Sunteți pe pagina 1din 6

Method of Measurement for

Road Works - General


Principles

CC-RMP-00053
March 2011

Construction &
CC Commissioning Standards
TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS

About TII

Transport Infrastructure Ireland (TII) is responsible for managing and improving the country’s
national road and light rail networks.

About TII Publications

TII maintains an online suite of technical publications, which is managed through the TII
Publications website. The contents of TII Publications is clearly split into ‘Standards’ and
‘Technical’ documentation. All documentation for implementation on TII schemes is collectively
referred to as TII Publications (Standards), and all other documentation within the system is
collectively referred to as TII Publications (Technical). This system replaces the NRA Design
Manual for Roads and Bridges (NRA DMRB) and the NRA Manual of Contract Documents for
Road Works (NRA MCDRW).

Document Attributes

Each document within TII Publications has a range of attributes associated with it, which allows
for efficient access and retrieval of the document from the website. These attributes are also
contained on the inside cover of each current document, for reference. For migration of
documents from the NRA and RPA to the new system, each current document was assigned with
new outer front and rear covers. Apart from the covers, and inside cover pages, the documents
contain the same information as previously within the NRA or RPA systems, including historical
references such as those contained within NRA DMRB and NRA MCDRW.

Document Attributes

TII Publication Title Method of Measurement for Road Works - General Principles
TII Publication
CC-RMP-00053
Number

Activity Construction & Standards


Document Set
Commissioning (CC)
Stream Requirements for Measuring Publication Date March 2011
and Pricing (RMP)
Document 00053 Historical MM Principles
Number Reference

NRA DMRB and MCDRW References

For all documents that existed within the NRA DMRB or the NRA MCDRW prior to the launch of
TII Publications, the NRA document reference used previously is listed above under ‘historical
reference’. The TII Publication Number also shown above now supersedes this historical
reference. All historical references within this document are deemed to be replaced by the TII
Publication Number. For the equivalent TII Publication Number for all other historical
references contained within this document, please refer to the TII Publications website.
MANUAL OF CONTRACT DOCUMENTS FOR ROAD WORKS: VOLUME 3
SECTION 1: METHOD OF MEASUREMENT FOR ROAD WORKS

Chapter II

General Principles

March 2011 1
Volume 3 – Section 1 Chapter II
Method of Measurement for Road Works General Principles

General Principles
Method of Measurement 1 (a) The Method of Measurement is intended for use for road
contracts based on the Public Works Contract for Civil
Engineering Works Designed by the Employer or the
Public Works Contract for Minor Building and Civil
Engineering Works Designed by the Employer.

(b) The Method of Measurement is based on the Specification for Road


Works and the NRA Road Construction Details and on the principle
that full details of construction requirements are provided in the
Contract. Additions or amendments to the Specification for Road
Works or the NRA Road Construction Details which are not
adequately covered by the Method of Measurement will necessitate
appropriate amendment to suit. Provision is made in Chapter III
Preambles to Bill of Quantities, “Amendments to the Method of
Measurement” to accommodate such amendments.

Bill of Quantities 2 In the Bill of Quantities the sub-headings and item descriptions identify
the work covered by the respective items read in conjunction with the
matters listed against the relevant marginal headings “Item coverage” in
Chapter IV of the Method of Measurement, Chapter III Preambles to Bill
of Quantities and amendments. The nature and extent of the work to be
performed is to be ascertained by reference to the Works
Requirements and Contract Conditions.

Itemisation – Groups 3 Each item description is to be consistent with and be compounded from
and Features one or more of the Groups listed under the marginal headings
“Itemisation” within the Series of Chapter IV of the Method of
Measurement incorporating amendments introduced in the Preambles to
the Bill of Quantities. An item description may contain Features from as
many Groups as necessary to identify the work required, but may include
only one Feature from any one Group.

Items in the Bill of 4 The Bill of Quantities, unless expressly stated otherwise in the Contract
Quantities is to contain all those items compounded in accordance with the foregoing
paragraph 3 required to comprise the Works.

March 2011 1
Ionad Ghnó Gheata na
Páirce,
www.tii.ie +353 (01) 646 3600
Stráid Gheata na Páirce,
Baile Átha Cliath 8, Éire

Parkgate Business Centre,


Parkgate Street, info@tii.ie +353 (01) 646 3601
Dublin 8, Ireland

S-ar putea să vă placă și