No. Title Descriptions
1 Hazards Present 1. The objective of this instruction is to implement safe work related to rentice clearing.
1. The scope of work shall be for a complete design (except for design of tower), manufacture, supply, erect,
testing and commissioning of double circuit of the 500kV overhead line from Point Y to Bentong South
2 PPE or Devices Required Substation.
2. To achieve a safe working environment for personnel involved in rentice clearing in accordance with the
OSHA 1994 and FMA 1986
1. Occupational Safety and Health Act 514 of 1994
3 Training Required 2. Factories and Machinery (BOWEC) (Safety) Regulations 1986 .
3. Environment Quality Act and Regulation 1974
4 Definitions 1. N/A
1. Ensure that resources are available to accomplish the task safely and that the work is performed accordingly
Project Manager
to the company’s Safety & Health Management System.
Project Engineer 1. Obtain Permit to Work (PTW). If necessary.
2. Client’s requirement to be followed.
Safety & Health Officer 3. Ensure the ground level is even and firm.
5 Responsibility Site Supervisor 4. To be caution of any traffic
5. Check machinery before used
Subcontractor 6. Conduct briefing prior to start work.
1. Ensure the tools and equipment in good working condition.
Worker 2. Wear safety helmet, safety shoes and gloves.
3. Ensure chain saw / knife is protected
SAFETY & HEALTH MANUAL
CONTRACT NO. : PROJECT CODE : REVISION DATE :
TNB 266/2015 PJ 86/2015 Rev. #0 Date: 01.04.2016
PROPOSED 500kV DOUBLE CIRCUIT TRANSMISSION LINES FROM
AYER TAWAR TO BENTONG SOUTH [ POINT Y (BORDER
SELANGOR/PAHANG) TO PMU BENTONG SOUTH]

Risk involved:

1. Lost in the middle of jungle


2. Machinery topple
3. Insect bites (mosquitoes, bees, etc)
4. Wild animals treat (snake, tiger, etc)
5. Shortage of meal and drinking water if lost in the jungle
6 Safe Work Procedure Risk control:

1. Team leader must have the knowledge on how to use compass.


2. Ensure the ground level is even and firm.
3. Always planned ahead before start work.
4. Take special medication (to avoid infection) by mosquito's bites etc.
5. Always drink enough water
6. Wear bright reflective safety coat when working alongside heavy roadside or highways.

S-ar putea să vă placă și