ð1  ed Þ; ð18Þ
function of the cohesion c. tan u

Z Z  d (=cd/c0 ) is the normalized dry


0:5v= cos x 0:5v
h  on the underlying prism, where c
I1 ¼ x ¼ ð0:5v tan x þ f sin xÞD dn2 df; ð11Þ unit weight of the ground and
0:5v= cos x 0:5v h0 1
x2 ¼ n 2 D tan u  
ed ¼ e r ðHH w Þ : ð19Þ
x3 ¼ f cos xD
Z v tan x Z  This load increases the silo pressure at the top of the wedge by
h 
0:5v
I3 ¼  x1 ¼ n1 D dn2 dn1 ; ð12Þ r0v d ¼ r0v T es : ð20Þ
0 0:5v h0
x2 ¼ n 2 D This term does not apply if the tunnel is subaqueous (Hw P H) or
x3 ¼ 0:5vD
d :
c > clim;d ¼ r c ð21Þ
where the normalized coordinates nk = xk/D.
In the latter case, Eq. (18) yields a negative pressure, which means
A.3. Silo pressure that the prismatic body above the water table is stable without sup-
port by the underlying prism. Consequently, the following may be
The effective vertical pressure r0 v exerted by the prism upon the written:
wedge (Fig. 2) can be expressed as follows (Anagnostou and Kovári, d  c
r c
1996):
r 0v d ¼ dd ð1  ed Þes ; ð22Þ
tan u
r0v ¼ r0v e þ r0v d þ r0v s ; ð13Þ where
0
where r v e is the contribution of the ground underneath the water 
1; if c < clim;d ^ Hw < H;
table in the case of hydraulic equilibrium; r0 v d represents the dd ¼ ð23Þ
0; if c P clim;d _ Hw P H:
contribution of the ground above the water table; and r0 v s is the
contribution of the seepage flow. The contribution of the seepage flow (third r.h.s. term of Eq.
The first r.h.s. term of Eq. (13) is obtained by applying silo- (13)) is determined based upon equation 19 of Anagnostou and
theory to the part of the prism underneath the water table. For Kovári (1996):
kp = 1,
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 69

Table B2
Parameters for the drainage schemes considered in working out the design nomograms.

Drainage measures n rdr/D ldr/D dp/D Lh/D Lv/D adr/D Nomograms for F0 to F3
None (only natural drainage action of the tunnel face) 0 Fig. 17 (n = 0)
Axis-parallel boreholesa through the tunnel face or niches 2–10 0.38 1.5 Fig. 17
2–10 0.38 3 Fig. 18
6 0.38, 0.67 3 Fig. 19
Co-axial pilot tunnel 0 0.05–0.5 Fig. 20
First tube of twin tunnel 0 1.4–5.5 0 Fig. 21
External pilot tunnel with permeable lining 0 0.3 2 1 Fig. 22 (n = 0)
Radial boreholesb from external pilot tunnel with permeable lining 1–6 3 0.3 2 1 1 Fig. 22
Radial boreholesb from external pilot tunnel with impermeable lining 1–6 3 0.3 2 1 1 Fig. 23
a
Borehole diameter: ddr/D = 0.01; Borehole location: see Fig. 6.
b
Borehole diameter: ddr/D = 0.01; Borehole location: see Fig. 14.

Fig. B1. Illustration of the curve-fitting procedure (u = 30°; 4 drainage boreholes of length ldr = 3D with locations according to Fig. 6): (a) exact and approximate normalized
support pressure s as a function of the normalized hydraulic head h 0 ; (b) coefficient a (Eq. (42)) and, (c), coefficient b (Eq. (43)) as a function of the cohesion c.

