CONSULTANTS

ABBREVIATIONS MECHANICAL SYMBOL LEGEND GENERAL NOTES: LABORATORY CONSULTANT


RFD - Research Facilities Design
AD ACCESS DOOR
1. ALL PIPING AND DUCTS IN FINISHED ROOMS OR SPACES SHALL BE CONCEALED IN FURRED 3965 Fifth Ave. Suite 400
CHASES OR SUSPENDED CEILINGS, UNLESS OTHERWISE NOTED. San Diego, CA 92103
ACU AIR CONDITIONING UNIT DUCTWORK SYMBOLS PIPING SYMBOLS FITTING SYMBOLS 2. PROVIDE ACCESS PANELS OR DOORS IN INACCESSIBLE CEILINGS AND/OR CHASES FOR Phone 619-297-0159
AD ACCESS DOOR
SINGLE LINE PIPE SYMBOLS ALL VALVES, TRAPS, DAMPERS, CLEANOUTS, COILS, FANS, CONTROLS, ETC. THEY SHALL
FLEXIBLE DUCT HWS HEATING WATER SUPPLY
AFF ABOVE FINISHED FLOOR BE FURNISHED UNDER DIVISION 23 AND INSTALLED UNDER THE ARCHITECTURAL CIVIL ENGINEER
AHU AIR HANDLING UNIT HWR HEATING WATER RETURN SPECIFICATION. ACCESS DOOR RATING SHALL MATCH CLASSIFICATION OF WALL AND
ACOUSTICAL DUCT LINING ELBOW - DOWN CEILING FIRE RATING. Lilley Engineering, Inc.
AL ACOUSTIC LINING CHWS CHILLED WATER SUPPLY
ELBOW - UP 5160 Calle Bellisima
MANUAL BALANCING DAMPER CHWR CHILLED WATER RETURN 3. WATER PIPE CONNECTIONS TO WATER COILS SHALL BE MADE SO THERE WILL BE
PIPE RISE - DROP
COUNTER FLOW BETWEEN WATER AND AIR.
Las Cruces, NM 88011
BHP BRAKE HORSEPOWER F.DPR HRS HEAT RECOVERY SUPPLY
ELBOW - DOWN TO TEE Phone 575-521-0006
FIRE DAMPER HRR HEAT RECOVERY RETURN
BOD BOTTOM OF DUCT TEE - DOWN 4 COORDINATE THE LOCATION OF ALL DIFFUSERS, GRILLES, REGISTERS, ACCESS DOORS,
S.DPR CD CONDENSATE DRAIN ETC., WITH THE ARCHITECTURAL REFLECTED CEILING PLAN(S).
BOP BOTTOM OF PIPE
SMOKE DAMPER TEE - UP STRUCTURAL ENGINEER
D DRAIN Stubbs Engineering, Inc.
BTU BRITISH THERMAL UNIT ELBOW - UP TO TEE 5 ALL ROUND RUNOUTS AND DROPS TO DIFFUSERS SHALL BE THE SAME NOMINAL SIZE AS
V VENT
BTUH BTU PER HOUR F/S DPR COMBINATION FIRE/SMOKE DAMPER THE SCHEDULED DIFFUSER NECK SIZE. 277 E. Amador Ave. Suite 200
MU MAKE-UP WATER END CAP
6. THE FIRST FIGURE OF DUCT SIZE INDICATES DIMENSION OF FACE SHOWN OR INDICATED.
Las Cruces, NM 88001
RS REFRIGERATION SUCTION FLEX CONNECTION
CA COMPRESSED AIR ALL DUCT SIZES SHOWN ON DRAWINGS ARE NET INSIDE DIMENSIONS. Phone 575-993-5228
1HR FIRE BARRIER (VERIFY WITH ARCHITECTURAL PIPE REDUCER - CONCENTRIC
DRAWINGS) RL REFRIGERATION LIQUID
CD CONDENSATE DRAIN
PIPE REDUCER - ECCENTRIC 7. PROVIDE 1/2" MANUAL AIR VENTS AT ALL HIGH POINTS OF CLOSED SYSTEM PIPING AND MECHANICAL/ELECTRICAL ENGINEER
2HR FIRE BARRIER (VERIFY WITH ARCHITECTURAL R REFRIGERATION
CFM CUBIC FEET PER MINUTE 1/2" MANUAL DRAIN VALVES WITH HOSE CONNECTION AT LOW POINTS AS REQUIRED TO
DRAWINGS) TWS TOWER WATER SUPPLY PIPE STRAINER Bridgers & Paxton Consulting Engineers
CO CLEANOUT PROVIDE COMPLETE SYSTEM DRAINAGE. WHERE DRAIN VALVES OCCUR ABOVE CEILING
2HR SMOKE BARRIER (VERIFY WITH ARCHITECTURAL UNION - SCREWED AREAS AND IN AREAS OUTSIDE MECHANICAL RANGE PROVIDE HOSE CONNECTION ON 4600-C Montgomery Blvd. NE
CONT. CONTINUATION DRAWINGS) TWR TOWER WATER RETURN
A VALVE. Albuquerque, NM 87109
TWB TOWER WATER BYPASS AIR VENT - AUTOMATIC
HPS STEAM - HIGH PRESSURE SUPPLY 8. PROVIDE TURNING VANES IN ALL SQUARE ELBOWS, EXCEPT TRANSFER AIR SOUND Phone 505-883-4111
D DRAIN CONNECT NEW DUCT TO EXISTING DUCT AIR VENT - MANUAL
P ELBOWS.
DX DIRECT EXPANSION HPR STEAM - HIGH PRESSURE RETURN GAUGE - DIFFERENTIAL
EXISTING DUCT TO BE REMOVED MPS STEAM - MEDIUM PRESSURE SUPPLY GAUGE - PRESSURE 9. THE CFM OF EACH DIFFUSER, REGISTER, ETC., IS INDICATED AS A NUMBER NEXT TO THE
PS SYMBOL DESIGNATION ON THE DRAWINGS.
ENT ENTERING MPR STEAM - MEDIUM PRESSURE RETURN GAUGE - PRESSURE
EXH EXHAUST FLEXIBLE CONNECTION 10. REFER TO THE ARCHITECTURAL DRAWINGS FOR EXACT LOCATION OF ALL FIRE RATED
D LPS STEAM - LOW PRESSURE SUPPLY GAUGE - PRESSURE WITH COCK D
AND/OR SMOKE RATED WALLS AND ASSEMBLIES. PROVIDE APPROVED FIRE DAMPERS IN
EMCS ENERGY MANAGEMENT CONTROL SYSTEM ALL REQUIRED PENETRATIONS FOR DUCTWORK, GRILLES, REGISTERS AND DIFFUSERS.
LPR STEAM - LOW PRESSURE RETURN
RISE IN DUCT GAUGE - TEMPERATURE ALL PIPE AND DUCTWORK PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS
°F DEGREES FAHRENHEIT CND STEAM - CONDENSATE RETURN SHALL BE CAULKED AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED
MITERED ELBOW (ALL MITERED ELBOWS ARE TO HAVE PIPE - CAPPED WITH SHUT-OFF VALVE FIRE PROOF CAULKING MATERIAL.
FB FLAT BOTTOM PC STEAM - PUMPED CONDENSATE
VANES EXCEPT TRANSFER AIR SOUND ELBOW) PIPE ANCHOR
FCO FLOOR CLEANOUT DOWN 11. CONTRACTOR SHALL COORDINATE ALL DUCTWORK, PIPING, PLUMBING AND FIRE
SHORT RADIUS VANED ELBOW (ALL SHORT RADIUS DIRECTION OF PIPE PITCH (DOWN) PIPE EXPANSION JOINT PROTECTION PIPING WITH STRUCTURAL AND ELECTRICAL SYSTEMS AND SHALL PROVIDE
FCU FAN COIL UNIT M ES I
L IR
ELBOWS ARE TO HAVE VANES PER SMACNA) PIPE GUIDE NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN EQUIPMENT ACCESS AND
FD FLOOR DRAIN DIRECTION OF FLOW F SERVICEABILITY. T
MEXI

I
SENSOR - FLOW

I
F.G. FILTER GAUGE STANDARD RADIUS ELBOW EXISTING PIPE TO REMAIN W

CO
NE
12. CONTRACTOR SHALL FURNISH ALL NECESSARY STRUCTURES, INSERTS, SLEEVES, AND
FLEX FLEXIBLE SWITCH - FLOW
EXISTING PIPE TO BE REMOVED
PS
HANGING DEVICES FOR INSTALLATION OF MECHANICAL AND PLUMBING EQUIPMENT, 20505
FPM FEET PER MINUTE SUPPLY DUCT, SECTION DUCTWORK AND PIPING, ETC. CONTRACTOR SHALL COORDINATE WITH GENERAL

E ER
P RO
SWITCH - PRESSURE
TS CONTRACTOR AND ALL BUILDING TRADES TO AVOID CONFLICTS AND TO MAINTAIN
FS FLOOR SINK SWITCH - TEMPERATURE ES

IN
EQUIPMENT ACCESS AND SERVICEABILITY.

F
EXHAUST DUCT, SECTION SI G
FT FLAT TOP O N A L EN
FT. FEET RETURN DUCT, SECTION TEMPERATURE - PRESSURE TEST FITTING 13. CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALL NECESSARY MISCELLANEOUS
ANGLES, CHANNELS, UNISTRUT, ETC., AS MAY BE REQUIRED TO ADEQUATELY SUPPORT
VALVE SYMBOLS THERMOMETER THE MECHANICAL PIPING, DUCTWORK, AND EQUIPMENT IN A MANNER APPROVED BY THE
GPH GALLONS PER HOUR CEILING DIFFUSERS (ARROWS DENOTE THROW PATTERN ARCHITECT, WHICH WILL NOT OVERLOAD THE BUILDING STRUCTURAL SYSTEM. PROJECT
GPM GALLONS PER MINUTE IF THROW IS SOMETHING OTHER THAN 4-WAY) SINGLE LINE PIPE SYMBOLS THERMOMETER WELL
14. CONTRACTOR SHALL PROVIDE RETURN AIR OR TRANSFER AIR OPENINGS IN FULL HEIGHT
WALLS SIZED AT 350 FPM (UNLESS OTHERWISE SPECIFICALLY SHOWN ON THE DRAWINGS)
GATE VALVE
HB
HD
HOSE BIBB
HAND DAMPER (VOLUME DAMPER)
DUCTED EXHAUST REGISTER
GLOBE VALVE DOUBLE LINE PIPE SYMBOLS
TO CREATE AND/OR MAINTAIN A RETURN AIR PATH AS REQUIRED. FIRE DAMPERS AND/OR
SMOKE DAMPERS SHALL BE PROVIDED IN SUCH OPENINGS WHERE REQUIRED BY NOTE # New Mexico State
10.
HEPA HIGH EFFICIENCY PARTICULATE AIR (FILTER)
DUCTED RETURN REGISTER
CHECK VALVE
ELBOW - DOWN
15. SEAL ALL TRANSVERSE JOINTS, LONGITUDINAL SEAMS, DUCT WALL PENETRATIONS AND
University
PLUG VALVE FITTING CONNECTIONS ON ALL DUCT SYSTEMS.
IN INCHES ELBOW - UP
CEILING RETURN AIR REGISTER OR TRANSFER AIR GRILLE PRESSURE REDUCING VALVE PIPE RISE - DROP 16. MECHANICAL ITEMS SUCH AS ROOF DRAINS, FLOOR DRAINS, PLUMBING FIXTURES, ETC.
KW
KWH
KILOWATT
KILOWATT HOUR
SIDEWALL EXHAUST OR RETURN AIR GRILLE
ELBOW - DOWN TO TEE
SHOWN ON THE ARCHITECTURAL DRAWINGS BUT NOT SHOWN ON THE MECHANICAL
DRAWINGS SHALL BE INCLUDED IN THE PROJECT. THESE ITEMS SHALL BE BROUGHT TO
Jett Hall and Jett Annex
MA MAIN AIR (CONTROLS)
OR REGISTER
SIDEWALL SUPPLY REGISTER
THREE-WAY MODULATING CONTROL VALVE
TEE - DOWN
THE ATTENTION OF THE ARCHITECT FOR INCLUSION IN ADDENDUM.
Renovations and
MCC MOTOR CONTROL CENTER
DUCT TRANSITION
Additions
TWO-WAY CONTROL VALVE END CAP
C NA NOT APPLICABLE C
NIC NOT IN CONTRACT 24"x12" INDICATES A RECTANGULAR DUCT SIZE (WIDTH x DEPTH) PIPE REDUCER - CONCENTRIC
SAFETY VALVE OR PRESSURE RELIEF
NO. NUMBER (QUANTITY)
12" o INDICATES A ROUND DUCT SIZE PIPE REDUCER - ECCENTRIC
MANUAL AIR VENT
OA OUTSIDE AIR UNION - SCREWED
24"/12" INDICATES A FLAT OVAL DUCT SIZE (WIDTH x DEPTH)
SOLENOID VALVE
OBD OPPOSED BLADE DAMPER
3/4" GATE VALVE WITH ADAPTER TO 3/4" PIPE STRAINER
ACCESS DOOR
PRV PRESSURE REDUCING VALVE HOSE THREAD
PSIG POUNDS PER SQUARE INCH GAGE BUTTERFLY VALVE
T ROOM THERMOSTAT/TEMP. TRANSMITTER LOCATION ONLY
SEE CONTROL DRAWINGS FOR TYPE
BALL VALVE
QTY QUANTITY
H ROOM HUMIDISTAT/HUMIDITY TRANSMITTER LOCATION ONLY VALVE IN RISE
QUAD QUADRANT SEE CONTROL DRAWINGS FOR TYPE

R.A. RETURN AIR


CO
2 ROOM CARBON DIOXIDE SENSOR LOCATION ONLY
WATER FLOW MEASURING DEVICE
VALVE ASSEMBLY
Construction
Rh RELATIVE HUMIDITY
RPM REVOLUTIONS PER MINUTE SD
DUCT MOUNTED SMOKE DETECTOR
VALVE - BALL LEVER Documents
VALVE - GATE MANUAL
SCD SMOKE CONTROL DAMPER
SP STATIC PRESSURE (INCHES OF WATER) VALVE - BUTTERFLY LEVER
SDVV SINGLE DUCT VARIABLE VOLUME M
DUCT MOUNTED STATIC PRESSURE PROBE
ST SOUND TRAP VALVE - BUTTERFLY MOTORIZED

VALVE - GLOBE MANUAL


TOPT TOP OF PIPE TRAPEZE
TP TOTAL PRESSURE (INCHES OF WATER) VALVE - GLOBE LEVER
TYP. TYPICAL
EQUIPMENT SYMBOLS VALVE - PLUG LEVER NOTE: NOT ALL ABBREVIATIONS AND
V VOLTS VALVE - PLUG MANUAL SYMBOLS APPLY TO THIS PROJECT.
VAC VOLTS, ALTERNATING CURRENT
VALVE - PRESSURE REGULATING
VAV VARIABLE AIR VOLUME LETTERS REFER TO THE EQUIPMENT TYPE
B VEL VELOCITY VALVE - CHECK B
XX - ## NUMBERS REFER TO SPECIFIC EQUIPMENT
VTR VENT THRU ROOF
SYMBOL INDICATES NEW EQUIPMENT VALVE - PRESSURE RELIEF
WCO WALL CLEANOUT IDENTIFIED IN EQUIPMENT SCHEDULE
WH WALL HYDRANT

SIDEWALL GRILLE DIMENSION WHERE


DOUBLE LINE PIPE SYMBOLS
SHOWN ON PLANS
##x# SYMBOL INDICATES GRILLE OR
DIFFUSER IDENTIFIED IN EQUIPMENT GATE VALVE
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

XX - #
### SCHEDULE
GLOBE VALVE
CFM
CHECK VALVE

PLUG VALVE

PRESSURE REDUCING VALVE

SECTION SYMBOLS SECTION AND DETAIL TITLES 3-WAY CONTROL VALVE

SECTION NUMBER X# 2-WAY CONTROL VALVE


X### SECTION
DRAWING NUMBER WHERE DETAILED
SECTION LOCATION X# SCALE
RELIEF VALVE
DETAIL REFERENCE
DETAIL LOCATION X#/X### DETAIL SOLENOID VALVE Mark Date Description
DETAIL LOCATION X# SCALE
Date September 11, 2015
DRAWING NUMBER WHERE DETAILED BUTTERFLY VALVE
Project Number 14400
BALL VALVE Drawn By PZP
A A Checked By IM
DIAPHRAGM VALVE
Copyright © VAN H. GILBERT ARCHITECT PC
CIRCUIT SETTER
SHEET TITLE
STEAM TRAP INVERTED BUCKET

MECHANICAL LEGEND
9/15/2015 6:41:41 PM

M-001
1 2 3 4 5 6 SHEET 108 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
ALL HVAC DUCTS, GRILLES,
DIFFUSERS, EQUIPMENT AND
GENERAL NOTES
PIPING TO BE REMOVED WITHIN A. CONTRACTOR SHALL VERIFY ALL REMOVALS WITH ARCHITECT AND
THIS AREA, UNLESS OWNER PRIOR TO DEMOLISHING.
OTHERWISE NOTED.
B. IN THE EVENT THAT UNANTICIPATED CONDITIONS ARE
ENCOUNTERED, INCLUDING MECHANICAL, ELECTRICAL OR
STRUCTURAL ELEMENTS THAT CONFLICT WITH THE INTENT OF THE
DEMOLITION DRAWINGS, REPORT SUCH CONDITIONS IMMEDIATELY
TO THE ARCHITECT.

C. ALL HVAC EQUIPMENT, DUCT, PIPING AND CONTROLS SHALL BE 2428 Baylor Dr SE Albuquerque, NM 87106
REMOVED ENTIRELY, UNLESS OTHERWISE NOTED. THE MECHANICAL Tel 505-247-9955 Fax 505-247-1826
CONTRACTOR SHALL COORDINATE WITH THE GENERAL E-mail info@vhgarchitect.com
CONTRACTOR TO REMOVE ALL THE HVAC EQUIPMENT, DUCT, PIPING
E AND CONTROLS NOT SHOWN ON PLANS. THE CONTRACTOR SHALL E Web Site www.vhgarchitect.com
BE RESPONSIBLE TO FIELD VERIFY ALL EXISTING CONDITIONS CONSULTANTS
BEFORE AND AFTER DEMOLITION.
LABORATORY CONSULTANT
D. ALL PENETRATIONS LEFT VACANT BY REMOVALS SHALL BE PATCHED
UNLESS NOTED OTHERWISE. CAP OR PATCH ALL OPENINGS LEFT IN RFD - Research Facilities Design
DUCTWORK CREATED BY DEMOLITION. CONCRETE AND BLOCK 3965 Fifth Ave. Suite 400
OPENINGS LEFT BY REMOVED DUCTS & PIPES SHALL BE FILLED WITH San Diego, CA 92103
SIMILAR MATERIAL.
Phone 619-297-0159

CIVIL ENGINEER
Lilley Engineering, Inc.
5160 Calle Bellisima
Las Cruces, NM 88011
Phone 575-521-0006

STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
Phone 575-993-5228

MECHANICAL/ELECTRICAL ENGINEER
Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
AIR HANDLER Phone 505-883-4111

2
D D

STEAM HEATER
(TYP.)

M ES I
L IR T
MEXI

I
W

CO
NE
20505

E ER
P RO
ES

IN
F
SI G
O N A L EN
KEYNOTES
1. ALL PIPING FROM EXISTING TUNNEL TO THE ANNEX SHALL BE PROJECT
2 REMOVED. SEE MP-103A FOR NEW PIPING REQUIREMENTS IN
TUNNELS.

2. REMOVALS IN THIS AREA SHALL BE CAREFULLY COORDINATED WITH


G.C. AND USERS. AS SOME EQUIPMENT MUST BE PROTECTED FROM New Mexico State
DAMAGE.

3. EXISTING WELDING HOOD AND EXHAUST FAN SHALL REMAIN IN


University
STEAM HEATER PLACE.
(TYP.)

Jett Hall and Jett Annex


Renovations and
Additions
C C
2

1 Construction
Project
Documents
North

B2 MECHANICAL
Scale: 1/16" = 1'-0"
DEMOLITION PLAN - FIRST FLOOR
0' 4' 8' 16'

NOTE:
ALL HVAC DUCTS, GRILLES,
CHWS/R, PC AND HPS PIPING IN TUNNEL
B DIFFUSERS, EQUIPMENT AND
PIPING TO BE REMOVED WITHIN
THIS AREA, UNLESS
SHALL BE REMOVED BACK TO THE B

OTHERWISE NOTED.
CAMPUS MAINS.
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

ALL HVAC DUCTS, EQUIPMENT


AND PIPING TO BE REMOVED
WITHIN THIS AREA, UNLESS
OTHERWISE NOTED.

Mark Date Description


Date September 11, 2015
Project Number 14400
Drawn By PZP
A A Checked By IM

DEMO NOTE: Copyright © VAN H. GILBERT ARCHITECT PC

DEMO DRAWINGS HAVE BEEN CREATED USING ORIGINAL SHEET TITLE


CONSTRUCTION DOCUMENTS.
NO ATTEMPT HAS BEEN MADE TO INTEGRATE THE MECHANICAL DEMO
9/15/2015 6:42:04 PM

Project
North
NUMEROUS RENOVATIONS AND TENANT IMPROVEMENTS PLANS - BASEMENT &
INTO THESE DRAWINGS.
FIRST FLOOR
A2 MECHANICAL DEMOLITION PLAN - BASEMENT
Scale: 1/16" = 1'-0" MD-101
1 2 3 4 0' 4' 8' 16' 5 6 SHEET 109 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ALL HVAC DUCTS, GRILLES, ARCHITECTURE • INTERIORS • PLANNING
DIFFUSERS, EQUIPMENT AND GENERAL NOTES
PIPING TO BE REMOVED WITHIN
THIS AREA, UNLESS OTHERWISE A. CONTRACTOR SHALL VERIFY ALL REMOVALS WITH ARCHITECT AND
NOTED. OWNER PRIOR TO DEMOLISHING.

B. IN THE EVENT THAT UNANTICIPATED CONDITIONS ARE


ENCOUNTERED, INCLUDING MECHANICAL, ELECTRICAL OR
STRUCTURAL ELEMENTS THAT CONFLICT WITH THE INTENT OF THE
DEMOLITION DRAWINGS, REPORT SUCH CONDITIONS IMMEDIATELY
TO THE ARCHITECT.

C. ALL HVAC EQUIPMENT, DUCT, PIPING AND CONTROLS SHALL BE 2428 Baylor Dr SE Albuquerque, NM 87106
REMOVED ENTIRELY, UNLESS OTHERWISE NOTED. THE MECHANICAL Tel 505-247-9955 Fax 505-247-1826
CONTRACTOR SHALL COORDINATE WITH THE GENERAL E-mail info@vhgarchitect.com
CONTRACTOR TO REMOVE ALL THE HVAC EQUIPMENT, DUCT, PIPING
E AND CONTROLS NOT SHOWN ON PLANS. THE CONTRACTOR SHALL E Web Site www.vhgarchitect.com
BE RESPONSIBLE TO FIELD VERIFY ALL EXISTING CONDITIONS CONSULTANTS
BEFORE AND AFTER DEMOLITION.
LABORATORY CONSULTANT
D. ALL PENETRATIONS LEFT VACANT BY REMOVALS SHALL BE PATCHED
UNLESS NOTED OTHERWISE. CAP OR PATCH ALL OPENINGS LEFT IN RFD - Research Facilities Design
DUCTWORK CREATED BY DEMOLITION. CONCRETE AND BLOCK 3965 Fifth Ave. Suite 400
OPENINGS LEFT BY REMOVED DUCTS & PIPES SHALL BE FILLED WITH San Diego, CA 92103
SIMILAR MATERIAL.
Phone 619-297-0159

CIVIL ENGINEER
Lilley Engineering, Inc.
NOTE: 5160 Calle Bellisima
Las Cruces, NM 88011
ALL MECHANICAL EQUIPMENT ON ROOF IS Phone 575-521-0006

TO BE REMOVED. CAP AND PATCH ROOF STRUCTURAL ENGINEER


Stubbs Engineering, Inc.
OPENINGS IN ACCORDANCE WITH 277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
ARCHITECTURAL DETAILS. Phone 575-993-5228

MECHANICAL/ELECTRICAL ENGINEER
Project
North Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE

D2 MECHANICAL DEMOLITION PLAN - PENTHOUSE Albuquerque, NM 87109


Phone 505-883-4111
Scale: 1/4" = 1'-0"
0' 2' 4' 8'

D D

M ES I
L IR T
MEXI

I
ALL HVAC DUCTS, GRILLES, W

CO
NE
DIFFUSERS, EQUIPMENT AND
PIPING TO BE REMOVED WITHIN 20505
THIS AREA, UNLESS OTHERWISE

E ER
P RO
NOTED.
ES

IN
F
SI G
O N A L EN
KEYNOTES
1. SEE ARCHITECTURAL DRAWINGS FOR THIS AREA. RECENT PROJECT
RENOVATIONS INCLUDE EQUIPMENT THAT MAY REMAIN IN PLACE AND
MUST BE PROTECTED, THEN RE-CONNECTED TO NEW BUILDING
SYSTEMS AS PART OF THIS PROJECT. SEE SHEET MH-103-E ALSO.
New Mexico State
University

Jett Hall and Jett Annex


Renovations and
Additions
C C

STEAM FIRED
WATER HEATER

Construction
Documents

B B
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

DEMO NOTE:
DEMO DRAWINGS HAVE BEEN CREATED USING ORIGINAL
CONSTRUCTION DOCUMENTS.
1 NO ATTEMPT HAS BEEN MADE TO INTEGRATE THE
NUMEROUS RENOVATIONS AND TENANT IMPROVEMENTS Mark Date Description
INTO THESE DRAWINGS. Date September 11, 2015
Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

Project MECHANICAL DEMO


9/15/2015 6:42:04 PM

North

PLANS - PENTHOUSE &


A2 MECHANICAL
Scale: 1/16" = 1'-0"
DEMOLITION PLAN - SECOND FLOOR
SECOND FLOOR
0' 8' 16' 32'
MD-102
1 2 3 4 5 6 SHEET 110 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
GENERAL NOTES ARCHITECTURE • INTERIORS • PLANNING

A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH


STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
SPECIFICATIONS 23 0500.

B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR


EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT
G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
MAE COMPUTER San Diego, CA 92103
MAE COMPUTER LAB H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
SUPPORT MAE COMPUTER LAB 501. Phone 619-297-0159
004
010 006
I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
DIAMETER.
Lilley Engineering, Inc.
SD-1 SD-1 SD-1 SD-1 SD-1 SD-1
J. REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
SD-1 THERMAL SCIENCE LAB SD-1 SD-1 265 265 265 265 265 265 Las Cruces, NM 88011
K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
275 016 275 275 CONNECTIONS TO LABORATORY EQUIPMENT.
Phone 575-521-0006
SUPPORT
012 10"x12" 10"x12" 10"x12" 10"x12" 10"x12" 10"x12"
STRUCTURAL ENGINEER
14"x14" 14"x14" 14"x14"
SD-1 Stubbs Engineering, Inc.
SD-1 SD-1 SD-1 SD-1 SD-1 SD-1
10"x12" 18"x14" 80 265 265 265 265 265 265
277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
2 2 2
MECHANICAL
SD-1 SD-1 SD-1 RHC3-001
SD-1 FCU-1 SD-1 FCU-2 SD-1 FCU-3 M002 Phone 575-993-5228
275 275 275 210 210 210
SD-1 SD-1
210 RG-1 210 SD-1 RG-1 MECHANICAL/ELECTRICAL ENGINEER
ER-1 24"x22" 24"x22" 24"x22" 210 ER-3 Bridgers & Paxton Consulting Engineers
12"ø 12"ø RG-1 RG-1
STORAGE 900 8x8
ER-1 8"x8" 10"x10" 4600-C Montgomery Blvd. NE
14"ø
SCV3-001 16"x14" 14"x12" 80
S018A 900 14"x12" 14"x12" 10"x10" Albuquerque, NM 87109
SD-2 CORRIDOR Phone 505-883-4111
14"x12"
RG-2 80 H002
SD-1 SCV3-007 RHC3-007 SD-1 SD-1
ECV3-001 160 160 160
10"ø
TU1-002 14"ø TU1-001 12"x10"
12"x10" 22"x16" 20"x12" 20"x12" 18"ø 18"ø 16"ø
D D
RG-1
22"x16"

8"ø OFFICE AEROSPACE JANITOR

10"ø
8"ø
14"x12"

8"ø

8"ø
SD-1 011 STRUCTURAL J003 WOMEN
SD-4 ECV3-004 ECV3-008
1
10"x10" 200 SD-1 DYNAMICS LAB
ER-1 230 ECV3-003 OFFICE SD-1 SD-1 ER-2 R001
14"ø

200 SD-1 009

6"ø
10"x8" 890 230 225 60
SD-1 200 007 ECV3-006
ECV3-005

8"ø
8"ø

8"ø
180 RHC3-002 8"x12" ER-1 SD-1 ACU-1
ER-1 10"ø
230
24"x18"

STORAGE SD-1 ECV3-002 SCV3-002 510 ER-1 ER-1 M ES I

6"ø
10"x10" 510 ER-2
L IR
10"x10"

S017A 80 510 610 T


SD-1 8"x12" 8"x12" 180
MEXI

I
ER-1 10"x12"

I
200 SD-4 RHC3-004 SD-2 W

8"ø

CO
450

NE
VESTIBULE RG-1 RHC3-003 230 RHC3-008 140
RHC3-005 CHASE
ACU-2 H017 SCV3-003 SCV3-004 SD-1 SD-1 RHC3-006 SD-1 001B 20505
SD-1 SD-1

E ER
FLIGHT RESEARCH LAB

P RO
SOLID MECHANICS LAB 200 200 230 230 225
013

8"ø
SCV3-005 SCV3-008 ES

IN
DATA

F
015 26"x18" SCV3-006 SI G
26"x18" NON-LINEAR DYNAMICS T005 O N A L EN
ELEVATOR EQUIPMENT VESTIBULE 18"ø 14"ø 12"ø 8"ø ER-2
KEYNOTES
26"x18"

& ENERGY HARVESTING 180


M017B H017C 005
1. 12"Ø SUPPLY AIR DUCT UP TO LEVEL 1. PROJECT
3
5
10"x10"
4
2. ACOUSTICALLY LINE (1") LOW PRESSURE RECTANGULAR SUPPLY AND
RETURN DUCTWORK.

AHU-3 3. 26"x18" MAKE-UP AIR DUCT TO AHU-3 IN MECHANICAL ROOM M123. New Mexico State
4. 26"x18" LAB EXHAUST AIR DUCT UP TO LEVEL 1. University
5. 10"x10" EXHAUST AIR DUCT UP IN CHASE TO LEVEL ABOVE.

C1 HVAC PLAN - BASEMENT Jett Hall and Jett Annex


Project
North
Scale: 1/8" = 1'-0"
Renovations and
0' 4' 8' 16'
Additions
C C

Construction
Documents

B B
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

KEY PLAN

Mark Date Description


Date September 11, 2015
Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

HVAC PLAN - BASEMENT


9/15/2015 6:42:06 PM

MH-103A
1 2 3 4 5 6 SHEET 111 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH
STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
SPECIFICATIONS 23 0500.

B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR


EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
DN C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
DN E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT

A2 / MH-103B
G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
San Diego, CA 92103
H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
501. Phone 619-297-0159
I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
DIAMETER.
Lilley Engineering, Inc.
LSD-1
465 J. REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
TYP. 3 Las Cruces, NM 88011
MAE DIRECTORS K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
OFFICE SUITE CONNECTIONS TO LABORATORY EQUIPMENT. Phone 575-521-0006
104
RG-1
MAE OFFICE MAE OFFICE MAE OFFICE MAE OFFICE MAE OFFICE STRUCTURAL ENGINEER
114 MAE OFFICE 106 104B SD-1
110 108 SD-1 SD-1 50
Stubbs Engineering, Inc.
112
SD-1 SD-1 SD-1 250 250 277 E. Amador Ave. Suite 200
325 325 150 SD-1 Las Cruces, NM 88001
SD-1 SD-1 SD-1 SD-1 MAIL

12"x14"
310
170 190 180 180 104A Phone 575-993-5228

16"x14"
10"x10"
12"x12" 12"x12" RG-1 RG-1 MECHANICAL/ELECTRICAL ENGINEER

12"x10"
8"x8"
SD-1 Bridgers & Paxton Consulting Engineers
TU1-110
170 14"x14" RG-1 14"x12" 4600-C Montgomery Blvd. NE
16"x14" SD-1 SD-1 SD-1 Albuquerque, NM 87109
190 180 180
SD-1 SD-1 TU1-114 SD-1 SD-1 Phone 505-883-4111
325 325 TU1-112 SD-1 SD-1
150 150 TU1-118
TU1-116 310 20"x18" 310
CONFERENCE ROOM 12"x12" RG-1 RG-1 RG-1 18"x18" TU1-117
12"x12"
116 RG-1 RG-1 TU1-121
SD-1
SD-1 SD-1
12"x12" 220 12"x12"
26"x18" TU1-122 220 220
D 12"x10" D
12"x10"
UNISEX
1
50"x20" 30"ø 30"ø 26"ø 26"ø 20"ø
R101
24"x18" 12"ø
60"x18" 60"x18" RG-1
OFFICE SD-1 SUPPORT BREAK ROOM
14"x12" 117D CLASSROOM 105A M ES I
L IR
117C 400 20"x18" 16"x14"
RG-1
TU1-115 RG-1 109 24"x18"
T
SD-1 SD-1 MEXI

I
ER-2

I
SD-1 SD-1 SD-1 SD-1 SD-1 SD-1 SD-1 SD-1 W

50"x20"
90 RG-1 90

CO
90

NE
16"x14" TU1-111 200 TU1-113 150 150 230 230 390 390 390
RG-1 RG-1 TU1-119 8"x8" 20505
MAE SEMINAR TU1-120

E ER
P RO
113 RG-1 ER-2

6"ø
STORAGE 160 ES

IN
F
S117B 12"x10" 12"x10" SD-2 SI G
RG-1 SD-1 10"x10" 14"x12" 18"x14" O N A L EN

8"ø
TU1-109 20"x16"
140
14"x12" 80 RG-1 MAE GRADUATE KEYNOTES
14"x14"

STUDENT OFFICE SD-1 SD-1 10"x10"

60"x18"
SD-1
420 115 150 150 SD-1 SD-1
SR-1 1. 12"Ø SUPPLY AIR DUCT DOWN TO BASEMENT. PROJECT

8"ø
VESTIBULE 230 230 SD-1 SD-1
5
8x6
50"x20"
STORAGE H117 RG-1 RG-1 230 230
50 SD-1 RG-1 COMPUTATIONAL FLOW WOMEN 12"x12" 2. 50"X20" SUPPLY AIR DUCT DOWN FROM LEVEL 2.
S117A SD-1 SD-1 SD-1 MAE OFFICE ER-2
RG-3 200 PHYSICS LAB - I 390 390 390 160 R151
8x6 DN 111
105
10"x10"
3. 16"x14" EXHAUST AIR DUCT UP IN CHASE TO LEVEL ABOVE.
New Mexico State
4. 10"x10" EXHAUST AIR DUCT DOWN IN CHASE TO LEVEL BELOW.
A1 / MH-103C A1 / MH-103C
University
4
5. OPENING IN SECOND FLOOR SLAB FOR RETURN AIR. SEE C2/MH-103D

A2 / MH-103B
5'CFH
FOR LOCATION OF RETURN AIR CHASE.

?
UP
Jett Hall and Jett Annex
?
VESTIBULE MECHANICAL Renovations and
H122 2 M123
Project
North Additions
C2 HVAC FIRST FLOOR PLAN - NORTHWEST
C C

Scale: 1/8" = 1'-0"


0' 4' 8' 16'

Construction
Documents
C2 / MH-103B

B CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE SD-1 SD-1 B
CHME OFFICE CHME OFFICE
150 152 154 156 158 160 162 164 240 240 168
166
10"x12" 10"x12" 10"x12" 10"x12"
SD-1
10"x12"
10"x12"

10"x12"

12"x12"
SD-1 SD-1 SD-1 SD-1 SD-1 230
SD-1 SD-1 275 275 275 270 270
275 275 SD-1

14"x12"
275
TU2-115 TU2-113 TU2-106 SD-1
RG-1 RG-1 RG-1 RG-1 TU2-114 RG-1 RG-1 RG-1 RG-1 RG-1 RG-1 240
12"x10" SD-1
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

12"x10" 12"x10" 12"x10" 12"x10" 12"x10" 10"x10"


240
12"x10" 12"x10"
12"x10"
CORRIDOR SD-1
180 20"x18" TU2-105
SD-1 H161
10"ø 180 16"ø 20"ø 24"ø 24"ø KEY PLAN
TU2-112
24"x16"

STOR CHME GRADUATE 20"x16" SD-1


RG-3 RG-1
157 8x6 STUDENT COMPUTER 120 CHME OFFICE
TU2-111 CLUSTER RG-1 163
SR-1 TU2-107
159 8"x8"
26"ø

RG-1 ER-2 8x6 SD-1 TU2-108


40
60 120 TU2-110 SD-1 SD-1 TU2-104
14"x14" 285 285 TU2-109
6"x8"
8"x10"

JANITOR SR-1
CHME OFFICE
14"x14"

J155 SD-1 8"x8" DATA ROOM TU2-103 10x6 ENTRY


MEN 159A 110 ACU-6 180
12"x10"

ER-2 RG-1 T165 H172


R153 8"x8" RG-1 Mark Date Description
180 10"x12"
CHME OFFICE
10"x12"

RG-1 Date September 11, 2015


3
SD-2 159G
RG-1 CHME OFFICE Project Number 14400
20"x16" RG-3
8"ø

140
8"x8"

159D 28"x18" 14x4


SD-1 SD-1 Drawn By PZP
10"x10" 180 10"x10" SD-1 180
A RG-1 RG-1 A
300 Checked By IM
8"ø

CHME OFFICE 20"x18" SD-1


SD-1 FSD
159C RG-1 18"x18" 110 FSD DN Copyright © VAN H. GILBERT ARCHITECT PC
14"x12" 80 SD-1
WOMEN 12"x12" SD-1 VESTIBULE
R151 ER-2 80 SD-1
CHME OFFICE 270 H174 RG-1
10"x10" 180 18"x16" 36"x14" 180 SHEET TITLE
159B 8"x8" FSD 30"x20"
FSD
A4 / MH-103C CHME OFFICE CHME OFFICE A4 / MH-103C HVAC FIRST FLOOR
9/15/2015 6:42:08 PM

36"x24"
C2 / MH-103B

159E 159F Project


RG-1 North
PLAN - NORTHWEST &
A2 HVAC FIRST FLOOR PLAN - NORTHEAST
Scale: 1/8" = 1'-0"
NORTHEAST
0' 4' 8' 16'
MH-103B
1 2 3 4 5 6 SHEET 112 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH
STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
SPECIFICATIONS 23 0500.

