Sub: Construction of [xtra-dosed RCC Bridge including viaduct and approaches over river Feni at Sabroom
on lndo-Bangladesh Border on NH'8 in the state of Tripura on EPC mode
"Ree. Submlssion of Chane.e of Scope (COSI items under clause-13,,1
Ref:
With reference the above mentioned subject, Contracto/s letter No. DRtpLlNHtDCLlplTl0oT/So/297
Dated 29106/2079 and Clause no. 13.2.2 of Contract Agreement, we have submit the Change of Scope
{COS) items but There are some Typing Mistakes.
1"- The Change of Scope shall be done during construction period and shall be complete in 9 (Nine)
months from date of "Change of Scope Ordef'
Corrected - The Change of Scope shall be done during construction period and shall be complete in 12
(Twelve) nronths from date of "Change of Scope Order"
The Change Scope {COS} shall be complete in the 9 months, therefor it is expected that extended date
-of completion (October 2}2ol.
-
Corrected - The Change of Scope {COS) shall be complete in the 12 months, therefor it is expected that
extended date of completion (October 2020).
--