Z !
0 tan u 0:5DþT

tan u x3 where the dimensionless coefficient
rv s ¼ cw h0 es  hav ð0:5vDÞ þ hav ðx3 Þe r ð D 0:5 vÞ
dx3 ;
r R v tan x R 0:5v 
0:5Dv h
Is ¼ es  v2 tan
1
x 0 0:5v h0  x1 ¼ n1 D dn2 dn1 þ
ð24Þ
x2 ¼ n2 D
where hav ðx3 Þ is the average piezometric head over the horizontal x3 ¼ 0:5vD
cross-section of the prism at elevation x3: tan u
R 0:5þT tan uðn 0:5vÞ R v tan x R 0:5v h 
Z Dv tan x Z 0:5Dv r
1
v2 tan x 0:5v
e r 3 0 0:5v h0 x1 ¼ n1 D
dn2 dn1 dn3 :
1
hav ðx3 Þ ¼ hdx2 dx1 : ð25Þ x2 ¼ n2 D
v2 D2 tan x 0 0:5Dv
x3 ¼ n3 D
Introducing Eqs. (25) into (24) we obtain: ð27Þ
c w h0  ;
r 0v s ¼ I ¼I h ð26Þ It can readily be verified that if the cohesion is sufficiently high,
c0 D s s 0 then Eq. (13) yields a negative silo pressure, which means that
70 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

the prism would be stable without support by the underlying parameters can be reduced by two (cd and H disappear from the
wedge. In this case, the silo pressure should be taken equal to zero. parameter list) if the upper boundary of the seepage flow domain
The limit cohesion is obtained from Eq. (13) (with r0v ¼ 0 and the r. is not too close to the tunnel crown (specifically, if T > 5D); and,
h.s. terms after Eqs. (14), (22) and (26)) with respect to c: (ii), an approximate linearized relationship can be considered
0 Is instead of Eq. (31), which is sufficiently accurate for practical design
d ð1  ed Þes Þr þ tan uh
ð1  es þ dd c
clim;s ¼ : ð28Þ purposes.
1  es þ dd ð1  ed Þes
In conclusion, based upon Eqs. (13), (14), (22) and (26), the silo B.1. Reduction in the number of parameters in the case of T > 5D
pressure is
  As T = min(H, Hw), the condition T > 5D is fulfilled by subaque-
d ð1  ed Þes Þ 1  es þ dd ð1  ed Þes
r ð1  es þ dd c 0 ;
r 0v ¼ ds  c þ Is h ous tunnels with an overburden of at least 5D and by mountain
tan u tan u tunnels at a depth of minimum 5D underneath the water table.
ð29Þ The coefficient es (Eq. (15)) decreases rapidly with increasing
where values of T and becomes practically zero for T/D > 5 even if the fric-
 tion angle is small and the wedge angle x big. For es = 0, the coef-
1; if c < clim;d ; ficients become Ncx = f(x, u, ds), Ncx = f(x, u, ds) and Nhx = f(x, u,
ds ¼ ð30Þ
0; if c P clim;d :  0 ; Is Þ
ds, I1, I3, Is) according to Eqs. (32)–(34), where ds ¼ f ðx; u; c; h
according to Eqs. (28) and (30).
The coefficients I1, I3 and Is appearing in these equations depend
A.4. Support pressure
on the hydraulic head field and, therefore, on the geometric param-
eters of the seepage flow domain (tunnel diameter D, distance T
Introducing Tv, Wk, r0 v (Eqs. (3), (9), (10) and (29)) into Eq. (7)
between tunnel crown and upper boundary of the seepage flow
results in the following expression for the normalized support
domain, location, length and diameter of the drainage boreholes)
pressure:
and on the hydraulic boundary conditions. At the far field bound-
0 ;
sx ¼ Ncx  Ncx c þ Nhx h ð31Þ aries and at x3 = T + D/2, the hydraulic head is equal to h0. At the
tunnel face and along the drainage boreholes, the pore pressure
where Ncx, Ncx and Nhx are dimensionless coefficients: is atmospheric and, consequently, the hydraulic head is equal to
 