B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR


EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
C1 E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
M-401
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT
G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
San Diego, CA 92103
H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
501. Phone 619-297-0159
B1
M-301 I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
DIAMETER.
36"x14" Lilley Engineering, Inc.
C2 / MH-103B C2 / MH-103B A2 / MH-103B 8"x8" A2 / MH-103BJ.
FSD 30"x20" REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
FSD
Las Cruces, NM 88011
A1 CHME OFFICE CHME OFFICE K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
SD-1 ELECTRICAL ROOM 159E 159F 36"x24"
CONNECTIONS TO LABORATORY EQUIPMENT.
Phone 575-521-0006
STORAGE 50 M-301
A4 E167 SD-1 SD-1 RG-1

38"x22"
S120 ACU-5
M-402 275 275 STRUCTURAL ENGINEER
ACU-7 TU2-101 Stubbs Engineering, Inc.
VESTIBULE SD-1 UP
SD-1 SD-1
277 E. Amador Ave. Suite 200
H122 240 Las Cruces, NM 88001
230 230
10"x12" MECHANICAL ACU-8 Phone 575-993-5228
CORRIDOR SD-1
M123
6"x12" H102 275

34"x22"
40"x100"
RG-1 SD-1 MECHANICAL/ELECTRICAL ENGINEER

18"x16"
275
Bridgers & Paxton Consulting Engineers
ELECTRICAL ROOM
10"x12"
E127
4600-C Montgomery Blvd. NE
RG-1 14"x14" MAE STUDENT LOUNGE SD-1 SD-1 Albuquerque, NM 87109
SD-1 RG-1
125 230 230
280 DN 64"x64"
Phone 505-883-4111
MECHANICAL ROOM SD-1
6"x12"

MAE OFFICE M198 275


124 SD-1
275
10"x12"

RG-1 7
D SD-1 SD-1 SD-1 D
MAE OFFICE SD-1 SD-1
10"x12"

280 RG-1 230 230


36"x20"

34"x22"
250 250
32"x20"

126 10"x12"
1 STUDENT PROJECTS
AHU-4 TU2-102
TU1-107
CENTER

14"x12"
196
14"x12"

SD-1
MAE OFFICE 240 M ES I
128 RG-1 SD-1 SD-1 5 RG-2 SD-2
SD-1 SD-1 L IR T
SD-3 60 MEXI

I
230 230

HEATING COIL

AIR MIXING SECTION


250

ACCESS SECTION
250 W

COOLING COIL
AIR HANDLING UNIT

SUPPLY FAN
LSD-2 265

CO
NE
SD-1 SUSPENDED FROM
6
500

30"x22"
280 TYP. 8 STRUCTURE SCV2-101 STORAGE 20505
S180

E ER
P RO
TU1-108
10"x12"
10"x12"

10"x12" ES

26"ø

IN
F
14"x14" 10"ø SI G
SD-1 RHC2-101 8"ø O N A L EN
20"x20"

280 SD-3
MAE OFFICE
10"x12"
RG-1
RG-1 265 SD-1 CHME STUDENT
KEYNOTES
130 60 PROJECT/STUDY AREA
24"ø

RHC3-108
18"ø

178 1. 28"X14" MAKE-UP AIR DUCT UP TO LEVEL 2. PROJECT


TU1-106 MAE WELDING BREAKROOM RG-1 2. 24"Ø SUPPLY AIR DOWN FROM LEVEL 2.
SCV3-108 182 179

MAE OFFICE
132
14"x12" 10'-0" LONG WELDING HOOD
WITH TWO 1" EXHAUST
SLOTS LOCATED AT 18" AND
CHME MINATURE 18"x12"
3. 30"Ø LAB EXHAUST AIR DUCT UP TO LEVEL 2.
New Mexico State
RG-1 CHEMICAL PILOT PLANT 4. 38"x16" LAB EXHAUST AIR DUCT UP TO LEVEL 2.
SR-1
University
20"x18"

SD-1 SD-1 SD-1 30" ABOVE WORK SURVACE. RHC2-102 SR-1 SR-1
18"ø

SD-1 184 20x6


220 215 215 REFER TO DETAIL A5/M-504. SCV2-102 20x6 20x6 5. 48"x30" OUTSIDE AIR LOUVER IN PLACE OF EXISTING GLAZING PANEL.
240 175 SR-1
175 175

24"ø
MECHATRONICS LAB 20x6
8"x12"

10"x10" 133 175 6. EXISTING WELDING HOOD AND EXHAUST FAN SHALL REMAIN IN
PLACE.
Jett Hall and Jett Annex
8"x12"

18"x12" 12"x12"
18"ø

SD-1 SD-1
12"x12"

SD-1 7. OUTSIDE AIR LOUVER. REFER TO ARCHITECTURAL DRAWINGS AND


215 215 16"Ø SR-1
MAE OFFICE
134
220
10"x10"
ER-2
1550
SR-1
20x6
SR-1
20x6 14"ø
20x6
175
SR-1
20x6
SPECIFICATIONS.
Renovations and
175 175 175
TU1-105 ECV3-108
10"ø ER-1 RG-3
ECV2-102 SCV2-106 SK4 Additions
940 ER-1
C RG-1 18x10 RHC2-106 C

20"ø
320

14"ø
SCV2-103

18"x12"
MAE OFFICE MDF RHC2-103
136 137A 10"ø
SD-1 MAE OFFICE
20"x18"

SD-1 SD-1 RG-1 ECV2-103


TU1-103

LSD-3 18"x10" 191A RHC2-104


230 260 260
250 SD-1
RG-1 ACU-10 SCV2-104
250
10"x10" STORAGE SD-3 SD-3
10"x10" S196B SD-1 240 690
8"x12"

16"ø
RG-1 MAE OFFICE 280
26"ø

MAE COMPUTER RG-3 12"x8"


18"ø

SD-1 12x8 196A

22"ø
MAE OFFICE 10"x10" (GRADUATE) LAB
230 RHC3-107
137 10"x10" MAE LAB
138 10"x10" SCV3-107
ELECTRICAL AHU-5 191
10"ø ECV3-106 MAE LAB
E194B ECV2-104
TU1-104 22"ø ER-1 191 ER-1 SD-3
RG-1 8"x12" RHC3-106
SCV3-106 990
VFD-12
540 240 REDUCED GRAVITY LAB
Construction
10"x10"

191C

14"x10"
SCV2-105
WOMEN
R140
SD-2
10"x10" 140
RHC2-105 Documents
28"ø

14"x12"

5
ACU-9 10"ø

16"ø
8"ø 8"ø SD-1

HEATING COIL

AIR MIXING SECTION


SD-4 SD-4

ACCESS SECTION
COOLING COIL
AIR HANDLING UNIT
SUPPLY FAN
22"ø 180
ER-2 ER-2 225 225 SUSPENDED FROM 12"x12" SD-1 SD-3
10"x12"
18"ø

150 150 LSD-4 STRUCTURE 180


ER-1 690

20"ø
28"ø SD-4 SD-4
425
2 225 225 790

8"x10"
TYP. 10
SD-2 ER-1
ER-2 70 ECV2-105 1550
UNISEX AERO FLUIDS LAB
100 SD-1
26"ø

R142 194
36"x26" 3 AUTONOMOUS 180

14"ø
18"ø

SYSTEMS LAB SD-1


MAE ROBOTICS LAB

16"x16"
141 180
191B
8"ø

18"ø
RHC3-103 14"ø ER-1 ECV2-106
8"ø
SCV3-103 510 ER-2
10"x10"

ECV3-105 SD-4 2000


B B
16"ø

230 20"x14"
SD-4
205 SD-4
230 SCV2-107A SCV2-107B CHME
8"x12"

ECV2-107A

18"ø

14"ø
10"x10" RHC3-105 RHC2-107A RHC2-107B UNDERGRADUATE LAB
16"ø

MAE CAPSTONE
PROJECTS - I 14"ø 193
14"ø

ECV3-103 8"ø
SD-4

18"x14"

18"x14"
145
205 SCV3-105
8"ø RHC3-104 MAE MATERIALS LAB
SR-1 SR-1 SR-1 SR-1 SR-1 SR-1
COMPOSITES LAB ER-1 147 24x6 24x6
24x6 24x6 24x6 24x6
14"ø

144 470 SCV3-104 300 300


D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

300 300 300 300


22"ø

10"x12"
6"ø
RHC3-102 ECV3-104 14"x14" 18"x14" 18"x14" 14"x14"

16"ø
ER-1
12"ø

SCV3-102 SD-4 SD-4


SD-4 240
12"ø

MAE LAB 225 225


210 ECV3-102
146
12"ø ER-1
COMPUTATIONAL FLOW
PHYSICS LAB - II
SR-1
24x6
SR-1
24x6
SR-1
24x6
SR-1
24x6
SR-1
24x6
SR-1
24x6 KEY PLAN
300 300 300 300 300 300
610 149A
10"ø

SD-1
12"x10" RG-1 22"ø
SCV3-101 50 RG-4
SD-1 12x8
14"ø

ECV3-101A
RHC3-101 230 250
VESTIBULE 10"x10" ECV2-107B
H149
SD-3 TU1-102
12"x12"

6"x12"
380 ECV3-101B

10"ø GRADUATE STUDENT MAE OFFICE

20"ø
22"x14"
OFFICE 194A
ER-1 18"x16" Mark Date Description
SD-1 149B SD-1
190
12"x12" 180 180 Date September 11, 2015
ER-2
TU1-101 Project Number 14400
4
2000
SD-3 RG-3 RG-3 Drawn By PZP
12"x12"
380 12x8 12x8
A A Checked By IM
SD-1 SD-1
MAE CAPSTONE
PROJECTS - II 180 180 Copyright © VAN H. GILBERT ARCHITECT PC
22"ø 38"x16"
148 RG-1
SHEET TITLE

DN
HVAC FIRST FLOOR
9/15/2015 6:42:12 PM

UP Project Project Project


North North North
PLAN - ANNEX, EAST &
A1 HVAC FIRST FLOOR PLAN - WEST WING
Scale: 1/8" = 1'-0"
A2 HVAC FIRST FLOOR PLAN - ANNEX
Scale: 1/8" = 1'-0"
A4 HVAC FIRST FLOOR PLAN - EAST WING
Scale: 1/8" = 1'-0"
WEST WING
0' 4' 8' 16' 0' 4' 8' 16' 0' 4' 8' 16' MH-103C
1 2 3 4 5 6 SHEET 113 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH
STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
SPECIFICATIONS 23 0500.

B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR


EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT

A2 / MH-103D
G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
San Diego, CA 92103
H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
501. Phone 619-297-0159

I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
DIAMETER.
Lilley Engineering, Inc.
J. REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
MAE OFFICE
Las Cruces, NM 88011
K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
204 CONNECTIONS TO LABORATORY EQUIPMENT.
Phone 575-521-0006

RG-1 CLASSROOM CLASSROOM CLASSROOM


CLASSROOM RG-1 SD-1 STRUCTURAL ENGINEER
206 SD-1
216 210 208 Stubbs Engineering, Inc.
RG-1 RG-1 SD-1 SD-1 SD-1 200 200 CORRIDOR
230 230 230 RG-1
SD-1 SD-1
RG-1 RG-1
SD-1
H201
277 E. Amador Ave. Suite 200
170 170 280 Las Cruces, NM 88001
RG-1
SD-1 SD-1 SD-1
Phone 575-993-5228
290 290 290
LSD-6
12"x12" 350
MECHANICAL/ELECTRICAL ENGINEER
10"x12" 18"x16" 16"x14" 8"x12" 8"x10" 10"x12"
Bridgers & Paxton Consulting Engineers

12"x10"
LSD-6 4600-C Montgomery Blvd. NE
SD-1
SD-1 350 Albuquerque, NM 87109
TU1-215 170 SD-1
SD-1 SD-1 SD-1 170 SD-1
200 Phone 505-883-4111
290 290 290 SD-1 SD-1 SD-1 280 14"x10"
TU1-211 TU1-213 TU1-217 TU1-218
230 230 16"x16" 230
16"x16" 16"x14" 16"x14"
SD-1 16"x16" SD-1
SD-1 170 170
170
24"x20" 14"x8" 14"x8" 14"x8"
D D
16"x14"
40"x20" 28"ø 24"ø 24"ø 18"ø TU1-219
CORRIDOR
H201
CORRIDOR
H201 20"x20" 18"ø
60"x18" 60"x18"
MAE OFFICE 20"x20" CLASSROOM
20"x18" CLASSROOM JANITOR M ES I
L IR
217A TU1-212 207 ACU-13
SD-1 SD-1 213 SD-1 SD-1 SD-1 SD-1 201A T
SD-1 DATA MEXI

I
VESTIBULE 200 200 TU1-214 290 290 290 290 W
320 T203

CO
SD-1 ER-3

NE
H217 SD-1 SD-1 SD-1 TU1-216
320 RG-1 CLASSROOM 280 280 280 60 20505

6"x6"

E ER
P RO
215 ER-2 SD-2
180 210 ES

IN
F
RG-2 SI G
O N A L EN

8"ø
8"x10" 12"x12" 16"x16" 10"x14" 20"x18" 14"x14"
14"x12" TU1-210 60"x18"
SD-1
8"x8"
STORAGE 10"x10"
KEYNOTES
SD-1 S207A
SD-1 SD-1 290

40"x22"
280 1. 20"X50" SUPPLY AIR DUCT DOWN TO LEVEL 1. PROJECT
280 280

8"ø
SD-1 SD-1 SD-2
SD-1 SD-1 SD-1 SD-1 SD-1 60 A1 2. 16"X14" EXHAUST AIR DUCT DOWN TO LEVEL 2.
320 40 RG-1 10"x10"
200 200 290 290 290 ER-2 M-301
WOMEN
STORAGE RG-1 RG-1 RG-1
S217B
RG-1

54"x30"
60"x24" 180 R201 3. 18"X18" EXHAUST AIR DUCT UP TO ROOF.
New Mexico State
A1 / MH-103E
DN
A1 / MH-103E University

A2 / MH-103D
54"x30"

PENTHOUSE
M301
ELECTRICAL ROOM
Jett Hall and Jett Annex
1
E301
Renovations and
Project
North Additions
C2 HVAC SECOND FLOOR PLAN - NORTHWEST
C C

Scale: 1/8" = 1'-0"


0' 4' 8' 16'

Construction
Documents
C2 / MH-103D

MEETING/WAITING
B CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE ROOM SD-1 CHME OFFICE SD-1
B
250 252 254 256 258 260 262 264 230 268 230

10"x12" 10"x12" 10"x12" 10"x12"


14"x12"
8"x12"
SD-1 SD-1 SD-1 SD-1 SD-1 SD-1 SD-1 SD-1
275 275 275 275 275 275 275 275
TU2-208 TU2-205
TU2-207 SD-1 14"x12"
TU2-209
RG-1 RG-1 230
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

12"x10" 12"x10" 12"x10" 12"x10" SD-3


TU2-204 230
SD-1 RG-1 RG-1 RG-1 RG-1 RG-1 RG-1 RG-1 RG-1
250 12"x10" 12"x10"
12"x10" 12"x10" 20"x16"
24"ø SD-1
190
18"ø 20"ø 20"ø 26"ø
TU2-202
CORRIDOR SD-1
KEY PLAN
H203 250

CHME OFFICE 8"x6"


CLASSROOM 26"x14"
STORAGE SD-1 263
12"x12" TU2-210 S257
26"x14" 259
110
TU2-206A RG-1
ER-2 SD-1 SD-1 SD-1 SD-1
60 TU2-206B 275 275 275 275 TU2-203 RG-1 TU2-201
SD-1
RG-1 JANITOR 270
J255 8"x8" 8"x6" SD-1
SD-1 SD-1
270
110 250 Mark Date Description
SD-1 ER-2 RG-1 16"x14"
14"x12"

28"x22"

185 180 14"x14" 10"x12" 10"x12" 14"x14"


Date September 11, 2015
SD-2 2
10"x12"
8"ø

150 CHME OFFICE Project Number 14400


3
20"x18"
265 SD-1
SD-1 Drawn By PZP
10"x10" 10"x10" 270
A SD-1
36"x18" 270
CHME CONFERENCE
A Checked By IM
185 MEN SD-1 SD-1 SD-1 SD-1 ROOM
8"ø

R253 275 275 275 275 Copyright © VAN H. GILBERT ARCHITECT PC


10"x10" 32"x24" 274
40"x30"
WOMEN ER-2 RG-1 RG-1 FSD
CHME OFFICE
R201 180 36"x18" SHEET TITLE
251
FSD

A4 / MH-103E A4 / MH-103E HVAC SECOND FLOOR


9/15/2015 6:42:14 PM

ELECTRICAL ROOM
C2 / MH-103D

Project
E267 50"x32"
North
PLAN - NORTHWEST &
32"x24"

A2 HVAC SECOND FLOOR PLAN - NORTHEAST


Scale: 1/8" = 1'-0"
ACU-12 NORTHEAST
0' 4' 8' 16'
MH-103D
1 2 3 4 5 6 SHEET 114 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH
STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELECTRICAL ROOM ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
E301 LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
PENTHOUSE SPECIFICATIONS 23 0500.
M301
A1
B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR
M-401
EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT
Project G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
North DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
San Diego, CA 92103
H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
Phone 619-297-0159

E3 HVAC PENTHOUSE PLAN - WEST WING 501.

CHME CONFERENCE I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
Scale: 1/8" = 1'-0" ROOM DIAMETER.
274 Lilley Engineering, Inc.
40"x30"
0' 4' 8' 16' RG-1 FSD J. REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
36"x18" Las Cruces, NM 88011
C2 / MH-103D C2 / MH-103D A2 / MH-103D A2 / MH-103D K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
FSD CONNECTIONS TO LABORATORY EQUIPMENT.
Phone 575-521-0006
VESTIBULE
MAE OFFICE DN COMBUSTION LAB STRUCTURAL ENGINEER
H221 ELECTRICAL ROOM
222 RG-1 225 50"x32" SD-3
E267 Stubbs Engineering, Inc.
SD-1 14"x14" LSD-5 340
277 E. Amador Ave. Suite 200

32"x24"
225 RHC2-210A SCV2-210A
240
TYP. 3 ACU-12 Las Cruces, NM 88001
8"x12" ACU-7 Phone 575-993-5228

12"ø
ECV2-210 ECV2-201A
ACU-11 12"ø MECHANICAL/ELECTRICAL ENGINEER
7
SD-1 8"ø
TU1-209 ACU-8
Bridgers & Paxton Consulting Engineers
240
14"x14" 12"ø 4600-C Montgomery Blvd. NE
ELECTRICAL ROOM SCV2-210B 14"x14" Albuquerque, NM 87109
ECV2-211
30"x16" SCV2-201
10"x10" E127 Phone 505-883-4111

12"x12"
ECV2-212
TU1-208 12"ø RHC2-201A SD-3 HAZARDOUS MATERIAL
12"x10"

32"x24"

RG-1 LAB

34"x18"
MAE OFFICE RHC2-210B ECV2-213 340
SD-1 278
224
210
12"x10" RG-1 18"ø ECV2-214

26"x22"
D 12"x12" D

50"x32"
ECV3-204A
8
12"ø
ER-1 ECV2-215 SD-3
SD-1 500 340
MAE OFFICE ECV2-216
120 ECV2-201B
226 SCV2-210C 14"ø
10"x10"
ECV3-204B
1
SD-1
12"ø

RG-1 M ES I
210 L IR T
26"ø

ECV2-202A 12"ø
MEXI

I
30"x16"

I
RG-1 SCV3-204 RHC3-204 ECV2-217 W

CO
NE
10"x10" SD-1 ECV2-218
230 12"ø
ECV2-202B RHC2-202 20505

E ER
RHC2-210C

P RO
MAE OFFICE ANALYTICAL /
ECV2-219

44"x18"
SD-1 TU1-207 SD-1
228 INSTRUMENTATION
ES

IN
6"ø

210 230

F
20"x10" 280 SI G
O N A L EN
22"ø

10"x10" RG-1 RHC3-203 SCV2-202


ER-1 ECV2-220
8"x12"

10"x10"
760
SD-3
KEYNOTES
SCV3-203
26"ø

CORRIDOR 650
1. 28"X14" MAKE-UP AIR DUCT UP FROM LEVEL 1. PROJECT
10"x10" H202 ECV2-221
MAE OFFICE 16"x14" 4
230 SD-1 2. 24"Ø SUPPLY AIR DUCT DOWN TO LEVEL 1.

14"x10"
ECV2-222
210

24"x18"
SD-1 SD-1 SD-1 SCV2-210D
New Mexico State
12"ø

120 3. 28"Ø LAB EXHAUST AIR DUCT DOWN IN CHASE TO LEVEL BELOW.
12"ø

RG-1 230 230


4. 54"x14" LAB EXHAUST AIR DUCT UP THRU OPENING IN CONCRETE TEE
RG-1
30"x16" TO LAB EXHAUST FAN ON ROOF. University
18"ø

TU1-206 ECV2-223
5. 36"x14" LAB EXHAUST AIR DUCT UP THRU OPENING IN CONCRETE TEE
SD-1 RHC2-210D ECV2-224 TO LAB EXHAUST FAN ON ROOF.
MAE OFFICE EXPERIMENTAL ER-1

40"x20"
232 210 RG-1 METHODS LAB 760 14"ø
ECV2-225 6. 16"x38" LAB EXHAUST AIR DUCT DOWN IN CHASE TO LEVEL BELOW. Jett Hall and Jett Annex
8"x12"

SD-3
10"x10" 10"x10" 233 650
7. REFER TO A1/M-401 FOR CONTINUATION OF DUCTWORK INTO
Renovations and

44"x30"
18"ø

ECV2-226 PENTHOUSE.
10"x8"

SD-1 SD-1
14"ø

10"x10"
26"ø

14"x14"
230 230
12"ø
8. OUTSIDE AIR LOUVER. REFER TO ARCHITECTURAL DRAWINGS AND
SPECIFICATIONS. Additions
MAE OFFICE SD-1 ECV2-227 RHC2-203
C 234 SD-1
120
ECV2-228 GLASSWARE / C
210 SCV2-210E 14"ø AUTOCLAVE
SD-3
RG-1 14"ø SCV2-203 282
700
ECV3-203
TU1-203 30"x16" 4
RG-1 ECV2-203 ER-1
TU1-205 RG-1 780
ECV2-229
MAE OFFICE RHC2-210E SD-3
SD-1
236 SD-1 RG-1 ECV2-232
130 SD-1 ECV2-230 660 RHC2-204
210
10"x10" 130 BSL-2 ROOM
10"x10"
24"ø

12"ø
284
18"ø
12"x10"

SCV2-204
10"x10" CHME RESEARCH LAB ER-4
289 ECV2-231 740
14"x14" 16"x14" SD-1 SD-1 ECV2-204
16"ø

SD-1
MAE OFFICE
238
210
TU1-204
SD-1
130
MAE GRADUATE
130 14"ø

ECV2-234
RHC2-205
SD-1
Construction
STUDENT OFFICE SCV2-210F ECV2-233
RG-1
120
237 12"ø 225
SCV2-205 Documents
MEN 36"x26" RG-1 5 30"x16"
14"x12"
24"ø

ER-2 12"ø
R240 SD-2 12"ø

54"x28"
260 140 SD-1 LASER ROOM
12"x12" RHC2-210F ECV2-235
TU1-202 225 286
2 8"ø ECV2-236

18"x18"
SD-1 SD-1 12"ø
ECV2-205A
18"x16"
34"x32"

36"x26" 200 200 ECV2-237 SD-1


225 8"x12"
24"ø

32"x26"
ECV2-238
5'CFH 10"ø 28"ø SD-1
ER-1 225
6"ø

ECV3-202A RG-1 12"ø


ECV2-239 800
RHC3-202 SCV2-210G ECV2-240
16"x16"

12"ø ECV2-205B
SD-1 SD-1
3
SD-3 ECV2-206
200 200 30"x16" RHC2-206
B 340 SCV3-202 B
14"x14"

SD-1
120 RHC2-210G 12"ø ER-1 MICROSCOPE ROOM
ECV2-241 400 SCV2-206 288
HEAT TRANSFER & SD-1
10"ø
18"ø

SURFACE ENGINEERING ECV2-242


360
LAB 12"ø
12"x12"

244 ECV2-243
SD-3 ECV2-207

54"x22"
340 SD-1 SD-1 RHC2-207
200 200 ECV2-244
ER-1
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

380 SCV2-207 EQUIPMENT ROOM

16"x16"
18"x16" 12"ø SD-1 290
14"ø

SCV2-210H 340
ECV2-245 ECV2-246
12"x12"

SD-3
30"x16"
340
SD-1 SD-1 RHC2-209 SCV2-209 KEY PLAN
200 200 ECV2-209
ECV3-202B RHC2-210H ECV2-208A
ER-1 16"x12"
10"ø
630 14"ø SD-3
ECV3-201B 735 SCV2-208
ER-1 RG-1
RENEWABLE ENERGY & 12"ø MULTIMEDIA FD
THERMAL SYSTEMS LAB 1020 INSTRUCTIONAL LAB RHC2-208
18"x12"
RHC3-201 SCV3-201 10"ø
248 245 ER-1
8"ø

1000
SD-3 SD-1
16"x14"

220 20"x14"
345 SD-1 SD-3
SD-3 16"x14" Mark Date Description
38"x16"
220 ECV2-208D 735
345 TU1-201
SD-1 SD-1 8"x12" Date September 11, 2015
12"x12" ENERGETIC MATERIAL
150 150 LAB
10"ø

16"x14" RG-1 Project Number 14400


SD-1 292
12"x10" 220 Drawn By PZP
SD-1 ECV2-208C SD-3
A 4"ø 4"ø 220 735 A Checked By IM
SD-3 SD-3 4"ø
345 345 SD-1 SD-1 Copyright © VAN H. GILBERT ARCHITECT PC
150 150
ECV2-208B
MAE GRADUATE 2"ø
LAB MANAGER OFFICE SHEET TITLE
STUDENT OFFICE 2"ø
4'CFH 10"ø 295
249
ECV3-201A
HVAC SECOND FLOOR
9/15/2015 6:42:20 PM

Project Project
North 6 North
PLAN - EAST & WEST
A1 HVAC SECOND FLOOR PLAN - WEST WING
Scale: 1/8" = 1'-0"
A4 HVAC SECOND FLOOR PLAN - EAST WING
Scale: 1/8" = 1'-0"
WING, & PENTHOUSE
0' 4' 8' 16' 0' 4' 8' 16' MH-103E
1 2 3 4 5 6 SHEET 115 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH
STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
SPECIFICATIONS 23 0500.

B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR


EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT

A2 / MH-123A
G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
San Diego, CA 92103
H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
501. Phone 619-297-0159

I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
DIAMETER.
Lilley Engineering, Inc.
J. REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
Las Cruces, NM 88011
K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
CONNECTIONS TO LABORATORY EQUIPMENT.
Phone 575-521-0006

STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
Phone 575-993-5228

MECHANICAL/ELECTRICAL ENGINEER
Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
Phone 505-883-4111

D D

1 1
CU-1 CU-13
M ES I
L IR T
MEXI

I
W

CO
NE
1 20505

E ER
P RO
CU-2
ES

IN
F
SI G
O N A L EN
KEYNOTES
1. XXXXXX
CONDENSING UNIT INSTALLED ON ROOF SKID PER DETAIL A2/M-504. PROJECT
ROUTE REFRIGERANT PIPING THROUGH ROOF PER DETAIL D5/M-503.
PROVIDE REFRIGERANT PIPING AND ALL ACCESSORIES FOR A
COMPLETE AND FUNCTIONAL SYSTEM PER MANUFACTURER'S
INSTALLATION MANUAL.
New Mexico State
2. ROOFTOP GENERAL EXHAUST FAN ON CURB. REFER TO DETAIL
A1 / MH-123B A1 / MH-123B B5/M-502. University

A2 / MH-123A
CU-14 3. AFTER REMOVING ALL SIX EXISTING RELIEF FANS, INSTALL THE NEW
UNITS IN EXISTING OPENINGS AND BLANK OFF THE OTHER (4) WITH
INSULATED SHEET METAL PLATES.
EF-3 EF-4
CU-15
Jett Hall and Jett Annex
Renovations and
Project
North Additions
C2 MECHANICAL ROOF PLAN - NORTHWEST
C C

Scale: 1/8" = 1'-0"


0' 4' 8' 16'

Construction
Documents
C2 / MH-123A

B B
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

KEY PLAN

2 CU-6

GEF-1

Mark Date Description


Date September 11, 2015
EF-1 EF-2
Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

A4 / MH-123B A4 / MH-123B MECHANICAL ROOF


9/15/2015 6:42:21 PM

3
C2 / MH-123A

Project
CU-3
North
PLAN - NORTHWEST &
A2 MECHANICAL
Scale: 1/8" = 1'-0"
ROOF PLAN - NORTHEAST NORTHEAST
0' 4' 8' 16'
MH-123A
1 2 3 4 5 6 SHEET 116 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. COORDINATE DUCT ROUTING AND EQUIPMENT INSTALLATION WITH
STRUCTURAL PLANS, ARCHITECTURAL PLANS AND ELECTRICAL
PLANS. GIVE SPECIAL ATTENTION TO STRUCTURAL BEAM
ELEVATIONS, CEILING HEIGHTS, CABLE TRAYS, AND ROOF DRAIN
LEADERS. SUBMIT 3D COORDINATION DRAWINGS FOR REVIEW PER
SPECIFICATIONS 23 0500.

B. COORDINATE WITH ARCHITECTURAL REFLECTED CEILING PLAN FOR


EXACT LOCATION OF GRILLES AND DIFFUSERS.
2428 Baylor Dr SE Albuquerque, NM 87106
C. SEE C5/M-501 FOR MEDIUM VELOCITY FITTING DETAILS. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
D. SEE B5/M-501 FOR LOW VELOCITY FITTING DETAILS.
E E Web Site www.vhgarchitect.com
E. SEE DETAILS A2/M-501 FOR DIFFUSER AND REGISTER CONNECTIONS. CONSULTANTS
F. MOUNT TEMPERATURE SENSORS PER SPECIFICATION. LABORATORY CONSULTANT
G. PROVIDE SOUND ELBOW FOR ALL CEILING RETURN AIR GRILLES PER RFD - Research Facilities Design
DETAIL A5/M-501. 3965 Fifth Ave. Suite 400
San Diego, CA 92103
H. PROVIDE TRANSFER AIR DUCT SIZED AS SHOWN. SEE DETAIL A4/M-
501. Phone 619-297-0159
B1
M-301 I. SEE TERMINAL UNIT SCHEDULE, SHEET M-702, FOR INLET DUCT CIVIL ENGINEER
DIAMETER.
Lilley Engineering, Inc.
C2 / MH-123A C2 / MH-123A A2 / MH-123A A2 / MH-123AJ. REFER TO SHEETS M-501 THROUGH M-504 FOR MECHANICAL DETAILS. 5160 Calle Bellisima
Las Cruces, NM 88011
K. REFER TO LAB DRAWINGS FOR EXACT LOCATION AND SIZE OF
Phone 575-521-0006
1
CONNECTIONS TO LABORATORY EQUIPMENT.
CU-14
CU-3
1
STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
1
EF-3 EF-4
CU-15
277 E. Amador Ave. Suite 200
CU-4
Las Cruces, NM 88001
1
CU-7 1
Phone 575-993-5228
EF-6 EF-5 CU-5 MECHANICAL/ELECTRICAL ENGINEER
1
CU-8 1 Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
6 CU-11 Albuquerque, NM 87109
1 Phone 505-883-4111
1
CU-12

D D

4
M ES I
L IR T
MEXI

I
W

CO
NE
20505

E ER
P RO
ES

IN
F
SI G
O N A L EN
54x14 EXHAUST DUCT
THROUGH ROOF
KEYNOTES
1. CONDENSING UNIT INSTALLED ON ROOF SKID PER DETAIL A2/M-504. PROJECT
ROUTE REFRIGERANT PIPING THROUGH ROOF PER DETAIL D5/M-503.
PROVIDE REFRIGERANT PIPING AND ALL ACCESSORIES FOR A
COMPLETE AND FUNCTIONAL SYSTEM PER MANUFACTURER'S

HRC-7 HRC-8
INSTALLATION MANUAL.
New Mexico State
2. ROOFTOP GENERAL EXHAUST FAN ON CURB. REFER TO DETAIL
LABORATORY EXHAUST FAN
B5/M-502. University
ON STRUCTURAL SUPPORT. 3. UTILITY SET FAN. SEE DETAIL B4/M-503.
REFER TO STRUCTURAL
DRAWINGS. 4. S.O.A.P. STATION. SEE DETAIL B4/M-502.

LABORATORY EXAHUST
LEF-1
5. 8" STEAM RELIEF THROUGH ROOF.
Jett Hall and Jett Annex
FAN ON STRUCTURAL
SUPPORT. REFER TO
STRUCTURAL DRAWINGS.
6" HRS 6. 3" STEAM VENT THROUGH ROOF FROM CONDENSATE PUMP. Renovations and
6" HRR
7. 4" HRS/R PIPING THROUGH ROOF.
Additions
C EF-7
HRC-9 HRC-10 C
3
54x14 EXHAUST DUCT
THROUGH ROOF

1
LEF-2
CU-10

7
HRC-11
1
CU-9

Construction
36x14 EXHAUST DUCT
ROOF PENETRATION Documents
2
GEF-2

B B
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

KEY PLAN

Mark Date Description


Date September 11, 2015
Project Number 14400
Drawn By PZP
A 5 A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL ROOF
9/15/2015 6:42:22 PM

Project Project Project


North North North
PLAN - ANNEX, EAST &
A1 MECHANICAL
Scale: 1/8" = 1'-0"
ROOF PLAN - WEST WING A2 MECHANICAL
Scale: 1/8" = 1'-0"
ROOF PLAN - ANNEX A4 MECHANICAL
Scale: 1/8" = 1'-0"
ROOF PLAN - EAST WING WEST WING
0' 4' 8' 16' 0' 4' 8' 16' 0' 4' 8' 16' MH-123B
1 2 3 4 5 6 SHEET 117 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. SEE EQUIPMENT SCHEDULE FOR PIPE SIZES TO EACH TERMINAL UNIT,
DUCT MOUNTED HEATING COILS, AND FAN COIL UNITS.

B. SEE DETAIL A2/M-503 AND B4/M-501 FOR PIPING PENETRATION DETAIL.

C. SEE DETAIL A1/M-503 FOR PIPE HANGING DETAIL.

D. VENT ALL HIGH POINTS IN PIPING SYSTEMS PER DETAIL A2/M-502.

E. PROVIDE DRAINS AT ALL LOW POINT OF PIPING SYSTEMS PER DETAIL 2428 Baylor Dr SE Albuquerque, NM 87106
A5/M-502. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
F. SEE SHEET M-501 THROUGH M-504 FOR MECHANICAL DETAILS.
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159

CIVIL ENGINEER
Lilley Engineering, Inc.
5160 Calle Bellisima
Las Cruces, NM 88011
MAE COMPUTER
Phone 575-521-0006
MAE COMPUTER LAB MAE COMPUTER LAB
THERMAL SCIENCE LAB SUPPORT
006 004
016 010 STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
FCU-1 FCU-2 FCU-3
MECHANICAL Phone 575-993-5228
SUPPORT
RHC3-001 M002
012
MECHANICAL/ELECTRICAL ENGINEER
SCV3-001 Bridgers & Paxton Consulting Engineers
1" 1" CHWR 2" 4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
Phone 505-883-4111
STORAGE SCV3-007 RHC3-007 6
S018A CORRIDOR CHWS 2"
H002
6
1 1/4" 1 1/4" 1 1/2" 1 1/2" 1 1/2" 1 1/2" HWR 1 1/2" 2"

D D
1 1/4" 1 1/4" 1 1/2" 1 1/2" 1 1/2" 1 1/2" HWS 1 1/2" 2"
JANITOR
2" CHWR J003
STORAGE 2" CHWS
AEROSPACE 2" HWR
S017A STRUCTURAL ACU-1
2" HWS
DYNAMICS LAB
RHC3-002 OFFICE 009
WOMEN M ES I
VESTIBULE SOLID MECHANICS LAB SCV3-002 011
NON-LINEAR DYNAMICS R001 L IR T
MEXI

I
RHC3-004

I
H017 015 RHC3-003 & ENERGY HARVESTING W
RHC3-005

CO
NE
ACU-2 RHC3-006 005
SCV3-004
RHC3-008 CHASE 20505
SCV3-003 001B

E ER
P RO
SCV3-005 SCV3-008
SCV3-006
ES

IN
F
FLIGHT RESEARCH LAB SI G
013 O N A L EN
ELEVATOR EQUIPMENT
M017B
KEYNOTES
1. 2" CHWS/R AND 2" HWS/R PIPING UP TO LEVEL ABOVE. PROJECT
1 DATA
T005 2. PROVIDE THREE NEW ISOLATION VALVES. ONE ISOLATION VALVE
SHALL BE INSTALLED IN THE NEW PIPE AND THE OTHER TWO IN THE
EXISTING PIPE (UPSTREAM AND DOWNSTREAM OF CONNECTION).
CONTRACTOR SHALL SUBMIT DRAWINGS TO ENGINEER AND NMSU New Mexico State
FOR APPROVAL BEFORE INSTALLATION.

3. PROVIDE ONE NEW ISOLATION VALVE IN NEW PIPE. CONTRACTOR


University
SHALL SUBMIT DRAWINGS TO ENGINEER AND NMSU FOR APPROVAL
BEFORE INSTALLATION.
Project

C1 MECHANICAL PIPING PLAN - BASEMENT Jett Hall and Jett Annex


North 4. EXISTING UTILITY PIPING IN TUNNEL.

Scale: 1/8" = 1'-0" 5.

6.
NEW CHWS/R, PC, AND HPS PIPING UP INTO ANNEX.

PROVIDE LINE-SIZE ISOLATION VALVES.


Renovations and
5
0' 4' 8' 16' Additions
C C

A2 / MP-103C A2 / MP-103C

Construction
Documents

6" CHWR
B B
6" CHWS
4" PC
4" HPS
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

KEY PLAN

ELECT
266E

Mark Date Description


Date September 11, 2015
Project Number 14400

4
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC
2 3
SHEET TITLE
2 3
Project
North
MECHANICAL PIPING
9/15/2015 6:42:29 PM

A3 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING PLAN - TUNNEL PLAN - BASEMENT
0' 4' 8' 16'
MP-103A
1 2 3 4 5 6 SHEET 118 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. SEE EQUIPMENT SCHEDULE FOR PIPE SIZES TO EACH TERMINAL UNIT,
DUCT MOUNTED HEATING COILS, AND FAN COIL UNITS.

B. SEE DETAIL A2/M-503 AND B4/M-501 FOR PIPING PENETRATION DETAIL.

C. SEE DETAIL A1/M-503 FOR PIPE HANGING DETAIL.

D. VENT ALL HIGH POINTS IN PIPING SYSTEMS PER DETAIL A2/M-502.

E. PROVIDE DRAINS AT ALL LOW POINT OF PIPING SYSTEMS PER DETAIL 2428 Baylor Dr SE Albuquerque, NM 87106
DN A5/M-502. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
F. SEE SHEET M-501 THROUGH M-504 FOR MECHANICAL DETAILS.
E E Web Site www.vhgarchitect.com
DN CONSULTANTS

LABORATORY CONSULTANT

A2 / MP-103B
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159

CIVIL ENGINEER
Lilley Engineering, Inc.
5160 Calle Bellisima
Las Cruces, NM 88011
Phone 575-521-0006

STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
CHME OFFICE 277 E. Amador Ave. Suite 200
MAE OFFICE 150
104B MAIL Las Cruces, NM 88001
CONFERENCE ROOM MAE OFFICE MAE OFFICE MAE OFFICE MAE OFFICE MAE OFFICE 104A Phone 575-993-5228
MAE DIRECTORS LOBBY
116 114 112 110 108 106 OFFICE SUITE H100
104 MECHANICAL/ELECTRICAL ENGINEER
TU1-114 Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
TU1-116
TU1-121 Albuquerque, NM 87109
TU1-110 Phone 505-883-4111
1" TU1-117 TU1-118
1" TU1-112

3" TU1-122 3" 3" CHWS 3"


D D
2
3" 3" 3" CHWR 3"
3" CHWS 3" 4"
3" CHWR 3" 4" 4"
4"
3"
3"
3"
3" HWS 3" M ES I
L IR
3" 3" 3" HWR 3" 3" HWS 4"
3" 3"
3" 3" 3" 3" HWR 4" UNISEX T
MEXI

I
OFFICE SUPPORT

I
R101 W
MAE SEMINAR BREAK ROOM

CO
117C 117D

NE
3"
2
3" 113 105A 20505
3" 3"

E ER
P RO
WOMEN
TU1-115 TU1-119 ES

IN
TU1-109 TU1-111 TU1-113 R151

F
TU1-120 SI G
VESTIBULE 3" O N A L EN
H117 CLASSROOM 6"
COMPUTATIONAL FLOW 109
3"
6" KEYNOTES
STORAGE 3" PHYSICS LAB - I
1
S117B 3"
3" 111 1. 2" HWS/R AND 2" CHWS/R PIPING DOWN TO BASEMENT. PROJECT
3" STORAGE
S117A MAE GRADUATE MAE OFFICE
STUDENT OFFICE 2. PROVIDE LINE-SIZE ISOLATION VALVES.
105
115
DN
3. 6" HRS/R PIPING UP FROM BASEMENT IN CHASE. SEE LEVEL ABOVE
FOR CONTINUATION. New Mexico State
A1 / MP-103C
STORAGE 3" CHWS
A1 / MP-103C 4. 6" CHWS/R PIPING DOWN IN CHASE TO BASEMENT. SEE LEVEL BELOW
FOR CONTINUATION.
University

A2 / MP-103B
CHWR HWS
S120 3" CHWR CHWS HWR 5. 4" HWS/R PIPING DOWN IN CHASE TO BASEMENT. SEE LEVEL BELOW
3" HWS 6" 6" FOR CONTINUATION.
3" HWR 6" 6" Jett Hall and Jett Annex
UP
Renovations and
Project
North Additions
C2 MECHANICAL PIPING FIRST FLOOR PLAN - NORTHWEST
C C

Scale: 1/8" = 1'-0"


0' 4' 8' 16'

Construction
Documents
C2 / MP-103B

CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE
150 152 154 156 158 160 162 164 166
B B
TU2-113 CHME OFFICE
TU2-115 TU2-114 TU2-106
168
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

TU2-112 CORRIDOR TU2-105


H161

4" 4" 4" 4"


4" 4" 4"
4"
4"
4"
4"
4"
4"
4"
4"
4"
4"
4"
4"
4"
4"
KEY PLAN
STOR
157
TU2-111 4" HWS 4"
JANITOR TU2-104 4"
4" 4" HWR
J155 CHME OFFICE TU2-108
159A TU2-110 CHME GRADUATE TU2-107
TU2-109 CHME OFFICE TU2-103
STUDENT COMPUTER CHME OFFICE 163
CLUSTER 159G 4"
DATA ROOM ACU-6 4"
WOMEN 159
T165
R151 MEN 2
4 5
R153
3 Mark Date Description
CHWS
6" CHWR Date September 11, 2015
2 HWR
6"
HWS Project Number 14400
DN
2
Drawn By PZP
CHME OFFICE
A CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE A
159C Checked By IM
159B 159D 159E 159F
2" Copyright © VAN H. GILBERT ARCHITECT PC
2"
A4 / MP-103C A4 / MP-103C
C2 / MP-103B

ELECTRICAL ROOM SHEET TITLE


E167
ACU-5
MECHANICAL PIPING
9/15/2015 6:42:31 PM

Project
North
FIRST FLOOR PLAN - NW
A2 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING FIRST FLOOR PLAN - NORTHEAST & NE
0' 4' 8' 16'
MP-103B
1 2 3 4 5 6 SHEET 119 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. SEE EQUIPMENT SCHEDULE FOR PIPE SIZES TO EACH TERMINAL UNIT,
DUCT MOUNTED HEATING COILS, AND FAN COIL UNITS.

