IV. EMBANKMENT:
QUANTITY: 47.48 cu. m.
● Embankment Materials 47.48 lgths P 350.00 P 16,618.00
TOTAL MATERIALS COST P 16,618.00
LABOR COST P 5,816.30
SUB-TOTAL P 22,434.30
CONTINGENCIES / MISCELLANEOUS P 2,243.45
SUPERVISION P
TOTAL COST P 24,677.75
X. CEILING WORKS:
QUANTITY: 314.96 sq. m.
● Pre-Painted Coloroof Spandrel, 0.40 mm. Thk. 57.6 sq. m. P 400.00 P 23,040.00
● Hardiflex Board, 4.5 mm. Thk. x 4 ft. x 8 ft. (Lite) 80 shts P 380.00 P 30,400.00
● Carrying Channel, 0.8 mm. x 5.00 m. 218 pcs P 140.00 P 30,520.00
● Double Furring Channel, 0.4 mm. x 5.00 m. 218 pcs P 130.00 P 28,340.00
● Single Furring Channel, 0.5 mm. x 5.00 m. 218 pcs P 110.00 P 23,980.00
● Double Furring Clip 1,530 pcs P 6.00 P 9,180.00
● Hardflex Board Screw 18,897 pcs P 1.00 P 18,897.00
● Blind Rivets, 1/8" Dia. x 1/2" (1,000 Pcs/Pack) 8 packs P 380.00 P 3,040.00
● Screw with Tox 1093 pcs P 3.50 P 3,825.50
TOTAL MATERIALS COST P 171,222.50
LABOR COST P 68,777.50
EQUIPMENT EXPENSES:
● 1 - Electrical Drill 30 days P 300.00 P 9,000.00
● 1 - Electrical Grinder 10 days P 300.00 P 3,000.00
SUB-TOTAL P 252,000.00
CONTINGENCIES / MISCELLANEOUS P 25,200.00
SUPERVISION P
TOTAL COST P 277,200.00
XVI. SUPPLY AND INSTALLATION OF STAINLES STEEL RAILINGS: (BALCONY AND STAIRS)
QUANTITY: 20.52 linear meters
● 2" Dia. Stainless Steel Tube, Top Rail and 3 - 1" Dia. 20.52 l.m. P 4,000.00 P 82,080.00
Stainless Steel Tube Center Rails with 1 1/2" Stainless
Steel Square Tube, Vertical Posts Spaced Equally
TOTAL MATERIALS COST P 82,080.00
LABOR COST P
SUB-TOTAL P 82,080.00
CONTINGENCIES / MISCELLANEOUS P 8,208.00
SUPERVISION P
TOTAL COST P 90,288.00