v d
1  es þ dd ð1  ed Þes c the elevation x3, which varies between 0.5D (tunnel floor) and
Ncx ¼ K þ ds r ; ð32Þ
2 tan u 0.5D (tunnel crown), i.e. jhj 6 0:5D. If T > 5D, the effect of this vari-
cos uð1 þ sin xÞ 1  es þ dd ð1  ed Þes ation is small relative to h0 (= 0.5D+Hw > 5.5D) and, consequently,
N cx ¼ þ ds K ; ð33Þ the head at the face and along the borehole walls can be taken
cos x sinðu þ xÞ tan u
approximately equal to zero. The hydraulic head field then
sin u 1 depends linearly on the boundary value h0 (due to the linearity
N hx ¼ I þ I þ d KI ; ð34Þ
v2 sinðu þ xÞ 1 v2 tanðu þ xÞ 3 s s of Darcy’s law). In addition, the size of the seepage flow domain
above the crown (T) is practically negligible for the head distribu-
with tion if it is more than a few tunnel diameters (Anagnostou and
  Kovári, 1996; Zingg and Anagnostou, 2012).
tan x sin u
K¼ 1 ð35Þ Consequently, if T/D > 5, the hydraulic head at every point xk
tanðu þ xÞ 3 cosðu þ xÞ
may be expressed in general as h ffi h0 f ðnk Þ, which means that the
and r , es, ed, ds, dd, I1, I3 and Is according to Eqs. (16), (15), (19), (30), dimensionless coefficients I1 and I2 depend only on the angle x
(23), (11), (12) and (27), respectively. The hydraulic head field, (see Eqs. (11) and (12)), while Is depends additionally on u and
which is needed for the computation of the last three coefficients, on T/D (Eq. (27)). The latter appears in the upper integration bound
is determined by a numerical seepage flow analysis. of the third r.h.s. term of Eq. (27), but is practically irrelevant if
T/D > 5 because of the rapid decay of the exponential term of the
Appendix B. Design equation and nomograms integrand.
Consequently, for given drainage layout, the critical angle xcr as
The starting point for developing a relatively simple design well as the coefficients N , N and N are functions of u, c and h 0
c c h
equation and working out design nomograms is the rigorous Eq. (see Fig. 8 and B2 for an example illustrating the dependency of
(31). The latter gives the support pressure sx for a specific value xcr on c and h0):
of the angle x. The critical support pressure s is obtained by max-
0 Þ  Nc ðu; c; h
s ¼ Nc ðu; c; h 0 Þc þ N ðu; c; h
 0 Þh
0 : ð38Þ
imizing sx with respect to x: h

0 ;
s ¼ Nc  N c c þ Nh h ð36Þ According to this equation, the support pressure depends non-
linearly on the cohesion c and on the hydraulic head h0. The non-
where Nc = Ncx(xcr, . . .), Nc = Ncx(xcr, . . .), Nh = Nhx(xcr, . . .) and xcr linearity is negligible in the absence of seepage flow (h0 = 0), but
is obtained by solving the non-linear equation significant when considering a wide range of hydraulic heads h0.
  
dN  
0 dNhx  dN cx 
c cx  h  ¼ : ð37Þ
dx x¼xcr dx x¼xcr dx x¼xcr B.2. Linearization

An examination of Eqs. (32) to (34) and (37) shows that the critical In order to find out whether the functional dependencies of
angle xcr as well as the coefficients Nc, Nc and Nh depend not only Eq. (38) can be simplified to a degree that would allow this equation
on the drainage layout and on u; c d and H, 0 ,
 but also on c and h to be applied in combination with the smallest possible number
which means that the support pressure s depends non-linearly on c of nomograms depicting its r.h.s. coefficients, we analysed the
0 . This in combination with the large number of influencing
and h computational results of a comprehensive parametric study.
parameters renders the elaboration of design nomograms practically Tables B1 and B2 summarize the value ranges considered for
impossible. However, it will be shown below that: (i), the number of the ground and drainage parameters, respectively. The geometric
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 71