B. SEE DETAIL A2/M-503 AND B4/M-501 FOR PIPING PENETRATION DETAIL.

C. SEE DETAIL A1/M-503 FOR PIPE HANGING DETAIL.

D. VENT ALL HIGH POINTS IN PIPING SYSTEMS PER DETAIL A2/M-502.

E. PROVIDE DRAINS AT ALL LOW POINT OF PIPING SYSTEMS PER DETAIL 2428 Baylor Dr SE Albuquerque, NM 87106
A5/M-502. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
F. SEE SHEET M-501 THROUGH M-504 FOR MECHANICAL DETAILS.
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
A4 A1 San Diego, CA 92103
M-402 M-301 Phone 619-297-0159

C1 CHME OFFICE
CHME OFFICE CHME OFFICE
CIVIL ENGINEER
159C
CHME OFFICE
M-401
159D 159E 159F Lilley Engineering, Inc.
C2 / MP-103B C2 / MP-103B A2 / MP-103B 2" A2 / MP-103B
2"
5160 Calle Bellisima
Las Cruces, NM 88011
STORAGE MECHANICAL
S120 3" CHWS M123 ELECTRICAL ROOM Phone 575-521-0006
HWR
3" CHWR E167 HWS
3" HWS 3 ACU-5 STRUCTURAL ENGINEER
3" HWR 2" HWR Stubbs Engineering, Inc.
UP 2" HWS 3" CHWR MECHANICAL ROOM 277 E. Amador Ave. Suite 200
3" CHWS M198
VESTIBULE LOBBY Las Cruces, NM 88001
H122 DN Phone 575-993-5228
H121
2" TU2-101
2" MECHANICAL/ELECTRICAL ENGINEER
Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
HRR 2 4" HRR
MAE OFFICE HRS 4" HRS
Albuquerque, NM 87109
124 HWS Phone 505-883-4111
HWR
CHME COMPUTER LAB
LPS 177 CHME STUDENT
PC HWS PROJECT/STUDY AREA
HWR 178
MAE OFFICE CHWS
AHU-4
D 126 CHWR D
2" MAE STUDENT LOUNGE 5 6
2" 2"
125 2"
4" 3
4"
TU1-107 6" 1 1/4" HWR TU2-102 2"
6" 1 1/4" HWS 2"
M ES I
L IR
2" 1 1/2" CHWR STORAGE
4" 2" S180
T
1 1/2" CHWS MEXI

I
MAE OFFICE 4"

I
HWS W
TU1-108

CO
128 HWR

NE
STUDENT PROJECTS 20505
CENTER

E ER
P RO
196 RHC2-101 ES

IN
F
SCV2-101 SI G
MAE OFFICE O N A L EN
2"
130 2"
CORRIDOR BREAKROOM 2"
2" KEYNOTES
H102 179
SCV3-108 1. PROVIDE LINE-SIZE ISOLATION VALVES. PROJECT
MAE WELDING
RHC3-108 182
2" 2. 4" HRS/R PIPING UP TO LEVEL ABOVE.
TU1-106 2"

1 1/2" RHC2-102
SCV2-102
HWS
3. PIPE ANCHORS.
New Mexico State
MAE OFFICE MECHATRONICS LAB 4. PIPE GUIDES.
132 1 1/2" 133
HWR
5. SEE D4/M-502 FOR CHILLED WATER COIL CONNECTIONS DETAIL.
University
HRR 2"
2" 6. SEE D5/M-502 FOR HOT WATER COIL CONNECTIONS DETAIL.
HRS

HWS
7. STEAM PRV ASSEMBLY LOCATED IN CEILING SPACE ABOVE OFFICE.
REFER TO DETAIL A4/M-503.
Jett Hall and Jett Annex
MAE OFFICE
134
HWR CHME MINATURE
CHEMICAL PILOT PLANT
HWS
HWR 8. NEW 6" CHWS/R, 4" PC AND 4" HPS UP FROM TUNNEL. Renovations and
184
STORAGE
S196B MAE OFFICE
SCV2-106 Additions
1 1/2"
C TU1-105 196A RHC2-106 C
1 1/2"
SCV2-103 1 1/2"
RHC2-103 1 1/2"
TU1-103 MAE COMPUTER
MAE OFFICE
(GRADUATE) LAB ACU-10
136 RHC2-104 HWR
137 AHU-5 MAE OFFICE SCV2-104 HWS
191A
1 1/2" MDF
SCV3-107 137A VFD-12 1 1/2" 4
1 1/2"
RHC3-107 1 1/2" 1 1/2"
MAE OFFICE ACU-9 1 1/2"
138
1 1/2" 5 6
1 1/2"
1 1/2" 1 1/2"
MAE LAB
TU1-104 1 1/2"
SCV3-106
RHC3-106
191
SCV2-105
1 1/2"
Construction
1 1/2"
WOMEN 4"
R140 4"
AERO FLUIDS LAB
194
RHC2-105 1 1/2" Documents
4 MAE ROBOTICS LAB
1 1/4" 191B 4
1 1/4"
AUTONOMOUS REDUCED GRAVITY LAB
SYSTEMS LAB 191C
141 1 1/4"
2 1 1/4"
1 1/4"
1 1/4"
UNISEX HWS
R142 HWR
1 1/4"
1 1/4"
RHC3-103 SCV3-103 4

B B
MAE CAPSTONE
PROJECTS - I
HWS SCV2-107A SCV2-107B
145
HWR
SCV3-105 4
COMPOSITES LAB RHC2-107A RHC2-107B
4" 4" 14'x7' PIPE
144 EXPANSION LOOP
RHC3-105

SCV3-104 CHWS LPS


1 1/4" PC
1 1/4" RHC3-104 CHWR CHME
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

UNDERGRADUATE LAB
193
RHC3-102
4
1"
SCV3-102 1"
MAE MATERIALS LAB 4"
HWS 147
HWR 4"
6"
KEY PLAN
MAE LAB
146 6"
1"
SCV3-101 1" VESTIBULE
MAE OFFICE
H149 194A
3
COMPUTATIONAL FLOW
PHYSICS LAB - II
RHC3-101 149A LPS
3/4"
3/4" 3/4" HWS PC
HWR
3
3/4" TU1-102
MAE CAPSTONE
PROJECTS - II CHWR
148 CHWS
GRADUATE STUDENT 4" HPS
OFFICE Mark Date Description
149B
Date September 11, 2015
A3 / MP-103A A3 / MP-103A
7 Project Number 14400
8
TU1-101
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

DN
MECHANICAL PIPING
9/15/2015 6:42:33 PM

UP Project Project Project


North North North
FIRST FLOOR PLAN -
A1 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING FIRST FLOOR PLAN - WEST WING A2 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING FIRST FLOOR PLAN - ANNEX A4 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING FIRST FLOOR PLAN - EAST WING ANNEX, E & W WING
0' 4' 8' 16' 0' 4' 8' 16' 0' 4' 8' 16' MP-103C
1 2 3 4 5 6 SHEET 120 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. SEE EQUIPMENT SCHEDULE FOR PIPE SIZES TO EACH TERMINAL UNIT,
DUCT MOUNTED HEATING COILS, AND FAN COIL UNITS.

B. SEE DETAIL A2/M-503 AND B4/M-501 FOR PIPING PENETRATION DETAIL.

C. SEE DETAIL A1/M-503 FOR PIPE HANGING DETAIL.

D. VENT ALL HIGH POINTS IN PIPING SYSTEMS PER DETAIL A2/M-502.

E. PROVIDE DRAINS AT ALL LOW POINT OF PIPING SYSTEMS PER DETAIL 2428 Baylor Dr SE Albuquerque, NM 87106
A5/M-502. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
F. SEE SHEET M-501 THROUGH M-504 FOR MECHANICAL DETAILS.
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT

A2 / MP-103D
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159

CIVIL ENGINEER
Lilley Engineering, Inc.
5160 Calle Bellisima
Las Cruces, NM 88011
Phone 575-521-0006

STRUCTURAL ENGINEER
CHME OFFICE Stubbs Engineering, Inc.
250 277 E. Amador Ave. Suite 200
MAE OFFICE Las Cruces, NM 88001
204 Phone 575-993-5228
CLASSROOM MECHANICAL/ELECTRICAL ENGINEER
216 CLASSROOM
CLASSROOM CLASSROOM 206 Bridgers & Paxton Consulting Engineers
TU1-215
210 208 4600-C Montgomery Blvd. NE
TU1-217 Albuquerque, NM 87109
TU1-218
Phone 505-883-4111
1 1/4"
TU1-211 TU1-213
1 1/4"

3" HWR 3" 4" 4"


D D
3" HWS CORRIDOR 3" 4" 4" 1 4"
1 HWR
4" CHWS H201 4" 4" 4" 4" 4"
4" CHWR 4" 4" 4" 4" HWS
TU1-219

1 M ES I
ACU-13
L IR
JANITOR
CLASSROOM HWR CHWS 201A
T
MAE OFFICE DATA MEXI

I
215 HWS CHWR T203 6" W
217A

CO
VESTIBULE

NE
4" 6"
H217 4" 20505

E ER
P RO
3" TU1-214 CLASSROOM CLASSROOM
TU1-212 TU1-216
4" 213 207 ES

IN
3"

F
SI G
TU1-210 4" CHME OFFICE O N A L EN
HWR WOMEN 251
CHWR
HWS R201
KEYNOTES
CHWS STORAGE
S207A 1. PROVIDE LINE-SIZED ISOLATION VALVES. PROJECT
STORAGE
S217B 2. 6" HRS/R PIPING UP IN CHASE FROM BELOW.

New Mexico State


A1 / MP-103E
DN
ELECTRICAL ROOM
A1 / MP-103E
HWS
University

A2 / MP-103D
E301 CHWR
HWR
CHWS
2" HWS
2" HWR
2"
2" 6"
6"
6" Jett Hall and Jett Annex
6"
Renovations and
Project
North Additions
C2 MECHANICAL PIPING SECOND FLOOR PLAN - NORTHWEST
C C

Scale: 1/8" = 1'-0"


0' 4' 8' 16'

Construction
Documents
C2 / MP-103D

CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE CHME OFFICE
250 252 254 256 258 260 262 MEETING/WAITING
ROOM
B 264 B
CHME OFFICE
268
TU2-209 TU2-208 TU2-207 TU2-205 TU2-204
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

CORRIDOR
4" 4" HWR 4" H203
TU2-202 4" 4" HWS 4" HWR
4" HWS 1"
4" 1"
HWR
HWS 4"
4" CHME OFFICE KEY PLAN
STORAGE 263
TU2-210 S257 4" TU2-201
4"

JANITOR TU2-206A TU2-203


MEN
J255
R253
TU2-206B CHME OFFICE
HWS
265 CHME CONFERENCE
CLASSROOM HWR ROOM
259 274
CHME OFFICE
WOMEN 251 2 Mark Date Description
4"
1" 1"
R201 4"
Date September 11, 2015

6" HRR Project Number 14400


6" HRS
Drawn By PZP
1
A HWS A Checked By IM
HWR
Copyright © VAN H. GILBERT ARCHITECT PC
A4 / MP-103E 2" A4 / MP-103E
HAZARDOUS MATERIAL
C2 / MP-103D

ELECTRICAL ROOM SHEET TITLE


LAB
E267
HWR 278
MECHANICAL PIPING
9/15/2015 6:42:34 PM

ACU-12 Project
North
SECOND FLOOR PLAN -
A2 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING SECOND FLOOR PLAN - NORTHEAST NW & NE
0' 4' 8' 16'
MP-103D
1 2 3 4 5 6 SHEET 121 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
GENERAL NOTES
A. SEE EQUIPMENT SCHEDULE FOR PIPE SIZES TO EACH TERMINAL UNIT,
DUCT MOUNTED HEATING COILS, AND FAN COIL UNITS.

B. SEE DETAIL A2/M-503 AND B4/M-501 FOR PIPING PENETRATION DETAIL.

C. SEE DETAIL A1/M-503 FOR PIPE HANGING DETAIL.

D. VENT ALL HIGH POINTS IN PIPING SYSTEMS PER DETAIL A2/M-502.

E. PROVIDE DRAINS AT ALL LOW POINT OF PIPING SYSTEMS PER DETAIL 2428 Baylor Dr SE Albuquerque, NM 87106
A5/M-502. Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
F. SEE SHEET M-501 THROUGH M-504 FOR MECHANICAL DETAILS.
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
6" HRR
Phone 619-297-0159
B1 6" HRS
3" CHWS
3" CHWR M-301
STORAGE CIVIL ENGINEER
S117A HWS Lilley Engineering, Inc.
C2 / MP-103D 3" HWS C2 / MP-103D A2 / MP-103D HWR A2 / MP-103D
3" HWR
5160 Calle Bellisima
Las Cruces, NM 88011
DN 2"
2" HAZARDOUS MATERIAL Phone 575-521-0006
ELECTRICAL ROOM ELECTRICAL ROOM
LAB
E127 E267
VESTIBULE HWR 278 STRUCTURAL ENGINEER
COMBUSTION LAB 3" HWS SCV2-210A HWR
H221 3" HWS Stubbs Engineering, Inc.
MAE OFFICE 225 ACU-12
222 ACU-7 277 E. Amador Ave. Suite 200
TU1-209
2"
Las Cruces, NM 88001
ACU-11 RHC2-210A 2" Phone 575-993-5228
RHC2-201A
ACU-8
MECHANICAL/ELECTRICAL ENGINEER
1 HRR Bridgers & Paxton Consulting Engineers
FOR CONTINUATION SHEET SEE SCV2-210B
RHC2-210B HRS SCV2-201 4600-C Montgomery Blvd. NE
2" PENTHOUS PLAN A1/M-401 Albuquerque, NM 87109
TU1-208 1"
2" HWR Phone 505-883-4111
HWS
MAE OFFICE
HWS
224 1"
HWS HWR
HWR

D D
MAE OFFICE
226
2"
2" 3" 6"
3" 2"
6"
2"

SCV2-210C RHC2-210C M ES I
L IR T
RHC2-202 MEXI

I
2" SCV3-204 RHC3-204 W

CO
NE
TU1-207 2"
MAE OFFICE 20505
228 SCV2-202

E ER
P RO
HWR ES

IN
HWS

F
RHC3-203 SI G
CORRIDOR HWS
SCV3-203 HWS O N A L EN
MAE OFFICE H202 HWR HWR
230 KEYNOTES
3" ANALYTICAL / 1. PIPE ANCHORS.
3" PROJECT
INSTRUMENTATION
280 2. PIPE GUIDES.
1 1/2"

TU1-206
1 1/2" EXPERIMENTAL
METHODS LAB SCV2-210D RHC2-210D
3. 6" HRS/R PIPING UP THROUGH ROOF TO HEAT RECOVERY COILS.
New Mexico State
4. 4" HRS/R PIPING UP THROUGH ROOF TO HEAT RECOVERY COILS.

2
233
CHME RESEARCH LAB 5. 4" HRS/R PIPING DOWN IN CHASE. SEE LEVEL BELOW FOR CONTINUATION.
University
289
MAE OFFICE
232 1 1/2" 2 1/2"
1 1/2"
2 1/2" 2" Jett Hall and Jett Annex
2"
MAE OFFICE
234
1 1/2"
1 1/2"
Renovations and
1 1/2" RHC2-210E 3 RHC2-203
SCV2-203
Additions
C 1 1/2" C
HWS
2 SCV2-210E HWR
GLASSWARE /
TU1-205 AUTOCLAVE
TU1-203 282
MAE GRADUATE HWS 1 1/2"
STUDENT OFFICE HWR 1 1/2"
MAE OFFICE 1 1/2" 237 RHC2-204
236
1 1/2"
MAE OFFICE 2 1/2" HWS SCV2-204
2 1/2" BSL-2 ROOM
238
4
HWR
284

1 1/2"
1 1/2"
TU1-204 HWS
HWR
RHC2-210F RHC2-205

SCV2-205
Construction
MEN
4"
4"
SCV2-210F
LASER ROOM
Documents
R240 286
HRS
HRR 1 1/2"
HWS
1 1/2" 1 1/2"
HWR
1 1/2"
5
2"
1 1/4" TU1-202
5'CFH 2"
1 1/4"
HWR
HWS

RHC3-202 HWS RHC2-210G


HWR
SCV2-210G RHC2-206
SCV3-202

HEAT TRANSFER &


B SURFACE ENGINEERING SCV2-206 B
1 1/4"
LAB MICROSCOPE ROOM
1 1/4"
244 HWS 288
MULTIMEDIA
INSTRUCTIONAL LAB HWR
245 HWS
RHC2-207
HWR
SCV2-207

1 1/2" 1 1/4" EQUIPMENT ROOM


1 1/2" 1 1/4" 290
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

RHC2-210H
SCV2-210H HWS RHC2-209
1 1/4"
HWR
1 1/4" SCV2-209

KEY PLAN
SCV2-208
1"
1"

RHC2-208
1
RHC3-201
SCV3-201 ENERGETIC MATERIAL
LAB
292
MAE GRADUATE
STUDENT OFFICE
Mark Date Description
RENEWABLE ENERGY & 249
THERMAL SYSTEMS LAB TU1-201 LAB MANAGER OFFICE Date September 11, 2015
248 295
Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC
4'CFH
SHEET TITLE

MECHANICAL PIPING
9/15/2015 6:42:36 PM

Project Project
North North
2ND FLOOR PLAN - E &
A1 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING SECOND FLOOR PLAN - WEST WING A4 MECHANICAL
Scale: 1/8" = 1'-0"
PIPING SECOND FLOOR PLAN - EAST WING W WING, &PENTHOUSE
0' 4' 8' 16' 0' 4' 8' 16' MP-103E
1 2 3 4 5 6 SHEET 122 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

LABORATORY EXHAUST FAN ON STRUCTURAL


SUPPORT. REFER TO STRUCTURAL DRAWINGS.
LEF-1

HRC-7 HRC-9
2428 Baylor Dr SE Albuquerque, NM 87106
Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT

14"x50"

14"x54"
14"x50"

14"x54"
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159
18"x34" 18"x44" 12"ø 14"ø 20"x40" 28"x54" 22"x54" 16"x38"
CIVIL ENGINEER
Lilley Engineering, Inc.
5160 Calle Bellisima
Las Cruces, NM 88011
CHME RESEARCH LAB CHME RESEARCH LAB Phone 575-521-0006
289 289
STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
12"x18" 10"x14" Phone 575-993-5228

SCV2-106 MECHANICAL/ELECTRICAL ENGINEER


RHC2-106 Bridgers & Paxton Consulting Engineers
CHME STUDENT CHME MINATURE
SD-3
SD-3
SCV2-107B RHC2-107B 4600-C Montgomery Blvd. NE
PROJECT/STUDY AREA CHEMICAL PILOT PLANT 690 CHME Albuquerque, NM 87109
690
178 184 UNDERGRADUATE LAB Phone 505-883-4111
REDUCED GRAVITY LAB 193 STORAGE
191C S193

D D

D1 MECHANICAL
Scale: 3/16" = 1'-0"
EAST WING SECTION L IR
M ES I
MEXI
T

I
W

CO
NE
20505

E ER
P RO
ES

IN
F
SI G
O N A L EN

PROJECT

LEF-2 LABORATORY EXHAUST FAN ON STRUCTURAL

HRC-11
SUPPORT. REFER TO STRUCTURAL DRAWINGS.
New Mexico State
University
48"x96"

30"x54"
Jett Hall and Jett Annex
Renovations and

14"x36"

14"x36"
Additions
C 18"ø 16"ø 12"ø C
24"x32"

20"x50"
CORRIDOR CORRIDOR
H202 H202

16"ø 18"ø 26"ø 24"ø 24"ø 18"x24"


Construction
ECV3-104
Documents
CORRIDOR
H102 CORRIDOR
H102

B1 MECHANICAL
Scale: 3/16" = 1'-0"
WEST WING SECTION
B B
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

PRV-2 22"ø 26"ø 20"ø 20"ø 26"ø

PRV-1

FCU-5
AHU-5 AHU-4
STUDENT PROJECTS
AERO FLUIDS LAB CENTER
194 MAE OFFICE 196 FMS HXP-1
MAE OFFICE 196A
194A VFD-11 VFD-7
Mark Date Description
Date September 11, 2015
Project Number 14400
MECHANICAL ROOM Drawn By PZP
M198
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

A1 MECHANICAL ANNEX SECTION SHEET TITLE

Scale: 3/16" = 1'-0"


MECHANICAL SECTIONS
9/15/2015 6:41:46 PM

M-301
1 2 3 4 5 6 SHEET 123 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

1
M-402

6 7 9 8

2428 Baylor Dr SE Albuquerque, NM 87106

AA AB
Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
DOUBLE WALL San Diego, CA 92103
PLENUM, SEE DETAIL
B1/M-504
Phone 619-297-0159

CIVIL ENGINEER

CHWS

CHWR

HWS
HWR
HRR
HRS
6" CHWS
A1 Lilley Engineering, Inc.
M-301 5160 Calle Bellisima
6" CHWR
5'-0"x4'-0" DAMPER Las Cruces, NM 88011
ELECTRICAL ROOM
E001
Phone 575-521-0006

STRUCTURAL ENGINEER
A1
FILTERS Stubbs Engineering, Inc.

6"
AIR LOCK
ACU-4 SF-1
277 E. Amador Ave. Suite 200

6"
OA SUPPLY FAN ARRAY Las Cruces, NM 88001
SHAFT OA
Phone 575-993-5228

6"

6"
ALL PIPING TO PENETRATE
EXTERIOR WALL AT 0'-10" MECHANICAL/ELECTRICAL ENGINEER
6"
ABOVE SECOND FLOOR SLAB. ACU-3
6"
Bridgers & Paxton Consulting Engineers

4"
4600-C Montgomery Blvd. NE

4"
6" CHWR
Albuquerque, NM 87109
6" CHWS
Phone 505-883-4111
6" HWR

HRR
HRS
CWC-1,2,3
6" HWS
COOLING COILS
(STACKED)
TYPICAL CWC-4,5,6
D ACCESS DOOR D
HWS 4"

A2
VESTIBULE HWR 4"
H001 6"
6" PCP-2
CHWP-2
COIL PUMP
VFD-10 M ES I
L IR
A3
VFD-9 T
MEXI

I
PHC-1,2,3 PHC-4,5,6 PRE-HEAT COILS W

CO
HRS
HRR
MECHANICAL ROOM

NE
(STACKED)
M003 20505
CHWP-1

E ER
P RO
HEAT RECOVERY COILS ES

IN
F
HRC-1,2,3 HRC-4,5,6 (STACKED) G
SI
HXP-1 O N A L EN
FILTERS

6"
6"
HWR CP-1 2 1/2" 2 1/2"

4"

4"
HWS
CHWR

4"
PROJECT
CHWS

4"
FCU-4 FCU-5
VFD-7
10 10

6" 6"
6" HRR
HRS
4"
4"
New Mexico State
VFD-8
MECHANICAL ROOM
M198 2" University
GFP-1 11
FMS
Jett Hall and Jett Annex
6" CHWR
6" CHWS
4" LPS
4" PC 2"
2"
VFD-11
5
HRP-2
Renovations and
ENERGY
RECOVERY PUMP
VFD-16 VFD-18
VFD-15 VFD-17 VFD-19
Additions
C C

C1 ENLARGED
Scale: 1/4" = 1'-0"
ANNEX MECHANICAL ROOM C4 ENLARGED
Scale: 1/4" = 1'-0"
MECHANICAL BASEMENT PLAN

RA

B1
VFD-24 RG-1
Construction
M-301 60"x24"
VFD-23
VFD-22
Documents
VFD-26
60"x30" 54"x30"

3" HWR VFD-27


ELECTRICAL ROOM
KEYNOTES
3" HWS 4" CHWR E301
1. REFER TO D4/M-502 FOR CHILLED WATER COIL CONNECTION DETAIL.

RA 2. REFER TO D5/M-502 FOR HOT WATER COIL CONNECTION DETAIL.


2" HWR VFD-25 2" HWR
2" HWS 3. INLINE PUMP. REFER TO DETAIL A4/M-504.
4" CHWS 2" HWS ACU-14 ACU-15
4. OUTSIDE AIR LOUVER. REFER TO ARCHITECTURAL DRAWINGS AND
SPECIFICATIONS.
PENTHOUSE
3
VFD-20
PCP-1 M301 5. FACILITY MANAGEMENT SYSTEM PANEL.
VFD-21
1 2
RA 36"x54" 6. 6" HRS/R PIPING UP IN CHASE TO LEVEL ABOVE.
B B
7. 6" CHWS/R PIPING UP IN CHASE TO LEVEL ABOVE.

AHU-1 8. 4" HWS/R PIPING UP IN CHASE TO LEVEL ABOVE.

9. 84"x42" SUPPLY AIR DUCT UP IN CHASE TO LEVEL ABOVE.


DISCHARGE PLENUM

AIR MIXING SECTION

54"x30"
FILTER SECTION

ACCESS SECTION

ACCESS SECTION

10. FAN COIL UNIT SUSPENDED FROM STRUCTURE. REFER TO B1/M-502.


COOLING COIL

HEATING COIL
SUPPLY FAN

140"x48"
2x1 ARRAY

11. GLYCOL FILL SYSTEM. SEE DETAIL B4/M-504.


88"x44"
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

24"x32"

2" HWS
2" HWR

Mark Date Description


Date September 11, 2015

A1 ENLARGED PENTHOUSE PLAN Project Number 14400


Drawn By PZP
Scale: 1/4" = 1'-0"
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

ENLARGED
9/15/2015 6:41:47 PM

MECHANICAL PLANS

M-401
1 2 3 4 5 6 SHEET 124 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

2428 Baylor Dr SE Albuquerque, NM 87106


Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159
KEYNOTES
CIVIL ENGINEER
1. REFER TO D4/M-502 FOR CHILLED WATER COIL CONNECTION DETAIL. Lilley Engineering, Inc.
2. REFER TO D5/M-502 FOR HOT WATER COIL CONNECTION DETAIL. 5160 Calle Bellisima
Las Cruces, NM 88011
3. INLINE PUMP. REFER TO DETAIL A4/M-504. Phone 575-521-0006
4. GLYCOL FILL SYSTEM. SEE DETAIL B4/M-504.
STRUCTURAL ENGINEER
Stubbs Engineering, Inc.
277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
Phone 575-993-5228

MECHANICAL/ELECTRICAL ENGINEER
Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
Phone 505-883-4111

D D

M ES I
L IR T

42"x84"
CHME COMPUTER LAB
MEXI

I
177

I
W

CO
NE
SEAL RETURN AIR 20505
PATH AIR TIGHT

E ER
P RO
DOUBLE WALL PLENUM
ES

IN
F
SI G
O N A L EN

PROJECT
VFD-2
VFD-1 VFD-3
MECHANICAL ROOM
M003 New Mexico State
University
VFD-4 VFD-6

VFD-5 CHILLED WATER PCP-2 Jett Hall and Jett Annex


COOLING COILS
TYPICAL ACCESS DOOR
HEAT RECOVERY COILS
HOT WATER HEATING COILS Renovations and
Additions
C 1 BASEMENT
Scale: 3/16" = 1'-0"
AHU-2-SECTION
C

Construction
Documents
26"x18"
MECHANICAL
M123

AHU-3

HEAT RECOVERY COIL


DISCHARGE PLENUM

ACCESS SECTION

ACCESS SECTION

ACCESS SECTION

ACCESS SECTION
FILTER SECTION

FILTER SECTION
COOLING COIL

HEATING COIL
SUPPLY FAN
1x2 ARRAY

68"x34"
24"x18"

B VFD-13 VFD-14 3 B
2" HWR 2" HWS
3" CHWR 3" CHWS 2
PCP-3

4" HRS
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

4" HRR

4" HRS 4
32"x20"

HRP-3 GFP-2

RG-1
MAE STUDENT LOUNGE
125

A4 ENLARGED
Scale: 1/4" = 1'-0"
MECHANICAL ROOM 123 PLAN

Mark Date Description


Date September 11, 2015
Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

ENLARGED
9/15/2015 6:41:48 PM

MECHANICAL PLANS

M-402
1 2 3 4 5 6 SHEET 125 OF 187
1 2 3 4 5 6
1
Van H. Gilbert Architect PC
1" OVERLAP ARCHITECTURE • INTERIORS • PLANNING
1" OVERLAP
ON ALL SIDES ON ALL SIDES 1
1/2" 12 12 OF DAMPER OF DAMPER
12 1. OPENINGS IN FLOOR OR WALLS SHALL BE LARGER THAN THE DAMPER BY
4 1/8" FOR EACH LINEAR FOOT IN HEIGHT AND WIDTH OF THE DAMPER TO
7 7
R R R R R
13 ALLOW FOR THERMAL EXPANSION, BUT THE OPENING SHALL NOT BE LESS
14 THAN REQUIRED TO MAINTAIN A MINIMUM OF 1/4" CLEARANCE BETWEEN THE
A A A A
A
3 SLEEVE AND WALL ON ALL SIDES. IN INSTALLATIONS WHERE THE OPENING
2 BETWEEN THE WALL AND SLEEVE REQUIRES FILLER MATERIAL (SEE NFPA 90A) 3 22-1/2 2-PIECE 30 2-PIECE 45 ELBOW 45 3-PIECE 60 3-PIECE
5 THE FILLER MATERIAL SHALL BE OF FLEXIBLE CONSISTENCY TO ALLOW ELBOW ELBOW (3" THRU 8") ELBOW ELBOW
16 FOR EXPANSION OF THE FIRE DAMPER-ASSEMBLY. 3
17 7 5
6 7 4 2428 Baylor Dr SE Albuquerque, NM 87106
15 15 2. THE FOLDED BLADE ASSEMBLY SHALL ALWAYS BE POSITIONED AT THE TOP
WHEN THE DAMPER IS PLACED IN A WALL OPENING. 10 10 Tel 505-247-9955 Fax 505-247-1826
7 15
AIRFLOW 4 AIRFLOW
E-mail info@vhgarchitect.com
8
3. THE DAMPER SHALL BE POSITIONED IN THE OPENING SO THE HORIZONTAL A B A
E 11 CLEARANCE ALLOWED FOR EXPANSION IS EQUALLY DIVIDED AT BOTH SWIDES 6 6 E Web Site www.vhgarchitect.com
B
9
OF THE DAMPER. R R CONSULTANTS

16 8 9 8
9 4. THE DAMPER SHALL BE POSITIONED IN THE OPENING SO THAT NO PART 2 RL RL LABORATORY CONSULTANT
10 4 OVERLAPS THE PLANE FORMED BY EITHER SIDE OF THE WALL OF THE FIRE
4 RATED FLOOR ASSEMBLY. 2 5 A A RFD - Research Facilities Design
90 ELBOW 90 5-PIECE CONCENTRIC REDUCER ECCENTRIC REDUCER 3965 Fifth Ave. Suite 400
5. THE DUCT SHALL NOT BE CONTINUOUS THROUGH THE WALL OPENING, BUT (3" THRU 8") ELBOW RL=A-B (MIN) RL=2(AB) San Diego, CA 92103
1 SHALL BE CONNECTED TO THE DAMPER (OR SLEEVE DEPENDING UPON THE
STYLE OF DAMPER) ON EITHER SIDE OF THE WALL. 3 6" 6" 4 6" 6" Phone 619-297-0159
C C C C
6. APPROVED RECTANGULAR DUCT BREAKAWAY CONNECTIONS ARE: PLAIN 'S' SLIP: CIVIL ENGINEER
GRILLE CONNECTION: GRILLE CONNECTION: THIN WALL HEMMED 'S' SLIP; DOUBLE 'S' SLIP; INSIDE SLIP JOINT; STANDING 'S'; STANDING 'S' 1 1 Lilley Engineering, Inc.
BOTH SIDES: (ONE SIDE) DUCT CONNECTION ANGLE OR BAR REINFORCED; STANDING 'S' ALTERNATE; AND DRIVE SLIP JOINT. L RL L
A A A B A RL B 5160 Calle Bellisima
FLANGED CONNECTION SYSTEMS MANUFACTURED BY DUCTMATE, NEXUS, WARD TDC
NOTE: FOR THIN WALL NOTE: FOR THIN WALL
SEE NOTE 15 SEE NOTE 15
(LOCK FORMER) AND TDF (ENGLE) MAY BE USED FOR BREAKAWAY CONNECTIONS MULTIBLADE NON-AIRFOIL MULTIBLADE AIRFOIL Las Cruces, NM 88011
WHERE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S INSTALLATION INSTRUCTIONS. L L
Phone 575-521-0006
APPROVED ROUND AND FLAT OVAL BREAKAWAY CONNECTIONS SHALL BE EITHER 4" (LOW VELOCITY APPLICATIONS (HIGH VELOCITY APPLICATIONS RL=A-B (MIN)
WIDE DRAW BAND OR #10 SHEET METAL SCREWS, SPACED EQUALLY AROUND THE D D
1500 FPM & LESS) IN EXCESS OF 1500 FPM)
19 19
CIRCUMFERENCE OF THE DUCT IN ACCORDANCE WITH THE MANUFACTURER'S LATERAL TEE LATERAL CROSS REDUCING REDUCING STRUCTURAL ENGINEER
13 INSTALLATION INSTRUCTIONS. DO NOT BOLT, SCREW, RIVET, TACK WELD, ETC., DUCT LATERAL TEE LATERAL CROSS Stubbs Engineering, Inc.
CONNECTIONS TO THE DUCT-SLEEVE. SEAL DUCT CONNECTIONS WITH HARDCAST INC.,
10 3 1 C C
277 E. Amador Ave. Suite 200
WALL OR FLOOR
7. DAMPER FRAME MAY BE OF DESIGN AND LENGTH AS TO FUNCTION AS THE SLEEVE IF C C Las Cruces, NM 88001
12 SO TESTED AND LABELED BY UL. OTHERWISE, THE SLEEVE SHALL BE CONTINUOUS 2 SLEEVE - SEE INSTALLATION NOTES Phone 575-993-5228
THROUGH THE WALL WITH ALL WELDED SEAMS AND SHALL EXTEND A MINIMUM DISTANCE
7 7 11 7
3
BEYOND THE PLANES FORMED BY BOTH WALLS OR FLOOR ASSEMBLY. EQUAL TO THE MOUNTING ANGLES CONTINUOUS AROUND SLEEVE WITH MINIMUM 1" OVERLAP
8
WIDTH OF THE RETAINING ANGLES, BUT SHALL NOT BE GREATER THAN WALL WIDTH
A A B A A B MECHANICAL/ELECTRICAL ENGINEER
4
PLUS MOUNTING ANGLE DIMENSIONS PLUS 8". SQUARE OR RECTANGULAR DAMPER FRAME FOR ROUND OR OVAL DUCTS, Bridgers & Paxton Consulting Engineers
6 PROVIDE DUCT TRANSITION 4600-C Montgomery Blvd. NE
8. THE SLEEVE GAUGE SHALL BE EQUAL TO OR HEAVIER THAN THE GAUGE OF THE DUCT L L RL L L RL
9 AS DEFINED BY THE APPROPRIATE SMAGNA DUCT CONSTRUCTION STANDARD. BUT THE
5
Albuquerque, NM 87109
18
BREAKAWAY DUCT CONNECTION - SEE INSTALLATION NOTES COMBINATION TEE REDUCING SPUN TEE REDUCING
SLEEVE SHALL BE NOT LESS THAN REQUIRED TO PROVIDE INSTALLATION EQUIVALENT TO Phone 505-883-4111
5 5 2 THE DAMPER MANUFACTURER'S UL TEST AND INSTALLATION INSTRUCTIONS. COMBINATION TEE SPUN TEE
18 6 FIRE DAMPER FUSIBLE LINK (NOT REQUIRED FOR COMBINATION FIRE/SMOKE L L
5
DAMPERS OR SMOKE DAMPERS) 1"
9. THE FIRE DAMPER SHALL BE BOLTED, SCREWED, RIVETED, OR TACK WELDED TO THE 1" 1"
Q Q RL
SLEEVE AND THE SPACING SHALL BE IN ACCORDANCE WITH MANUFACTURER'S
7
1/4" MINIMUM EXPANSION CLEARANCE - SEE INSTALLATION NOTES L=1.414 C+5"
4 INSTALLATION INSTRUCTIONS. (MAX)
C D
17 17
A A B A
1" 1"
4 8
NEGATIVE SPRING (NOT REQUIRED FOR COMBINATION FIRE/SMOKE DAMPER Q=(A/2)+.707C+3"
D 1 10. THE SLEEVE-FIRE DAMPER ASSEMBLY SHALL BE THEN HELD IN PLACE IN THE WALL OR SMOKE DAMPERS) (MAX) D
(OR FLOOR BY MOUNTING ANGLES, (MINIMUM OF 1-1/2" X 16 GAUGE, BUT NOT LESS H=.707A+.5C+3" L TYPE: ONE TAP
THAN REQUIRED SLEEVE GAUGE AND MANUFACTURER'S INSTALLATION INSTRUCTIONS) ON 1"
APPROVED CAULKING MATERIAL IN ACCORDANCE WITH MANUFACTURER'S (MAX) L=C+2"
DUCT CONNECTION DUCT CONNECTION DUCT CONNECTION BOTH SIDES OF WALL OR FLOOR ASSEMBLY. THESE MOUNTING ANGLES SHALL BE 9 INSTALLATION INSTRUCTIONS H 1" H 1" TYPE: TWO TAPS
WELDED TO THE SLEEVE AT A SPACING IN ACCORDANCE WITH MANUFACTURER'S 4" C 4" C
DAMPER DAMPER DAMPER L=C+D+4"
INSTALLATION INSTRUCTIONS. MOUNTING ANGLES SHALL OVERLAP THE WALL A MINIMUM U.L. APPROVED DAMPER ACTUATOR ASSEMBLY WITH MOUNTING BRACKET, REDUCING
(ROUND OR OVAL (BLADES OUT OF (BLADES IN CONICAL LATERAL TANGENTIAL TEE
DUCT-BLADES OUT AIRSTREAM) AIRSTREAM)
OF ONE (1) INCH ON ALL SIDES AND SHALL NOT BE ATTACHED TO THE WALL. 10 ELECTRIC FUSE LINK, AND OPERATING JACK SHAFT LINKAGE. DAMPER CONICAL LATERAL
OF AIR STREAM) ACTUATOR SHALL BE MOUNTED ON DUCT OUTSIDE AIR STREAM C C C
11. WHEN MULTIPLE SECTIONS OF STEEL DAMPERS ARE JOINTED, THE CONNECTIONS SHALL M ES I
BE ON BOTH SIDES OF DAMPER CURTAIN, AT A MAXIMUM DISTANCE OF 2" FROM ANY
5"MIN.
5"MIN.
5"MIN. L IR T
1
OF THE FOUR CORNERS AND A MAXIMUM SPACING OF 12" 0.C. WITH A MINIMUM OF 5"MIN. MEXI

I
WALL (OR FLOOR) L L=LARGER OF W
TWO CONNECTIONS IN EACH SIDE, TOP AND BOTTOM. A

CO
* FUSIBLE ROD IS NOT REQUIRED FOR SMOKE DAMPER APPLICATION (C OR D)+4"

NE
2 SLEEVE - SEE INSTALLATION NOTES A A B
12. PROVIDE DUCT ACCESS DOORS AT ALL FIRE DAMPER LOCATIONS OF SUFFICIENT SIZE 5"MIN.
20505
3

E ER
P RO
MOUNTING ANGLES CONTINUOUS AROUND SLEEVE WITH WELDED JOINTS TO ALLOW EASY INSPECTION AND RESETTING OF DAMPER LINKAGES. PROVIDE CEILING
L L=C+4" L RL L=C+4"
ACCESS DOORS IN ALL GYP. BOARD, PLASTER, OF CONCEALED SPLINE CEILINGS TO D ES
4

IN
X=(C/2)+2"
FIRE DAMPER, SMOKE DAMPER, AND

F
SERVICE ALL REQUIRED DUCT ACCESS DOORS. PROVIDE ACCESS DOORS IN ALL CONICAL TEE REDUCING CONICAL CROSS SI G
SQUARE OR RECTANGULAR DUCT
WALLS OR FLOORS THAT BLOCK ACCESS TO DUCT DOOR PROVIDING ACCESS TO THE CONICAL TEE O N A L EN
5 BREAKAWAY DUCT CONNECTION FIRE DAMPER. DUCT ACCESS FOR SMALL FIRE DAMPERS 6" SQUARE DIAMTER AND COMBINATION FIRE SMOKE DAMPER DETAILS
LESS, MAY BE PROVIDED BY MEANS OF REMOVABLE FLEXIBLE DUCT SUBJECT TO THE D4 SCALE = NONE
NOTE: SEE SPECIFICATIONS FOR DUCT MATERIALS AND CONSTRUCTION
6 FIRE DAMPER FRAME APPROVAL OF THE BUILDING CODE AUTHORITY HAVING JURISDICTION.
PROJECT
7 FIRE DAMPER CURTAIN TYPE SQUARE OF RECTANGULAR 13. ALL FIRE DAMPERS SHALL BE INSTALLED IN ACCORDANCE WITH MANUFACTURER'S
INSTALLATION INSTRUCTIONS AND IN ACCORDANCE WITH THE FOLLOWING: UL STANDARD
8 CURTAIN TRACT 555 FIRE DAMPERS; UL STANDARD 555S SMOKE DAMPERS AND LABELED AS UL MEDIUM VELOCITY AND ROUND DUCT FITTINGS
9 BOLT, SCREW, RIVET, OR TACK WELDED CONNECTION
LEAKAGE CLASS 1; NFPA STANDARD 90A AND 90B; INTERNATIONAL BUILDING CODE,
2003 EDITION, AND THE INTERNATIONAL MECHANICAL CODE, 2003 EDITION. 1 FLOOR STRUCTURE, SEE ARCH.
DRAWINGS FOR RATING
C5 SCALE = NONE New Mexico State
10 CORNER SPACING PER INSTALLATION INSTRUCTION 13. COMBINATION FIRE AND SMOKE DAMPERS SHALL BE MULTIBLADE TYPE DAMPER
CERTIFIED AND LABELED IN ACCORDANCE WITH UL 555 CLASSIFICATION AND UL 555S 9 2
3
2
PIPE SLEEVES, SEE SECTION University
11 CLASSIFICATION AS LEAKAGE CLASS 15. DAMPER ASSEMBLY INSTALLATION SHALL BE 6 15060. PROVIDE WATERSTOP
INTERMEDIATE SPACING PER INSTALLATION INSTRUCTION FOR BELOW GRADE
PROVIDED IN ACCORDANCE WITH MANUFACTURER'S APPROVED INSTALLATION
12 PENETRATIONS

13
1/8" PER LINEAR FOOT BOTH DIMENSIONS, AND 1/4" MINIMUM INSTRUCTIONS. DAMPERS SHALL BE FURNISHED BY THE MANUFACTURER WITH UL
APPROVED DAMPER ACTUATOR AND FUSE LINK IN ACCORDANCE WITH SPECIFICATION
ROCKWOOL OR APPROVED FIRE
20 30
FT

FB
A° 3.73xH
Jett Hall and Jett Annex
1" MINIMUM OVERLAP OF STRUCTURAL OPENING SECTION 15800. 3 SAVING PIPE INSULATION THRU
8
14 14. COMBINATION FIRE AND SMOKE DAMPERS SHALL BE MULTIBLADE TYPE DAMPER
PENETRATION, MIN. 6" BOTH 20° 30
A° A°
Renovations and
5
ALTERNATE MOUNTING ANGLE METHOD AS REQUIRED BY GRILLE SIDES OF WALL OR FLOOR
CERTIFIED AND LABELED IN ACCORDANCE WITH UL 555 CLASSIFICATION AND UL 555S PLAN
15 MAXIMUM WIDTH 1-7/8" RUSKIN MODEL IBDT OR APPROVED EQUAL CLASSIFICATION AS LEAKAGE CLASS 15. DAMPER ASSEMBLY INSTALLATION SHALL BE
PROVIDED IN ACCORDANCE WITH MANUFACTURER'S APPROVED INSTALLATION
4
1
(FOR INSULATED PIPING ONLY)
TRANSITION FT FB
ELEVATION
RISE
Additions
4
PIPE INSULATION (WHERE w/ EQUIPMENT
C 16 GRILLE OR REGISTER WITH A MIN. 1/2" OVERLAP. GRILLE OR REGISTER SHALL BE STEEL INSTRUCTIONS. DAMPERS SHALL BE FURNISHED BY THE MANFUCTURER WITH UL
REQUIRED)
A° A° C
MINIMUM 26 GAGE FRAME THICKNESS AND SHALL NOT BE ATTACHED DIRECTLY TO APPROVED DAMPER ACTUATOR AND FUSE LINK IN ACCORDANCE WITH SPECIFICATION PLAN
WALL SECTION 15800.
U.L. LISTED SILICONE FOAM OR A°
5 OTHER FIRE SAFE MATERIAL
DUCT OFFSET
17 ROUND OR OVAL DUCT BETWEEN PIPE AND PIPE
FT FB
FLOOR PENETRATION SLEEVES OR PIPE SLEEVE AND A°
18 ROUND OR OVAL DUCT COLLAR FURNISHED WITH RECTANGULAR DAMPER ASSEMBLY ROCKWOOL INSULATION FOR
PLAN VIEW PLAN VIEW PLAN VIEW
9 INSULATED PIPING
19 ROUND OR OVAL DUCT BREAKAWAY CONNECTION WITH EITHER DRAWBAND OR SHEET METAL 7
SCREWS IN ACCORDANCE WITH MANUFACTURERS INSTALLATION INSTRUCTIONS. 2 IF SILICONE FOAM IS NOT
5 6
4 USED AS FIRE SAFING 45°
FIRE DAMPER INSTALLATION NOTES 3
MATERIAL, SEAL WATER-PROOF A° A°
W
C2 SCALE = NONE
WITH SILICONE SEALANT 1/2 W
(4"MIN.)
A° PLAN
7 PARTITIONI OR WALL, SEE A°
FIRE DAMPER DETAIL - CURTAIN TYPE ARCH. DWGS FOR RATING ELEVATION ELEVATION ELEVATION BRANCH DUCT
C1 SCALE = NONE
8
ANCHOR ONE PIPE DIAMETER
LONG 90° APART NOTES
Construction
9
PIPE SLEEVES NOT REQUIRED
IN GYP-BOARD WALLS
1. ANGLE A=30 MAXIMUM WHEN AIR FLOWS IN
DIRECTION OF ARROS. (SUPPLY AIR) Documents
2. ANGLE A=15 WHEN AIR FLOWS IN OPPOSITE
WALL PENETRATION DIRECTION OF ARROS (R.A. OR EXHAUST)
SELF DRILLING ANCHOR
PROVIDE HAND DAMPER
1-1/2"x2"x1/8" STEEL CHANNEL
WITH ACCESS DOOR
(1) NECK DIA. MIN. WHERE SHOWN ON PLANS
PIPE PENETRATION THRU FIRE RATED BARRIER LOW VELOCITY DUCT FITTING DETAIL
B4 B5 SCALE = NONE
SCALE = NONE

STRUCTURAL SLAB EXTENDED 6" THRU


SEE ARCH. & STRUCT. WALL. SEAL TIGHT
DUCT DWGS FOR TYPE TO WALL ON BOTH
BRANCH
SIDES (SEE SECTION)
DUCT

1-1/2 W
B 3/8" DIAMETER ALL
THREADED STEEL
A BRANCH
MIN. B

6
HANGER ROD MAIN
FIXED CEILINGS
SECTION A PLAN A
5

2
SUPPORT FLEX DUCT WITH
26 GA. 1-1/2" STRAP. MAX.
4' SPACING
FLEX DUCT, DIAMETER EQUAL
1-1/2"x1/2"x1/8" ANGLE 1-1/2 W
TO DIFFUSER NECK SIZE (MIN..
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

TRAPEZE OR P-3000 2 OR 3x90 DEG. ELBOWS AS


PROVIDE RIGID
7
UNISTRUT SHOWN ON PLANS)
FLEX SUPPORT FROM
4
DIFFUSER COLLAR -
THERMAFLEX FLEXFLOW OR EQUAL

LARGE DUCT SUPPORT DETAIL 1


B1 SCALE = NONE BELLMOUTH OR
CONICAL FITTING B WALL OR
PARTITION L (MIN)
W/HAND DAMPER
RIGID DUCT WHERE W
SECTION B RUN-OUT EXCEEDS PLAN B 6" 1-1/2 L
6'-0" SEAL TIGHT

4
LAY-IN CEILINGS

RIGID DUCT WHERE 22


PROVIDE HAND DAMPER
RUN-OUT EXCEEDS 3 5 3
SHEET METAL 4'-0"
WITH ACCESS DOOR
WHERE SHOWN ON PLENUM FLEX. DUCT FOR LAY-IN 1
CEILING APPLICATION
PLANS
Mark Date Description
SECTION (NOT TO SCALE) 1 SECURE SOUND ELBOW TO RETURN GRILLE. Date September 11, 2015
2 RETURN AIR GRILLE IN CEILING. SEE PLANS AND SCHEDULE FOR SIZE AND Project Number 14400
EXHAUST GRILLE TYPE.
Drawn By PZP
SEE FLOOR PLAN
A FOR SIZE, TYPE, AND 3 COORDINATE SOUND ELBOW INSTALLATION WITH STRUCTURE, LIGHTS, AND OTHER A
LOCATION 1 COORDINATE SOUND ELBOW INSTALLATION WITH STRUCTURE, LIGHTS, OBSTRUCTIONS. POINT OPENING AWAY FROM EQUIPMENT.
Checked By IM
C AND OTHER OBSTRUCTIONS Copyright © VAN H. GILBERT ARCHITECT PC
SECTION C PLAN C 4 MAINTAIN SAME FREE AREA AS GRILLE. (MINIMUM).
2 SUPPORT FROM STRUCTURE SIMILAR TO DUCTWORK
5 SUPPORT FROM STRUCTURE SIMILAR TO DUCTWORK. SHEET TITLE
3
EXHAUST REGISTER CONSTRUCT SOUND ELBOW OF 1" THICK RIGID ACOUSTIC INSULATION
FOR LAY-IN AND FIXED CEILINGS OR AS SHOWN ON DRAWINGS
6 CONSTRUCT SOUND ELBOW OF 1" THICK RIGID ACOUSTIC INSULATION.

