Documente Academic
Documente Profesional
Documente Cultură
Abstract—The interest in power quality has been increased depending on the sag duration, type, and its impact [5]. The
in the last decade. Uninterruptible Power Supplies (UPS’s) are impact could be stoppage of manufacturing process, shutdown
designed to feed emergency power when the main power source of sensitive equipment’s, etc. To resolve such type of power
fails. To avoid this impact and to protect effectively the sensitive quality problems like sag, swell and interruptions to save
loads, one solution is to provide a redundant loading system costly equipment from damage in economical way and not to
using a dual power energy source other than the UPS to achieve let them stoppage of the process running in an industry needs
an automatic static transfer when necessary. In this work, an some fast switching technologies to switch the critical loads
additional module has been designed and connected between a to some backup power source.
critical load and the output of two independent UPS systems; if
primary UPS fails, the module automatically transfers the load
to the other one with a minimum transfer switching time. The
results presented demonstrate a transfer switch time below 3 II. CAUSES OF POWER QUALITY DISTURBANCE
ms, compared to commercial products of 4 to 6 ms. Faults that occur on the same feeder, parallel feeder,
Keywords—switching, STS, triacs, Faults, transfer time
starting of heavy loads, switching on and off large capacitor
banks, lightning, etc[6][7]. All these disturb power quality at
I. INTRODUCTION the utility side as well as at the customer end.
In the modern power system, the role of distribution A. Faults on Parallel Feeders
system is significant. If any kind of fault occurs on distribution When faults occur on parallel feeders, the customer end
network like sag, swell and interruptions it will affect the voltage can be calculated by calculating the voltage level at
connected customers to that network. The interest in power
the substation end. The magnitude of the voltage at the
quality has been increased in the last decade. Power quality is
substation depends upon the location and fault impedance.
actually the measurement of variation in power if variation is
Voltage for a specific sensitive load can be computed as
less at the customer end it means power is of good quality, and
follows:
if the variation is more at customer end it means power is of
bad [1] quality. 𝐸𝑝𝑎𝑟𝑎𝑙𝑙𝑒𝑙 (𝑉𝑠 ) = 𝐴1 × 𝐷𝑝1 + 𝐴3 × 𝐷𝑝3
In order to minimize these power quality problems, one Where A1 and A3 give data about faults performance that
way is to use fast switching technology. The duration of this occur in miles per month when three phase and single line to
type of faults is usually less than 100ms.In this research work ground faults occur, and Dp1 and Dp3 are the total exposed
a broad concept about fast switching technology, constraints, distance to these faults on parallel feeders which cause voltage
and their problems will be developed. On the basis of these sag whose value is less than the minimum required voltage Vs
studies fast switching system will be developed for a load to at the customer end.
transfer the load to an alternate source almost in 3 ms by using
a static transfer switch (STS) to avoid different types of short B. Faults occur on the same Feeder
duration faults and to improve the power quality of the When a fault occurs on same feeder the voltage sag
sensitive equipment’s. magnitude at the customer can be calculated as a function of
fault [3] location on the same feeder.
Voltage sag and interruptions have bad impact on large
industries due to suffering of critical and cause significant For specific equipment, the voltage sag performance with
financial loss. During manufacturing, [2] [8]those industries ride-through voltage Vs is calculated as follows:
in which production is automated in lines, a few cycles of
voltage sag can stop or interrupt the whole production line and 𝐸𝑠𝑎𝑚𝑒 (𝑉𝑠 ) = 𝐴1 × 𝐷𝑠1 + 𝐴3 × 𝐷𝑠3
result significant loss. Due to voltage sags and interruption Where Ds1 and Ds3 are the total circuit miles of exposure to
different utilities and customers facing financial loss a single line to ground fault and three lines to ground fault that
Figure 6