parameters for the drainage schemes were chosen in accordance conservatively in order for the proposed design equation to pro-
with the results of Section 3. vide an estimate of the required support pressure that is slightly
Analysis of the computational results showed that they can be on the safe side for the practically relevant ranges of cohesion
approximated sufficiently accurately by the following equation, and support pressure (c > 0:2; 0 6 s 6 4) and up to very high
which maintains the structure of the rigorous Eq. (38), but is linear hydraulic head ðh  0 6 25Þ. A normalized support pressure s of 4
in c and h0. clearly corresponds to extremely heavy face reinforcement, while
face stability in a ground with a normalized cohesion c lower
0
s ¼ F 0 ðuÞ  F 1 ðuÞc þ ðF 2 ðuÞ  F 3 ðuÞcÞh ð39Þ than 0.2 would anyway require additional improvement mea-
sures such as grouting.
According to this equation, the coefficients F0 and F1, which corre- Fig. B1 illustrates the principle of curve fitting. The solid curves
spond to the coefficients Nc and Nc of Eq. (38), can be taken as func- show the exact normalized support pressure s as a function of the
tions only of the friction angle u for a given drainage layout, i.e. the 0 for different values of the normal-
normalized hydraulic head h
dependency of Nc and Nc on c and h0 can be neglected. As can be
ized cohesion c; a fixed value of the friction angle (u = 30°) and a
seen from the last bracketed r.h.s. term, which corresponds to Nh,
given drainage layout (n = 4 as in Fig. 6). Within the considered
the dependency of Nh on c can be linearized, while the effect of h0 0 6 25; indicated with dotted lines), s depends
range (s 6 4; h
can be neglected. The coefficients F2 and F3 thus depend only on
almost linearly on h 0 :
the friction angle and on the drainage layout.
The coefficients F0 to F3 were determined by fitting Eq. (39)
0 ;
s ffi a þ bh ð40Þ
to the results of a parametric study. Their values were chosen

0 and of the normalized cohesion c for advance drainage,


Fig. B2. Exact and approximate normalized support pressure s as a function of the normalized initial hydraulic head h
(a), via boreholes from the face or, (b), a co-axial pilot tunnel.
72 S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73

where Eq. (39) can be compensated by increasing the coefficient F2 by


8 4sjh ¼0 about 15% (see marked points in the diagrams in Fig. B2). The cor-
>
> a ¼ sjh0 ¼0 ; b ¼ h 0 ; if sjh0 ¼0 P 0; rection is satisfactory even for c ¼ 0 or very high hydraulic heads
>
> 0 js¼4
>
>  0 > 25). Several comparative computations with n = 2–10 bore-
< (h
a ¼  h j 0jsh¼0j ; b ¼ h j 4 h j ; if sjh0 ¼0 < 0 and sjh0 ¼25 > 4;
4h

> holes (drainage layout in Fig. 18) showed that increasing the
>
>
0 s¼4 0 s¼0 0 s¼4 0 s¼0