4
MECHANICAL DETAILS
9/15/2015 6:41:48 PM

FURNISH AND INSTALL SOUND ELBOWS AS SHOWN ON DRAWINGS


7 FURNISH AND INSTALL SOUND ELBOWS FOR EACH RETURN GRILLE UNLESS
NOTED OTHERWISE ON DRAWINGS.
DIFFUSER AND REGISTER CONNECTION DETAIL 5
WHEN FIRE DAMPER OR SMOKE DAMPER IS NEEDED AT THE WALL,
A2 SCALE = NONE
INSTALL SOUND ELBOW ATTACHED AND SEALED TO WALL.

SOUND ELBOW DETAIL FOR RETURN GRILLE


A5 SCALE = NONE
SOUND ELBOW DETAIL FOR TRANSFER OPENINGS
A4 SCALE = NONE M-501
1 2 3 4 5 6 SHEET 126 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
HWR 15
ARCHITECTURE • INTERIORS • PLANNING
9 12
1 2 16
11
4
10 4 8
3
RAIN CAP -
WELD TO VENT 5 8

~
HWS
14 5
4 CHS 14

6'-0"
3 7 14
12 2428 Baylor Dr SE Albuquerque, NM 87106
6
HWS 5 7 11
8 Tel 505-247-9955 Fax 505-247-1826
15 5 CHR E-mail info@vhgarchitect.com
SHEET METAL FLASHING Web Site www.vhgarchitect.com
E 12 E

~
9 6 3
DO NOT ATTACH TO VENT HWR
6 12
ROOF CONSULTANTS
6
10 9 3 6 13
1
13 6
17
LABORATORY CONSULTANT
7 6 RFD - Research Facilities Design
COIL SUPPLY WATER SHALL BE CONNECTED TO AIR 3965 Fifth Ave. Suite 400
RELIEF VALVE
11
CEILING PLATE - DO 5 1
COIL LEAVING SIDE OF COIL San Diego, CA 92103
8
NOT ATTACH TO VENT 8 1
AIR FLOW
Phone 619-297-0159
10 1
AIR FLOW 2 COLLECT ALL DRAINS, INSTALL HOSE
SUPPLY WATER SHALL BE CONNECTED
VENT TO ATMOSPHERE, 3 3 TO AIR LEAVING SIDE OF COIL CONNECTION AND CAP
ONE PIPE SIZE LARGER
CIVIL ENGINEER
10
THAN RELIEF VALVE 3 TEMP. AND PRESS. FITTING TYP. Lilley Engineering, Inc.
DISCHARGE 1 METAL STRAP SUPPORT FROM STRUCTURE. (TYPICAL) 2 COLLECT ALL DRAINS, INSTALL HOSE 5160 Calle Bellisima
CONNECTION AND CAP PRESSURE GAUGE Las Cruces, NM 88011
4
DRIP PAN ELBOW, KUNKLE 2 MANUAL AIR VENT ON HWR PIPING AT ALL HIGH POINTS
Phone 575-521-0006
VALVE CO. FIG. 299 OR 3 TEMP. AND PRESS. FITTING TYP. 5 THERMOMETER
EQUIVALENT. SIZE TO MATCH 3 FACTORY FABRICATED SOUND ATTENUATOR
RELIEF VALVE DISCHARGE D STRUCTURAL ENGINEER
4
HOT WATER COIL. UNION OR FLANGE. INSTALL SO AS TO ALLOW
4 6 Stubbs Engineering, Inc.
3
COIL PRESSURE GAUGE
3/4" REMOVING COIL WITHOUT MAJOR REMOVAL OF
COIL PIPING
277 E. Amador Ave. Suite 200
5 VALVE ACTUATOR
5 THERMOMETER
Las Cruces, NM 88001
6 PROVIDE ACCESS DOOR UPSTREAM OF THE COIL IN THE BOTTOM OF TERMINAL UNIT. 7 AUTOMATIC TWO-WAY CONTROL VALVE Phone 575-993-5228
2 6
3/4" TO FLOOR DRAIN 7 DRAIN VALVE WITH HOSE CONNECTION AND CAP 11 UNION MECHANICAL/ELECTRICAL ENGINEER
2 BALL VALVE OR BUTTERFLY VALVE PER
TEMPERATURE-PRESSURE FITTING (TYP.) 16 8 Bridgers & Paxton Consulting Engineers
7
8 SPECIFICATIONS. TYPICAL
AUTOMATIC TWO-WAY CONTROL VALVE 4600-C Montgomery Blvd. NE
9 LOW VELOCITY DUCTWORK TO DISTRIBUTION Albuquerque, NM 87109
DRIP PAN ELBOW DETAIL 8
9 MANUAL AIR VENT
Phone 505-883-4111
D1 SCALE = NONE 10 REFER TO PLANS FOR PIPE SIZES
BUTTERFLY VALVE
GENERAL NOTES
1/2" DRAIN
10
9
GENERAL NOTES A PROVIDE MANUAL AIR VENTS AT ALL HIGH POINTS
11 3-WAY CONTROL VALVE MANUAL AIR VENT
IN SYSTEM 11 FLOW BALANCING VALVE
1 PROVIDE MANUAL AIR VENTS AT ALL
12 BALL VALVE (TYP) HIGH POINTS IN SYSTEM.
10
B SEE PLANS AND/OR PIPING SCHEMATIC FOR
1/2" GATE VALVE AND DRAIN 12 FULL SIZE BYPASS
D PIPE SIZES. D
13 UNION (TYP). INSTALL 2" FROM COIL 2 SEE PLANS AND/OR PIPING
C TEMP./PRESS.FITTINGS INSTALLED IN PIPING 2"
4
SCHEMATIC FOR PIPE SIZES. THERMAL WELL TO ENERGY MANAGEMENT
AND SMALLER SHALL BE INSTALLED IN ELBOW 13
3
TYPICAL PIPING REQUIREMENTS FOR
7 14 REDUCER (TYP), PROVIDE AS REQUIRED 11 MULTIPLE COILS OR IN THE BRANCH SIDE OF A 2" TEE. SYSTEM.
3 TEMP./PRESS. FITTINGS INSTALLED
8 IN PIPING 2" AND SMALLER SHALL
HIGH VELOCITY RIGID SUPPLY DUCT, 3 FT. MINIMUM STRAIGHT RUN
5
15 14
2
SILENT CHECK VALVE
10
BE INSTALLED IN ELBOW OR IN THE
PRIOR TO TERMINAL UNIT CONNECTION. SEE SCHEDULE FOR VALVE AND DUCT SIZE
BRANCH SIDE OF A 2" TEE. 12 FLOW BALANCING VALVE, SEE SPECIFICATIONS
15 INLINE BOOSTER PUMP. SEE EQUIPMENT M ES I
16 FLOW BALANCING VALVE
SCHEDULE FOR SIZE. PUMP SHALL RUN WHEN L IR T
MEXI

I
17 LOW VOLTAGE CONTROLS TO BE IN SEPARATE COMPARTMENT. OUTSIDE TEMPERATURE IS 40 deg F W
9

CO
NE
(ADJUSTABLE)
CHILLED WATER COIL PIPING SCHEMATIC 20505
16 TYPICAL PIPING REQUIREMENTS FOR MULTIPLE

E ER
P RO
D4 SCALE = NONE COILS
SINGLE DUCT VAV TERMINAL ES

IN
F
G
15
SI
O N A L EN
12 11
UNIT WITH REHEAT COIL (3-WAY VALVE)
13
D1 M-502 SCALE = NONE HOT WATER COIL PIPING SCHEMATIC
14
D5 SCALE = NONE PROJECT
CHS
1
CHR 9 New Mexico State
16 11
HWS 1 2 AIR FLOW
2'-0" University
6 14 11 CONVERSION FACTOR:
mm = in. x 25.4
HWR 3 10
No. OF 1/8" HOLES = FROM HP
Jett Hall and Jett Annex
3
1'-0" A
11
16 11
HWR (BRANCH AREA, SQ. TRAP OUTLET

1 T & P FITTING TYP


4 16 IN.)/(0.0125) Renovations and
2 FLEXIBLE DUCT CONNECTION
13
L
Additions
1
C 3 DUCT HANGER STRAP HWS 11 C
4 1/4" DIA. STEEL HANGER ROD 2 1/8" HOLES, 3/4" O.C. FLOW

5 CYLINDRICAL RUBBER ISOLATOR MOUNT, TYPICAL OF 4 10


8'-0" ABOVE ROOF
17 7
6 CONTROL VALVE 6 LOCATE IN CENTER
12 L" = No. OF HOLES/(4)
OF ROOF
14 SECTION A-A
7
A
MANUAL AIR VENT 5 GRAVITY
15 CONDENSATE
8 DUCT TRANSITION 8
RETURN LINE
9
9 FILTER
1 METAL STRAP SUPPORT FROM STRUCTURE. (TYPICAL)
4
CONDENSATE CONNECTION DETAIL
10 RETURN AIR PLENUM. PROVIDE REMOVAL SPACE FOR FILTERS
10
5 C5 SCALE = NONE
8
11 8
2 MANUAL AIR VENT ON HWR PIPING AT ALL HIGH POINTS
ISOLATION VALVE, SEE SPECIFICATIONS

12
3/4" CONDENSATE DRAIN REFER TO PLUMBING DRAWINGS FOR ROUTING AND 3 FACTORY FABRICATED SOUND ATTENUATOR Construction
DETAILS

13 FLEXIBLE CONNECTION, SEE SPECIFICATION


4 HOT WATER COIL. Documents
5 VALVE ACTUATOR 7
14 STRAINER WITH BLOWDOWN AND HOSE CONNECTION 6
6 PROVIDE ACCESS DOOR UPSTREAM OF THE COIL IN THE BOTTOM OF TERMINAL UNIT.
15 INSULATED DOUBLE THICKNESS DRAIN PAN PITCHED TO CONDENSATE DRAIN.
1
SECONDARY DRAIN PAN TO EXTEND BELOW CONTROL VALVES AND COIL
7 DRAIN VALVE WITH HOSE CONNECTION & CAP 1 POWER ROOF EXHAUSTER
CONNECTION ACCESSORIES AND PITCH TO PRIMARY DRAIN PAN
2 BIRDSCREEN
16 FLOW CONTROL VALVE, SEE SPECIFICATIONS 8 TEMPERATURE-PRESSURE FITTING (TYP.)
3
1
INTEGRAL CURB CAP SECURE
9 LOW VELOCITY DUCTWORK TO DISTRIBUTION STATIC OUTSIDE AIR PROBE 7 1/2" PIPE CONNECTED TO THE AND CAULK TO CURB
AIR MONTIR S.O.A.P.-1 OR BUILDING STATIC PRESSURE
10 REFER TO PLANS FOR PIPE SIZES
EQUIVALENT REFERENCE PORTS. SEE CONTROLS.
4 FACTORY CURB SECURELY
3
ANCHORED TO ROOF OR AS
2
NOTE: SHOWN ON ARCHITECTURAL
2 8
11 PRESSURE-INDEPENDENT 2-WAY CONTROL VALVE, NORMALLY OPEN. FAIL TO HEAT GUIDE WIRES (MIN 4) SEE ARCH. DRAWINGS FOR PIPE
*PROVIDE 24"x24" ACCESS PANEL LOCATED IN ALL FIXED CEILINGS DRAWINGS. FLASH AND COUNTERFLASH
FOR CHANGING FILTERS. PROVIDE A 24"x24" ACCESS PANEL IN ALL PENETRATION DETAILS
12 BALL VALVE (TYP)
6 5
FIXED CEILINGS FOR SERVICING CONTROL VALVES. ROOF OPENING - MIN. 1" LARGER
3 2" PIPE THAN DUCT SIZE AS SHOWN ON PLANS
B *SEE FLOOR PLAN FOR PIPE SIZE. 13 UNION (TYP). INSTALL 2" FROM COIL 9
TURN BUCKLES (TYPICAL) 4 4 B
6
MOTORIZED
4
*INSTALL STRAINERS, CONTROL VALVES AND UNIONS ABOVE DRAIN PANS. REDUCER (TYP), PROVIDE AS REQUIRED UNION FOR S.O.A.P. STATION DAMPER
14
10
REMOVAL 1" STEEL PIPE WELDED TO PLATE,
BOLTED TO ROOF DECK
15 HIGH VELOCITY RIGID SUPPLY DUCT, 3 FT. MINIMUM STRAIGHT RUN,
FAN COIL UNIT DETAIL PRIOR TO TERMINAL UNIT CONNECTION. SEE SCHEDULE FOR VALVE AND DUCT SIZE 5 BUILT-UP ROOF 7
ACOUSTICALLY LINED DUCT
B1 SCALE = NONE 11 EYELET (TYPICAL) 5
UNLESS EXHAUSTING MOIST AIR
16 FLOW BALANCING VALVE 7
6 2-1/2"x1/2" REDUCER
17 LOW VOLTAGE CONTROLS TO BE IN SEPARATE COMPARTMENT.
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

S.O.A.P. DETAIL POWER ROOF EXHAUSTER DETAIL


B4 SCALE = NONE B5 SCALE = NONE
FLOAT-THERMOSTATIC TRAP. SINGLE DUCT VAV TERMINAL
SPIRAX SARCO MODEL
STRAINER FT-553 TV, 3/4" SIZE UNIT WITH REHEAT COIL (2-WAY VALVE)
D WITH BLOW B2 M-502 SCALE = NONE STRUCTURE CLEAR FROM ALL PIPING
L

DOWN CONTAINING WATER

TYPICAL
4"

CEILING WALL
TYPICAL WATER PIPING
CHECK VALVE WATER PIPING
1" BLOW-DOWN
VALVE SPIRA-TEC STEAM LOSS 42" MINIMUM IN 6'-0" OR TO
DETECTOR. SPIRAX SARCO COMPLIANCE WITH SURFACE CLEAR FOR REDUCER AS
MODEL ST-171, 3/4" SIZE ARTICLE 110 IN THE NEC CONDUIT REQUIRED

1/2"x4" NIPPLE ADAPTER TO 3/4" GATE VALVE


3/4" HOSE 3/4" GATE VALVE
MAIN D L
RECESSED OF SURFACE THREAD HOSE CAP Mark Date Description
MOUNTED ELECTRICAL ADAPTER TO
3/4" 3/4" 16" 3'-6"x6'-6" 3/4" HOSE
HIGH PANEL Date September 11, 2015
HOSE CAP THREAD
16" MINIMUM Project Number 14400
1" 1"
1/2" BALL
CIRCULATING 6'-0" OR TO Drawn By PZP
VALVE 7'-0"
1-1/2" 1-1/2" 16" WATER PIPING SURFACE CLEAR FOR ELEVATION ELEVATION
A.F.F
A FLOOR CONDUIT A Checked By IM
THREADED PIPE WELDED PIPE
2" 2" 16" HOSE CONNECTION Copyright © VAN H. GILBERT ARCHITECT PC

3" 2" 16"


VENT ALL HIGH POINTS NOTES:
SHEET TITLE
4" 2" 16" IN PIPING SYSTEM
EXCLUSIVELY DEDICATED ELECTRICAL SPACE. NO WATER 1 DRAIN ALL LOW POINTS OF PIPING
ELECTRICAL SPACE. NO PIPING PIPING SHALL BE ALLOWED
MECHANICAL DETAILS
9/15/2015 6:41:49 PM

6" 4" 16" OR DUCT SHALL BE ALLOWED WITHIN THESE AREAS 2 DRAIN ALL SCALE POCKETS AS
WITHIN THESE AREAS SHOWN ON PLANS AND/OR PIPING
DIAGRAMS

DRIP LEG (LOW OR MEDIUM PRESSURE) MANUAL AIR VENT DETAIL CLEARANCE REQUIREMENTS AT ELECTRICAL PANELS
A1 SCALE = NONE A2 SCALE = NONE A4 DRAIN VALVE DETAIL
SCALE = NONE A5 SCALE = NONE
M-502
1 2 3 4 5 6 SHEET 127 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
PUMP DISCHARGE ARCHITECTURE • INTERIORS • PLANNING
1
PC 3
CONTROL CABINET NOTE:
8 7
EXTRA 2
STRONG SEE PLANS FOR PIPE
STEEL PIPE 6 SIZE.
GRAVITY RETURN
6
VENT
FROM FLASH TANK IF 3
SHOWN ON PLANS
4 2428 Baylor Dr SE Albuquerque, NM 87106
12'-0" O.C. RECEIVER THERMOMETER
Tel 505-247-9955 Fax 505-247-1826
LPR IF SHOWN 14
5 E-mail info@vhgarchitect.com
P-1000 4'-0" O.C.
E WATER ON PLANS E Web Site www.vhgarchitect.com
UNISTRUT 5 8
LEVEL GAUGE
1
4
6"x6"x1/4" PLATE FLUSHING CONNECTION BASE FLASHING. CONSULTANTS
PITCH PAN
4" CONCRETE 7 LABORATORY CONSULTANT
3
HOUSEKEEPING 12
PAD FLOOR 2 FIBER CANT STRIP SET IN RFD - Research Facilities Design
MIN. 6" GREATER THAN BITUMEN
DUCT DIMENSION AS 9 11 3965 Fifth Ave. Suite 400
SHOWN ON PLANS 3/4" DRAIN San Diego, CA 92103
DISCHARGE INTO 3 FASTENERS APPROXIMATELY 6" Phone 619-297-0159
NEAREST FLOOR SINK O.C.

NOTE: 2 CIVIL ENGINEER


4
FASTENERS APPROXIMATELY Lilley Engineering, Inc.
WHEN CONDENSATE PUMP IS INSTALLED IN PIT, MOUNT 10
1
24" O.C.
CABINET ON WALL OUTSIDE OF PIT. SEE PLANS FOR LOCATION. 5160 Calle Bellisima
ABOVE ROOF DUCT SUPPORT DETAIL
E1 SCALE = NONE
1 DISCHARGE PIPING. 10 1/2" DRAIN LINE FROM MECHANICAL
SLOPE PIPES AWAY FROM
Las Cruces, NM 88011
SEAL PUMPS WHICH HAVE A DRAIN
5
Phone 575-521-0006
TYPICAL CONNECTIONS TO CONDENSATE PUMP HOOD.
D2 SCALE = NONE 2 SUCTION PIPING.
FITTING AND ALL PUMPS WITH STUFFING
BOXES TO NEAREST F.D. STRUCTURAL ENGINEER
SHEET METAL OR FLEX-TUBE Stubbs Engineering, Inc.
6 COLLAR.
BUTTERFLY VALVE, 2-1/2" AND
277 E. Amador Ave. Suite 200
3 11 ADJUSTABLE SUPPORT LEG.
LARGER BALL VALVE, 2" AND SMALLER. Las Cruces, NM 88001
7 SHEET METAL HOOD. Phone 575-993-5228
ECCENTRIC STEAM MAIN
FLOAT AND ECCENTRIC
STRAINER 12 ANCHOR PUMP BASE TO CONCRETE PAD
8
THERMOSTATIC UNION STRAINER
4 NOT USED WITH HILTI OR REDHEAD ANCHORS. INSULATE INSIDE OF MECHANICAL/ELECTRICAL ENGINEER
STEAM TRAP METALWORK IN COLD CLIMATES.
WHEN REQUIRED, THE MOTOR Bridgers & Paxton Consulting Engineers
FLASH AND COUNTER FOUNDATION SHOULD BE ELEVATED TO 4600-C Montgomery Blvd. NE
FLASH FULL SIZE INCREASER.
SCALE POCKET
5 AVOID INTERFERENCE BETWEEN THE Albuquerque, NM 87109
10" PUMP CASING AND THE CONCRETE Phone 505-883-4111
SEE ARCH. DRAWINGS FOR BASE. PIPING THRU ROOF DETAIL
ROOF TYPE. FLASH AND
COUNTERFLASH CHECK VALVE
6 SILENT CHECK VALVE.
13 NOT USED D5 SCALE = NONE
CONDENSATE MAIN
ELEVATION SUCTION DIFFUSER WITH STRAINER.
7 14 FLEXIBLE COUPLING GUARD.
D ROOF OPENING - MIN.
NOTE: D
1" LARGER THAN DUCT 7
8 COMPOUND PRESSURE GAUGE WITH 1
SIZE AS SHOWN ON PLANS GAGE VALVE AND STRAINER ON LINE ENTERING TRAP ARE NOT
REQUIRED ON EQUIPMENT WITH GATE VALVE AND STRAINER AT GAUGE COCKS.
3 AIR FLOW
CONTROL VALVE
4" THICK CONCRETE PAD.
9
2
DUCT THRU ROOF DETAIL END OF MAIN DRIP TRAP DETAIL L IR
M ES I
T
D1 C2 SCALE = NONE
PUMP AND BASE DETAIL MEXI

I
SCALE = NONE W
C4

CO
9

NE
8 20505

E ER
P RO
11 HWR
DRIP LEG OR EQUIPMENT ES

IN
F
BYPASS-INSTALL IN HORIZONTAL CONNECTION. SEE NOTE G
SI
PLANE LEVEL WITH TRAP OR IN NO. 1 O N A L EN
VERTICAL PLANE AND BELOW TRAP DISCHARGE 6"-0" MIN. HWS
EXTRA STRONG ABOVE FINISH ROOF 14
WEATHERPROOF VENTLON
STEEL PIPE
FLEXIBLE CONNECTION
EXTRA STRONG 12" MIN. PROVIDE GALV. SHEET 8 PROJECT
SEE STRUCTURAL STEEL PIPE 12
HEIGHT METAL SUNSHIELD OVER GUY-WIRE (TYPICAL OF 4)
SEE STRUCTURAL DRAWINGS FOR
SEE DRAWINGS FLEX. CONNECTION 10
DRAWINGS FOR BEAM BUILDING STRUCTURE
FOR SIZE
LOCATIONS AND SIZES
TO RETURN
13 5
New Mexico State
MAIN 6
DIELECTRIC FITTING
6" MIN.
TURNING VANES
TURN BUCKLE
(TYPICAL OF 4)
University
(WHERE RETURN IS
COPPER) IN SQUARE ELBOW
STRAINER WITH BLOW DOWN
VALVE AND HOSE CONNECTION 1 METAL STRAP SUPPORT FROM STRUCTURE. (TYPICAL)

FLOAT AND THERMOSTATIC OR STEAM TRAP LEAK DETECTOR


ALL DUCT SEAMS
AND JOINTS
1-1/2"
DIA. OF DISCHARGE DAMPER WITH 2 MANUAL AIR VENT ON COIL OR HWR PIPING.
Jett Hall and Jett Annex
SHALL BE SEALED 115 ACTUATOR &
INVERTED BUCKET TRAP. SEE
DETAILS AND SPECIFICATIONS
SARCO SPIRA-TEC OR
EQUIVALENT
WATERTIGHT
FAN INLET
WEATHERPROOF ENCLOSURE
3 HOT WATER COIL
Renovations and
SUPPORT TRAPEZE
FROM STRUCTURAL
BEAM, TYPICAL NOTES:
SECURE SUNSHIELD
TO INLET DUCT 4 NOT USED Additions
VERTICAL
C "U" BOLT
DISCHARGE 5 DRAIN C
PIPE TYPE HSN VIBRATION 1. ALL DRIP POINTS ON STEAM SHALL BE PROVIDED WITH A 12" MINIMUM
GUIDE ISOLATOR, SEE HIGH DRIP LEG FROM BOTTOM OF STEAM MAIN OR EQUIVALENT CONNECTION
SPEC. SECTION TO TRAP INLET. DRIP LEG SHALL HAVE 6" MINIMUM LENGTH SCALE DRAIN 6 TEMPERATURE-PRESSURE FITTING (TYP.)
TYPICAL
15240 POCKET BELOW TRAP INLET. OUTLET
SHEET METAL LOW VELOCITY DUCTWORK TO DISTRIBUTION.
WEATHERPROOF 7
DUCT THRU
2. NO BYPASS IS REQUIRED ON THE TRAP SET PROVIDED FOR THE DRIPPING ROOF MOTOR HOUSING
OF LOW PRESSURE SUPPLY MAINS (15 PSIG OR LESS). 8 REFER TO PLANS FOR PIPE SIZES.
PIPING WITH
INSULATION, SEE
FLOOR PLANS FOR 9 2-WAY CONTROL VALVE, NORMALLY CLOSED. FAIL TO COOL.
SIZES AND LOCATIONS STEAM TRAP DETAIL BALL VALVE (TYP)
B2 SCALE = NONE
ROOF CURB, FLASH
AND COUNTERFLASH
SEISMIC RESTRAINT VIBRATION
ISOLATORS. MASON MODEL SLR
10

SEE ARCHITECTURAL OR EQUIVALENT. SECURE TO 11 UNION (TYP)


DRAWINGS FOR FAN BASE WITH BOLT &
HORIZONTAL ANGLE FLASHING REQUIREMENTS WASHWER IN AN APPROVED REDUCER (TYP)
ROUND HANGER RODS, 1 12
SEE SPEC. SECT. 15060
FOR SIZE REQUIREMENTS
TRAPEZE OR EQUAL CONCRETE STRUCTURE
ROOF MOUNTING CURB WITH
SHEET METAL CURB CAP.
MANNER & WATER PROOF
ATTACHMENTS.
13 HIGH VELOCITY RIGID SUPPLY DUCT, 3 FT. MINIMUM STRAIGHT RUN PRIOR TO Construction
2
TERMINAL UNIT CONNECTION. SEE SCHEDULE FOR VALVE AND DUCT SIZE.
PIPE SLEEVE SIZED FOR PIPE
WITH INSULATION
FLASH & COUNTER FLASH
SEE ARCHITECTURAL ANCHOR GUIDE WIRE TO ROOF
STRUCTURE. FLASH AND 14 FLOW CONTROL VALVE, SEE SPECIFICATIONS.
Documents
DRAWINGS FOR FLASHING
NOTES: REQUIREMENTS COUNTERFLASH, SEE ARCHITECTURAL
7 7 3
6
WATERSTOP DRAWINGS FOR FLASHING
1 "U" BOLTS SHALL BE USED AS GUIDES ONLY, NOT 6 REQUIREMENTS
ANCHORS. 5 9 8 LABORATORY CONTROL AIR VALVE WITH REHEAT PIPING DETAIL
4
EXTEND SLEEVE 4" ABOVE
2 UTILITY VENT SET DETAIL
2 "U" BOLTS SHALL BE ON EVERY THIRD TRAPEZE (MIN.)
4 4 10
FINISHED FLOOR LEVEL B5
3 DO NOT TIGHTEN "U" BOLTS ON PIPING OR INSULATION,
B4 SCALE = NONE
SCALE = NONE

LEAVE LOOSE AS PIPE GUIDE. MINIMUM 18" LONG ALUMINUM


5 INSULATION JACKET
4 PROVIDE 14 GA. GALV. STEEL PROTECTION SADDLE, 12"
3 3
LONG AT ALL TRAPEZE HANGER 1
11 FLANGE OR
6 INSULATION - SEE SPECS FOR BYPASS, SAME SIZE AS LARGEST UNION (TYP.)
5 REFER TO SPECIFICATION SECTION 15060 THICKNESS CONTROL VALVE BODY
VENT TO
PREPOSITIONED SLEEVE PREPOSITIONED SLEEVE ATMOSPHERE
6 CONTRACTOR MAY SUPPORT TRAPEZE FROM INSERT
POURED IN PLACE IN SLAB ABOVE. SEE SPEC SECTION 15060
BUILDING ENTRY 7 PIPE NOTE 1
DRIP PAN ELBOW,
B SEE DETAIL STRAINER B
8
SEE NOTE 3
PIPE HANGER DETAIL WITH VIBRATION ISOLATORS SEAL WITH WATERPROOF
CAULKING
RELIEF VALVE
B1 SCALE = NONE
SEE NOTE 3
N.C. NOTE 1
7 7 9 MINIMUM 3/4" POURED LEAD
6 6

5 9 8 10 THIAKOL PLASTIC CEMENT (FOR


2
D2
TEMPERATURES OVER 200°F USE
4 4 10 ASBESTOS ROPE)
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

SIPHON VACUUM CONTROL VALVE


11 PIPE SLEEVE (I.D. MIN. 1" D1 PILOT
BREAKER
LARGER THAN O.D. OF PIPE) CONTROL LINE
12 12
HWS
HWR
1
STEAM
11
12
MAIN
13 13
GAUGE WITH
WATERPROOF GROUT STEAM TRAP ANTI-SYPHON PIG TAIL RELIEF
CORE DRILLED SLEEVE CORE DRILLED SLEEVE AND GAUGE COCK VALVE
2"x2"x1/8" ANGLE D1 D2 STEAM
WELDED TO JOISTS LOCATED ANGLE AT FOR 1-1/4" AND LARGER BUILDING ENTRY 13 CORE DRILL MIN. 1" LARGER
TRAP REDUCER IF
JOIST PANEL HOLE THAN O.D. OF PIPE SLEEVE STEAM
(12" MAXIMUM CORE DRILL SIZE) REQUIRED FULL SIZE
POINTS ONLY TRAP
TO F.S.
FLANGE OR
14 EXTERIOR INSULATION JACKET UNION (TYP.)
HANGER ROD 7 7
4 D2 MIN.
14 14 15 PITCH PAN, 18 GA. GALV. SHEET TYPICAL CONVERTOR
"U" BOLT METAL BY MECHANICAL
16
3" 3"
PIPE GUIDE 16 CONTRACTOR, SUPPLIED TO
2"x2"x1/8" ANGLE PIPE
15 15 18
18
ROOFING CONTRACTOR 10 D1 MIN. 20 D2 MIN.
TRAPEZE OR P-3000 SEE STEAM TRAP DETAIL
UNISTRUT 15" Mark Date Description
16
MIN.
FILL WITH PLASTIC FLASHING D=PIPE DIAMETER Date September 11, 2015
NOTES: SEE PIPING SCHEMATIC
CONDENSATE Project Number 14400
19 17
20
CONCRET ROOF DECK
NOTES: 17 2 1. SEE PIPING SCHEMATIC FOR PIPE SIZES. 6" Drawn By PZP
NOTE:
A 1 5 PROVIDE SHEET METAL SLEEVE AROUND PIPE INSULATION 6 18 2. SEE PIPING SCHEMATIC AND EQUIPMENT SCHEDULE FOR VALVE DATA. INSTALL VALVES A
6 ROOFING BLOW DOWN Checked By IM
AT ALL PIPE HANGERS. SEE SPECS. FOR INSULATION AS RECOMMENDED BY MANUFACTURER. 1 TRAP SIZED FOR 200% OF
VALVE Copyright © VAN H. GILBERT ARCHITECT PC
CONVERTER CAPACITY USING 1/4"
2 "U" BOLTS SHALL BE USED AS GUIDES ONLY, NOT ROOF PENETRATION ROOF PENETRATION 3. BYPASS VALVE DISCHARGE PIPE SHALL BE SAME SIZE AS D2 FOR THE LARGEST PRV. PSIG P.D. THRU EACH TRAP.
ANCHORS. 19 CAULK WITH FIBEROUS MATERIAL BYPASS VALVE SIZE SHALL BE IN ACCORDANCE WITH THE NATIONAL BOARD INSPECTION 3/4" HOSE CONNECTION
BEFORE ADDING PLASTIC CODE OF THE NATIONAL BOARD OF BOILER AND PRESSURE VESSEL INSPECTORS. THE 2 SEE SCHEMATICS AND PLANS FOR SHEET TITLE
FLASHING SAFETY RELIEF VALVE SHALL BE CAPABLE OF HANDLING THE MAXIMUM FLOW OF THE PIPE SIZES
3 "U" BOLTS SHALL BE ON EVERY THIRD TRAPEZE (MIN.)

4 DO NOT TIGHTEN "U" BOLTS ON PIPING OR INSULATION, 20


LARGEST PRV OR BYPASS.
3 PROVIDE SADDLE SUPPORTS AND MECHANICAL DETAILS
9/15/2015 6:41:50 PM

STEEL DECK WITH INSULATION 4. PROVIDE UNIONS FOR THE REMOVAL OF VALVES WITH SCREWED CONNECTIONS. LEGS OR HANGERS FOR CONVERTOR.
LEAVE LOOSE AS PIPE GUIDE.

DUAL STEAM PRESSURE REDUCING STATION DETAIL STEAM TO HOT WATER CONVERTOR DETAIL
PIPE HANGER DETAIL A4 SCALE = NONE A5 SCALE = NONE
A1 SCALE = NONE PIPE PENETRATION DETAIL
A2 SCALE = NONE
M-503
1 2 3 4 5 6 SHEET 128 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

1 CADILLAC BTU METER PROVIDED BY NMSU

2 EXISTING STEAM CONDENSATE PIPING - FLOOR ABOVE 1 HEIGHT AS NOTED OR AS 5 20 GA. SLEEVE
VERIFY SIZE DIRECTED AT JOB SITE
ANCHOR TO BEAM,
3 SEE STRUCTURAL 6 8 9
ISOLATION VALVE 3" MIN. CLEAR
DRAWINGS 2 22 GA. WEATHERPROOF HOOD 2428 Baylor Dr SE Albuquerque, NM 87106
4 COUPLING WELD PLATE TO Tel 505-247-9955 Fax 505-247-1826
BEAM, BOTH SIDES 7 2" MIN.
5 3
E-mail info@vhgarchitect.com
NOMINAL FLOW METER DIAMETER "D" PIPING WITH 1/2" WELD PLATE 20 GA. FLASHING COLLAR 4
E E Web Site www.vhgarchitect.com
6 8
INSULATION, SEE
CONNECT TO EXISTING SPACER (TYPICAL) 6 3 1
4
PLANS FOR SIZE AND WELD PIPE CLAMP CONSULTANTS
LOCATION BRACKET TO WELD PLATE SPACER ROD WELDED IN PLACE
5 LABORATORY CONSULTANT
2 2 2 RFD - Research Facilities Design
5 D 1 3965 Fifth Ave. Suite 400
1
San Diego, CA 92103
8 Phone 619-297-0159
2 6
6 6
TWO 180°BONDSTRAND TWO-PIECE PIPE CLAMP
SADDLES BONDED TO OF 1/4" THICK STEEL,
BOTH SIDES OF PIPE 7
CIVIL ENGINEER
WITH ELASTOMERIC PAD
CLAMP BETWEEN PIPE AND PIPE Lilley Engineering, Inc.
4 4 3 9
5 CLAMP 5160 Calle Bellisima
7
D
Las Cruces, NM 88011
3 3 Phone 575-521-0006
1
1.5D 1.5D
PIPE ANCHOR DETAIL SLOT DIFFUSER, SEE PLANS FOR NUMBER OF SLOTS
D2 SCALE = NONE
AND LENGTH
STRUCTURAL ENGINEER
6 2 INTERNAL INSULATION
Stubbs Engineering, Inc.
4
BTU STEAM CONDENSATE METER DETAIL 3 FACTORY PLENUM 277 E. Amador Ave. Suite 200
5 Las Cruces, NM 88001
D1 M-503 SCALE = NONE 4 BRANCH RUNOUT, SEE PLANS FOR SIZE
Phone 575-993-5228
5 OVAL INLET
3 1 BOLT AND WING NUT AT MAX.
MECHANICAL/ELECTRICAL ENGINEER
3" O.C. *IF STACK HEIGHT IS MORE THAN 36", INSTALL COLLAR AND GUY 6 SOFFIT, SEE ARCH. DWGS. FOR CONSTRUCTION
Bridgers & Paxton Consulting Engineers
1 2 TACK WELD BOLT TO DUCT
WIRE CABLES SET IN PITCH PANS BOLTED TO DECK.
4600-C Montgomery Blvd. NE
7
PLENUM SUPPORT MOUNTED PLENUM AND ARCH.
2
3
*COORDINATE WITH ROOFING AND DECK INSTALLATION. BLOCK OUT FRAMING Albuquerque, NM 87109
PROVIDE GASKET BETWEEN OPENINGS AND WELD ANGLE FRAMES TO ROOF JOINTS (OR TO
D DUCT AND ACCESS DOOR 8 Phone 505-883-4111
5
3/4D DECK, IF APPROVED BY STRUCTURAL ENGINEER FOR SMALL OPENINGS). SUPPLY DUCT, SEE PLANS FOR SIZE
4 HANDLE *INSTALL FLASHING COLLAR ON THE BASE SHEET; RUN UPPER PLYS 9 ARCHITECTURAL ENCLOSURE, SEE ARCH DWGS.
4 OVER COLLAR BASE.
5 INSULATE COVER AS REQUIRED
BY DUCT INSULATION SPEC. *CABLES SET IN PITCH PANS BOLTED TO DECK.

D B SECTION A
6 MIN. 20 GA FRAME WELDED TO *DO NOT SUPPORT PIPE OR STACK WITH THE SLEEVE AND HOOD NOTE: D
DUCT ASSEMBLY.
R.A. SLOTS SIMILAR, EXCEPT NO
7
PRESSURE SENSITIVE LATCH *THIS DETAIL SHOWS GENERAL APPROACH INSTALL TO BE FLEX DUCT CONNECTION OR
L FOR VACUUM RELEASE PLENUM REQUIRED
COMPATIBLE WITH ROOFING. FOLLOW MANUFACTURERS
1 1 9 1 6
10 10 10 8 RETAINER CHAIN
INSTRUCTIONS ON FLASHING.