>
>  j coefficient F2 by 10–20% (more specifically: 9% for n = 2, 12% for
sjh ¼0 < 0 and s
sjh ¼25 h sjh ¼25
>
: a ¼  0  s¼0 ; b ¼ 0
0
; if < 4:
25h0 j 25h0 j 0  ¼25 n = 4–6, 14% for n = 8–10) also makes it possible to assess face
s¼0 s¼0 h 0
stability for T/D < 5. As indicated by the results in Fig. B2b, this rule
ð41Þ
of thumb also applies to the other drainage layouts.
Fig. B1b and c show the coefficients a and b, respectively, as functions The nomograms were developed for a normalized borehole
of the normalized cohesion c. They depend practically linearly on c: diameter ddr/D = 0.01. This assumption is adequate for typical
cross-sections of traffic tunnels and typical diameters of drainage
a ffi F 0  F 1 c; ð42Þ
boreholes (about 10 m and 10 cm, respectively), but leads to an
under- or overestimation of the effects of advance drainage (and
b ffi F 2  F 3 c; ð43Þ
thus to an over- or underestimation of the necessary support pres-
where F0 to F3 can be determined by linear regression. As the sðh 0 Þ sure) in the case of smaller or larger tunnel cross-sections.
curves in Fig. B1a are nearly parallel, their slopes b are almost equal In order to quantify the error arising with normalized borehole
(F3 is small), while their intercept a with the vertical axis depends diameters other than ddr/D = 0.01, the example of a tunnel with
markedly on the normalized cohesion c. Eqs. (40), (42) and (43) advance drainage via 6 boreholes is considered (see inset in
result in the approximate design Eq. (39), which is represented by Fig. B3). The red solid line in the diagram in Fig. B3 shows the
the dashed lines in Fig. B1a. required support pressure as a function of the cohesion under
The linear approximation in Fig. B1a slightly overestimates the the nomograms. The black lines show the exact results for several
support pressure inside the range considered and may underesti- values of the normalized borehole diameter ddr/D. If the ratio ddr/D
mate the support pressure outside this range (i.e. at hydraulic is extremely large (0.05, which would apply, e.g., to a very small
heads that are either higher than the head that necessitates a nor- tunnel diameter of 2 m and borehole diameter of 0.1 m), then the
malized support pressure of 4, or lower than the head, where the nomograms overestimate the necessary support pressure by up
necessary support pressure becomes equal to zero). This is, how- to 0.5c0 D (compare points D and B in Fig. B3). However, the error
ever, irrelevant from a practical point of view. At hydraulic heads soon becomes very small for ddr/D = 0.02 (maximum 0.2c0 D). On

above the range considered (i.e. for h 0 > h0  ) the approximate
s¼4
support pressure is anyway higher than 4, thus indicating that
advance drainage is insufficient for stability without ground
improvement (remember that a normalized support pressure s of
4 corresponds to a very heavy face support). On the other hand,

0 < h
for h 0 
s¼0 the exact support pressure will be ‘‘less” negative,
but still negative, i.e. the face will anyway be stable without
support.

B.3. Design nomograms

As Fig. B1 applies to a specific drainage layout and a specific


value of the friction angle, the coefficients F0 to F3 also depend
on u and on the drainage layout. They are given in Figs. 17–23,
each applying to a different drainage layout (see last column of
Table B2 for an overview).

B.4. Applicability limits of the nomograms

Due to the underlying fitting procedure, the nomograms are not


applicable where there is no seepage flow. In addition as men-
tioned above, Eq. (38) presupposes that the upper boundary of
the seepage flow domain is not too close to the tunnel crown. If
T/D < 5, the hydraulic gradients will be higher than those in the
nomograms, which will then consequently underestimate the nec-
essary support pressure. The greater the drainage-induced pore
pressure relief (i.e. the lower the factor F2), the greater will be
the error.
In order to quantify the error, a shallow tunnel (T/D = 1.85) is
considered with advance drainage either from the face (via 6 bore-
holes, see inset in Fig. B2a) or via a co-axial pilot tunnel (Fig. B2b).
The black lines in the diagrams in Fig. B2 show the exact support
pressure s as a function of the initial hydraulic head h0 and the
cohesion c. The red lines were obtained from the design Eq. (39)
using the coefficients F0 to F3 according to Figs. 18 and 20. The dif-
ference between the exact and the approximate support pressure Fig. B3. Exact and approximate normalized support pressure s as a function of the
clearly increases with the hydraulic head. The error of design normalized cohesion c and of the normalized borehole diameter ddr/D.
S. Zingg, G. Anagnostou / Tunnelling and Underground Space Technology 58 (2016) 49–73 73