*IF STACK HEIGHT MORE THAN 36", INSTALL COLLAR AND GUY WIRE.
7 9 MIN. 22 GA GALV. STEEL SIDEWALL LINEAR DIFFUSER DETAIL M ES I
2 W FRAME D5 L IR T
2
*HOT PIPE (SUCH AS VENTS FROM STEAM SYSTEM, DISCHARGE
2 2 MEXI
SCALE = NONE

I
2

I
PIPING, PIPING FROM HOT WATER AND STEAM RELIEF VALVES, ETC.). W
4 10

CO
FRAME SECURED TO DUCT

NE
WITH 5/8" NOTCHED 20505
KNOCK-OVER EDGES ON ALL

E ER
P RO
3 3 9 7
SIDES
3 ES

IN
11
STANDARD PANEL SECTION B

F
B G
1 10 3
CONTINUOUS HINGE HOT PIPE THRU ROOF DETAIL SI
O N A L EN
INTERIOR
10 12
D4 SCALE = NONE
1 SURFACE CAM LATCH
FLAT OVAL DUCT
ROUND 13
2 1 MAJOR AXIS MINOR AXIS MIN. 22 GA DOOR
2
WXL DUCT
WHEN MOUNTED WHEN MOUNTED 4 PROJECT
DIAMETER
10 ON MAJOR AXIS ON MAJOR AXIS
A 3
8" X 12" 8" - 12" 8" - 16" 8" - 11"

2 1 3
12" X 12" 13" X 18" 17" - 24" 12" - 13" New Mexico State
1 1
14" X 20" 19" + 25" + 14" +
SOLID/SOLID PANEL SEPTUM PANEL
ROUND OR FLAT OVAL DUCT, 8" +
AIR VENT,
TYPICAL.
A RELIEF VALVE
University
SEE SPECS
5
12 9 PRESSURE
11 9
PREFORMED L
CORNER S
SENSOR TO
ACTIVATE PUMP Jett Hall and Jett Annex
10
10 2
10 W
AIR PURGER
FROM LINE TO
2 Renovations and
3 PUMP
2
10
11
11 10 12
RELIEF VALVES
SUCTION 45° 45° Additions
6 7
C
4 13
SECTION A C
8
SECTION C
4 C CW FROM BACKFLOW PREVENTER 1 EXPOSED ROUND SUPPLY DUCT. SIZE PER PLAN. DO NOT PAINT. DO NOT USE

D
DUCT SEALANT.
THE OTHER
2
WALL PANEL VENTLOCK 310 HARDWARE
DUCT DIMENSION ON WHICH OUTSIDE FRAME NOTE: GLYCOL WATER PRICE MODEL SDS LINEAR SUPPLY DIFFUSER WITH FRAME TYPE 16 FOR
AT FLOOR PREHUNG DOOR ACCESS DOOR IS PLACED WXL DUCT ACCESS DOORS SHALL SYSTEMS MOUNTING DIRECTLY TO SPIRAL DUCT. MOUNT 45 DEGREES FROM CENTER,
BE PROVIDED AT EACH 3/4" 3/4" ANGLED DOWN. DIFFUSER SHALL BE BRUSHED METAL FINISH.
6" - 8" 5" X 12" FIRE DAMPER, SMOKE DAMPER,
3
GLYCOL-WATER FEED UNIT
9" - 12" 8" X 8" DUCT MOUNTED EQUIPMENT, FROM OTHER LOAD-RATED FASTENERS
13" - 15" 12" X 12" AND AS REQUIRED FOR DUCT SYSTEM
1 18 GAUGE GALVANIZED SHEET METAL (MIN. GA.) 16" - 33" 14" X 14" CLEANING AND INSPECTION PRESSURE HB 4 THREADED ROD HANGER
SENSOR
2 34" - 66" (2) 14" X 14"
16 GAUGE GALVANIZED SHEET METAL REINFORCING (MIN. GA.)
67" + (3) 14" X 14" EXPOSED DUCT SUPPORT WITH LINEAR DIFFUSERS
3 22 GAUGE GALVANIZED PERFORATED SHEET METAL (MIN. GA.)
RECTANGULAR DUCTS
C5 SCALE = NONE

4 16 GAUGE ALL WELDED FRAME (MIN. GA.)


TANK
Construction
5

6
20 GAUGE GALVANIZED OFFSET HINGE.

CHANNEL ANCHORED SECURELY TO FINISH FLOOR. DUCT ACCESS DOOR DETAIL 3" CONCRETE PAD Documents
7
B2 SCALE = NONE
GASKET MATERIAL FOR TIGHT SEAL, PER MFR. RECOMMENDATIONS. PROVIDE ADDITONAL PUMP(S)
FOR OTHER SYSTEMS WHERE 16"Ø
8 FINISH FLOOR. NOTED

9 SEALING BEAD AT ALL LAP JOINTS FOR AIR TIGHT SEAL, (TYP.). NOTE:
SET REGULATING VALVE TO MAINTAIN MAKE-UP
10 INSULATED PANELS, THICKNESS AS NOTED ON DRAWINGS. 2 14 PRESSURE 15 PSIG ABOVE HIGHEST SYSTEM PRV
SETTING.
11 GASKET, CONTINUOUS AROUND DOOR PERIMETER. 1
15
12 AIR CONTROL AND MAKE-UP FOR GLYCOL SYSTEM
20 GAUGE GALVANIZED SHEET METAL (MIN. GA.). 8" MIN.
B4 SCALE = NONE DUCT CLAMP TO REMOVE
DUCT FOR CLEANING
GALVANIZED STEEL EXHAUST
DUCT
3
GENERAL NOTES: 4 ELEVATION
B B
* SEPTUM PANELS SHALL BE INSTALLED AT INTERIOR PARTITIONS, 5 8 ~
AROUND COILS, AIR WASHERS, FILTERS, FAN DISCHARGE (INTERIOR)
PLENUM PARTY WALLS. 6 9 SILENT
CHECK SHEET METAL HOOD
* PIPING AND DUCT PENETRATIONS THRU WALLS AND CEILINGS OF
PLENUM SHALL BE SEALED AIRTIGHT. FOLLOW MFR'S 7 10 VALVE WITH TWO 1"
RECOMMENDATIONS. SLOTS AND TRANSITION
11
SHUT-OFF VALVE
TYPICAL
* PANELS SHALL BE MFR'D BY SEMCO OR EQUIVALENT, UNITS
HAVING CERTIFIED TEST DATA ON SOUND & THERMAL TRANSMISSION. P/T PLUG
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

TYPICAL 45°
* ALL ACCESS DOORS SHALL BE 24" x 60" MIN. SIZE, UNLESS
13 12 1" EXHAUST SLOT
OTHERWISE NOTED SECTION PRESSURE GAUGE 2000 CFM PER SLOT
TYPICAL

DOUBLE WALL PLENUM DETAIL 9


4.5" WIDTH
B1 1 LOCATE SKIDS FOR SECURE COUNTERFLASHING WITH FASTENERS
SCALE = NONE
EQUIPMENT SUPPORT 24" O.C. 12"
TABLE BY
OTHERS
2 SKID SHALL SPAN TWO BEAMS 10 FIBER CANT STRIP. SET IN BITUMEN 18"
MINIMUM

11 ROOF INSULATION. SEE ARCHITECTURAL 120"


SECURE HOOD
3 INSTALL SKIDS PERPENDICULAR TO DRAWINGS
TO WALL
ROOF BEAMS
(TYP. OF 4)

12
MOP SKID IN PLACE WITH HOT
4 ROOF, SEE ARCHITECTURAL DRAWINGS ASHPHALT TAR OR AS DIRECTED BY
2.5" WIDTH
ARCHITECT
MINIMUM OF 3 PIPE
5 8"x8" TREATED REDWOOD SKID DIAMETERS
Mark Date Description
13 BLOCKING. ANCHOR SECURELY TO
ROOF DECK, SAME THICKNESS AS Date September 11, 2015
6 FASTENERS AT 8" O.C. ROOF INSULATION. STRAINER WITH
NOTES:
1 ALL DUCTWORK SHALL BE TESTED AT 10" S.P. (MINIMUM). Project Number 14400
BLOW OFF
Drawn By PZP
7
2 USE FACTORY FABRICATED FITTINGS SEE SPECIFICATIONS SECTION 15800.
BASE FLASHING 14 SET SKIDS TO BE LEVEL WHEN
A INSTALLED ON SLOPING ROOF
3 ALL DUCTS SHALL BE SECURELY SUPPORTED, AND SHALL BE FREE OF VIBRATION
A Checked By IM
8 20 GAUGE GALVANIZED SHEET METAL CAP
WHEN UNIT IS OPERATING. Copyright © VAN H. GILBERT ARCHITECT PC
4 ALL JOINTS SHALL BE WELDED OR SOLDERED.
SHEET TITLE
5 ALL EXPOSED DUCTS SHALL BE PAINTED (2 COATS). COLOR AS SELECTED BY
OWNER.
ROOF SKID DETAIL MECHANICAL DETAILS
A2 ~
9/15/2015 6:41:50 PM

SCALE = NONE
IN-LINE PUMP DETAIL PLASMA TABLE HOOD EXHAUST DETAIL
A4 SCALE = NONE
A5 SCALE = NONE

M-504
1 2 3 4 5 6 SHEET 129 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

ROOF

2428 Baylor Dr SE Albuquerque, NM 87106


Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159
CHILLED WATER
SUPPLY BYPASS STEAM VENT CIVIL ENGINEER
REFER TO SECTION 253500 SEE DETAIL B2/M-503 Lilley Engineering, Inc.
FOR VALVE SPECIFICATION
NEW INSULATED (TOP AND 5160 Calle Bellisima

PIPING CHASE
TO FMS
BOTTOM) Las Cruces, NM 88011
ARCHITECTURAL Phone 575-521-0006
ROOF ENCLOSURE

STRUCTURAL ENGINEER
6" 6" 6" 6" 6" 6" 6" Stubbs Engineering, Inc.
CHWR
M
CHWR CHWR CHWR 277 E. Amador Ave. Suite 200
CHWS CHWS CHWS CHWS Las Cruces, NM 88001
2-1/2" Phone 575-993-5228
HWR HWR
PC HWS HWS SECOND LEVEL

MECHANICAL/ELECTRICAL ENGINEER
5" Bridgers & Paxton Consulting Engineers
8" 2/3 4600-C Montgomery Blvd. NE
LPS LPS LPS Albuquerque, NM 87109
6"
5" 1/3 5" Phone 505-883-4111

HWS
6" 5"
6"

HWR
5"
2/3 6"
D D
5" 1/3

4"

6"
4"
HWS
M ES I
2-1/2"
L IR T
CHWS

CHWS

1/4"/ft
MEXI

I
3" DOWN W

CO
NE
HWR
6"
2-1/2"
4"
AS-1
6" OUTSIDE 20505
6" 6" STEAM TRAP 6"

E ER
P RO
SEE DETAIL B3/M-504 A
TO F.S.
~
6" 6" ES

IN
F
SI G
HWS
O N A L EN
PC

2-1/2"
1/4"/ft
CHWS

V
CHWS

3/4"

HWS

HWS
DOWN
2-1/2" 3"

~
~
TO F.S. PROJECT
SEE PLUMBING FLOW METER
VFD VFD 3" STEAM TRAP
FOR CONTINUATION CONNECT TO FMS VFD VFD
3" SEE DETAIL B3/M-504

MECHANICAL ROOM - M198 ET-1


GRADE FIRST LEVEL
New Mexico State
CHWP-1 CHWP-2 CF-1 HWP-1 HWP-2 University
CHEMICAL BYPASS
FEEDER
WITH FILTER
5 GALLONS MINIMUM
Jett Hall and Jett Annex
Renovations and
Additions
C C
CHILLED WATER BTU METER. CONNECT RELIEF DISCHARGE ON TOP OF
ISOLATION VALVES AT EACH CONNECTION METER TO NETWORK SWITCH. SEE CONTROL ROOF. SEE DETAIL B2/M-504
(TOTAL OF 4) DRAWINGS/230900 SPECIFICATIONS FOR D4/M-503
SEE TABLE 230504-1 FOR VALVE TYPE TYPE AND CONNECTIONS.

STEAM CONDENSATE BTU METER. INSTALL 8"


PER DETAIL A1/M-503
CONNECT METER TO NETWORK SWITCH. SEE
CONTROL DRAWINGS/230900 SPECIFICATIONS
FOR TYPE AND CONNECTIONS.

R
6" 6" M
6"
P T
CHWR CHWR CHWR
P T
CHWS CHWS CHWS
P T
2-1/2" 2-1/2" 2-1/2"

2-1/2"
PC PC PC
Construction
P T M R

5"
HPS
100 PSIG 5"
SET AT 24 PSIG
8"
Documents
1/2" 15 PSIG
LPS LPS LPS

8" N.C. 8" 8"


8"
PRV-1 1/3

A SIPHON

~
2,373 LBS/HR
4"
STEAM
2/3 TRAP
PRV-2
CHWR

PC
B

~
~
4,818 LBS/HR
CHWS

6"

100 PSIG
HPS STEAM
TRAP STEAM
TRAP

B B

6"

2-1/2"

5"
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

ISOLATION VALVES AT EACH CONNECTION


(TOTAL OF 4)
SEE TABLE 230504-1 FOR VALVE TYPE
ANNEX BUILDING

FULLY CLOSE VALVE


AFTER FILL & PURGE COMPLETION GRADE

6" 6" 6" 6"


CHWR CHWR CHWR

CHWS CHWS CHWS


2-1/2" 2-1/2" 2-1/2" 2-1/2"
PC PC PC
5" 5" 5" 5"
HPS HPS HPS
100 PSIG 100 PSIG 100 PSIG
HPS Mark Date Description
Date September 11, 2015

CHWS Project Number 14400


Drawn By PZP
A MAKE NEW PIPING EXISTING TUNNEL EXISTING TUNNEL A Checked By IM
CONNECTIONS
AT THIS LOCATION
Copyright © VAN H. GILBERT ARCHITECT PC

CND CHWR SHEET TITLE

EXISTING MAIN TUNNEL PIPING DIAGRAM


9/15/2015 6:41:51 PM

A1 MECHANICAL
Scale: NTS
PIPING DIAGRAM

M-601
1 2 3 4 5 6 SHEET 130 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
AIR HANDLING UNITS
SUPPLY FAN HEAT RECOVERY COIL (40% PROPELYNE GLYCOL) CHILLED WATER COOLING COIL HOT WATER HEATING COIL
EACH MOTOR DATA MAX. WATER TEMP MAX PRESSURE MAX. WATER TEMP MAX PRESSURE
TOTAL FAN FAN EACH EACH EACH EACH (EACH) FACE TOTAL SENSIBLE EAT (°F) LAT (°F) (°F) LOSS FACE TOTAL (°F) LOSS OPER. MIN
MANUFACTURER & AIRFLOW ARRAY AIRFLOW EXT. SP. TOTAL SP. FAN FAN EAT S.P. LAT LAT VEL. CAPACITY CAPACITY AIR WATER VEL. CAPACITY EAT LAT AIR WATER WEIGHT OUTSIDE
SYMBOL MODEL NO. TYPE LOCATION (CFM) QTY. (CFM) (IN. WC) (IN. WC) BHP RPM HP V PH HZ FAN SIZE AND TYPE EAT DB WB DROP DB WB EWT LWT (FPM) (MBH) (MBH) DB WB DB WB GPM ENT. LVG. (IN. WC) (FT. WC) (FPM) (MBH) (°F) (°F) GPM ENT. LVG. (IN. WC) (FT. WC) (LBS.) AIR
2428 Baylor Dr SE Albuquerque, NM 87106
AHU-1 TRANE CSAA057 PERF. C.C. WEST PENTHOUSE 31,500 2 15,775 2.0 5.41 23.6 1800 30 460 3 60 30" AF N/A N/A N/A N/A N/A N/A N/A 555 806 926 80 65 63 52.2 42 58 .473 11.4 555 1,320 45 90 180 140 4.06 Tel 505-247-9955 Fax 505-247-1826
AHU-3 TRANE CSAA035 TALL PERF. C.C. WEST- 1ST 17,500 2 8,750 2.0 3.781 9.1 2,186 15 460 3 60 22.25" AF 12 .40 513 620 620 96 61 55 45 42 58 .558 8.19 539 1,021 12 80 180 140 7,500 100% E-mail info@vhgarchitect.com
E AHU-4 TRANE CSAA010 SUSPENDED ANNEX 4,500 1 4,500 0.5 1.97 2.62 1,010 3 460 3 60 15" AF N/A N/A N/A N/A N/A N/A N/A 451 125.4 110.9 79 63 53 52.9 15.6 42 58 0.501 1.18 451 126.0 60 90 6.3 180 140 0.101 0.80 2,200 15% E Web Site www.vhgarchitect.com
AHU-5 TRANE CSAA010 SUSPENDED ANNEX 4,500 1 4,500 0.5 1.97 2.62 1,010 3 460 3 60 15" AF N/A N/A N/A N/A N/A N/A N/A 451 125.4 110.9 79 63 53 52.9 15.6 42 58 0.501 1.18 451 126.0 60 90 6.3 180 140 0.101 0.80 2,200 15% CONSULTANTS

LABORATORY CONSULTANT
NOTE: RFD - Research Facilities Design
FOR REFERENCE AND CLARITY, THE BUILT-UP BASEMENT AIR HANDLING SYSTEM WILL COLLECTIVELY BE REFERRED TO AS AHU-2.
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159

CIVIL ENGINEER
EXHAUST FANS Lilley Engineering, Inc.
MOTOR DATA PER 5160 Calle Bellisima
NOZZLE EFFECTIVE Las Cruces, NM 88011
S.P. OUTLET PLUME BHP FAN OUTLET SOUND POWER BY OCTAVE BAND
Phone 575-521-0006
MANUFACTURER & TOTAL (IN. FAN VELOCITY HEIGHT PER 63 125 250 500 1000 2000 4000 8000 OPERATING
SYMBOL MODEL NO. LOCATION SERVICE TYPE CFM WC) RPM (FT/MIN) (FT.) FAN HP V PH HZ HZ HZ HZ HZ HZ HZ HZ HZ WEIGHT (LBS.) NOTES STRUCTURAL ENGINEER
EF-1 GREENHECK - SBE 3H30 EAST PENTHOUSE RELIEF AIR - SYSTEM SF-1 PROPELLER 8,000 1.0 1370 N/A N/A 2.75 3 460 3 60 91 94 93 93 90 86 82 81 400 Stubbs Engineering, Inc.
EF-2 GREENHECK - SBE 3H30 EAST PENTHOUSE RELIEF AIR - SYSTEM SF-1 PROPELLER 8,000 1.0 1370 N/A N/A 2.75 3 460 3 60 91 94 93 93 90 86 82 81 400 277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
EF-3 GREENHECK - LBP 30 WEST PENTHOUSE RELIEF AIR - SYSTEM AHU-1 BELT DRIVE LOUVERED CENTRIFUGAL ROOF EXHAUST FAN 6250 0.75 593 N/A N/A 1.36 1 1/2 460 3 60 78 82 74 66 63 60 55 51 286
Phone 575-993-5228
EF-4 GREENHECK - LBP 30 WEST PENTHOUSE RELIEF AIR - SYSTEM AHU-1 BELT DRIVE LOUVERED CENTRIFUGAL ROOF EXHAUST FAN 6250 0.75 593 N/A N/A 1.36 1 1/2 460 3 60 78 82 74 66 63 60 55 51 286
EF-5 GREENHECK - LBP 30 WEST PENTHOUSE RELIEF AIR - SYSTEM AHU-1 BELT DRIVE LOUVERED CENTRIFUGAL ROOF EXHAUST FAN 6250 0.75 593 N/A N/A 1.36 1 1/2 460 3 60 78 82 74 66 63 60 55 51 286 MECHANICAL/ELECTRICAL ENGINEER
EF-6 GREENHECK - LBP 30 WEST PENTHOUSE RELIEF AIR - SYSTEM AHU-1 BELT DRIVE LOUVERED CENTRIFUGAL ROOF EXHAUST FAN 6250 0.75 593 N/A N/A 1.36 1 1/2 460 3 60 78 82 74 66 63 60 55 51 286 Bridgers & Paxton Consulting Engineers
EF-7 GREENHECK - IP 15A ANNEX PLASMA CUTTER SD CLASS 4,000 1.25 950 N/A N/A 1.71 3 460 3 60 102 102 90 83 78 73 67 60 662 ARRANGEMENT 10, THDISCH 4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
GEF-1 GREENHECK - GB 141 NORTH ROOF GENERAL EXHAUST BELT DRIVE CENTRIFUGAL ROOF EXHAUST FAN 2,170 0.5 1390 N/A N/A 0.53 3/4 115 1 60 82 77 80 74 67 66 61 56 120 Phone 505-883-4111
GEF-2 GREENHECK - GB 101 WEST ROOF GENERAL EXHAUST BELT DRIVE CENTRIFUGAL ROOF EXHAUST FAN 700 0.5 1296 N/A N/A 0.13 1/4 115 1 60 70 72 66 61 52 50 46 39 65
LEF-1 STROBIC - TS1L150B18 WEST ROOF LAB EXHAUST - GENERAL (2) FAN SYSTEM 16,000 5.25 1800 4373 42 10.5 15 460 3 60 102 92 88 84 84 80 79 76 4,656 FURNISH ACOUSTIC LOUVER WITH BYPASS DAMPERS
LEF-2 STROBIC - TS3S300D12 EAST ROOF LAB EXHAUST - CHEM (3) FAN SYSTEM 48,000 5.25 1203 4167 59 22.3 30 460 3 60 89 96 90 86 84 82 80 75 10,815 FURNISH ACOUSTIC LOUVER WITH BYPASS DAMPERS

D D

M ES I
CONDENSATE PUMP L IR T
MEXI

I
W
ELECTRIC PUMPS

CO
MANUFACTURER & MODEL RECEIVER CAPACITY PUMPED FLOW DISCHARGE

NE
SYMBOL NO. LOCATION (GAL) (GPM) PRESSURE (PSIG) VOLT PHASE HZ MOTOR HP CONTROL DUPLEX NOTES 20505

E ER
P RO
CP-1 BELL & GOSSETT 302.5CC M198 36 30 25 460 3 60 1-1/2 115/1/60 YES
ES

IN
F
DUPLEX SI G
O N A L EN
CONTROL PANEL: NEMA 2 Type Control PanelUnit Mounted & Wired CSA Label, Liquid Tight Conduit. Provide Magnetic Starters with Fused Disconnect w/ FusesAuxiliary Contactor on Starter Alarm With Silencing RelayAlarm, Pilot Light Selector Switches - Auto-Off-Hand, Electrical Alternator, Pump Pilot Light, Single Power
Point Connection, Mounting Plate, Push to Test ButtonsU.L. Listing
OPTIONS: Gauge GlassDial ThermometerInlet Basket Strainer - 2 in.Discharge Pressure GaugeNEMA 1 High Level Float SwitchButterfly Suction Valve
PROJECT

STEAM PRESSURE REDUCING VALVES New Mexico State


SYMBOL
MANUFACTURER & MODEL
NO. LOCATION SERVICE TYPE
VALVE SIZE
(IN)
STEAM LOAD
(LBS/HR)
ENTERING PRESSURE
(PSIG)
LEAVING PRESSURE
(PSIG) NOTES
University
PRV-1 HOFFMAN SPECIALTY 2200 194 HEATING SYSTEM STEAM 2-1/2 4818 100 15 PARALLEL VALVE (SPLIT FLOW)
PRV-2 HOFFMAN SPECIALTY 2100 194 HEATING SYSTEM STEAM 1-1/4 2373 100 15 PARALLEL VALVE (SPLIT FLOW)
Jett Hall and Jett Annex
Renovations and
PUMPS
Additions
C C
MANUFACTURER & CAPACITY TOTAL HEAD PUMP MOTOR ELECTRICAL DATA
SYMBOL MODEL NO. LOCATION SERVICE TYPE (GPM) (FT. WG) RPM HP VOLT PHASE HZ FLA NOTES
CHWP-1 B&G SERIES 1510 4BC NORTH ANNEX BLDG CHILLED WATER BASE MOUNTED CENTRIFUGAL PUMP 500 60 1750 15 460 3 60 18.5
CHWP-2 B&G SERIES 1510 4BC NORTH ANNEX BLDG CHILLED WATER BASE MOUNTED CENTRIFUGAL PUMP 500 60 1750 15 460 3 60 18.5
HRP-2 B&G SERIES 1510 5E EAST BASEMENT - SF-1 SYSTEM (AHU-2) HEAT RECOVERY BASE MOUNTED CENTRIFUGAL PUMP 660 35 1150 10 460 3 60 12.6
HRP-3 B&G SERIES 1510 2-1/2BB AHU-3 HEAT RECOVERY BASE MOUNTED CENTRIFUGAL PUMP 125 32 1150 3 460 3 60 4.4
PCP-1 B&G SERIES 60 2x6-1/4 AHU-1 COIL PUMP INLINE CENTRIFUGAL PUMP 66 20 1750 0.75 460 3 60 1.5
PCP-2 B&G SERIES 1510 2-1/2BB EAST BASEMENT - SF-1 SYSTEM (AHU-2) COIL PUMP BASE MOUNTED CENTRIFUGAL PUMP 160 20 1150 1.5 460 3 60 2.4
PCP-3 B&G SERIES 60 2x6-1/4 AHU-3 COIL PUMP INLINE CENTRIFUGAL PUMP 51 20 1750 0.75 460 3 60 1.5

Construction
HEAT TRANSFER PACKAGE Documents
HEAT EXCHANGER - EACH PUMPS - EACH EXPANSION TANK AIR SEPARATOR
SHELL SIDE - STEAM TUBE SIDE - WATER ELECT. PACKAGE
MANUFACT. & STEAM SURFACE MAX TANK ACCEPT. WATER WATER PIPE OPER.
PACKAGE PACKAGE MODEL COMP. COMP. CAPACITY PRESS. FLOW AREA FLOW EWT LWT P.D. LENGTH FOULING COMP. COMP. MODEL CAPACITY TOTAL HEAD PUMP MOTOR COMP. COMP. VOL. VOL. COMP. COMP. FLOW TEMP CONN. WEIGHT
SYMBOL NO. LOCATION SERVICE SYMBOL MODEL NO. (BTU/HR) (PSIG) (LBS/HR) (FT²) (GPM) (°F) (°F) (PSIG) (IN) PASS FACTOR SYMBOL NO. TYPE QTY. (GPM) (FT WG) RPM HP V PH HZ SYMBOL MODEL NO. (GAL) (GAL) SYMBOL MODEL NO. (GPM) (°F) (IN) (LBS)
HXP-1 FLOW THERM M198 HEATING HX-1 & 2 SU124-2 3,250,000 15 4,230 82.6 273 150 180 0.38 48 2 0.00053 HWP-1 & 2 1510 2-1/2BB BASE MOUNTED 2 400 60 1,750 10 460 3 60 ET-1 D-240V 132 46 AS-1 RL-5 400 180 6 6,000
SYSTEM SYSTEM CENTRIFUGAL

THE HEAT TRANSFER PACKAGE SHALL BE A COMPLETE MANUFACTURED SYSTEM WITH THE FOLLOWING COMPONENTS:
1. PUMPS (WITH SUCTION DIFFUSERS), 2. AIR SEPARATOR, 3. HEAT EXCHANGERS, 4. SUCTION/DISCHARGE PRESSURE GAUGE, 5. ASME SAFETY RELIEF VALVE, 6. PRESSURE REGULATING SYSTEM FILL VALVE, 7. PUMP SERVICING SHUT-OFF VALVES, 8. ASME DIAPHRAM PRESSURIZED EXPANSION TANK, 9. TRIPLE DUTY VALVE, 10. 5 GALLON CHEMICAL POT FEEDER (WITH FILTER BAG KIT), 11. STEEL SUPPORT (FACTORY PAINTED). SET ET-1 AT XX PSIG INITIAL PRESSURE.

B B

FAN COIL UNITS


SUPPLY FAN COOLING COIL HEATING COIL FILTER PIPE SIZE (IN.)
ELECTRICAL DATA TOTAL SENSIBLE EAT (°F) HEATING EAT OPERATING
MANUFACTURER & NOMINAL ESP MOTOR HP COOLING COOLING EWT LWT P.D. CAPACITY DB EWT LWT P.D. EFFICIENCY CHILLED HOT WEIGHT
SYMBOL MODEL NO. LOCATION TYPE CFM (IN WC) (MOTOR 1/MOTOR 2) MCA V PH HZ DRIVE (MBH) (MBH) DB WB (°F) (°F) GPM (FT HD) (MBH) (°F) (°F) (°F) GPM (FT HD) TYPE QTY. (%) WATER WATER (LBS) NOTES
FCU-1 TRANE FCCB12 004 HORIZONTAL CONCEALED 1044 0.40 0.24/0.24 3.6 277 1 60 DIRECT 34.0 30.6 80 63 42 51.1 7.7 16.11 39.7 60 180 140 2.0 18.74 1" THROWAWAY 1 MERV 8 1-1/4 3/4 220
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

FCU-2 TRANE FCCB12 006 HORIZONTAL CONCEALED 1044 0.40 0.24/0.24 3.6 277 1 60 DIRECT 34.0 30.6 80 63 42 51.1 7.7 16.11 39.7 60 180 140 2.0 18.74 1" THROWAWAY 1 MERV 8 1-1/4 3/4 220
FCU-3 TRANE FCCB12 010 HORIZONTAL CONCEALED 1044 0.40 0.24/0.24 3.6 277 1 60 DIRECT 34.0 30.6 80 63 42 51.1 7.7 16.11 39.7 60 180 140 2.0 18.74 1" THROWAWAY 1 MERV 8 1-1/4 3/4 220
FCU-4 TRANE FCDB12 M198 HORIZONTAL CABINET 921 0 0.24/0.24 3.6 277 1 60 DIRECT 26.3 25.0 80 63 42 52.0 5.3 8.11 36.5 60 180 140 1.8 16.09 1" THROWAWAY 1 MERV 8 1 3/4 240
FCU-5 TRANE FCDB12 M198 HORIZONTAL CABINET 921 0 0.24/0.24 3.6 277 1 60 DIRECT 26.3 25.0 80 63 42 52.0 5.3 8.11 36.5 60 180 140 1.8 16.09 1" THROWAWAY 1 MERV 8 1 3/4 240

SUPPLY FANS

TOTAL FAN EACH EACH MOTOR DATA


AIRFLOW TOTAL SP. ARRAY EACH FAN FAN FAN (EACH) MANUFACTURER &
SYMBOL (CFM) (IN. WC) QTY. AIRFLOW BHP RPM HP V PH HZ ARRANGEMENT FAN SIZE AND TYPE LOCATION NOTES
SF-1 61,000 5.0 6 10,165 13.4 2,246 15 460 3 60 TRANE 22.25 in. STACKED DD M003 (AHU-2)
Mark Date Description
3X2 ARRAY PLENUM, 120% WIDTH
Date September 11, 2015
PROVIDE DISCONNECT SWITCH, FUSES, CONTACTORS, AND FAN CONTROLS. Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC
GLYCOL FILL SYSTEM
SHEET TITLE
MANUFACTURER
SYMBOL & MODEL NO. LOCATION GPM V/P/H NOTES
MECHANICAL
9/15/2015 6:41:51 PM

GFP-1 AXIOM - MF 300 BASEMENT EAST 0.70 115/1/60 17 GALLON TANK, CONTROLS 25PSIG MAX FILL PRESS
GFP-2 AXIOM - MF 300 FAN ROOM WEST LEVEL 1 0.70 115/1/60 17 GALLON TANK, CONTROLS 25PSIG MAX FILL PRESS EQUIPMENT
NOTE:
SCHEDULES
ALL EQUIPMENT SELECTED AT AN ELEVATION OF 4,000 FEET ABOVE SEA LEVEL.
M-701
1 2 3 4 5 6 SHEET 131 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

TERMINAL UNITS
MAX MIN MAX TERMINAL INLET INLET DUCT
COOLING COOLING HEATING HEATING HEATING PIPE SIZE COIL TERMINAL CONTROL DIAMETER DIAMETER ENVIRO-TECH
SYMBOL ROOMS SERVED CFM CFM CFM MBH GPM (INCH) ROWS EWT (F) TYPE VALVE (INCH) (INCH) MODEL V/PH/HZ NOTES
TU1-001 R001 & H002 620 186 372 13.5 1.4 3/4 2 180 VV 2-WAY 6 6 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-002 012, 017A, 018A & H017 390 117 234 8.5 0.9 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
2428 Baylor Dr SE Albuquerque, NM 87106
TU1-101 149B 720 216 432 15.7 1.6 3/4 2 180 VV 3-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Tel 505-247-9955 Fax 505-247-1826
TU1-102 149 & 149A 240 72 144 5.3 0.6 3/4 2 180 VV 3-WAY 6 6 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER E-mail info@vhgarchitect.com
E TU1-103 120, 122, H102 & R140 1160 348 696 25.3 2.6 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER E Web Site www.vhgarchitect.com
TU1-104 136 & 138 450 135 270 9.8 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER CONSULTANTS
TU1-105 132 & 134 440 132 264 9.6 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER LABORATORY CONSULTANT
TU1-106 128 & 130 560 168 336 12.2 1.3 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER RFD - Research Facilities Design
TU1-107 124 & 126 560 168 336 12.2 1.3 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER 3965 Fifth Ave. Suite 400
San Diego, CA 92103
TU1-108 125 1000 300 600 21.8 2.2 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Phone 619-297-0159
TU1-109 117B, 117C & H117 1040 312 624 22.7 2.3 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-110 116 1300 390 780 28.3 2.9 3/4 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER CIVIL ENGINEER
TU1-111 115 380 114 228 8.3 0.9 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Lilley Engineering, Inc.
5160 Calle Bellisima
TU1-112 112 & 114 720 216 432 15.7 1.6 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
Las Cruces, NM 88011
TU1-113 113 600 180 360 13.1 1.4 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Phone 575-521-0006
TU1-114 108 & 110 720 216 432 15.7 1.6 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-115 111 930 279 558 20.3 2.1 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER STRUCTURAL ENGINEER
TU1-116 106 450 135 270 9.8 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Stubbs Engineering, Inc.
277 E. Amador Ave. Suite 200
TU1-117 104A & 104B 560 168 336 12.2 1.3 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Las Cruces, NM 88001
TU1-118 104 930 279 558 20.3 2.1 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Phone 575-993-5228
TU1-119 109 2320 696 1392 50.6 5.1 1 2 180 VV 2-WAY 14 14 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-120 105 & 105A 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER MECHANICAL/ELECTRICAL ENGINEER
Bridgers & Paxton Consulting Engineers
TU1-121 107 1400 420 840 30.5 3.1 3/4 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
4600-C Montgomery Blvd. NE
TU1-122 H101 800 240 480 17.5 1.8 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Albuquerque, NM 87109
TU1-201 249 600 180 360 13.1 1.4 3/4 2 180 VV 3-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Phone 505-883-4111
TU1-202 245 1600 480 960 34.9 3.5 1 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-203 237 540 162 324 11.8 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-204 H202 & R240 740 222 444 16.2 1.7 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-205 236 & 238 420 126 252 9.2 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
D D
TU1-206 232 & 234 420 126 252 9.2 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-207 228 & 230 420 126 252 9.2 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-208 224 & 226 420 126 252 9.2 1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-209 222 480 144 288 10.5 1.1 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-210 217A & 217B 1020 306 612 22.3 2.3 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER M ES I
TU1-211 216 1720 516 1032 37.5 3.8 1 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER L IR T
MEXI

I
W
TU1-212 215 780 234 468 17 1.7 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER

CO
NE
TU1-213 210 1340 402 804 29.2 3 3/4 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER 20505

E ER
P RO
TU1-214 213 1660 498 996 36.2 3.7 1 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
ES

IN
F
TU1-215 208 680 204 408 14.9 1.5 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER SI G
O N A L EN
TU1-216 207 & 207A 2340 702 1404 51 5.1 1 2 180 VV 2-WAY 14 14 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-217 206 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU1-218 204 580 174 348 12.7 1.3 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER PROJECT
TU1-219 H201 1420 426 852 31 3.1 3/4 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-101 178 & 179 1840 552 1104 40.1 4.1 1 2 180 VV 2-WAY 14 14 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-102 177 & 180 1770 531 1062 38.6 3.9 1 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER New Mexico State
TU2-103
TU2-104
172 & 174
163
720
120
216
36
432
72
15.7
2.7
1.6
0.3
3/4
3/4
2
2
180
180
VV
VV
2-WAY
2-WAY
10
6
10
6
SDR-SA
SDR-SA
277/1/60
277/1/60
PROVIDE 277/24 VAC TRANSFORMER
PROVIDE 277/24 VAC TRANSFORMER
University
TU2-105 168 960 288 576 20.9 2.1 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-106
TU2-107
162 & 164
159F & 159G
770
220
231
66
462
132
16.8
4.8
1.7
0.5
3/4
3/4
2
2
180
180
VV
VV
2-WAY
2-WAY
10
6
10
6
SDR-SA
SDR-SA
277/1/60
277/1/60
PROVIDE 277/24 VAC TRANSFORMER
PROVIDE 277/24 VAC TRANSFORMER
Jett Hall and Jett Annex
TU2-108 159D & 159E 160 48 96 3.5 0.4 3/4 2 180 VV 2-WAY 6 6 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Renovations and
TU2-109 159 570 171 342 12.5 1.3 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-110 159B & 159C 570 171 342 12.5 1.3 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
Additions
C TU2-111 159A 120 36 72 2.7 0.3 3/4 2 180 VV 2-WAY 6 6 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER C
TU2-112 157 & H161 720 216 432 15.7 1.6 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-113 158 & 160 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-114 154 & 156 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-115 150 & 152 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-201 274 1330 399 798 29 2.9 3/4 2 180 VV 2-WAY 12 12 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-202 H202 650 195 390 14.2 1.5 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-203 263 & 265 220 66 132 4.8 0.5 3/4 2 180 VV 2-WAY 6 6 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-204 268 & 268A 1140 342 684 24.9 2.5 3/4 2 180 VV 2-WAY 10 10 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-205 262 & 264 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-206A
TU2-206B
259
259
1100
1100
330
330
660
660
24
24
2.4
2.4
3/4
3/4
2
2
180
180
VV
VV
2-WAY
2-WAY
10
10
10
10
SDR-SA
SDR-SA
277/1/60
277/1/60
PROVIDE 277/24 VAC TRANSFORMER
PROVIDE 277/24 VAC TRANSFORMER
Construction
TU2-207 258 & 260 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER Documents
TU2-208 254 & 256 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-209 250 & 252 550 165 330 12 1.2 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER
TU2-210 251 370 111 222 8.1 0.9 3/4 2 180 VV 2-WAY 8 8 SDR-SA 277/1/60 PROVIDE 277/24 VAC TRANSFORMER

HYDRONIC HEAT RECOVERY COILS


MAX PRESSURE
SUMMER WINTER LOSS
MAX FACE TOTAL WATER TEMP TOTAL WATER TEMP
TRANE COIL VELOCITY CAPACITY (°F) EAT (°F) LAT (°F) CAPACITY (°F) EAT (°F) LAT (°F) AIR P.D. FLUID P.D. COIL DIMENSIONS
B SYMBOL MODEL NO. LOCATION ROWS CFM GPM % GLYCOL (FPM) (MBH) ENT. LVG. DB WB DB WB (MBH) ENT. LVG. DB WB DB WB (IN. WC) (FT. WC) (COIL HEIGHT X FINNED LENGTH) B
HRC-1 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 8 10,167 110 40 488 546 84.8 86.7 96 61 86.5 57.8 1,239 44.7 40.5 12 11 33.8 24.9 0.46 10.62 37" X 80"
HRC-2 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 8 10,167 110 40 488 546 84.8 86.7 96 61 86.5 57.8 1,239 44.7 40.5 12 11 33.8 24.9 0.46 10.62 37" X 80"
HRC-3 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 8 10,167 110 40 488 546 84.8 86.7 96 61 86.5 57.8 1,239 44.7 40.5 12 11 33.8 24.9 0.46 10.62 37" X 80"
HRC-4 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 8 10,167 110 40 488 546 84.8 86.7 96 61 86.5 57.8 1,239 44.7 40.5 12 11 33.8 24.9 0.46 10.62 37" X 80"
HRC-5 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 8 10,167 110 40 488 546 84.8 86.7 96 61 86.5 57.8 1,239 44.7 40.5 12 11 33.8 24.9 0.46 10.62 37" X 80"
HRC-6 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 8 10,167 110 40 488 546 84.8 86.7 96 61 86.5 57.8 1,239 44.7 40.5 12 11 33.8 24.9 0.46 10.62 37" X 80"
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

HRC-7 EAST ROOF - LEF-1 SYSTEM 8 12,000 165 40 477 546 86.7 84.8 73 60 85.2 63.9 1,239 40.5 44.7 75 56 47.6 45.0 0.44 25.16 36" X 100"
HRC-8 EAST ROOF - LEF-1 SYSTEM 8 12,000 165 40 477 546 86.7 84.8 73 60 85.2 63.9 1,239 40.5 44.7 75 56 47.6 45.0 0.44 25.16 36" X 100"
HRC-9 EAST ROOF - LEF-1 SYSTEM 8 12,000 165 40 477 546 86.7 84.8 73 60 85.2 63.9 1,239 40.5 44.7 75 56 47.6 45.0 0.44 25.16 36" X 100"
HRC-10 EAST ROOF - LEF-1 SYSTEM 8 12,000 165 40 477 546 86.7 84.8 73 60 85.2 63.9 1,239 40.5 44.7 75 56 47.6 45.0 0.44 25.16 36" X 100"
HRC-11 WEST ROOF- LEF-2 SYSTEM 8 16,000 110 40 569 140 85.5 82.7 73 60 82.4 63.0 300 42.6 48.7 75 56 55.1 48.3 0.60 8.48 45" x 90"

HYDRONIC COOLING AND HEATING COILS


WATER TEMP MAX PRESSURE
MAX FACE TOTAL SENSIBLE (°F) EAT (°F) LAT (°F) LOSS
TRANE COIL VELOCITY CAPACITY CAPACITY AIR P.D. FLUID P.D. COIL DIMENSIONS
SYMBOL MODEL NO. LOCATION ROWS CFM (FPM) (MBH) (MBH) ENT. LVG. GPM DB WB DB WB (IN. WC) (FT. WC) (COIL HEIGHT X FINNED LENGTH) Mark Date Description
CWC-1 DWLB36084 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 4 10,167 481 411 411 42 58 51.2 96 61 53 44.6 0.37 4.61 36" X 84"
Date September 11, 2015
CWC-2 DWLB36084 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 4 10,167 481 411 411 42 58 51.2 96 61 53 44.6 0.37 4.61 36" X 84"
Project Number 14400
CWC-3 DWLB36084 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 4 10,167 481 411 411 42 58 51.2 96 61 53 44.6 0.37 4.61 36" X 84"
Drawn By PZP
CWC-4 DWLB36084 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 4 10,167 481 411 411 42 58 51.2 96 61 53 44.6 0.37 4.61 36" X 84"
A A Checked By IM
CWC-5 DWLB36084 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 4 10,167 481 411 411 42 58 51.2 96 61 53 44.6 0.37 4.61 36" X 84"
Copyright © VAN H. GILBERT ARCHITECT PC
CWC-6 DWLB36084 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 4 10,167 481 411 411 42 58 51.2 96 61 53 44.6 0.37 4.61 36" X 84"
PHC-1 D5WB36058 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 1 10,167 701 503 - 180 140 25.1 12 - 65 - 0.17 2.93 36" X 58"
SHEET TITLE
PHC-2 D5WB36058 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 1 10,167 701 503 - 180 140 25.1 12 - 65 - 0.17 2.93 36" X 58"
PHC-3 D5WB36058 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 1 10,167 701 503 - 180 140 25.1 12 - 65 - 0.17 2.93 36" X 58"
MECHANICAL
9/15/2015 6:41:51 PM

PHC-4 D5WB36058 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 1 10,167 701 503 - 180 140 25.1 12 - 65 - 0.17 2.93 36" X 58"

NOTE: PHC-5 D5WB36058 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 1 10,167 701 503 - 180 140 25.1 12 - 65 - 0.17 2.93 36" X 58" EQUIPMENT
PHC-6 D5WB36058 EAST BASEMENT - SF-1 SYSTEM (AHU-2) 1 10,167 701 503 - 180 140 25.1 12 - 65 - 0.17 2.93 36" X 58"
ALL EQUIPMENT SELECTED AT AN ELEVATION OF 4,000 FEET ABOVE SEA LEVEL. SCHEDULES
M-702
1 2 3 4 5 6 SHEET 132 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
DUCT MOUNTED REHEAT COILS
AIR DATA HEATING FLUID DATA COIL DIMENSIONS (IN.)
MANUFACTURER & EAT DB LAT DB AIR PRESSURE LOSS CAPACITY EWT LWT MAX FLUID P.D. COIL CONTROL WEIGHT
SYMBOL MODEL NO. AREA SERVED CFM (°F) (°F) (IN. WC) (MBH) (°F) (°F) GPM (FT. HD) ROWS FINS/FOOT VALVE FINNED LENGTH HEIGHT (LBS.) NOTES
RHC2-101 DP2B12014G0BA133 182 530 55 95 0.144 19.9 180 160 2.00 0.94 2 133 2-WAY 14 12 30
RHC2-102 DP4B18024G0BA127 184 1380 55 95 0.139 51.9 180 160 5.20 1.54 2 127 2-WAY 24 18 50
RHC2-103 DSTB09010G0BA150 191A 280 55 95 0.168 11.6 180 160 1.16 1.03 2 150 2-WAY 10 9 20 2428 Baylor Dr SE Albuquerque, NM 87106
Tel 505-247-9955 Fax 505-247-1826
RHC2-104 DSTB09010G0BA150 191 480 55 95 0.187 20.3 180 160 2.04 3.01 2 150 2-WAY 16 9 20 E-mail info@vhgarchitect.com
E RHC2-105 DP2B12018G0BA129 191B 710 55 95 0.147 26.7 180 160 2.68 1.53 2 129 2-WAY 18 12 40 E Web Site www.vhgarchitect.com
RHC2-106 DP4B18024G0BA127 191C 1380 55 95 0.139 51.9 180 160 5.20 1.54 2 127 2-WAY 24 18 50 CONSULTANTS
RHC2-107A DWLB18028G0BA173 193 1785 55 95 0.200 67.1 180 160 6.73 0.71 2 173 3-WAY 28 18 50 LABORATORY CONSULTANT
RHC2-107B DWLB18028G0BA173 193 1785 55 95 0.200 67.1 180 160 6.73 0.71 2 173 3-WAY 28 18 50 RFD - Research Facilities Design
RHC2-201A DP2B12024G0BA125 278 940 55 95 0.140 35.4 180 160 3.54 2.73 2 125 2-WAY 24 12 40 3965 Fifth Ave. Suite 400
RHC2-202 DP4B18022G0BA130 280 1290 55 95 0.147 48.5 180 160 4.86 1.35 2 130 2-WAY 22 18 50 San Diego, CA 92103
Phone 619-297-0159
RHC2-203 DP2B12018G0BA128 282 700 55 95 0.144 26.36 180 160 2.64 1.50 2 128 2-WAY 18 12 40
RHC2-204 DP2B12016G0BA136 284 660 55 95 0.170 24.8 180 160 2.49 1.31 2 136 2-WAY 16 12 30 CIVIL ENGINEER
RHC2-205 DP2B12022G0BA129 286 900 55 95 0.156 33.9 180 160 3.39 2.42 2 129 2-WAY 22 12 40 Lilley Engineering, Inc.
RHC2-206 DSTB09012G0BA150 288 360 55 95 0.187 14.9 180 160 1.49 1.56 2 150 2-WAY 12 9 20 5160 Calle Bellisima
RHC2-207 DSTB09012G0BA150 290 340 55 95 0.172 14.3 180 160 1.43 1.48 2 150 2-WAY 12 9 20 Las Cruces, NM 88011
Phone 575-521-0006
RHC2-208 DWLB18036G0BA156 292 2205 55 95 0.165 82.9 180 160 8.31 0.95 2 156 3-WAY 36 18 60
RHC2-209 DP2B12022G0BA127 295 870 55 95 0.145 32.7 180 160 3.28 2.30 2 127 2-WAY 22 12 40 STRUCTURAL ENGINEER
RHC2-210A DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80 Stubbs Engineering, Inc.
RHC2-210B DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80 277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
RHC2-210C DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80
Phone 575-993-5228
RHC2-210D DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80
RHC2-210E DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80 MECHANICAL/ELECTRICAL ENGINEER
RHC2-210F DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80 Bridgers & Paxton Consulting Engineers
RHC2-210G DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 2-WAY 54 18 80 4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
RHC2-210H DWLB18054G0BA156 289 3750 55 95 0.202 141.0 180 160 14.14 2.34 2 156 3-WAY 54 18 80 Phone 505-883-4111
RHC3-001 DWLB18026G0BA177 016 1640 55 95 0.202 61.7 180 160 6.18 0.65 2 177 3-WAY 26 18 50
RHC3-002 DP2B12020G0BA130 015 810 55 95 0.156 30.5 180 160 3.05 1.95 2 130 3-WAY 20 12 40
RHC3-003 DSTB09016G0BA150 013 460 55 95 0.176 19.8 180 160 1.98 2.88 2 150 2-WAY 16 9 20
RHC3-004 DSTB09014G0BA150 011 400 55 95 0.137 15.8 180 160 1.58 1.87 2 150 2-WAY 14 9 20
D RHC3-005 DSTB09016G0BA150 009 460 55 95 0.176 19.8 180 160 1.98 2.88 2 150 2-WAY 16 9 20 D
RHC3-006 DP2B12014G0BA131 005 550 55 95 0.150 20.7 180 160 2.07 0.99 2 131 2-WAY 14 12 30
RHC3-007 DP4B18022G0BA129 004, 006, 010 1260 55 95 0.140 47.4 180 160 4.75 1.31 2 129 2-WAY 22 18 50
RHC3-008 DSTB09016G0BA150 007 460 55 95 0.176 19.8 180 160 1.98 2.88 2 150 2-WAY 16 9 20
RHC3-101 DP2B12018G0BA134 148 760 55 95 0.173 28.6 180 160 2.86 1.69 2 134 3-WAY 18 12 40
M ES I
RHC3-102 DSTB09009G0BA150 146 210 55 95 0.129 9.1 180 160 0.91 0.76 2 150 2-WAY 9 9 20 L IR T
MEXI

I
RHC3-103 DSTB09014G0BA150 144 410 55 95 0.180 17.3 180 160 1.74 2.15 2 150 2-WAY 14 9 20 W

CO
NE
RHC3-104 DP2B12014G0BA131 147 550 55 95 0.150 20.7 180 160 2.07 0.99 2 131 2-WAY 14 12 30 20505

E ER
P RO
RHC3-105 DSTB09016G0BA150 145 460 55 95 0.176 19.8 180 160 1.98 2.88 2 150 2-WAY 16 9 20
ES

IN
RHC3-106 DP2B12022G0BA128 141 890 55 95 0.152 33.5 180 160 3.35 2.38 2 128 2-WAY 22 12 40

F
SI G
O N A L EN
RHC3-107 DP2B12014G0BA136 137 520 55 95 0.145 19.6 180 160 1.96 0.92 2 136 2-WAY 14 12 30
RHC3-108 DP2B12022G0BA125 133 850 55 95 0.138 32.0 180 160 3.20 2.22 2 125 2-WAY 22 12 40
RHC3-201 DP4B1802460BA127 248 1380 55 95 0.139 51.9 180 160 5.20 1.54 2 127 3-WAY 24 18 50 PROJECT
RHC3-202 DP4B12024G0BA142 244 1020 55 95 0.190 38.4 180 160 3.84 0.84 2 142 2-WAY 24 12 40
RHC3-203 DP4B18024G0BA127 233 1380 55 95 0.139 51.9 180 160 5.20 1.54 2 127 2-WAY 24 18 50
RHC3-204 DP2B12016G0BA135 225 670 55 95 0.173 25.2 180 160 2.53 1.34 2 135 2-WAY 16 12 30 New Mexico State
NOTES:
PROVIDE TURBULATORS, CONTROL VALVES, AND HIGH EFFICIENT TYPE FINS.
University
REFER TO DRAWINGS FOR ORIENTATION OF COIL CONNECTIONS.

Jett Hall and Jett Annex


SUPPLY AIRFLOW CONTROL VALVES (SEE SPECIFICATION SECTION 230900) Renovations and
OCCUPIED UNOCCUPIED PRESSURE VALVE VALVE WEIGHT Additions
C SYMBOL ACCUTROL MODEL NO. FLOOR SERVED ROOM SERVED CFM CFM DROP (IN. WC) SIZE (IN.) QUANTITY (LBS.) NOTES C
SCV2-101 AVC514X-08 1ST FLOOR EAST 182 530 150 0.20 8 1 20
SCV2-102 AVC514X-14 1ST FLOOR EAST 184 1380 520 0.10 14 1 20
SCV2-103 AVC514X-08 1ST FLOOR EAST 191A 280 90 0.06 8 1 20
SCV2-104 AVC514X-08 1ST FLOOR EAST 191 480 190 0.17 8 1 20
SCV2-105 AVC514X-10 1ST FLOOR EAST 191B 710 270 0.14 10 1 20
SCV2-106 AVC514X-14 1ST FLOOR EAST 191C 1380 520 0.10 14 1 20
SCV2-107A AVC514X14 1ST FLOOR EAST 193 1785 680 0.18 14 1 20
SCV2-107B AVC514X14 1ST FLOOR EAST 193 1785 680 0.18 14 1 20
SCV2-201 AVC514X-12 2ND FLOOR EAST 278 1020 380 0.14 12 1 20
SCV2-202 AVC514X-12 2ND FLOOR EAST 280 1300 860 0.23 12 1 20
SCV2-203 AVC514X-10 2ND FLOOR EAST 282 700 120 0.13 10 1 20 Construction
SCV2-204 AVC514X-10 2ND FLOOR EAST 284 660 120 0.12 10 1 20
SCV2-205 AVC514X-10 2ND FLOOR EAST 286 900 230 0.22 10 1 20 Documents
SCV2-206 AVC514X-08 2ND FLOOR EAST 288 360 90 0.10 8 1 20
SCV2-207 AVC514X-08 2ND FLOOR EAST 290 340 100 0.09 8 1 20
SCV2-208 AVC524X-24 2ND FLOOR EAST 292 2205 860 0.14 12X24 2 50
SCV2-209 AVC514X-10 2ND FLOOR EAST 295 870 360 0.20 10 1 20
SCV2-210A AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
SCV2-210B AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
SCV2-210C AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
SCV2-210D AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
SCV2-210E AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
SCV2-210F AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
SCV2-210G AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100
B SCV2-210H AVC524X-36 2ND FLOOR EAST 289 3750 1215 0.16 12X36 2 100 B
SCV3-001 AVC514X-14 BASEMENT 016 1640 720 0.15 14 1 20
SCV3-002 AVC514X-10 BASEMENT 015 810 430 0.18 10 1 20
SCV3-003 AVC514X-08 BASEMENT 013 460 220 0.15 8 1 20
SCV3-004 AVC514X-08 BASEMENT 011 400 190 0.12 8 1 20
SCV3-005 AVC514X-08 BASEMENT 009 460 220 0.15 8 1 20
SCV3-006 AVC514X-08 BASEMENT 005 550 270 0.22 8 1 20
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

SCV3-007 AVC514X-12 BASEMENT 004, 006 AND 010 1260 1260 0.22 12 1 20
SCV3-008 AVC514X-08 BASEMENT 007 460 220 0.15 8 1 20
SCV3-101 AVC514X-10 1ST FLOOR WEST 148 760 210 0.16 10 1 20
SCV3-102 AVC514X-06 1ST FLOOR WEST 146 210 90 0.21 6 1 10
SCV3-103 AVC514X-08 1ST FLOOR WEST 144 410 170 0.12 8 1 20
SCV3-104 AVC514X-08 1ST FLOOR WEST 147 550 210 0.22 8 1 20
SCV3-105 AVC514X-08 1ST FLOOR WEST 145 460 180 0.15 8 1 20
SCV3-106 AVC514X-10 1ST FLOOR WEST 141 890 350 0.21 10 1 20
SCV3-107 AVC514X-08 1ST FLOOR WEST 137 520 160 0.19 8 1 20
SCV3-108 AVC514X-10 1ST FLOOR WEST 133 850 330 0.20 10 1 20
SCV3-201 AVC514X-14 2ND FLOOR WEST 248 1380 330 0.10 14 1 20
SCV3-202 AVC514X-12 2ND FLOOR WEST 244 1020 300 0.14 12 1 20
SCV3-203 AVC514X-14 2ND FLOOR WEST 233 1380 540 0.10 14 1 20
SCV3-204 AVC514X-10 2ND FLOOR WEST 225 670 450 0.12 10 1 20 Mark Date Description
Date September 11, 2015
Project Number 14400
Drawn By PZP
A
DUCT MATERIAL SCHEDULE A Checked By IM
SYSTEM SERVICE DUCT TERMINATION DUCT ORIGINATION DUCT MATERIAL NOTES
Copyright © VAN H. GILBERT ARCHITECT PC
MINIMUM DUCT THICKNESS CONFORM TO IMC TABLE 510.8,
OFFICE AREAS SUPPLY DIFFUSER 5'-0 FROM DIFFUSER FLEXIBLE DUCT MAXIMUM THICKNESS PER PRESSURE CLASS
MINIMUM DUCT THICKNESS CONFORM TO IMC TABLE 510.8, SHEET TITLE

NOTE: OFFICE AREAS SUPPLY 5-'-0" FROM DIFFUSER MAIN AIR HANDLER GALVANIZED MAXIMUM THICKNESS PER PRESSURE CLASS
MINIMUM DUCT THICKNESS CONFORM TO IMC TABLE 510.8, MECHANICAL
9/15/2015 6:41:51 PM

ALL EQUIPMENT SELECTED AT AN ELEVATION OF 4,000 FEET ABOVE SEA LEVEL. LABORATORIES SUPPLY DIFFUSER MAIN AIR HANDLER GALVANIZED MAXIMUM THICKNESS PER PRESSURE CLASS
MINIMUM DUCT THICKNESS CONFORM TO IMC TABLE 510.8, EQUIPMENT
LABORATORIES EXHAUST EXHAUST GRILLE BRANCH CONNECTION 316L STAINLESS STEEL MAXIMUM THICKNESS PER PRESSURE CLASS

LABORATORIES EXHAUST FUME HOOD (FH) BRANCH CONNECTION


MINIMUM DUCT THICKNESS CONFORM TO IMC TABLE 510.8,
316L STAINLESS STEEL MAXIMUM THICKNESS PER PRESSURE CLASS
SCHEDULES
M-703
1 2 3 4 5 6 SHEET 133 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
VARIABLE FREQUENCY DRIVES OUTDOOR SPLIT SYSTEM SCHEDULE

MANUFACTURER & ELECTRICAL DAIKIN RATED COMPRESSOR DATA ELECTRICAL DATA SOUND
SYMBOL MODEL NO. LOCATION EQUIPMENT SERVED VOLT PHASE HZ MOTOR HP NOTES OUTDOOR CORRESPONDING CAPACITY AMBIENT REFRIG. LIQUID SUCTION POWER WEIGHT
VFD-1 ABB ACH550 M003 SF-1 (AHU-2) 460 3 60 15 NEMA 3R, DISCONNECT SYMBOL MODEL NUMBER LOCATION INDOOR UNIT TYPE (BTUH) DB (F) TYPE TYPE SIZE SIZE VOLTS PH HZ MCA MOP (dBA) (LBS) HEIGHT/ WIDTH/ DEPTH (IN)
VFD-2 ABB ACH550 M003 SF-1 (AHU-2) 460 3 60 15 NEMA 3R, DISCONNECT CU-1 RKN24KEVJU ROOF ACU-1 COOLING ONLY 21,500 95 INVERTER R-410A 1/4" 5/8" 208 1 60 17.5 20 66 160 23-7/16" X 31 5/16" X 11-13/16"
VFD-3 ABB ACH550 M003 SF-1 (AHU-2) 460 3 60 15 NEMA 3R, DISCONNECT CU-2 RKN24KEVJU ROOF ACU-2 COOLING ONLY 21,500 95 INVERTER R-410A 1/4" 5/8" 208 1 60 17.5 20 66 160 23-7/16" X 31 5/16" X 11-13/16"
VFD-4 ABB ACH550 M003 SF-1 (AHU-2) 460 3 60 15 NEMA 3R, DISCONNECT CU-3 RZR30PVJU ROOF ACU-3 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" 2428 Baylor Dr SE Albuquerque, NM 87106
VFD-5 ABB ACH550 M003 SF-1 (AHU-2) 460 3 60 15 NEMA 3R, DISCONNECT CU-4 RZR30PVJU ROOF ACU-4 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" Tel 505-247-9955 Fax 505-247-1826
VFD-6 ABB ACH550 M003 SF-1 (AHU-2) 460 3 60 15 NEMA 3R, DISCONNECT CU-5 RKN18KEVJU ROOF ACU-5 COOLING ONLY 18,000 95 INVERTER R-410A 1/4" 1/2" 208 1 60 13.75 20 61 105 23-7/16" X 31 5/16" X 11-13/16" E-mail info@vhgarchitect.com
E CU-6 RKN24KEVJU ROOF ACU-6 COOLING ONLY 21,500 95 INVERTER R-410A 1/4" 5/8" 208 1 60 17.5 20 66 160 23-7/16" X 31 5/16" X 11-13/16" E Web Site www.vhgarchitect.com
VFD-7 ABB ACH550 M198 HWP-1 460 3 60 7.5 DISCONNECT
CU-7 RZR30PVJU ROOF ACU-7 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" CONSULTANTS
VFD-8 ABB ACH550 M198 HWP-2 460 3 60 7.5 DISCONNECT
VFD-9 ABB ACH550 M198 CHWP-1 460 3 60 15 DISCONNECT CU-8 RZR30PVJU ROOF ACU-8 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" LABORATORY CONSULTANT
CU-9 RKS30LVJU ROOF ACU-9 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 3/8" 208 1 60 19.5 20 68 180 38-15/16" X 37" X 12-5/8" RFD - Research Facilities Design
VFD-10 ABB ACH550 M198 CHWP-2 460 3 60 15 DISCONNECT
3965 Fifth Ave. Suite 400
VFD-11 ABB ACH550 M198 AHU-4 460 3 60 3 CU-10 RXS30LVJU ROOF ACU-10 HEAT PUMP 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 19.5 20 68 180 38-15/16" X 37-1/2" X 12-5/8"
San Diego, CA 92103
VFD-12 ABB ACH550 E194B AHU-5 460 3 60 3 CU-11 RZR30PVJU ROOF ACU-11 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" Phone 619-297-0159
VFD-13 ABB ACH550 M123 AHU-3 460 3 60 15 DISCONNECT CU-12 RZR30PVJU ROOF ACU-12 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8"
VFD-14 ABB ACH550 M123 AHU-3 460 3 60 15 DISCONNECT CU-13 RKN24KEVJU ROOF ACU-13 COOLING ONLY 21,500 95 INVERTER R-410A 1/4" 5/8" 208 1 60 17.5 20 66 160 23-7/16" X 31 5/16" X 11-13/16" CIVIL ENGINEER
CU-14 RZR30PVJU ROOF ACU-14 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" Lilley Engineering, Inc.
VFD-15 ABB ACH550 M003 EF-1 460 3 60 3 NEMA 3R 5160 Calle Bellisima
VFD-16 ABB ACH550 M003 EF-2 460 3 60 3 NEMA 3R CU-15 RZR30PVJU ROOF ACU-15 COOLING ONLY 30,000 95 INVERTER R-410A 3/8" 5/8" 208 1 60 16.5 20 60 180 30-5/16" X 35-7/16" X 12-5/8" Las Cruces, NM 88011
VFD-17 ABB ACH550 M003 LEF-1 460 3 60 30 NEMA 3R, BYPASS FOR UNITS CU-1,2,5,6,9,10,13: Phone 575-521-0006
VFD-18 ABB ACH550 M003 LEF-1 460 3 60 30 NEMA 3R, BYPASS INDOOR UNIT SHALL BE ELECTRICALLY SERVED FROM THE OUTDOOR UNIT PER THE MANUFACTURER'S ELECTRICAL REQUIREMENTS AND DIAGRAMS. PROVIDE REFRIGERANT PIPING AND ALL ACCESSORIES
FOR A COMPLETE AND FUNCTIONAL SYSTEM PER MANUFACTURER'S INSTALLATION MANUAL. DISCONNECT BY DIVISION 26. SEE SPECIFICATION 23 2313. STRUCTURAL ENGINEER
VFD-19 ABB ACH550 M003 LEF-1 460 3 60 30 NEMA 3R, BYPASS Stubbs Engineering, Inc.
FOR UNITS CU-3,4,7,8,11,12,14,15:
VFD-20 ABB ACH550 M300 AHU-1 460 3 60 30 NEMA 3R, DISCONNECT INDOOR UNIT AND OUTDOOR UNIT SHALL BE POWERED SEPARATELY PER THE MANUFACTURER'S ELECTRICAL REQUIREMENTS AND DIAGRAMS. PROVIDE REFRIGERANT PIPING AND ALL ACCESSORIES 277 E. Amador Ave. Suite 200
VFD-21 ABB ACH550 M300 AHU-1 460 3 60 30 NEMA 3R, DISCONNECT FOR A COMPLETE AND FUNCTIONAL SYSTEM PER MANUFACTURER'S INSTALLATION MANUAL. DISCONNECT BY DIVISION 26. SEE SPECIFICATION 23 2313. Las Cruces, NM 88001
VFD-22 ABB ACH550 M300 EF-3 460 3 60 1.5 NEMA 3R Phone 575-993-5228
VFD-23 ABB ACH550 M300 EF-4 460 3 60 1.5 NEMA 3R
MECHANICAL/ELECTRICAL ENGINEER
VFD-24 ABB ACH550 M300 EF-5 460 3 60 1.5 NEMA 3R Bridgers & Paxton Consulting Engineers
VFD-25 ABB ACH550 M300 EF-6 460 3 60 1.5 NEMA 3R
EXHAUST AIRFLOW CONTROL VALVES (SEE SPECIFICATION SECTION 230900)
4600-C Montgomery Blvd. NE
VFD-26 ABB ACH550 M300 LEF-2 460 3 60 15 NEMA 3R, BYPASS ROOM OCCUPIED UNOCCUPIED PRESSURE VALVE WEIGHT Albuquerque, NM 87109
VFD-27 ABB ACH550 M300 LEF-2 460 3 60 15 NEMA 3R, BYPASS SYMBOL ACCUTROL MODEL NO. FLOOR SERVED SERVED SERVICE CFM CFM DROP (IN. WC) SIZE (IN.) (LBS.) NOTES Phone 505-883-4111
ECV2-102 AVC513X-14 1ST FLOOR EAST 184 GENERAL LAB EXAHUST 1550 580 0.13 14 30
ECV2-103 AVC513X-08 1ST FLOOR EAST 191A GENERAL LAB EXAHUST 320 120 0.08 8 20
ECV2-104 AVC513X-08 1ST FLOOR EAST 191 GENERAL LAB EXAHUST 540 240 0.21 8 20
INDOOR SPLIT SYSTEM SCHEDULE
D ECV2-105 AVC513X-10 1ST FLOOR EAST 191B GENERAL LAB EXAHUST 790 320 0.17 10 20 D
COOLING HEATING EAT EAT SOUND MOTOR DATA ECV2-106 AVC513X-14 1ST FLOOR EAST 191C GENERAL LAB EXAHUST 1550 580 0.13 14 30
DAIKIN INDOOR AREA REFRIG AIRFLOW CAPACITY CAPACITY DB WB LEVEL WEIGHT HEIGHT / WIDTH / DEPTH ECV2-107A AVC513X-14 1ST FLOOR EAST 193 GENERAL LAB EXAHUST 2000 760 0.23 14 30
SYMBOL MODEL NUMBER SERVED TYPE TYPE (CFM) (BTUH) (BTUH) (F) (F) (dBA) SEER VOLT PH HZ (LBS) (IN)
ECV2-107B AVC513X-14 1ST FLOOR EAST 193 GENERAL LAB EXAHUST 2000 760 0.23 14 30
ACU-1 FTXN24KEVJU T005 COOLING ONLY R-410A 570 22,000 N/A 80 67 62 18 208 1 60 27 11-7/16" X 41-5/16" X 9-3/8"
ECV2-201A AVC513X-08 2ND FLOOR EAST 278 FUME HOOD EXHAUST 500 200 0.18 8 20
ACU-2 FTXN24KEVJU M017B COOLING ONLY R-410A 570 22,000 N/A 80 67 62 18 208 1 60 27 11-7/16" X 41-5/16" X 9-3/8"
ECV2-201B AVC513X-10 2ND FLOOR EAST 278 FUME HOOD EXHAUST 650 250 0.11 10 20 M ES I
ACU-3 FCQ30PAVJU E001 COOLING ONLY R-410A 670 30,000 N/A 80 67 35 15.8 208 1 60 70 9-11/16" X 33-1/16" X 33-1/16" L IR T
ECV2-202A AVC513X-12 2ND FLOOR EAST 280 FUME HOOD EXHAUST 800 300 0.09 12 30 MEXI

I
ACU-4 FCQ30PAVJU E001 COOLING ONLY R-410A 670 30,000 N/A 80 67 35 15.8 208 1 60 70 9-11/16" X 33-1/16" X 33-1/16" W

CO
NE
ECV2-202B AVC513X-10 2ND FLOOR EAST 280 OTHER EXHAUST 660 660 0.12 10 20
ACU-5 FTXN18KEVJU E167 COOLING ONLY R-410A 570 18,000 N/A 80 67 61 18 208 1 60 27 11-7/16" X 41-5/16" X 9-3/8" 20505
ECV2-203 AVC513X-10 2ND FLOOR EAST 282 GENERAL LAB EXAHUST 780 160 0.16 10 20

E ER
P RO
ACU-6 FTXN24KEVJU T165 COOLING ONLY R-410A 570 22,000 N/A 80 67 62 18 208 1 60 27 11-7/16" X 41-5/16" X 9-3/8"
ECV2-204 AVC513X-10 2ND FLOOR EAST 284 GENERAL LAB EXAHUST 740 160 0.15 10 20 ES

IN
F
ACU-7 FCQ30PAVJU E127 COOLING ONLY R-410A 670 30,000 N/A 80 67 35 15.8 208 1 60 70 9-11/16" X 33-1/16" X 33-1/16" SI G
ECV2-205A AVC513X-06 2ND FLOOR EAST 286 OTHER EXHAUST 200 200 0.19 6 20 O N A L EN
ACU-8 FCQ30PAVJU E127 COOLING ONLY R-410A 670 30,000 N/A 80 67 35 15.8 208 1 60 70 9-11/16" X 33-1/16" X 33-1/16"
ECV2-205B AVC513X-10 2ND FLOOR EAST 286 GENERAL LAB EXAHUST 800 120 0.17 10 20
ACU-9 FTXS30LVJU E194B COOLING ONLY R-410A 705 30,000 N/A 80 67 37 19.3 208 1 60 38 13-3/8" X 41-5/16" X 9-3/4"
ECV2-206 AVC513X-08 2ND FLOOR EAST 288 GENERAL LAB EXAHUST 400 120 0.12 8 20
ACU-10 FTXS30LVJU-HP 137A HEAT PUMP R-410A 705 30,000 34,800 80 67 37 19.3 208 1 60 38 13-3/8" X 41-5/16" X 9-3/4" PROJECT
ECV2-207 AVC513X-08 2ND FLOOR EAST 290 GENERAL LAB EXAHUST 380 120 0.11 8 20
ACU-11 FCQ30PAVJU E267 COOLING ONLY R-410A 670 30,000 N/A 80 67 35 15.8 208 1 60 70 9-11/16" X 33-1/16" X 33-1/16"
ECV2-208A AVC513X-10 2ND FLOOR EAST 295 FUME HOOD EXHAUST 500 200 0.07 10 20
ACU-12 FCQ30PAVJU E267 COOLING ONLY R-410A 670 30,000 N/A 80 67 35 15.8 208 1 60 70 9-11/16" X 33-1/16" X 33-1/16"
ACU-13 FTXN24KEVJU T203 COOLING ONLY R-410A 570 22,000 N/A 80 67 62 18 208 1 60 27 11-7/16" X 41-5/16" X 9-3/8"
ECV2-208B
ECV2-208C
AVC513X-10
AVC513X-10
2ND FLOOR EAST
2ND FLOOR EAST
295
295
FUME HOOD EXHAUST
FUME HOOD EXHAUST
650
650
250
250
0.11
0.11
10
10
20
20
New Mexico State
ACU-14
ACU-15
FCQ30PAVJU
FCQ30PAVJU
E301
E301
COOLING ONLY
COOLING ONLY
R-410A
R-410A
670
670
30,000
30,000
N/A
N/A
80
80
67
67
35
35
15.8
15.8
208
208
1
1
60
60
70
70
9-11/16" X 33-1/16" X 33-1/16"
9-11/16" X 33-1/16" X 33-1/16"
ECV2-208D AVC513X-10 2ND FLOOR EAST 295 FUME HOOD EXHAUST 650 250 0.11 10 20 University
ECV2-209 AVC513X-12 2ND FLOOR EAST 295 GENERAL LAB EXAHUST 1000 420 0.14 12 30
FOR UNITS ACU-1,2,5,6,9,10,13: ECV2-210 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.19 12 30
INDOOR UNIT SHALL BE ELECTRICALLY SERVED FROM THE OUTDOOR UNIT PER THE MANUFACTURER'S ELECTRICAL REQUIREMENTS AND DIAGRAMS. PROVIDE REFRIGERANT PIPING AND ALL ACCESSORIES FOR A COMPLETE AND FUNCTIONAL
SYSTEM PER MANUFACTURER'S INSTALLATION MANUAL. PROVIDE WIRELESS T-STAT AND CONDENSATE PUMP. CONDENSATE PUMP TO BE POWERED BY INDOOR UNIT. DISCONNECT BY DIVISION 26. SEE SPECIFICATION 23 2313. ECV2-211 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30 Jett Hall and Jett Annex
ECV2-212 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
FOR UNITS ACU-3,4,7,8,11,12,14,15:
INDOOR UNIT AND OUTDOOR UNIT SHALL BE POWERED SEPARATELY PER THE MANUFACTURER'S ELECTRICAL REQUIREMENTS AND DIAGRAMS. PROVIDE REFRIGERANT PIPING AND ALL ACCESSORIES FOR A COMPLETE AND FUNCTIONAL ECV2-213 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30 Renovations and
SYSTEM PER MANUFACTURER'S INSTALLATION MANUAL. PROVIDE WIRELESS T-STAT AND CONDENSATE PUMP. CONDENSATE PUMP TO BE POWERED BY INDOOR UNIT. DISCONNECT BY DIVISION 26. SEE SPECIFICATION 23 2313.
ECV2-214
ECV2-215
AVC513X-12
AVC513X-12
2ND FLOOR EAST
2ND FLOOR EAST
289
289
FUME HOOD EXHAUST
FUME HOOD EXHAUST
800
800
300
300
0.09
0.09
12
12
30
30
Additions
C C
ECV2-216 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-217 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
GRILLES AND DIFFUSERS ECV2-218 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-219 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
MANUFACTURER FACE NECK ECV2-220 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
& FRAME DIMENSIONS DIMENSIONS T.P. MAX ECV2-221 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
SYMBOL MODEL NO. TYPE STYLE (INCH) (INCH) CFM RANGE (IN. W.G.) NC NOTES ECV2-222 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
PRICE SCDA, TYPE 3 SUPPLY DIFFUSER LAY-IN CEILING 24X24 6 91-130 0.02-0.06 24 ECV2-223 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-224 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
PRICE SCDA, TYPE 3 SUPPLY DIFFUSER LAY-IN CEILING 24X24 8 131-210 0.02-0.06 28
ECV2-225 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30

SD-1
PRICE SCDA, TYPE 3 SUPPLY DIFFUSER LAY-IN CEILING 24X24 10 211-320 0.03-0.06 30 ECV2-226
ECV2-227
AVC513X-12
AVC513X-12
2ND FLOOR EAST
2ND FLOOR EAST
289
289
FUME HOOD EXHAUST
FUME HOOD EXHAUST
800
800
300
300
0.09
0.09
12
12
30
30
Construction
PRICE SCDA, TYPE 3 SUPPLY DIFFUSER LAY-IN CEILING 24X24 12 321-420 0.03-0.06 30
ECV2-228 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30 Documents
PRICE SCDA, TYPE 3 SUPPLY DIFFUSER LAY-IN CEILING 24X24 14 421-530 0.04-0.06 30 ECV2-229 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-230 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
PRICE SCDA, TYPE 3 SUPPLY DIFFUSER LAY-IN CEILING 24X24 15 531-630 0.03-0.06 30
ECV2-231 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
PRICE SCDA, TYPE 1 SUPPLY DIFFUSER FIXED CEILING 24X24 6 91-130 0.02-0.09 30 ECV2-232 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-233 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
PRICE SCDA, TYPE 1 SUPPLY DIFFUSER FIXED CEILING 24X24 8 131-210 0.02-0.09 30
ECV2-234 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
SD-2 PRICE SCDA, TYPE 1 SUPPLY DIFFUSER FIXED CEILING 24X24 10 211-320 0.02-0.08 30 ECV2-235 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-236 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
PRICE SCDA, TYPE 1 SUPPLY DIFFUSER FIXED CEILING 24X24 12 321-420 0.02-0.08 30
ECV2-237 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
PRICE SCDA, TYPE 1 SUPPLY DIFFUSER FIXED CEILING 24X24 14 421-530 0.03-0.08 30 ECV2-238 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-239 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
PRICE RFD RADIAL FLOW DIFFUSER LAY-IN CEILING 24X24 8 200-500 0.04-0.26 40
B ECV2-240 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30 B
SD-3
PRICE RFD RADIAL FLOW DIFFUSER LAY-IN CEILING 24X48 12 501-1000 0.03-0.19 42 ECV2-241 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-242 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
PRICE RCD SUPPLY DIFFUSER EXPOSED 13.5Ø 6 60-140 0.03-0.09 20
ECV2-243 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
PRICE RCD SUPPLY DIFFUSER EXPOSED 18Ø 8 141-240 0.03-0.09 21 ECV2-244 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 800 300 0.09 12 30
ECV2-245 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
SD-4 PRICE RCD SUPPLY DIFFUSER EXPOSED 22.5Ø 10 241-360 0.04-0.08 21
ECV2-246 AVC513X-12 2ND FLOOR EAST 289 FUME HOOD EXHAUST 1400 300 0.27 12 30
PRICE RCD SUPPLY DIFFUSER EXPOSED 27Ø 12 361-550 0.04-0.09 23 ECV3-001 AVC513X-14 BASEMENT 016 GENERAL LAB EXAHUST 1800 790 0.18 14 30
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

ECV3-002 AVC513X-10 BASEMENT 015 GENERAL LAB EXAHUST 890 480 0.21 10 20
PRICE RCD SUPPLY DIFFUSER EXPOSED 31.5Ø 14 551-740 0.05-0.09 24 ECV3-003 AVC513X-08 BASEMENT 013 GENERAL LAB EXAHUST 510 260 0.19 8 20
SR-1 PRICE 520 SIDEWALL SUPPLY FLAT MARGIN SEE PLAN SEE PLANS SEE PLANS 0.03-0.06 26 ECV3-004 AVC513X-08 BASEMENT 011 GENERAL LAB EXAHUST 450 230 0.15 8 20
ECV3-005 AVC513X-08 BASEMENT 009 GENERAL LAB EXAHUST 510 260 0.19 8 20
SR-2 PRICE 520D SIDEWALL SUPPLY FLAT MARGIN SEE PLAN SEE PLANS SEE PLANS 0.03-0.06 26 PROVIDE OPPOSED BLADE DAMPER ECV3-006 AVC513X-10 BASEMENT 005 GENERAL LAB EXAHUST 610 320 0.10 10 20
LSD-1 PRICE SDA LINEAR SUPPLY SURF MOUNTED 5' LONG 10 SEE PLANS 0.03-0.06 30 PROVIDE LINEAR SLOT PLENUM, (4) 1" SLOTS ECV3-008 AVC513X-08 BASEMENT 007 GENERAL LAB EXAHUST 510 260 0.19 8 20
ECV3-101A AVC513X-10 1ST FLOOR WEST 148 FUME HOOD EXHAUST 650 250 0.11 10 20
LSD-2 PRICE SDS LINEAR SUPPLY DUCT MOUNTED 5' LONG N/A 500 0.04-0.07 30 TYPE 16 FRAME, (3) 1" SLOTS ECV3-101B AVC513X-06 1ST FLOOR WEST 148 GENERAL LAB EXAHUST 190 30 0.17 6 20
LSD-3 PRICE SDS LINEAR SUPPLY DUCT MOUNTED 3' LONG N/A 250 0.03-0.06 25 TYPE 16 FRAME, (3) 1" SLOTS ECV3-102 AVC513X-06 1ST FLOOR WEST 146 GENERAL LAB EXAHUST 240 120 0.27 6 20
ECV3-103 AVC513X-08 1ST FLOOR WEST 144 GENERAL LAB EXAHUST 470 210 0.16 8 20
LSD-4 PRICE SDS LINEAR SUPPLY DUCT MOUNTED 4' LONG N/A 425 0.05-0.09 35 TYPE 16 FRAME, (3) 1" SLOTS ECV3-104 AVC513X-10 1ST FLOOR WEST 147 GENERAL LAB EXAHUST 610 250 0.10 10 20
LSD-5 PRICE SDS LINEAR SUPPLY DUCT MOUNTED 3' LONG N/A 225 0.03-0.06 26 TYPE 16 FRAME, (3) 1" SLOTS ECV3-105 AVC513X-08 1ST FLOOR WEST 145 GENERAL LAB EXAHUST 510 220 0.19 8 20
ECV3-106 AVC513X-10 1ST FLOOR WEST 141 GENERAL LAB EXAHUST 990 400 0.26 10 20 Mark Date Description
LSD-6 PRICE SDA LINEAR SUPPLY SURF MOUNTED 3' LONG 8 350 0.03-0.06 26 PROVIDE LINEAR SLOT PLENUM, (4) 1" SLOTS ECV3-108 AVC513X-10 1ST FLOOR WEST 133 GENERAL LAB EXAHUST 940 380 0.24 10 20
Date September 11, 2015
RG-1 PRICE 80 RETURN GRILLE LAY-IN CEILING 24x24, 24x12 SEE PLANS - N/A N/A ECV3-201A AVC513X-10 2ND FLOOR WEST 248 FUME HOOD EXHAUST 500 200 0.07 10 20
Project Number 14400
ECV3-201B AVC513X-12 2ND FLOOR WEST 248 GENERAL LAB EXAHUST 1020 180 0.14 12 30
RG-2 PRICE 80 RETURN GRILLE FIXED CEILING 24x24, 24x12 SEE PLANS - N/A N/A Drawn By PZP
12x12 ECV3-202A AVC513X-10 2ND FLOOR WEST 244 FUME HOOD EXHAUST 500 200 0.07 10 20
A A Checked By IM
RG-3 PRICE 530 RETURN GRILLE SIDEWALL SEE PLAN SEE PLANS - N/A N/A ECV3-202B AVC513X-10 2ND FLOOR WEST 244 GENERAL LAB EXAHUST 630 150 0.11 10 20
Copyright © VAN H. GILBERT ARCHITECT PC
ECV3-203 AVC513X-14 2ND FLOOR WEST 233 GENERAL LAB EXAHUST 1520 600 0.13 14 30
ER-1 PRICE 80D EXHAUST GRILLE LAY-IN CEILING 24x24, 24x12 SEE PLANS SEE PLANS 0.01-0.08 25 PROVIDE OPPOSED BLADE DAMPER
12x12 ECV3-204A AVC513X-08 2ND FLOOR WEST 225 GENERAL LAB EXAHUST 500 100 0.18 8 20
SHEET TITLE
ER-2 PRICE 80D EXHAUST GRILLE FIXED CEILING 24x24, 24x12 SEE PLANS SEE PLANS 0.01-0.08 25 PROVIDE OPPOSED BLADE DAMPER ECV3-204B AVC513X-10 2ND FLOOR WEST 225 FUME HOOD EXHAUST 650 250 0.11 10 20
12x12
MECHANICAL
9/15/2015 6:41:52 PM

ER-3 PRICE 80D EXHAUST GRILLE SIDEWALL SEE PLAN SEE PLANS - N/A N/A PROVIDE OPPOSED BLADE DAMPER

NOTE: EQUIPMENT
ALL EQUIPMENT SELECTED AT AN ELEVATION OF 4,000 FEET ABOVE SEA LEVEL. SCHEDULES
M-704
1 2 3 4 5 6 SHEET 134 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

2428 Baylor Dr SE Albuquerque, NM 87106


Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
CONSULTANTS

LABORATORY CONSULTANT
RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
San Diego, CA 92103
Phone 619-297-0159

CIVIL ENGINEER
Lilley Engineering, Inc.
5160 Calle Bellisima
Las Cruces, NM 88011
NOTE: Phone 575-521-0006

3D PIPING ISOMETRIC VIEWS ARE FOR STRUCTURAL ENGINEER


Stubbs Engineering, Inc.
REFERENCE ONLY. REFER TO PIPING PLANS, 277 E. Amador Ave. Suite 200
Las Cruces, NM 88001
ENLARGED PLANS , DETAILS AND DIAGRAMS Phone 575-993-5228

FOR PIPE ROUTING, SIZES, VALVES, ETC. MECHANICAL/ELECTRICAL ENGINEER


Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
Phone 505-883-4111

D D

D4 BASEMENT
Scale:
AIR HANDLING SYSTEM (AHU-2)

M ES I
L IR T
MEXI

I
W

CO
NE
20505

E ER
P RO
ES

IN
F
SI G
O N A L EN

PROJECT

New Mexico State


University

Jett Hall and Jett Annex


Renovations and
Additions
C C

Construction
Documents

B B
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

A1 MECHANICAL
Scale:
PIPNIG OVERALL 3D PLAN

Mark Date Description


Date September 11, 2015
Project Number 14400
Drawn By PZP
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL PIPING
9/15/2015 6:42:03 PM

ISOMETRICS

M-801
1 2 3 4 5 6 SHEET 135 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

2428 Baylor Dr SE Albuquerque, NM 87106


Tel 505-247-9955 Fax 505-247-1826
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
INSTRUMENTATION SOCIETY OF AMERICA TABLE
CONSULTANTS