the other hand, if the ratio ddr/D is smaller than the one assumed Höfle, R., Fillibeck, J., 2007. Time dependent deformation and stability of tunnel
faces in fine-grained soils under groundwater. In: Eberhardsteiner, E. (Ed.),
by the nomograms, then they will slightly underestimate the nec-
ECCOMAS Thematic Conference on Computational Methods in Tunnelling
essary support pressure (by less than 4% in the case of ddr/ (EURO:Tun 2007), Vienna.
D = 0.005, see points A and B in Fig. B3). In conclusion, the accuracy Lee, I.-M., Nam, S.-W., 2001. The study of seepage forces acting on the tunnel lining
of the approximate design Eq. (39) is acceptable in the range ddr/ and tunnel face in shallow tunnels. Tunn. Undergr. Space Technol. 16, 31–40.
Lee, I.-M., Nam, S.-W., Ahn, J.-H., 2003. Effect of seepage forces on tunnel face
D = 0.005  0.02, i.e. for most practical purposes (a borehole diam- stability. Can. Geotech. J. 40, 342–350.
eter of 10 cm and tunnel diameters of 5–15 m). Mair, R.J., 2008. Tunnelling and geotechnics: new horizons. Géotechnique 58 (9),
713–720.
McDonald, J., Burger, W., 2009. Lake-Mead-Zulauftunnel Nr. 3. Tunnel 4, 43–48.
References Nicola, A., Nickerson, J., Bono, R., Donadoni, N., Anagnostou, G., Schürch, R., Zingg, S.,
2014. Lake Mead Intake Tunnel No. 3 – A step beyond the limits, Swiss Tunnel
Anagnostou, G., 2012. The contribution of horizontal arching to tunnel face stability. Congress, Lucerne, pp. 166–173.
Geotechnik 35, 34–44. Nilsen, B., 1999. Key factors determining stability and water leakage of hard rock
Anagnostou, G., 2014. Some critical aspects of subaqueous tunnelling. In: ITA-AITES subsea tunnel. In: Amadei, Kranz, Scott, Smeallie (Eds.), Rock Mechanics for
World Tunnel Congress (WTC2014). Muir Wood Lecture, Brazil, pp. 1–20. Industry. Balkema, Rotterdam, pp. 593–599.
Anagnostou, G., Cantieni, L., Nicola, A., Ramoni, M., 2010. Face stability assessment Nilsen, B., 2011. Cases of instability caused by weakness zones in Norwegian
for the Lake Mead Intake No 3 Tunnel, Tunnel Vision Towards 2020, ITA-AITES tunnels. Bull. Eng. Geol. Environ. 70, 7–13.
World Tunnel Congress (WTC2010), Vancouver. Nilsen, B., Palmström, A., 2001. Stability and water leakage of hard rock subsea
Anagnostou, G., Kovári, K., 1994. The face stability of slurry-shield driven tunnels. tunnels. In: Adachi, T., Tateyama, K., Kimura, M. (Eds.), Modern Tunneling
Tunn. Undergr. Space Technol. 9 (2), 165–174. Science and Technology. Swets & Zeitlinger, Kyoto, pp. 497–502.
Anagnostou, G., Kovári, K., 1996. Face stability conditions with Earth Pressure Pellet, F., Descoeudres, F., Egger, P., 1993. The effect of water seepage forces on the
Balanced shields. Tunn. Undergr. Space Technol. 11 (2), 165–173. face stability of an experimental mircotunnel. Can. Geotech. J. 30, 363–369.
Anagnostou, G., Schuerch, R., Ramoni, M., 2014. TBM tunnelling in complex rock Perazzelli, P., Leone, T., Anagnostou, G., 2014. Tunnel face stability under seepage
formations. XV MIR Conference ‘‘Interventi e opere nelle formazioni flow conditions. Tunn. Undergr. Space Technol. 43, 459–469.
complesse”, Torino, 307–331. Sellner, P., Janotta, M., Koinig, J., 2008. Systematic drainage measures in the tunnel
Anagnostou, G., Serafeimidis, K., 2007. The dimensioning of tunnel face construction – experiences in the Neogene Sections of the Investigation Tunnels
reinforcement, Underground Space – the 4th Dimension of Metropolises. In: for the Koralm Tunnel. Geomechanik und Tunnelbau 1, 287–293.
ITA-AITES World Tunnel Congress (WTC2007), Prague, pp. 291–296. Sieber Cassina und Handke AG, IG PV Alvra, 2014. Neubau Albulatunnel II,
Anagnostou, G., Zingg, S., 2013. On the stabilizing effect of advance drainage in Bauprojekt Raibler-Formation, Aufschlüsse und Färbversuche Albulatunnel I
tunnelling. Geomech. Tunnell. 6, 338–354. vom 22.07.2014 (not published).
Broere, W., 2001. Tunnel face stability & new CPT applications. In: Civil Engineering. Ströhle, P., Vermeer, P.A., 2009. Die Stabilität der Ortsbrust bei strömendem
Technische Universiteit Delft, Delft, p. 208. Grundwasser, Kolloquium Bauen in Boden und Fels. In: TAE, Ostfildern 2010,
de Buhan, P., Cuvillier, A., Dormieux, L., Maghous, S., 1999. Face stability of shallow pp. 117–123.
circular tunnels driven under the water table: a numerical analysis. Int. J. Theiler, A., Zingg, S., Anagnostou, G., 2013. Analysis of a demanding historical
Numer. Anal. Meth. Geomech. 12, 79–95. tunnel: Albula. In: ITA-AITES World Tunnel Congress (WTC2013), Geneva, pp.
Celestino, T.B., Giambastiani, M., Bortolucci, A.A., 2001. Water inflows in tunnels: 2022–2029.
back-analysis and role of different lining system. In: Proc. 2001 World Vermeer, P.A., Ruse, N.M., Marcher, T., 2002. Tunnel heading stability in drained
Tunnelling Congress (WTC2001), VII, Milano, pp. 547–554. ground. Felsbau 20, 8–18.
COMSOLÒ. Subsurface Flow Module (Comsol Multiphysics 5.0). COMSOL 1998– Wang, T.T., Wang, W.L., Lin, M.L., 2004. Harnessing the catastrophic inrush of water
2016. into New Yungchuen Tunnel in Taiwan. In: ITA-AITES World Tunnel Congress
Droniuc, N., Magnan, J.P., Al Hallak, R., 2004. The Stability of Tunnel Face Accounting (WTC2004), Singapore, pp. 1–8.
for the Effects of Groundwater, Numerical Models in Geomechanics (NUMOG Wongsaroj, J., 2005. Three-dimensional finite analysis of short- and long-term
IX). Pande & Pietruszczak, London, pp. 433–438. ground response to open face tunnelling in stiff clay. In: Ph.D. Thesis, Cambridge
Fellner, D., Gärber, R., 2004. Hydrogeological aspects for the design of deep seated University.
tunnels. Lombardi AG (www.lombardi.ch; last access 27.01.2015), p. 15. Zingg, S., Anagnostou, G., 2012. The effects of advance drainage on face stability in
Feroz, M., Jensen, M., Lindell, J.E., 2007. The Lake Mead Intake 3 water tunnel and homogeneous ground. In: ITA-AITES World Tunnel Congress (WTC2012),
pumping station, Las Vegas, Nevada, USA. In: Taylor, M.T., Townsend, J.W. (Eds.), Bangkok.
Rapid Excavation and Tunneling Conference (RETC2007). Society for Mining Zingg, S., Anagnostou, G., 2013. Effect of tunnel diameter on the efficiency of
Metallurgy and Exploration, Toronto, pp. 647–662. advance drainage with respect to face stability. In: International Symposium on
Franzen, T., Celestino, T.B., 2002. Lining of tunnels under groundwater pressure. Tunnelling and Underground Space Construction for Sustainable Development
ITA-AITES Downunder, 2002, vol. 1, pp. 481–487. (TU-Seoul 2013), Seoul, pp. 277–280.
Fulcher, B., Bell, M., Garshol, K., 2008. Pre-Excavation Drilling and Grouting for Zingg, S., Bronzetti, D., Anagnostou, G., 2013. Face stability improvement by
Water Control and Ground Improvement in Highly Variable Ground Conditions advance drainage via pilot tunnel. ITA-AITES World Tunnel Congress
at the Arrowhead Tunnels Project, North American Tunneling Conference (WTC2013), Geneva, 701–708.
(NAT2008). SME Inc., Littleton, San Francisco, pp. 749–765.

S-ar putea să vă placă și