FIRST LETTER SUCCEEDING LETTERS (3) GENERAL INSTRUMENT OR FUNCTION SYMBOLS HOA HAND-OFF-AUTO SWITCH
LABORATORY CONSULTANT
MEASURING OR MODIFIER READOUT OR OUTPUT MODIFIER AUXILIARY AUXILIARY
RFD - Research Facilities Design
FIELD PANEL
INITIATING PASSIVE FUNCTION FUNCTION MOUNTED MOUNTED LOCATION LOCATION NORMALLY CLOSED OVERLOAD CONTACTS 3965 Fifth Ave. Suite 400
ACCESSIBLE INACCESSIBLE OL
VARIABLE
San Diego, CA 92103
SWITCH
ALARM DISCRETE INSTRUMENTS
Phone 619-297-0159
A ANALYSIS FUSE
B BURNER FLAME USER CHOICE USER CHOICE USER CHOICE CONTACT NORMALLY CLOSED CIVIL ENGINEER
C CONDUCTIVITY CONTROL (13)
CONTACT NORMALLY OPEN Lilley Engineering, Inc.
D DENSITY DIFFERENTIAL 5160 Calle Bellisima
C COIL IN MOTOR STARTER
E VOLTAGE SENSOR Las Cruces, NM 88011
SHARED DISPLAY, SHARED CONTROL
PRIMARY ELEMENT R PILOT LIGHT (COLOR INDICATION) Phone 575-521-0006
F FLOW RATE RATIO FRACTION EP COIL IN MOTOR STARTER
G GAUGE GLASS, STRUCTURAL ENGINEER
TRANSFORMER
VIEWING DEVICE Stubbs Engineering, Inc.
H HAND HIGH 277 E. Amador Ave. Suite 200
I CURRENT INDICATE Las Cruces, NM 88001
J POWER SCAN ABBREVIATIONS Phone 575-993-5228
IA INSTRUMENTATION AIR
K TIME TIME RATE OF CONTROL STATION PROGRAMMABLE LOGIC CONTROL DDC DIRECT DIGITAL CONTROL
C COMMON VALVE PORT
MECHANICAL/ELECTRICAL ENGINEER
CHANGE OR DIRECT DIGITAL CONTROL
F.O FAIL OPEN Bridgers & Paxton Consulting Engineers
L LEVEL LIGHT LOW F.C FAIL CLOSED 4600-C Montgomery Blvd. NE
MOMENTARY MIDDLE SR SPRING RANGE
M MOTION
TR THROTTLING RANGE Albuquerque, NM 87109
INTERMEDIATE PH PREHEAT Phone 505-883-4111
N HUMIDITY USER DEFINED USER DEFINED USER DEFINED COMPUTER FUNCTION HR HEAT RECOVERY
CPA CONTROL POINT ADJUSTMENT
O USER CHOICE ORIFICE RESTRICTION SPDT SINGLE POLE DOUBLE THROW
P PRESSURE, VACUUM POINT (TEST) DPDT DOUBLE THROW DOUBLE POLE
DA DIRECT ACTING
CONNECTION RA REVERSE ACTING
D Q QUANTITY INTEGRATE, D
PROCESS CODES
TOTALIZE
INDICATING LIGHTS, ALARMS OR HORNS TW COOLING TOWER OR CONDENSER WATER
R RADIATION RECORD CHW CHILLED WATER
S SPEED, FREQUENCY SAFETY SWITCH SCHW SECONDARY CHILLED WATER
HW HOT WATER
T TEMPERATURE TRANSMIT SHW SECONDARY HOT WATER
STM STEAM
U MULTI-VARIABLE MULTI-FUNCTION MULTI-FUNCTION MULTI-FUNCTION
M ES I
V VIBRATION, MECHANICAL VALVE, DAMPER L IR T
MEXI

I
ANALYSIS LOUVER W
DUAL (MULTI)

CO
NE
W WEIGHT, FORCE WELL
FUNCTION INSTRUMENT LINE LEGEND 20505
X UNCLASSIFIED X-AXIS UNCLASSIFIED UNCLASSIFIED UNCLASSIFIED

E ER
P RO
Y EVENT, STATE OR Y-AXIS RELAY, COMPUTE ELECTRICAL SIGNAL
ES

IN
F
PRESENCE CONVERT SI G
PNEUMATIC SIGNAL O N A L EN
Z POSITION Z-AXIS DRIVER, ACTUATOR
UNDEFINED INTERLOCK LOGIC FLOW ARROW
DIMENSION UNCLASSIFIED I INTERNAL SYSTEM LINK
XXX INDICATES
FINAL CONTROL ELEMENT AIR TYPE PROJECT

INSTRUMENTATION TYPE ABBREVIATION LIST


ZZZ
CODE DESCRIPTION CODE DESCRIPTION CODE DESCRIPTION XXX
INSTRUMENT NAMING CONVENTION
New Mexico State
AA ANALYTICAL ALARM LA LEVEL ALARM VA VIBRATION ALARM AAA-NNN
AE ANALYTICAL ELEMENT LC LEVEL CONTROLLER (STAND ALONE) VS VIBRATION SWITCH
XXX - FUNCTION ID
ZZZ - USER CHOICE
University
AET ANALYTICAL ELEMENT TRANSMITTER LCV LEVEL CONTROL VALVE AAA - UNIT ASSOCIATION OR
PROCESS CODE
AI ANALYTICAL INDICATOR LE LEVEL ELEMENT XV SOLENOID VALVE
AC ANALYTICAL CONTROLLER LIC LEVEL INDICATING CONTROLLER
NNN - DEVICE NUMBER
Jett Hall and Jett Annex
AIC ANALYTICAL INDICATING CONTROLLER LIT LEVEL INDICATING TRANSMITTER YA EQUIPMENT ALARM
CONTROL VALVE BODY/ DAMPER SYMBOLS PRESSURE
AT ANALYTICAL TRANSMITTER LS LEVEL SWITCH YI EQUIPMENT STATUS Renovations and
AIT ANALYTICAL INDICATING CONTROLLER LT LEVEL TRANSMITTER YCD SMOKE DAMPER
Additions

~
ACV ANALYTICAL CONTROL VALVE LY LEVEL SIGNAL CONVERTER YS SMOKE DETECTOR GENERAL SYMBOL PARALLEL BLADE
PD
AY ANALYTICAL SIGNAL CONVERTER DIRECT MOUNTED DIFFERENTIAL PRESSURE
C C

~
MV MANUAL HAND VALVE ZC POSITION CONTROL ANGLE ELEMENT/SENSOR ELEMENT/SENSOR
~
EI VOLTAGE INDICATOR ZI POSITION INDICATOR
EA VOLTAGE ALARM NT HUMIDITY TRANSMITTER ZS POSITION SWITCH
BUTTERFLY

~
ES VOLTAGE SWITCH (CONTROL RELAY)
ESL VOLTAGE SWITCH LOW (24 VAC OR LESS) PA PRESSURE ALARM

~
ROTARY VALVE

~
ET VOLTAGE TRANSMITTER PCV PRESSURE CONTROL VALVE VA VIBRATION ALARM

~
EY VOLTAGE SIGNAL CONVERTER PDI PRESSURE DIFFERENTIAL INDICATOR VS VIBRATION SWITCH
OPPOSED BLADE
PDS PRESSURE DIFFERENTIAL SWITCH

~
FA FLOW ALARM PDT PRESSURE DIFFERENTIAL TRANSMITTER ~
THREE - WAY
LEVEL
FCV FLOW CONTROL VALVE PI PRESSURE INDICATOR
PIS PRESSURE INDICATING SWITCH

~
FE FLOW ELEMENT FOUR - WAY
L L
FET
FI
FLOW ELEMENT\TRANSMITTER
FLOW INDICATOR
PIT
PS
PRESSURE INDICATING TRANSMITTER
PRESSURE SWITCH
~
LEVEL TRANSMITTER Construction
TANK MOUNTED
FIT FLOW INDICATING TRANSMITTER PT PRESSURE TRANSMITTER
GLOBE Documents

~
FS FLOW SWITCH PY PRESSURE SIGNAL CONVERTER FLOAT TYPE PADDLE TYPE
L
FT FLOW TRANSMITTER
FY FLOW SIGNAL CONVERTER SC SPEED CONTROL
SCM SPEED CONTROL MANUAL TEMPERATURE
HK MANUAL VARIABLE CONTROL
HS HAND SWITCH TA TEMPERATURE ALARM
HSI HAND SWITCH INDICATOR TC TEMPERATURE CONTROLLER
L
TCV TEMPERATURE CONTROL VALVE
II CURRENT INDICATOR TE TEMPERATURE ELEMENT SONIC OR
TE DUCT MOUNTED TE AVERAGING RADIOACTIVE

~ ~~
IA CURRENT ALARM TET TEMPERATURE ELEMENT TRANSMITTER ELEMENT/SENSOR
ELEMENT/SENSOR
IS CURRENT SWITCH TI TEMPERATURE INDICATOR
IT CURRENT TRANSMITTER TIT TEMPERATURE INDICATING TRANSMITTER
IY CURRENT SIGNAL CONVERTER TIC TEMPERATURE INDICATING CONTROLLER
B TS TEMPERATURE SWITCH B
TE TE
JIT POWER INDICATING TRANSMITTER TSL FREEZE STAT WELL MOUNTED SURFACE MOUNTED
JY POWER SIGNAL CONVERTER TT TEMPERATURE TRANSMITTER ELEMENT/SENSOR ELEMENT/SENSOR FLOW
KC TIME CLOCK

~
~

~
CURRENT FE FE TURBINE OR FE VORTEX
ORIFICE PLATE PROPELLER SENSOR
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

TYPE

FMS SYSTEM OPERATING CONSTRAINTS


~

~
~

~
M
THE FMS CONTROL SYSTEM SHALL OPERATE WITHIN THE FOLLOWING SYSTEM CONSTRAINTS FOR CONTROL:
CURRENT SENSOR/TRANSMITTER TARGET MAGNETIC SONIC FLOWMETER
FE
TYPE TYPE "DOPPLER" OR
SUPPLY AIR DRYBULB TEMPERATURE +/- 0.5°F OF SETPOINT WITH HUNTING OF < 5% OF THE C ONTROL SIGNAL FT FT
SENSOR TRANSMITTER TRANSIT TIME
MIXED AIR DRYBULB TEMPERATURE +/- 0.5°F OF SETPOINT WITH HUNTING OF < 5% OF THE C ONTROL SIGNAL
WATER TEMPERATURE +/- 0.5°F OF SETPOINT WITH HUNTING OF < 5% OF THE C ONTROL SIGNAL
DUCT STATIC PRESSURE +/- 0.1" W.C. OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL
SUPPLY/ RETURN AIR VOLUME +/- 2.5% OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL
OUTSIDE AIR/ RELIEF AIR VOLUME +/- 2.5% OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL
BUILDING PRESSURE +/- 0.01" W.C. OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL
ROOM TEMPERATURE +/- 1.0°F OF SETPOINT WITH HUNTING OF < 5% OF THE C ONTROL SIGNAL
ROOM AIR VOLUME +/- 2.5% OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL
HUMIDITY LEVEL +/- 2.5% R.H. OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL
WATER TEMPERATURE +/- 1.0°F OF SETPOINT WITH HUNTING OF < 5% OF THE C ONTROL SIGNAL
WATER DIFFERENTIAL PRESSURE +/- 1.0 PSI OF SETPOINT WITH HUNTING OF < 5% OF THE CONTROL SIGNAL Mark Date Description
Date September 11, 2015
Project Number 14400
Drawn By SDB
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL
9/15/2015 6:42:23 PM

INSTRUMENTATION
LEGEND
MI-001
1 2 3 4 5 6 SHEET 136 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

E.A
GENERAL NOTES
CONTROL

~
POWER

~ ~
~

~ ~
1. LABORATORY CONTROLLERS SHALL BE FURNISHED BY AIR VALVE
MANUFACTURER AS PART OF A COMPLETE ENGINEERED SYSTEM. 2428 Baylor Dr SE Albuquerque, NM 87106
FO 2. REFER TO MECHANICAL FLOOR PLAN SHEETS FOR EXACT REQUIREMENTS Tel 505-247-9955 Fax 505-247-1826
FOR EACH LAB.
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
CONSULTANTS
SASH PROX. LABORATORY FMS LABORATORY CONSULTANT

~
TT CONTROLLER
SENSOR SENSOR NETWORK
SCV-02 H RFD - Research Facilities Design
3965 Fifth Ave. Suite 400
S.A San Diego, CA 92103
GENERAL
EXHAUST C Phone 619-297-0159

HWR CIVIL ENGINEER


Lilley Engineering, Inc.
TCV
5160 Calle Bellisima
SCV-01
FUMEHOOD NO Las Cruces, NM 88011
MONITOR HWS Phone 575-521-0006
CONTROL STRUCTURAL ENGINEER

~
POWER
Stubbs Engineering, Inc.
VAV FUMEHOOD ROOM TIT 277 E. Amador Ave. Suite 200
SENSOR
SCV-01 Las Cruces, NM 88001
FROM LAST UNIT ON LAN
Phone 575-993-5228

~
TO NEXT UNIT ON LAN

~
FROM LAST UNIT ON LAN

~
~
TO NEXT UNIT ON LAN
CONTROL POWER

~
- PDIT + MECHANICAL/ELECTRICAL ENGINEER
CONTROL POWER

~
SCV-01
Bridgers & Paxton Consulting Engineers
FMS 4600-C Montgomery Blvd. NE

~
NETWORK FMS
ROOM CONTROLLER FMS Albuquerque, NM 87109
PRESSURE TT CONTROLLER
MONITOR TT Phone 505-883-4111
FCU-01
FCU-01
C
H C
TYPICAL FUMEHOOD LABORATORY CONTROL DIAGRAM RETURN
RETURN
AIR
TIT AIR
C
D FCU-01
C C TIT D
FCU-01
LOCATE SENSOR
WHERE SHOWN LOCATE SENSOR
ES
E.A

LINE ON THE PLANS ES WHERE SHOWN

~
FCU-01 LINE ON THE PLANS

~
FCU-01
CHWS

~
HWS CHWS M ES I

~
IS CONTROL TCV IS L IR T

~
CONTROL CONTROL MEXI

I
FCU-01 POWER TCV TCV

I
~

~
FCU-01 FCU-01 POWER POWER W

CO
NE
CONTROL NO FCU-01 FCU-01

~
CHWR NO NC 20505

~
POWER
HWR CHWR

E ER
P RO
~
~

ES

IN
F
SI G
MAX O N A L EN
FAN ON MAX
FAN ON FAN ON

PROJECT
LABORATORY FMS

~
TT

CFM, RELATIVE AIRFLOW


CONTROLLER NETWORK
H

CFM, RELATIVE AIRFLOW


SCV-02

HO
New Mexico State

OW
TW
S.A

FL
OW

AT
GENERAL FL

R
C
University

TE
ER
EXHAUST ER
AT

WA
FL
W

OW

W
W
HWR CH

CH
TLV
SCV-01
Jett Hall and Jett Annex
NO 0
HWS 0 0 50 100
0
0 0 50 100
Renovations and
CONTROL SIGNAL, PERCENT
CONTROL SIGNAL, PERCENT
Additions
C FAN COIL UNIT SHALL PROVIDE THE FLOW CHARACTERISTICS SHOWN ON THE GRAPH. FAN COIL UNIT SHALL PROVIDE THE FLOW CHARACTERISTICS SHOWN ON THE GRAPH. C
ROOM TLV EACH FAN COIL UNIT SHALL BE EQUIPPED WITH ITS OWN STAND ALONE CONTROLLER EACH FAN COIL UNIT SHALL BE EQUIPPED WITH ITS OWN STAND ALONE CONTROLLER
SENSOR SCV-01 WHICH SHALL HAVE THE CAPABILITIES DESCRIBED IN THE SPECIFICATION. THE WHICH SHALL HAVE THE CAPABILITIES DESCRIBED IN THE SPECIFICATION. THE
WIRING SHOWN IS PROVIDED AS A GENERAL DESCRIPTION AND IS NOT AS A WIRING SHOWN IS PROVIDED AS A GENERAL DESCRIPTION AND IS NOT AS A
DETAILED WIRING DIAGRAM WHICH VARIES WITH THE MANUFACTURER. DETAILED WIRING DIAGRAM WHICH VARIES WITH THE MANUFACTURER.
- PDIT +
SCV-01
FMS TYPICAL CHILLED WATER FAN COIL UNIT CONTROL DIAGRAM TYPICAL CHW & HW FAN COIL UNIT CONTROL DIAGRAM
~

NETWORK
ROOM
PRESSURE
MONITOR

TYPICAL NON-FUMEHOOD LABORATORY CONTROL DIAGRAM


Construction
PROVIDE BY NMSU AND INSTALLED PROVIDED BY NMSU AND
BY DIVISION 25 INSTALLED BY DIVISION 26 Documents

B B

PROVIDE BY DIVISION 27 AND


INSTALLED BY DIVISION 27
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

PROVIDE BY DIVISION 25 AND INSTALLED


BY DIVISION 25

Mark Date Description


Date September 11, 2015
Project Number 14400
Drawn By SDB
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL DIAGRAMS
9/15/2015 6:42:26 PM

(CONTROLS)
PROVIDE BY NMSU AND INSTALLED BY PROVIDED BY NMSU AND INSTALLED
DIVISION 25 BY DIVISION 25

MI-601
1 2 3 4 5 6 SHEET 137 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

KEYED NOTES
1. VFD'S SHALL BE CONNECTED TO THE FMS NETWORK THROUGH A DIRECT
NETWORK CONNECTION AS WELL AS THROUGH THE HARDWIRED POINTS 2428 Baylor Dr SE Albuquerque, NM 87106
TT
TT FT INDICATED. IT IS THE RESPONSIBILITY OF THE FMS CONTRACTOR TO Tel 505-247-9955 Fax 505-247-1826
CHWS-01 CHWR-01 COORDINATE AND ADAPT THE FMS NETWORK TO THE COMMUNICATIONS E-mail info@vhgarchitect.com
CHWS-03
PROTOCOLS AVAILABLE FROM THE VFD MANUFACTURER. THE FOLLOWING
E POINTS SHALL BE INTEGRATED INTO THE FMS: E Web Site www.vhgarchitect.com
CHWR CHWR

~
~
CONSULTANTS
A. SPEED FEEDBACK
4 FCV B. FREQUENCY OUTPUT LABORATORY CONSULTANT
CHWS-01 C. CURRENT RFD - Research Facilities Design
D. TORQUE 3965 Fifth Ave. Suite 400
E. POWER
F. DC BUS VOLTAGE
San Diego, CA 92103
CHWS CHWS Phone 619-297-0159

~
G. OUTPUT VOLTAGE
FACTORY H. KWH COUNTER
TT
CONTROLLER TT I. DRIVE TEMPERATURE CIVIL ENGINEER
CHWS-02 CHWP-2 J. ALARMS
CHWS-01 Lilley Engineering, Inc.
K. STATUSES
5160 Calle Bellisima
R CONTROL Las Cruces, NM 88011
BTU METER 2. BTU METER, FLOW METER, AND TEMPERATURE SENSORS FURNISHED BY OWNER.

~
CAT5/6

~
POWER INSTALL INSTRUMENTATION AND CONNECT INSTRUMENTATION TO BTU METER. Phone 575-521-0006
RETURN ETHERNET
PROVIDE POWER TO BTU METER.
AIR 1 FMS

~
2 VFD
C LOCATE SENSOR STRUCTURAL ENGINEER
WHERE SHOWN 3. WATER METER AND SIGNAL CONVERTER FURNISHED BY OWNER. INSTALL
ON THE PLANS INSTRUMENTATION AND PROVIDE RS-485 MODBUS RTU (BELDEN 88723) CABLE Stubbs Engineering, Inc.
BETWEEN METER AND SIGNAL CONVERTER. PROVIDE POWER TO METER AND 277 E. Amador Ave. Suite 200
TT TT SIGNAL CONVERTER. Las Cruces, NM 88001
ACU-01 ACU-01 CHWP-1 Phone 575-993-5228
4. PROVIDE FULL PORT BUTTERFLY VALVE

5. GAS METER AND SIGNAL CONVERTER FURNISHED BY OWNER. INSTALL


MECHANICAL/ELECTRICAL ENGINEER
INSTRUMENTATION AND PROVIDE RS-485 MODBUS RTU (BELDEN 88723) CABLE Bridgers & Paxton Consulting Engineers
1 FMS
BETWEEN METER AND SIGNAL CONVERTER. PROVIDE POWER TO METER AND 4600-C Montgomery Blvd. NE

~
VFD SIGNAL CONVERTER. Albuquerque, NM 87109

ROOM TEMP.
Phone 505-883-4111

(AI)

TI
D D
ACU-01

CHWR PRESSURE
CHWS PRESSURE
SPEED SIGNAL

SPEED SIGNAL

OPEN/CLOSE
START/STOP

START/STOP
TYPICAL SPLIT SYSTEM CONTROL DIAGRAM
M ES I

STATUS

STATUS
L IR T
MEXI

I
(DO) (DI) (AO) (DO) (DI) (AO) (AI) (DO) (AI) W

CO
NE
HS YI SC HS YI SC PI FCV PI 20505

E ER
P RO
CHWP1-01 CHWP1-01 CHWP1-01 CHWP2-01 CHWP2-01 CHWP2-01 CHWS-01 CHWS-01 CHWR-01
ES

IN
F
SI G
O N A L EN
CHILLED WATER SYSTEM CONTROL DIAGRAM
PROJECT

New Mexico State


MS
University
~

LINE

Jett Hall and Jett Annex

~
FROM PREVIOUS UNIT ON LAN

~
TO NEXT UNIT ON LAN

~
TO NEXT UNIT ON LAN

~
FCV ES IS FROM PREVIOUS UNIT ON LAN
GEF-01 GEF-01 GEF-01 CONTROL PANEL
CONTROL POWER
Renovations and

~
~
CONTROL POWER
FC

FCV
FMS
CONTROLLER FCV
FMS
CONTROLLER Additions
E.A

TT TT

ALARM
C TU-01 TU-01 C
TU-02 TU-02 LOCATE SENSOR
START/STOP

LOCATE SENSORS
H WHERE SHOWN H WHERE SHOWN (DI)
ON THE PLANS ON THE PLANS
STATUS

YA
TIT CO2 TIT CO2 SE-01
(DO) (DI)
C TU-01 TU-01 C TU-01 TU-01
HS II
GEF-01 GEF-01 HWR HWS

TLV TLV TYPICAL SEWAGE EJECTOR CONTROL DIAGRAM


TU-01 TU-01
TYPICAL GENERAL EXHAUST FAN CONTROL DIAGRAM NO NC
HWS HWR
(TYPICAL FOR GEF-1 AND GEF-2) NO
Construction
MAX
CONTROL PANEL Documents
DW M DW
~

CFM, RELATIVE AIRFLOW

ALARM
FT

LO
PT

HO
3

RF
DWS-01 DWS-01

TW
(DI)

AI
AT
YA

ER
FY CONTROL
CAT5/6
~
~

CO
DWS-01 POWER SP-01
ETHERNET
DWS PRESSURE

IL
3

0 TYPICAL SUMP PUMP CONTROL DIAGRAM


(AI) 0 25 50 75 100
B CONTROL SIGNAL, PERCENT B
PI
VARIABLE VOLUME CONTROL
DWS-01
THE TERMINAL UNIT SHALL PROVIDE THE FLOW CHARISTICS SHOWN ON THE GRAPH.
EACH TERMINAL UNIT SHALL BE EQUIPPED WITH ITS OWN STAND ALONE CONTROLLER
WHICH SHALL HAVE THE CAPABILITIES DESCRIBED IN THE SPECIFICATION. THE
DOMESTIC WATER METER CONTROL DIAGRAM WIRING SHOWN IS PROVIDED AS A GENERAL DESCRIPTION AND IS NOT AS A
DETAILED WIRING DIAGRAM WHICH VARIES WITH THE MANUFACTURER.

TYPICAL VAV TERMINAL UNIT WITH HW REHEAT CONTROL DIAGRAM


D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

DHWS DHWS
~

LINE ES
~

DHWP-01
COMPRESSE AIR WATER SOFTENER
GLYCOL FILL SYSTEM RO SYSTEM DI SYSTEM SYSTEM VACUUM SYSTEM SYSTEM GAS M GAS

~
IS
DHWP-01 CONTROL PANEL CONTROL PANEL CONTROL PANEL CONTROL PANEL CONTROL PANEL CONTROL PANEL FT
5
DWS-01
START/STOP

FY CONTROL
CAT6

~
~
STATUS

ALARM

ALARM

ALARM

ALARM

ALARM

ALARM
DWS-01 POWER
ETHERNET
Mark Date Description
(DI) (DO) (DI) (DI) (DI) (DI) (DI) (DI)
5 Date September 11, 2015
II HS YA YA YA YA YA YA
Project Number 14400
DHWP-01 DHWP-01 GFP-01 RO-01 DI-01 CA-01 VA-01 WS-01
Drawn By SDB
A (TYP OF 2) A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC
DOMESTIC HW PUMP CONTROL DIAGRAM LABORATORY UTILITIES MONITORING CONTROL DIAGRAM
SHEET TITLE

MECHANICAL DIAGRAMS
9/15/2015 6:42:26 PM

(CONTROLS)

MI-602
1 2 3 4 5 6 SHEET 138 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

KEYED NOTES 2428 Baylor Dr SE Albuquerque, NM 87106


Tel 505-247-9955 Fax 505-247-1826
1. VFD'S SHALL BE CONNECTED TO THE FMS NETWORK THROUGH A DIRECT E-mail info@vhgarchitect.com
NETWORK CONNECTION AS WELL AS THROUGH THE HARDWIRED POINTS Web Site www.vhgarchitect.com
E INDICATED. IT IS THE RESPONSIBILITY OF THE FMS CONTRACTOR TO
E
COORDINATE AND ADAPT THE FMS NETWORK TO THE COMMUNICATIONS CONSULTANTS
PROTOCOLS AVAILABLE FROM THE VFD MANUFACTURER. THE FOLLOWING
POINTS SHALL BE INTEGRATED INTO THE FMS: LABORATORY CONSULTANT
RFD - Research Facilities Design
R.A A. SPEED FEEDBACK 3965 Fifth Ave. Suite 400
B. FREQUENCY OUTPUT San Diego, CA 92103
TT C. CURRENT
D. TORQUE
Phone 619-297-0159
AHU4-04
E. POWER
F. DC BUS VOLTAGE CIVIL ENGINEER
G. OUTPUT VOLTAGE Lilley Engineering, Inc.
H. KWH COUNTER
5160 Calle Bellisima
I. DRIVE TEMPERATURE
FCV J. ALARMS Las Cruces, NM 88011
AHU4-02 K. STATUSES Phone 575-521-0006
NO
CONTROL I 2. CONDENSATE METER AND SIGNAL CONVERTER FURNISHED BY OWNER. INSTALL STRUCTURAL ENGINEER

~
POWER INSTRUMENTATION AND PROVIDE RS-485 MODBUS RTU (BELDEN 88723) CABLE
PDT BETWEEN METER AND SIGNAL CONVERTER. PROVIDE POWER TO METER AND Stubbs Engineering, Inc.
FCV
AHU4-01 SIGNAL CONVERTER. 277 E. Amador Ave. Suite 200
AHU4-01 TSL Las Cruces, NM 88001
3. STRAP-ON TEMPERATURE SENSOR NEAR CONDENSATE PUMP INLET. Phone 575-993-5228
AHU4-01
NC H C
~ ~ ~ S.A
O.A MECHANICAL/ELECTRICAL ENGINEER
~ ~ ~ Bridgers & Paxton Consulting Engineers
C C TT YS
FAS

~
AHU4-03 AHU4-01 4600-C Montgomery Blvd. NE
TT TCV TT TCV
Albuquerque, NM 87109
AHU4-01 AHU4-01 AHU4-02 AHU4-02 I 1 ROOM SENSOR Phone 505-883-4111
NO NC CHWR
VFD ES

~
HWR FAS

~
FMS
AHU4-01 TIT
AHU4-05

HWS CHWS

D CONTROL D

~
CONTROL

~
POWER POWER

M ES I
L IR T
MEXI

I
W

CO
NE
20505

E ER
P RO
ES

IN
F
SI G
O N A L EN

FIRE ALARM SHUTDOWN

OCCUPANCY OVERRIDE
ROOM TEMPERATURE
FILTER DIFF. PRESS.

FREEZESTAT ALARM
MA TEMPERATURE

PH TEMPERATURE
RA TEMPERATURE

SA TEMPERATURE
DAMPER SIGNAL

DAMPER SIGNAL

SPEED SIGNAL
VALVE SIGNAL
VALVE SIGNAL
PROJECT

START/STOP

SETPOINT
STATUS
(AO) (AO) (AI) (AI) (AI) (AO) (AI) (DI) (AO) (DO) (DI) (AO) (AI) (DI) (AI) (AI) (DI)
New Mexico State
FCV FCV PDI TI TI TCV TI TA TCV HS YI SC TI YA TI TC YI University
AHU4-02 AHU4-01 AHU4-01 AHU4-01 AHU4-04 AHU4-01 AHU4-02 AHU4-01 AHU4-02 AHU4-01 AHU4-01 AHU4-01 AHU4-03 AHU4-01 AHU4-05 AHU4-01 AHU4-03

AIR HANDLING UNIT AHU-4 CONTROL DIAGRAM


Jett Hall and Jett Annex
(TYPICAL FOR AHU-5) Renovations and
Additions
C C

TCV CONTROL
~

HXPI-01 POWER
FC
0-33 %

PT PT
TT TT TCV CONTROL

~
STM-01 STM-02 POWER
STM-01 STM-02 HXPI-02
PT
HPS STEAM FC FCV TT FCV
Construction
~

PRV HWR-01
34-100 % HXPI-01 HWR-01 HWS-01
FO
HWR
FC
Documents

~
~
TT HEAT EXCHANGER
3
HWS

~
~
COND-01

CONDENSATE TT
COND. M
~

PT
PUMP CP-1 HWS-01
HWS-01
TT TCV CONTROL
1
~

COND-01 HXPI-03 POWER


FC
1 FMS

~
0-33 % VFD
FY CONTROL
CAT5/6
~
~

COND-01 POWER
ETHERNET
TCV
1 HXPI-04
FC FCV
B 34-100 % HXPI-02 B
FO

HEAT EXCHANGER
1 FMS
~

VFD
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

COND TEMPERATURE

HWR TEMPERATURE
HWS TEMPERATURE
HPS TEMPERATURE
LPS TEMPERATURE

HWR PRESSURE
HWS PRESSURE
HPS PRESSURE
LPS PRESSURE

SPEED SIGNAL

SPEED SIGNAL
VALVE SIGNAL

VALVE SIGNAL

VALVE SIGNAL

VALVE SIGNAL

VALVE SIGNAL
OPEN/CLOSE

OPEN/CLOSE

START/STOP

START/STOP
STATUS

STATUS
ALARM

(AI) (AI) (AI) (AI) (DI) (AI) (AO) (AO) (AO) (AO) (DO) (DO) (DO) (DI) (AO) (DO) (DI) (AO) (AI) (AI) (AI) (AI) (AO) Mark Date Description
PI TI TI PI YA TI TCV TCV TCV TCV FCV FCV HS YI SC HS YI SC TI TI PI PI FCV Date September 11, 2015
STEAM-02 STEAM-02 STEAM-01 STEAM-01 COND-01 COND-01 HXP1-01 HXP1-02 HXP1-03 HXP1-04 HXP1-02 HXP1-01 HXP1-01 HXP1-01 HXP1-01 HXP1-02 HXP1-02 HXP1-02 HWS-01 HWR-01 HWS-01 HWR-01 HWS-01 Project Number 14400
Drawn By SDB
A HOT WATER SYSTEM CONTROL DIAGRAM A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL DIAGRAMS
9/15/2015 6:42:26 PM

(CONTROLS)

MI-603
1 2 3 4 5 6 SHEET 139 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

KEYED NOTES
1. VFD'S SHALL BE CONNECTED TO THE FMS NETWORK THROUGH A DIRECT 2428 Baylor Dr SE Albuquerque, NM 87106
NETWORK CONNECTION AS WELL AS THROUGH THE HARDWIRED POINTS
INDICATED. IT IS THE RESPONSIBILITY OF THE FMS CONTRACTOR TO
Tel 505-247-9955 Fax 505-247-1826
COORDINATE AND ADAPT THE FMS NETWORK TO THE COMMUNICATIONS E-mail info@vhgarchitect.com
E PROTOCOLS AVAILABLE FROM THE VFD MANUFACTURER. THE FOLLOWING E Web Site www.vhgarchitect.com
POINTS SHALL BE INTEGRATED INTO THE FMS:
CONSULTANTS
A. SPEED FEEDBACK LABORATORY CONSULTANT
B. FREQUENCY OUTPUT
RFD - Research Facilities Design

E.A

E.A
C. CURRENT
D. TORQUE 3965 Fifth Ave. Suite 400
E. POWER San Diego, CA 92103
F. DC BUS VOLTAGE Phone 619-297-0159
G. OUTPUT VOLTAGE
1 I 1 I H. KWH COUNTER
I. DRIVE TEMPERATURE CIVIL ENGINEER
VFD VFD
FMS Lilley Engineering, Inc.

~
FMS

~
J. ALARMS
K. STATUSES 5160 Calle Bellisima
NC FCV NC FCV Las Cruces, NM 88011
2. PROVIDE A MINIMUM OF ONE STATIC PRESSURE PROBE PER FLOOR FOR EACH
LEF2-01 LEF2-02
AIR HANDLING UNIT. LOCATE THE STATIC PRESSURE PROBES 2 3 THE LENGTH OF
Phone 575-521-0006
CONTROL FCV THE MAIN DUCT RUNS.

~
POWER LEF2-03 STRUCTURAL ENGINEER
ATM
Stubbs Engineering, Inc.
NC PT 277 E. Amador Ave. Suite 200
~ ~ ~ ~ ~ ~ ~
HI LO LEF2-01 Las Cruces, NM 88001
O.A Phone 575-993-5228
~ ~ ~ ~ ~ ~ ~

MECHANICAL/ELECTRICAL ENGINEER
HR Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
~
E.A E.A E.A Albuquerque, NM 87109
~
C Phone 505-883-4111
TT TT PS
I
LEF2-02 LEF2-01 LEF2-01
STATIC PRESSURE PROBE 2

D D

RA TEMPERATURE

STATIC PRESSURE
DAMPER SIGNAL

CLOSE STATUS

CLOSE STATUS
OPEN/CLOSE

OPEN/CLOSE
M ES I
L IR
STATUS

STATUS
T
MEXI

I
W

RA TEMPERATURE

PRESSURE ALARM

CO
NE
(AO) (DI) (DO) (DI) (DI) (DO) (DI) (AI) (AI)
20505

SPEED SIGNAL

SPEED SIGNAL
OPEN STATUS

OPEN STATUS
FCV YI FCV ZIC YI FCV ZIC TI PI
START/STOP

START/STOP

E ER
P RO
LEF2-03 LEF2-01 LEF2-01 LEF2-01 LEF2-02 LEF2-02 LEF2-02 LEF2-01 LEF2-01
ES

IN
F
SI G
O N A L EN
(DO) (AO) (DI) (DO) (AO) (DI) (AI) (DI)

HS SC ZIO HS SC ZIO TI PA
PROJECT
LEF2-01 LEF2-01 LEF2-01 LEF2-02 LEF2-02 LEF2-02 LEF2-02 LEF2-01

New Mexico State


University

Jett Hall and Jett Annex


TT TT
AHU3-10 AHU3-09
HRP-3
FT CONTROL
Renovations and

~
CONTROL
AHU3-02 POWER
Additions
~

~
POWER LINE MS
~

C C
~
C
NO TCV ES
AHU3-03 IS AHU3-04
NC AHU3-02
I 1
VFD
FMS

~
ATM
PT
CONTROL TT I LO HI AHU3-01
~

POWER PDT
AHU3-11
PDT AHU3-02
FCV FT CONTROL
AHU3-01

~
AHU3-01 AHU3-01 POWER

NC
TSL
AHU3-01 ~
Construction
C
~~~~~
HR H
O.A
~ ~ ~ ~~~~ ~
~~~ ~~ ~
S.A S.A S.A Documents
~ ~ ~ ~~~~~
PS TT YS
C C I FAS

~
C AHU3-01 AHU3-04 AHU3-01
TT TT TT
STATIC PRESSURE PROBE 1
AHU3-01 AHU3-02 AHU3-03 TT TT I 1
AHU3-07 AHU3-08 VFD ES
TT TT

~
FAS

~
FMS
AHU3-05 AHU3-06 AHU3-03
TCV
AHU3-01 TCV
AHU3-02
NO HWR
NC
CHWR

HWS
CHWS
CONTROL
~

PCP-3
B POWER CONTROL B

~
POWER

LINE MS
~

ES
IS AHU3-01
AHU3-01
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

FIRE ALARM SHUTDOWN


CHWR TEMPERATURE
HRWS TEMPERATURE

CHWS TEMPERATURE
HWR TEMPERATURE
HWS TEMPERATURE

FREEZESTAT ALARM
OA TEMPERATURE

PRESSURE ALARM
VALVE SIGNAL
OPEN STATUS

START/STOP

AIR VOLUME

AIR VOLUME
STATUS

STATUS

STATUS
HRWR TEMPERATURE

HRWR TEMPERATURE
FILTER DIFF. PRESS.

FILTER DIFF. PRESS.


HRA TEMPERATURE

STATIC PRESSURE
PH TEMPERATURE

SA TEMPERATURE
(DI) (AI) (AI) (AI) (DO) (AI) (DI) (AO) (DI) (AI) (AI) (DI) (AI) (DI) (AI) (DI) (DI)
CLOSE STATUS

SPEED SIGNAL

SPEED SIGNAL
Mark Date Description
VALVE SIGNAL

VALVE SIGNAL
OPEN/CLOSE

ZIO TI TI TI HS TI TA TCV II TI TI YI FI YI FI PA YA
START/STOP

START/STOP

START/STOP
Date September 11, 2015
AHU3-01 AHU3-10 AHU3-01 AHU3-05 AHU3-03 AHU3-06 AHU3-01 AHU3-03 AHU3-02 AHU3-07 AHU3-08 AHU3-01 AHU3-01 AHU3-02 AHU3-02 AHU3-01 AHU3-01
STATUS

Project Number 14400


Drawn By SDB
(DO) (DI) (AI) (AI) (DI) (AO) (AI) (AI) (AI) (DO) (AO) (DO) (AO) (DO) (AO) (AI) (AI) (AI)
A A Checked By IM
FCV ZIC PDI TI II TCV TI TI TI HS TCV HS SC HS SC PDI TI PI
Copyright © VAN H. GILBERT ARCHITECT PC
AHU3-01 AHU3-01 AHU3-01 AHU3-02 AHU3-01 AHU3-01 AHU3-03 AHU3-11 AHU3-09 AHU3-04 AHU3-02 AHU3-01 AHU3-01 AHU3-02 AHU3-02 AHU3-02 AHU3-04 AHU3-01

SHEET TITLE
WEST MAKE-UP/EXHAUST AIR HANDLING SYSTEM AHU-3 CONTROL DIAGRAM
MECHANICAL DIAGRAMS
9/15/2015 6:42:27 PM

(CONTROLS)

MI-604
1 2 3 4 5 6 SHEET 140 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

KEYED NOTES
1. VFD'S SHALL BE CONNECTED TO THE FMS NETWORK THROUGH A DIRECT
NETWORK CONNECTION AS WELL AS THROUGH THE HARDWIRED POINTS
INDICATED. IT IS THE RESPONSIBILITY OF THE FMS CONTRACTOR TO
COORDINATE AND ADAPT THE FMS NETWORK TO THE COMMUNICATIONS
PROTOCOLS AVAILABLE FROM THE VFD MANUFACTURER. THE FOLLOWING
POINTS SHALL BE INTEGRATED INTO THE FMS:
2428 Baylor Dr SE Albuquerque, NM 87106
A. SPEED FEEDBACK Tel 505-247-9955 Fax 505-247-1826
B. FREQUENCY OUTPUT E-mail info@vhgarchitect.com
C. CURRENT
E E Web Site www.vhgarchitect.com
D. TORQUE
E. POWER CONSULTANTS
F. DC BUS VOLTAGE
G. OUTPUT VOLTAGE LABORATORY CONSULTANT
H. KWH COUNTER RFD - Research Facilities Design
I. DRIVE TEMPERATURE 3965 Fifth Ave. Suite 400
J. ALARMS
San Diego, CA 92103
K. STATUSES
Phone 619-297-0159
2. PROVIDE A MINIMUM OF ONE STATIC PRESSURE PROBE PER FLOOR FOR EACH
AIR HANDLING UNIT. LOCATE THE STATIC PRESSURE PROBES 2 3 THE LENGTH OF CIVIL ENGINEER
THE MAIN DUCT RUNS. (ONE PER BLDG) Lilley Engineering, Inc.

E.A

E.A

E.A
5160 Calle Bellisima

E.A

E.A
3. TYPICAL OF 3 FANS CONNECTED TO ONE VFD AND ONE FLOW TRANSMITTER.
Las Cruces, NM 88011
Phone 575-521-0006
ROOF
1 I 1 I 1 I STRUCTURAL ENGINEER
VFD VFD VFD 1 I 1 I Stubbs Engineering, Inc.

~
FMS

~
FMS FMS

~
EF-1 EF-2 CEILING SPACE
FMS
VFD VFD PDT 277 E. Amador Ave. Suite 200

~
FMS

~
NC FCV NC FCV NC FCV AHU2-03 Las Cruces, NM 88001
LEF1-01 LEF1-02 LEF1-03 NC FCV NC FCV
Phone 575-993-5228
CONTROL FCV EF1-01 EF2-01
~

POWER LEF1-04 S.A.P. STATION MECHANICAL/ELECTRICAL ENGINEER


ATM
Bridgers & Paxton Consulting Engineers
NC PT 4600-C Montgomery Blvd. NE
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
HI LO LEF1-01 Albuquerque, NM 87109
O.A Phone 505-883-4111
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

HR

E.A

E.A
~
E.A E.A E.A
D ~ D
C
TT TT PS I
LEF1-02 LEF1-01 LEF1-01
STATIC PRESSURE PROBE 2

M ES I
L IR T
MEXI

I
W

CO
NE
STATIC PRESSURE
RA TEMPERATURE
20505
DAMPER SIGNAL

CLOSE STATUS

CLOSE STATUS

CLOSE STATUS

E ER
P RO
OPEN/CLOSE

OPEN/CLOSE

OPEN/CLOSE

OPEN/CLOSE

OPEN/CLOSE
ES

IN
F
SI G
O N A L EN
STATUS

STATUS

STATUS

STATUS

STATUS
RA TEMPERATURE

SPACE PRESSURE
PRESSURE ALARM
(AO) (DI) (DO) (DI) (DI) (DO) (DI) (DI) (DO) (DI) (AI) (AI) (DI) (DO) (DI) (DO)
SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL
PROJECT
OPEN STATUS

OPEN STATUS

OPEN STATUS
FCV YI FCV ZIC YI FCV ZIC YI FCV ZIC TI PI YI FCV YI FCV
START/STOP

START/STOP

START/STOP

START/STOP

START/STOP
LEF1-04 LEF1-01 LEF1-01 LEF1-01 LEF1-02 LEF1-02 LEF1-02 LEF1-03 LEF1-03 LEF1-03 LEF1-01 LEF1-01 EF1-01 EF1-01 EF2-01 EF2-01

(DO) (AO) (DI) (DO) (AO) (DI) (DO) (AO) (DI) (AI) (DI) (DO) (AO) (DO) (AO) (AI)
New Mexico State
HS SC ZIO HS SC ZIO HS SC ZIO TI PA HS SC HS SC PDI University
LEF1-01 LEF1-01 LEF1-01 LEF1-02 LEF1-02 LEF1-02 LEF1-03 LEF1-03 LEF1-03 LEF1-02 LEF1-01 EF1-01 EF1-01 EF2-01 EF2-01 AHU2-03

Jett Hall and Jett Annex


Renovations and
Additions
C C
TT TT HRP-2
AHU2-10 AHU2-09
FT CONTROL

~
AHU2-02 POWER
CONTROL 3
~

~
POWER LINE MS
~

~
C
NO TCV ES
AHU2-03 IS AHU2-04
NC AHU2-02
I 1
VFD

~
FMS

ATM
PT
Construction
CONTROL I LO HI AHU2-01 Documents
~

TT
POWER PDT
AHU2-11
PDT AHU2-02
FCV FT CONTROL
AHU2-01

~
AHU2-01 TSL AHU2-01 POWER
AHU2-01 3
NC HR H C ~~ ~~~ ~
~ ~ ~ ~~~~~
~~~ ~~ S.A S.A S.A
~
O.A ~ ~ ~~~~
~ ~ C PS TT YS
C I

~
FAS
C TT AHU2-01 AHU2-04 AHU2-01
TT TT
STATIC PRESSURE PROBE 1
AHU2-01 AHU2-02 AHU2-03 TT TT I 1
AHU2-07 AHU2-08 VFD ES
TT TT FAS

~
FMS

~
AHU2-05 AHU2-06 AHU2-03
TCV
AHU2-01 TCV
B NO AHU2-02 B
HWR
NC CHWR

HWS
CHWS
CONTROL
~

PCP-2 POWER CONTROL


~

POWER
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

LINE MS
~

ES
IS AHU2-01
AHU2-01

FIRE ALARM SHUTDOWN


CHWR TEMPERATURE
HRWS TEMPERATURE

CHWS TEMPERATURE
HWR TEMPERATURE
HWS TEMPERATURE

FREEZESTAT ALARM
OA TEMPERATURE

PRESSURE ALARM
Mark Date Description
VALVE SIGNAL
OPEN STATUS

Date September 11, 2015


START/STOP

AIR VOLUME

AIR VOLUME
Project Number 14400
STATUS

STATUS

STATUS
HRWR TEMPERATURE

HRWR TEMPERATURE

Drawn By SDB
FILTER DIFF. PRESS.

FILTER DIFF. PRESS.


HRA TEMPERATURE

STATIC PRESSURE
PH TEMPERATURE

SA TEMPERATURE
A (DI) (AI) (AI) (AI) (DO) (AI) (DI) (AO) (DI) (AI) (AI) (DI) (AI) (DI) (AI) (DI) (DI) A Checked By IM
CLOSE STATUS

SPEED SIGNAL

SPEED SIGNAL
VALVE SIGNAL

VALVE SIGNAL
OPEN/CLOSE

ZIO TI TI TI HS TI TA TCV II TI TI YI FI YI FI PA YA Copyright © VAN H. GILBERT ARCHITECT PC


START/STOP

START/STOP

START/STOP

AHU2-01 AHU2-10 AHU2-01 AHU2-05 AHU2-03 AHU2-06 AHU2-01 AHU2-03 AHU2-02 AHU2-07 AHU2-08 AHU2-01 AHU2-01 AHU2-02 AHU2-02 AHU2-01 AHU2-01
STATUS

SHEET TITLE

(DO) (DI) (AI) (AI) (DI) (AO) (AI) (AI) (AI) (DO) (AO) (DO) (AO) (DO) (AO) (AI) (AI) (AI)
MECHANICAL DIAGRAMS
9/15/2015 6:42:27 PM

FCV ZIC PDI TI II TCV TI TI TI HS TCV HS SC HS SC PDI TI PI


AHU2-01 AHU2-01 AHU2-01 AHU2-02 AHU2-01 AHU2-01 AHU2-03 AHU2-11 AHU2-09 AHU2-04 AHU2-02 AHU2-01 AHU2-01 AHU2-02 AHU2-02 AHU2-02 AHU2-04 AHU2-01 (CONTROLS)
EAST MAKE-UP/EXHAUST AIR HANDLING SYSTEM AHU-2 CONTROL DIAGRAM
MI-605
1 2 3 4 5 6 SHEET 141 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING

KEYED NOTES
1. VFD'S SHALL BE CONNECTED TO THE FMS NETWORK THROUGH A DIRECT
NETWORK CONNECTION AS WELL AS THROUGH THE HARDWIRED POINTS
INDICATED. IT IS THE RESPONSIBILITY OF THE FMS CONTRACTOR TO 2428 Baylor Dr SE Albuquerque, NM 87106
COORDINATE AND ADAPT THE FMS NETWORK TO THE COMMUNICATIONS Tel 505-247-9955 Fax 505-247-1826
PROTOCOLS AVAILABLE FROM THE VFD MANUFACTURER. THE FOLLOWING
POINTS SHALL BE INTEGRATED INTO THE FMS:
E-mail info@vhgarchitect.com
E E Web Site www.vhgarchitect.com
A. SPEED FEEDBACK CONSULTANTS
B. FREQUENCY OUTPUT
C. CURRENT LABORATORY CONSULTANT
D. TORQUE RFD - Research Facilities Design
E. POWER
F. DC BUS VOLTAGE
3965 Fifth Ave. Suite 400
G. OUTPUT VOLTAGE San Diego, CA 92103
H. KWH COUNTER Phone 619-297-0159
I. DRIVE TEMPERATURE
J. ALARMS
CIVIL ENGINEER
K. STATUSES
Lilley Engineering, Inc.
2. PROVIDE A MINIMUM OF ONE STATIC PRESSURE PROBE PER FLOOR FOR EACH 5160 Calle Bellisima

E.A

E.A

E.A

E.A
AIR HANDLING UNIT. LOCATE THE STATIC PRESSURE PROBES 2 3 THE LENGTH OF Las Cruces, NM 88011
THE MAIN DUCT RUNS. Phone 575-521-0006

STRUCTURAL ENGINEER
1 I 1 I 1 I 1 I Stubbs Engineering, Inc.
VFD EF-3 VFD EF-4 VFD EF-5 VFD EF-6 277 E. Amador Ave. Suite 200

~
FMS FMS

~
FMS FMS

~
Las Cruces, NM 88001
Phone 575-993-5228
NC FCV NC FCV NC FCV NC FCV
EF3-01 EF4-01 EF5-01 EF6-01
MECHANICAL/ELECTRICAL ENGINEER
Bridgers & Paxton Consulting Engineers
4600-C Montgomery Blvd. NE
Albuquerque, NM 87109
Phone 505-883-4111

E.A

E.A

E.A
E.A
S.O.A.P. STATION
(ONE PER BLDG)
D D

ROOF

M ES I
CEILING SPACE PDT L IR T
MEXI

I
AHU1-02 W

CO
NE
20505
FT CONTROL

E ER
P RO
~
AHU1-03 POWER
ES

IN
S.A.P. STATION

F
R.A SI G
O N A L EN

TT PS I YS

~
FAS
AHU1-04 AHU1-02 AHU1-02
PROJECT

I 1
VFD New Mexico State

~
FCV FMS
AHU1-03 ATM
University

~~~~
~~~~
PT
NO
CONTROL I LO HI AHU1-01
~

POWER
PDT
FCV FT CONTROL
Jett Hall and Jett Annex

~
AHU1-01
AHU1-02 AHU1-02 POWER
TSL

ECONOMIZER
NC H
AHU1-01 C ~~~~~ Renovations and
S.A S.A S.A
Additions
~ ~~ ~
~~~~~
O.A ~~ ~
~ C PS TT YS
C I

~
C FAS C
AHU1-01 AHU1-03 AHU1-01
TT TCV TT TCV
CONTROL STATIC PRESSURE PROBE 2
~

POWER AHU1-01 AHU1-01 AHU1-02 AHU1-02 I 1


FCV NO NC CHWR
VFD ES
FAS

~
HWR FMS

~
AHU1-01 AHU1-02

NC
MINIMUM HWS CHWS
O.A PCP-1
CONTROL

~
CONTROL ~
POWER POWER

LINE ES
~

FIT CONTROL
~

AHU1-01
AHU1-01 POWER

IS
Construction
AHU1-01
Documents

B B

FIRE ALARM SHUTDOWN


FILTER DIFF. PRESS.

FREEZESTAT ALARM

SPACE PRESSURE
PRESSURE ALARM
RA TEMPERATURE
DAMPER SIGNAL

DAMPER SIGNAL
SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL

SPEED SIGNAL
VALVE SIGNAL
START/STOP

START/STOP

START/STOP

START/STOP

START/STOP

START/STOP
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

STATUS
MA TEMPERATURE

STATIC PRESSURE
PH TEMPERATURE
PRESSURE ALARM

(DI)

SA TEMPERATURE
(DO) (AO) (DO) (AO) (DO) (AO) (DO) (AO) (AO) (AO) (AI) (AI) (DI) (AO) (DI) (DO) (AO) (DO) (AO) (DI) (AI)
DAMPER SIGNAL

VALVE SIGNAL
HS SC HS SC HS SC HS SC FCV FCV PDI TI II TCV TA HS SC HS SC PA YA PDI
OPEN/CLOSE

OPEN/CLOSE

OPEN/CLOSE

OPEN/CLOSE

START/STOP
AIR VOLUME

AIR VOLUME

AIR VOLUME
EF3-01 EF3-01 EF4-01 EF4-01 EF5-01 EF5-01 EF6-01 EF6-01 AHU1-03 AHU1-01 AHU1-01 AHU1-04 AHU1-01 AHU1-01 AHU1-01 AHU1-01 AHU1-01 AHU1-02 AHU1-02 AHU1-01 AHU1-01 AHU1-02
STATUS

STATUS

STATUS

STATUS

STATUS

STATUS
(DI) (AO) (DI) (AO) (DI) (AO) (DI) (AO) (AO) (AI) (AI) (DI) (DO) (AI) (AO) (DI) (AI) (DI) (AI) (AI) (AI)

YI FCV YI FCV YI FCV YI FCV FCV FI TI PA HS TI TCV YI FI YI FI TI PI


EF3-01 EF3-01 EF4-01 EF4-01 EF5-01 EF5-01 EF6-01 EF6-01 AHU1-02 AHU1-01 AHU1-01 AHU1-02 AHU1-03 AHU1-02 AHU1-02 AHU1-01 AHU1-02 AHU1-02 AHU1-03 AHU1-03 AHU1-01

AIR HANDLING UNIT AHU-1 CONTROL DIAGRAM


Mark Date Description
Date September 11, 2015
Project Number 14400
Drawn By SDB
A A Checked By IM
Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL DIAGRAMS
9/15/2015 6:42:27 PM

(CONTROLS)

MI-606
1 2 3 4 5 6 SHEET 142 OF 187
1 2 3 4 5 6
Van H. Gilbert Architect PC
ARCHITECTURE • INTERIORS • PLANNING
General Hot Water Coil Pump
The FMS shall operate the pump anytime the outside air is below 35°F (adjustable) when the air handlin g unit is operating. The FMS shall monitor the status of the Typical Laboratory Controls
Programming pump through a current switch installed on the motor. If a pump failure is detected, the FMS shall initiate an alarm.
The FMS shall be programmed according to the following sequence of operations including all energy reduction operations described in this sequence General
and in the project specifications. Exhaust Fan LEF-1 Control Each laboratory shall be installed with dedicated variable air volume control systemS which shall control the variable volume fume hoods, supply air valve,
The fans shall operate with two lead fans and one standby fan. The lead fans shall operate anytime the make-up unit is operating. The FMS shall operate the fans at reheat coil, and general exhaust air valve. The variable air volume control systems shall communicate with the FMS through a direct network connection to
System Status Display the speed set by the test and balance contractor. The FMS shall modulate the outside air deficit damper to maintain the exhaust duct static pressure at setpoint. the FMS. The control systems shall include all required exhaust air valves, supply air valves, controllers, network routers, and sensors for a complete and
The FMS shall provide operating status for all systems controlled by the FMS. The displays shall include all points indicated on the drawings and any The lead/standby configuration of the fans shall be rotated monthly. The ramp of the VFD shall be adjusted to restrict the rate of change of the VFD output to sixty operational system. The system shall operate between 6 and 2 air changes per hour. Refer to mechanical floor plans for exact requirements in each lab.
others required to achieve the sequence of operations. The FMS shall be able to integrate system diagnostics into control action decisions. This shall seconds for a zero to one hundred percent control signal change.
also include the ability to designate individual units as being in maintenance mode to avoid generating alarms. All system control and status events shall VAV Fume Hood Control (Standard Fumehoods)
be recorded, at the operator's selection, in the FMS event log to facilitate troubleshooting. All detected alarms or failures shall initiate an alarm within Exhaust Fan LEF-1 Monitoring Each fume hood face velocity and exhaust volume shall be continuously measured. The face velocity controller shall modulate the fume hood air valve to 2428 Baylor Dr SE Albuquerque, NM 87106
the FMS. The VFD’s operations shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall stop the fan initiate an maintain the face velocity setpoint and minimum exhaust volume set point at all times. If a failure is detected in the fume hood system, the local fume hood
alarm. The FMS shall automatically start the standby fan if a failure is detected in the lead fan. indicator shall alarm as well as an alarm shall be initiated by the FMS. The system shall maintain a set fume hood face velocity based on proximity sensors.
Tel 505-247-9955 Fax 505-247-1826
Power Failure Recovery E-mail info@vhgarchitect.com
E The FMS shall contain a power failure recovery mode (operator adjustable). The power failure recovery capability shall return the system to its last state Exhaust Fan LEF-1 Isolation Damper CAV Fume Hood Control E Web Site www.vhgarchitect.com
(before the building lost power). Each damper shall be open anytime the associated exhaust fan is operating. The FMS shall monitor the open and closed status of the damper through damper actuator Each fume hood shall be installed with a constant volume air valve which shall provide a constant amount of exhaust to the hood. Each hood shall have a
end switches. If a damper failure is detected, the FMS shall initiate an alarm. If the damper fails in the closed position the FMS shall stop the associated fumehood monitor which shall alarm if flow in the hood is below the required minimum. CONSULTANTS
Occupancy Control exhaust fan and start the next fan in the sequence.
The FMS shall be setup with an occupancy schedule for different areas of the building. The owner shall be interviewed by the contractor at start-up to Constant Volume Exhaust Devices LABORATORY CONSULTANT
establish these schedules. Some areas of the building shall be setup to be continuously occupied. Relief Fan EF-1 & EF-2 Control Some devices in the laboratory shall be installed with constant volume air valves to maintain a constant exhaust volume at all time. RFD - Research Facilities Design
The fans shall operate in a lead/lag configuration to maintain the building pressure at setpoint. If the building pressure rises above 0.05” w.c. (adjustable) the FMS 3965 Fifth Ave. Suite 400
West Penthouse Air Handling Unit AHU-1 shall open the lead fan damper and modulate the fan speed to maintain the building pressure at setpoint. If the speed of the lead fan reaches 100% and building Variable Volume Room Pressure Control
pressure is above setpoint, the FMS shall open the lag fan damper and modulate both fans together to maintain the building pressure at setpoint. With both fans The laboratory control system shall control supply and auxiliary exhaust airflow devices in order to maintain a volumetric offset (negative). Offset shall be San Diego, CA 92103
Mixed Air Damper Interlocks operating, if the speed of the fans falls below 40%, the FMS shall stop the lag fan. The lead/lag configuration of the fans shall be rotated monthly. The ramp of maintained regardless of any change in flow or static pressure. This offset shall be field adjustable and represents the volume of air, which will enter Phone 619-297-0159
Control signals from the FMS system shall modulate the mixed air dampers. Upon initial start-up, the FMS system will not begin modulation of the mixing the VFD shall be adjusted to restrict the rate of change of the VFD output to sixty seconds for a zero to one hundred percent control signal change. (or exit) the room from the corridor or adjacent spaces. The pressurization control algorithm shall sum the flow values of all supply and exhaust airflow
dampers for five minutes (adjustable) to allow the control loops to stabilize. devices and command appropriate controlled devices to new set points to maintain the desired offset. The offset shall be adjustable. The pressurization
Relief Fan EF-1 & EF-2 Monitoring control algorithm shall consider both networked devices, as well as up to three non-networked devices providing a linear analog flow signal and any number CIVIL ENGINEER
Mixed Air Damper Control The VFD’s operations shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall stop the fan initiate an of constant volume devices where the total of supply devices and the total of exhaust devices may be factored into the pressurization control algorithm. Lilley Engineering, Inc.
The FMS system shall modulate the mixed air dampers to maintain the supply air temperature at set point. Whenever the outside air temperature is alarm. The FMS shall automatically start the lag fan if a failure is detected in the lead fan. Volumetric offset shall be the only acceptable means of controlling room pressurization. Systems that rely on differential pressure as a means of control shall 5160 Calle Bellisima
greater than the return air temperature and mechanical cooling is required, the mixed air dampers shall be in their normal position (full return air with provide documentation to demonstrate that space pressurization can be maintained if fume hood sashes are changed at the same time a door to the space is
minimum outside air). When the air handling unit is stopped, the FMS shall close all outside air dampers and the relief damper and open the return air West Fan Room Air Handling Unit AHU-3/ LEF-2 opened. The pressurization control algorithm shall support the ability to regulate the distribution of total supply flow across multiple supply airflow control Las Cruces, NM 88011
damper. devices in order to optimize air distribution in the space. Phone 575-521-0006
Outside Air Damper
Minimum Outside Air Control The damper shall be open anytime the air handling unit is operating. The FMS shall monitor the open and closed status of the damper through damper actuator end Variable Volume Temperature Control
The minimum outside air volume shall be controlled by the FMS through the minimum outside air flow measuring damper which measures the minimum switches. If a damper failure is detected, the FMS shall initiate an alarm. If the damper fails in the closed position the FMS shall stop the supply fans. The temperature of the lab shall be continuously measured. If the lab requires cooling, the supply air valve and general exhaust air valve shall be modulated STRUCTURAL ENGINEER
outside air volume. The FMS shall not modulate the minimum outside air volume damper below minimum outside air volume setpoint. If the air handling together between the minimum and maximum cooling air flows to maintain the space temperature at the occupied cooling setpoint of 76°F (adjustable). If th e Stubbs Engineering, Inc.
unit is stopped, the FMS shall close the damper. If the minimum outside air damper is fully open with the economizer damper closed and the minimum Supply Air Temperature Setpoint Control lab requires heating, the reheat coil valve shall be modulated to maintain the space temperature at the occupied heating setpoint of 70°F (adjustable). The 277 E. Amador Ave. Suite 200
outside air volume is below setpoint, the FMS shall modulate the return air damper to maintain the minimum outside air volume at setpoint. The FMS The FMS shall control the air handling unit to maintain an adjustable supply air temperature setpoint. The temperature setpoint shall be reset from 55°F lab temperature setpoint shall be adjustable through the FMS. During unoccupied periods, the space temperature setpoint shall be reset to 55°F for heati ng
shall trend and log the outside air volume being brought in by the air handling unit. (adjustable) to 75°F (adjustable) based on the dema nd of the terminal units and laboratory control air valves served by it so that at least one unit is in full cooling and 85°F for cooling. If during an unoccupied peri od the space occupancy switch is activated, the space shall return to the occupied setpoints for a period of Las Cruces, NM 88001
and still maintaining the room temperature setpoint. two hours before switch back to the unoccupied state. Phone 575-993-5228
Supply Air Temperature Setpoint Control
The FMS shall control the air handling unit to maintain an adjustable supply air temperature setpoint. The temperature setpoint shall be reset from 55°F Supply Air Static Setpoint Control Constant Volume Temperature Control
(adjustable) to 75°F (adjustable) based on the dema nd of the terminal units served by it so that at least one terminal unit is in full cooling (max airflow The FMS shall reset the static pressure setpoint using a trim and respond logic within the range of 0.5” w.g. to 1.5” w.g. When the fan is off, the setpoint shall be If the lab requires heating, the reheat coil valve shall be modulated to maintain the space temperature at the occupied heating setpoint of 70°F (adjusta ble). MECHANICAL/ELECTRICAL ENGINEER
setpoint) and still maintaining the room temperature setpoint. 1.0” w.g. Once the fan is started, the setpoint shall be trimmed by 0.04” w.g. every two minutes if there are two or fewer zone pressure requests. If there are The lab temperature setpoint shall be adjustable through the FMS. During unoccupied periods, the space temperature setpoint shall be reset to 55°F for Bridgers & Paxton Consulting Engineers
more than two zone pressure requests, respond by increasing the setpoint by 0.06” w.g. A zone pressure request is generated when a VAV damper or air valve is greater heating. If during an unoccupied period the space occupancy switch is activated, the space shall return to the occupied setpoints for a period of two hours 4600-C Montgomery Blvd. NE
Supply Air Static Setpoint Control than 95% open until it drops to 80% open or based on pressure request signal from the air valve. All setpoints shall be adjustable through the operator workstation. before switch back to the unoccupied state.
The FMS shall reset the static pressure setpoint using a trim and respond logic within the range of 0.5” w.g. to 1.5” w.g. When the fan is off, the setpoint Albuquerque, NM 87109
shall be 1.0” w.g. Once the fan is started, the setpoint shall be trimmed by 0.04” w.g. every two minutes if there are two or fewer zone pressure requests. Heat Recovery Coil Pump Control Variable Air Volume Terminal Units w/ Hot Water Reheat Phone 505-883-4111
If there are more than two zone pressure requests, respond by increasing the setpoint by 0.06” w.g. A zone pressure request is generated when a VAV The FMS shall operate the heat recovery pump anytime the outside air temperature is 10°F (adjustable) below the supply air temperature setpoint for the air handling
damper is greater than 95% open until it drops to 80% open. All setpoints shall be adjustable through the operator workstation. unit or is above exhaust air temperature when the air handling unit is operating. The FMS shall modulate the heat recovery coil valve to maintain the supply air Each terminal unit shall modulate the supply air damper to maintain the space temperature conditions. If the zone requires cooling, the supply air damper
temperature at setpoint. If the exhaust air temperature leaving the heat recovery coil falls below 38°F (adjustable), the FMS shall switch control of th e heat shall be modulated between the minimum and maximum cooling air flows to maintain the space temperature at the cooling setpoint of 76°F (adjustable) for
Supply Air Temperature Control recovery coil valve to maintain the exhaust discharge temperature above 38°F (adjustable), to prevent the coil from freezing. occupied periods and 85°F (adjustable) during unocc upied periods. If the zone calls for heating, the supply air damper shall be modulated to a minimum and
The FMS shall modulate the hot water coil valve and chilled water coil valve to maintain the supply air temperature setpoint. The FMS shall prevent the heating valve shall be modulated open to maintain the space temperature at the heating setpoint of 72°F (adjustable) for occupied periods and 55°F fo r
simultaneous heating and cooling. Heat Recovery Coil Pump Monitoring unoccupied periods. If additional heating is required when the valve is fully open, the supply air damper shall be modulated to meet the room temperature
D The FMS shall monitor the status of the pump through a current switch installed on the motor. If a failure occurs, the FMS shall stop the pump and initiate an requirements. If during an unoccupied period the space occupancy switch is activated, the space shall return to the occupied setpoints for a period of two D
Supply Fan Control alarm. hours before switch back to the unoccupied state.
The supply fan VFD’s shall be started and stopped by the FMS system based on an occupancy schedule for the space programmed into the FMS. The
fans shall operate continuously during occupied periods. If during unoccupied periods, any of the space temperatures rise above the unoccupied Supply Air Temperature Control Chilled Water System
cooling setpoint or fall below the unoccupied heating setpoint, the air handling unit shall start and operate to change the space temperature 2°F The FMS shall modulate the chilled water and hot water coil valves to maintain the supply air temperature setpoint. The FMS shall prevent simultaneous heating and
(adjustable) before stopping. If during unoccupied periods, any of the space occupancy switches are activated, the air handling unit shall start and cooling. Chilled Water System Differential Pressure Setpoint
operate for a period of two hours before stopping. The FMS shall reset the system differential pressure setpoint using a trim and respond logic within the range of 5 psig to 20 psig once the maximum chilled
Supply Fan Control water temperature setpoint is reached. Once the temperature setpoint is reached, the differential pressure setpoint for the controlling zone shall be trimmed
Supply Fan VFD Control The supply fan VFD’s shall be started and stopped by the FMS system. The fans shall operate continuously. by 0.1 psig every two minutes until a valve in the system is 50% open. When a valve in the system rises to 80% open, the differential pressure setpoint for M ES I
The VFD’s shall be modulated together to maintain the supply duct static pressure at setpoint for the duct static pressure sensor which is farthest below the controlling zone shall be increased by 0.1 psig every two minutes. All setpoints shall be adjustable through the operator workstation for each differential L IR T
MEXI

I
setpoint. The ramp of the VFD’s shall be adjusted to restrict the rate of change of the VFD output to sixty seconds for a zero to one hundred percent Supply Fan VFD Control pressure sensor.

I
W
control signal change. The VFD’s shall be modulated together to maintain the supply duct static pressure at setpoint for the duct static pressure sensor which is farthest below setpoint. The

CO
NE
ramp of the VFD’s shall be adjusted to restrict the rate of change of the VFD output to sixty seconds for a zero to one hundred percent control signal change. Chilled Water Pump Control 20505
Supply Fan Monitoring The chilled water pumps shall operate in a lead/standby configuration. The lead pump shall operate anytime the chilled water system differential pressure

E ER
P RO
The VFD’s operations shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall initiate an Supply Fan Monitoring falls below setpoint. The pumps shall modulate to maintain the system differential pressure at setpoint for the controlling zone. The controlling zone shall be
alarm. The VFD’s operations shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall initiate an alarm. the differential pressure sensor which is furthest below its setpoint. The bypass valve shall be closed anytime the chilled water pumps are operating, and ES

IN
F
open when they are off. SI G
O N A L EN
Relief Fan EF-3, EF-4, EF-5, & EF-6 Control Filter Monitoring
The relief fans shall operate in a lead/lag/lag/lag configuration whenever the supply fan operates and the building pressure is above setpoint. The FMS The differential pressure across the filters shall be monitored by the FMS through a differential pressure transmitter. If the differential pressure exceeds set Chilled Water Pump Rotation
shall modulate the speed of the lead fan to maintain the differential pressure measured in the space and the outside air pressure at a positive space point, the FMS shall initiate an alarm. Manual or automatic rotation of the pumps shall be allowed. Rotation time interval shall be 30 days (adjustable). The application shall also provide a setting
pressure of 0.05" w.c. (adjustable). Each time the speed of the fans reache 100% and the building pressure is above setpoint, the FMS shall start the (operator selectable) to allow a forced rotation which shall cause the pumps to be immediately enabled /disabled.
next lag fan and modulate the fans together to maintain the differential pressure at setpoint. With all fans operating, if the speed of the fans falls below Freezestat PROJECT
70%, the FMS shall stop the last lag fan. With three fans operating if the speed of the fans falls below 60%, the FMS shall stop the next lag fan. With A freezestat set at 35°F located downstream of the hot water coil shall initiate an alarm at the FMS and stop the supply fan if an alarm conditionis detected. Chilled Water Pump Failure Detection and Recovery
two fans operating, if the speed of the fans falls below 40%, the FMS shall stop the first lag fan. The lead/lag configuration of the fans shall be rotated The FMS shall monitor the status of each pump through a set of contacts in the VFD. Upon sensing a pump failure, the FMS shall lockout that pump and
monthly. The ramp of the VFD shall be adjusted to restrict the rate of change of the VFD output to sixty seconds for a zero to one hundred percent Smoke Detectors immediately initiate the start of the next pump in the rotation sequence. When a pump is marked as having failed, the failed pump shall be taken out of the
control signal change. Smoke detectors located in the supply air streams, shall stop the fans through the fire alarm system if an alarm condition is detected. When the fans are stopped,
the FMS shall position the dampers to their normal state.
rotation. New Mexico State
Relief Fan Monitoring
The VFD operation shall be indicated to the FMS through a set of contacts in the VFD. If an alarm condition is detected, the FMS shall stop the fan and Duct Pressure Safety Switches
Chilled Water Pump Failure Reset
When an individual pumps failure is reset at the operator workstation, the FMS shall re-insert that pump into the rotation of pumps. All failures shall be reset University
initiate an alarm. The FMS shall automatically start the next fan in the rotation and operate it place of the failed fan. Safety switches installed in the supply and exhaust air ducts for the unit shall alarm the FMS if the duct pressure is above the high alarm setpoint. The high alarm through the FMS operator workstation.
setpoint shall be 150% of the normal operating static of the system. If the FMS senses an alarm condition, the FMS shall stop the supply and exhaust fans.
Relief Damper Control Hot Water System
The FMS shall open the relief air damper anytime the associated relief fan is operating. Hot Water Coil Pump
The FMS shall operate the pump anytime the outside air is below 35°F (adjustable) when the air handlin g unit is operating. The FMS shall monitor the status of the Hot Water Temperature Control Jett Hall and Jett Annex
Filter Monitoring pump through a current switch installed on the motor. If a pump failure is detected, the FMS shall initiate an alarm. The FMS control system shall reset the secondary hot water temperature setpoint based on the outside air temperature conditions. At an outside air
The differential pressure across the filters shall be monitored by the FMS through a differential pressure transmitter. If the differential pressure exceeds
set point, the FMS shall initiate an alarm. Exhaust Fan LEF-2 Control
temperature of 70 °F (adjustable), the hot water te mperature setpoint shall be 140 °F (adjustable). A t an outside air temperature of 40 °F (adjustable), the hot
water temperature setpoint shall be 180 °F (adjusta ble). The FMS shall monitor and trend the
Renovations and
Freezestat
A freezestat set at 35°F located downstream of the hot water coil shall initiate an alarm at the FMS and stop the supply fan if an alarm condition is
The fans shall operate in a lead/standby configuration. The lead fan shall operate anytime the make-up unit is operating. The FMS shall operate the fan at the speed
set by the test and balance contractor. The FMS shall modulate the outside air deficit damper to maintain the exhaust duct static pressure at setpoint. The
lead/standby configuration of the fans shall be rotated monthly. The ramp of the VFD shall be adjusted to restrict the rate of change of the VFD output to sixty
temperatures and pressures of the system as indicated on the control diagrams.

Heat Exchanger Control


Additions
C detected. seconds for a zero to one hundred percent control signal change. The FMS shall operate the heat exchangers in a lead/standby configuration. When a heat exchanger is in operation, the hot water isolation valve shall be C
open and the FMS shall modulate the steam valves in sequence to maintain the hot water supply temperature at setpoint.
Smoke Detectors Exhaust Fan LEF-2 Monitoring
Smoke detectors located in the supply air and return air streams, shall stop the fans through the fire alarm system if an alarm condition is detected. The VFD’s operations shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall stop the fan initiate an Hot Water System Differential Pressure Setpoint
When the fans are stopped, the FMS shall position the dampers to their normal state. alarm. The FMS shall automatically start the standby fan if a failure is detected in the lead fan. The FMS shall reset the system differential pressure setpoint using a trim and respond logic within the range of 5 psig to 20 psig once the maximum hot
water temperature setpoint is reached. Once the temperature setpoint is reached, the differential pressure setpoint for the controlling zone shall be trimmed
Duct Pressure Safety Switches Exhaust Fan LEF-2 Isolation Damper by 0.1 psig every two minutes until a valve in the system is 50% open. When a valve in the system rises to 80% open, the differential pressure setpoint for
Safety switches installed in the supply and return air ducts for each unit shall alarm the FMS if the duct pressure is above the high alarm setpoint. The Each damper shall be open anytime the associated exhaust fan is operating. The FMS shall monitor the open and closed status of the damper through damper actuator the controlling zone shall be increased by 0.1 psig every two minutes. All setpoints shall be adjustable through the operator workstation for each differential
high alarm setpoint shall be 150% of the normal operating static of the system. If the FMS senses an alarm condition, the FMS shall stop the supply and end switches. If a damper failure is detected, the FMS shall initiate an alarm. If the damper fails in the closed position the FMS shall stop the associated pressure sensor.
return fans. exhaust fan and start the next fan in the sequence.
Hot Water Pump Control
Hot Water Coil Pump Annex Air Handling Units AHU-4 & AHU-5 The hot water pumps shall operate in a lead/standby configuration. The lead pump shall operate anytime the hot water system is enabled. The pump shall
The FMS shall operate the pump anytime the outside air is below 35°F (adjustable) when the air handlin g unit is operating. The FMS shall monitor the modulate to maintain the system differential pressure at setpoint for the controlling zone. The controlling zone shall be the differential pressure sensor which
status of the pump through a current switch installed on the motor. If a pump failure is detected, the FMS shall initiate an alarm. Mixed Air Damper Interlocks is furthest below its setpoint.
Control signals from the FMS system shall modulate the mixed air dampers. Upon initial start-up, the FMS system will not begin modulation of the mixing
East Basement Built Up Air Handling Units AHU-2/ LEF-1 dampers for five minutes (adjustable) to allow the control loops to stabilize. Hot Water Pump Rotation
Manual or automatic rotation of the pumps shall be allowed. Rotation time interval shall be 30 days (adjustable). The application shall also provide a setting
Outside Air Lab Make-Up Damper
The damper shall be open anytime the air handling unit is operating. The FMS shall monitor the position of the damper through damper actuator
Mixed Air Damper Control
The FMS system shall modulate the mixed air dampers to maintain the supply air temperature at set point. Whenever the outside air temperature is greater than
(operator selectable) to allow a forced rotation which shall cause the pumps to be immediately enabled /disabled.
Construction
position sensor. If a damper failure is detected, the FMS shall initiate an alarm. If the damper fails in the closed position the FMS shall stop the supply the return air temperature and mechanical cooling is required, the mixed air dampers shall be in their normal position (full return air with minimum outside Hot Water Pump Failure Detection and Recovery
fans. air). When the air handling unit is stopped, the FMS shall close all outside air dampers and the relief damper and open the return air damper. The FMS shall monitor the status of each pump through a set of contacts in the VFD. Upon sensing a pump failure, the FMS shall lockout that pump and
immediately initiate the start of the next pump in the rotation sequence. When a pump is marked as having failed, the failed pump shall be taken out of the
Documents
Mixed Air Damper Control Minimum Outside Air Control rotation.
The FMS system shall modulate the mixed air dampers to maintain the supply air temperature at set point. Whenever the outside air temperature is The minimum outside air volume shall be controlled by the FMS through a damper position setpoint set by the test and balance contractor and programmed into the
greater than the return air temperature and mechanical cooling is required, the FMS shall operate in a return air mode. The FMS shall modulate the FMS. The FMS shall not modulate the outside air damper below minimum outside air position setpoint. Hot Water Pump Failure Reset
mixed air dampers to control the return airflow to match the total supply airflow of the terminal units in the non-laboratory spaces minus an adjustable When an individual pumps failure is reset at the operator workstation, the FMS shall re-insert that pump into the rotation of pumps. All failures shall be reset
offset for building pressure. When the air handling unit is stopped, the FMS shall close all outside air dampers and the relief damper and open the Supply Air Temperature Setpoint Control through the FMS operator workstation.
return air damper. The FMS shall control the air handling unit to maintain an adjustable supply air temperature setpoint. The temperature setpoint shall be reset from 55°F
(adjustable) to 95°F (adjustable) based on the dema nd of the space to maintain the space temperature at setpoint. Minimum Hot Water Flow Control
Supply Air Temperature Setpoint Control The FMS shall modulate the hot water system bypass valve to maintain the flow in the system. When the lead hot water pump modulates back to the
The FMS shall control the air handling unit to maintain an adjustable supply air temperature setpoint. The temperature setpoint shall be reset from 55°F Supply Air Temperature Control minimum speed setpoint, the FMS shall bypass valve to maintain the differential pressure for the system at setpoint.
(adjustable) to 75°F (adjustable) based on the dema nd of the terminal units and laboratory control air valves served by it so that at least one unit is in The FMS shall modulate the hot water coil valve and chilled water coil valve to maintain the supply air temperature setpoint. The FMS shall prevent simultaneous
full cooling and still maintaining the room temperature setpoint. heating and cooling. Domestic Hot Water Pump

Supply Air Static Setpoint Control Supply Fan Control The FMS shall operate the pump based on an occupancy schedule programmed into the FMS. The pump shall operate continuously during occupied
The FMS shall reset the static pressure setpoint using a trim and respond logic within the range of 0.5” w.g. to 1.5” w.g. When the fan is off, the setpoint The supply fan VFD shall be started and stopped by the FMS system based on an occupancy schedule for the space programmed into the FMS. The fan shall operate periods. The FMS shall monitor the status of the pump through a current switch installed on the motor. If a pump failure is detected, the FMS shall initiate an
shall be 1.0” w.g. Once the fan is started, the setpoint shall be trimmed by 0.04” w.g. every two minutes if there are two or fewer zone pressure requests. continuously during occupied periods. If during unoccupied periods, the space temperatures rise above the unoccupied cooling setpoint or falls below the unoccupied alarm.
If there are more than two zone pressure requests, respond by increasing the setpoint by 0.06” w.g. A zone pressure request is generated when a VAV heating setpoint, the air handling unit shall start and operate to change the space temperature 2°F (a djustable) before stopping. If during unoccupied periods, the
damper or air valve is greater than 95% open until it drops to 80% open or based on pressure request signal from the air valve. All setpoints shall be space occupancy switches is activated, the air handling unit shall start and operate for a period of two hours before stopping. Building Systems Monitoring
adjustable through the operator workstation.
B Supply Fan VFD Control The FMS shall monitor the alarm conditions for the following building equipment from a set of contacts in the packaged equipment control panels. If an alarm B
Heat Recovery Coil Pump Control The VFD shall be modulated as a second stage of heating or cooling in the space when the valves are fully open. The ramp of the VFD’s shall be adjusted to restrict condition is detected, the FMS shall initiate an alarm.
The FMS shall operate the heat recovery pump anytime the outside air temperature is 10°F (adjustable) below the supply air temperature setpoint for the rate of change of the VFD output to sixty seconds for a zero to one hundred percent control signal change. 1. Reverse Osmosis Generator
the air handling unit or is above exhaust air temperature when the air handling unit is operating. The FMS shall modulate the heat recovery coil valve to 2. Deionized Water Pressure Booster Pump
maintain the supply air temperature at setpoint. If the exhaust air temperature leaving the heat recovery coil falls below 38°F (adjustable), the FMS sh all Supply Fan Monitoring 3. Lab Air Compressed Air System
switch control of the heat recovery coil valve to maintain the exhaust discharge temperature above 38°F (adjustable), to prevent the coil from freezing. The VFD operation shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall stop the unit and initiate an 4. Lab Vacuum System
alarm. 5. Sump Pumps
Heat Recovery Coil Pump Monitoring 6. Sewage Ejectors
The FMS shall monitor the status of the pump through a current switch installed on the motor. If a failure occurs, the FMS shall stop the pump and Filter Monitoring 7. Glycol Fill Systems
initiate an alarm. The differential pressure across the filters shall be monitored by the FMS through a differential pressure transmitter. If the differential pressure exceeds set
point, the FMS shall initiate an alarm. Typical Split System
Supply Air Temperature Control
D:\Revit 2015\Projects\7168 MEP-JETT HALL_PZPHARES.rvt

The FMS shall modulate the hot water coil valve and chilled water coil valve to maintain the supply air temperature setpoint. The FMS shall prevent Freezestat Each unit shall be provided with a factory packaged control system which shall control the unit to maintain the space temperature at setpoint. The FMS shall
simultaneous heating and cooling. A freezestat set at 35°F located downstream of the hot water coil shall initiate an alarm at the FMS and stop the supply fan if an alarm condition is detected. monitor the space temperature through a separate space temperature sensor and shall initiate an alarm if the space temperature rises above the space high
temperature alarm setpoint.
Supply Fan Control General Exhaust Fans
The supply fan VFD’s shall be started and stopped by the FMS system. The fans shall operate continuously. Chilled Water Fan Coil Unit
Exhaust Fan Control
Supply Fan VFD Control Each fan shall operate based on the occupancy schedule in the FMS. The fan shall operate continuously during occupied periods. The fan coil unit shall modulate the chilled water to maintain the space temperature at a cooling setpoint of 76 °F (adjustable). The fan shall only ope rate
The VFD’s shall be modulated together to maintain the supply duct static pressure at setpoint for the duct static pressure sensor which is farthest below when cooling is needed by the space. The FMS shall monitor the status of the fan through a current switch. If a fan failure is detected, the FMS shall initiate
setpoint. The ramp of the VFD’s shall be adjusted to restrict the rate of change of the VFD output to sixty seconds for a zero to one hundred percent Exhaust Fan Monitoring an alarm.
control signal change. The fan operation shall be indicated to the FMS through a current switch installed in the motor starter. If a fan failure is detected, the FMS shall stop the fan and
initiate an alarm. Chilled Water & Hot Water Fan Coil Unit
Supply Fan Monitoring
The VFD’s operations shall be indicated to the FMS through sets of contacts in the VFD’s. If an alarm condition is detected, the FMS shall initiate an Exhaust Fan Isolation Damper Control The fan coil unit shall modulate the chilled water and hot water valves to maintain the space temperature at a cooling setpoint of 76 °F (adjustable) and a
alarm. Each exhaust fan damper shall be open anytime the fan is operating. If the fan is stopped, the damper shall close. heating setpoint of 72 °F (adjustable). The fan sh all only operate when cooling or heating is needed by the space. The FMS shall monitor the status of the
fan through a current switch. If a fan failure is detected, the FMS shall initiate an alarm.
Filter Monitoring
The differential pressure across the filters shall be monitored by the FMS through a differential pressure transmitter. If the differential pressure exceeds
set point, the FMS shall initiate an alarm.

Freezestat
A freezestat set at 35°F located downstream of the hot water coil shall initiate an alarm at the FMS and stop the supply fan if an alarm conditionis
detected. Mark Date Description
Smoke Detectors Date September 11, 2015
Smoke detectors located in the supply air air streams, shall stop the fans through the fire alarm system if an alarm condition is detected. When the fans
are stopped, the FMS shall position the dampers to their normal state. Project Number 14400
Drawn By SDB
Duct Pressure Safety Switches
A Safety switches installed in the supply and exhaust air ducts for each unit shall alarm the FMS if the duct pressure is above the high alarm setpoint. The A Checked By IM
high alarm setpoint shall be 150% of the normal operating static of the system. If the FMS senses an alarm condition, the FMS shall stop the supply and
exhaust fans. Copyright © VAN H. GILBERT ARCHITECT PC

SHEET TITLE

MECHANICAL DIAGRAMS
9/15/2015 6:42:28 PM

(CONTROLS)

MI-607
1 2 3 4 5 6 SHEET 143 OF 187