PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Formworks

Table of Contents
1- Purpose ………………………………………………. 3
2- Scope of Work ………………………………………………. 3
3- References ………………………………………………. 3
4- Resources ……………………………………………..... 3
5- Work Methodology ……………………………………..... 4
6- Responsibility and Supervision ……………………………..... 5
7- Health and Safety ……………………………………..... 6
8- Quality Assurance ……………………………………..... 7

Page 2
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Formworks

1- PURPOSE

The purpose of this method statement is to cover the requirements and methodology for
Concrete Formworks for the buildings, including materials, tools and equipment, health
and safety requirements, quality assurance and all other related works.

2- SCOPE OF WORK

This method statement is applicable to all buildings of Border Stations D14, Sector
Headquarters D15, Border Compounds D15p and Rear Gates.

3- REFERENCES

1. Approved Drawing
2. Approved QA/QC Documents
3. Approved Formwork Shop Drawings and Calculation

4- RESOURCES

4.1 Materials 4.2 Equipments 4.3 Personnel


- Steel Form (if needed) - Crane - Project Engineer
- Timber - Lorry - QA/QC Engineer
- Plywood - Survey Equipments - Safety Officer
- Nails - Minor Tools - Construction Supervisor
- Scaffolding - Surveyor
- Frame / Accessories - Skilled Worker / Operator
- Form Release Agent - Unskilled Worker
- Wedges

Page 3
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Formworks

5- WORK METHODOLOGY

5. 1 Constructing the formworks

Preparations

a. Obtain relevant approved drawings.


b. Set out the locations, centre lines and levels for formwork along with reference lines.
c. Prepare necessary formwork panels to the required dimensions and sizes.
d. Coat formwork surface evenly and thinly with approved release agent.

Execution

a. Construct the forms according to setting points and reference lines by providing
sufficient shoring, props and struts including necessary bracing.
b. Use scaffolding and staging arrangements, where necessary.
c. Seal gaps with appropriate material (tape) to avoid leakage of grout.
d. Ensure checking for the required shape and dimensions as per drawings.
e. Submit Request for Inspection Form for joint inspection with consultant using Concrete
Formworks Checklist.
f. On completion of joint inspection, request consultant to sign on the checklist and file as
per Project Filing Index.

5. 2 Stripping and Reshoring of formworks

Preparations

a. Obtain compressive test reports of on-site cured concrete samples to represent the
developmental strength of the concrete structures involved for stripping.
b. Seek approval to remove formworks based on the minimum strength requirement or by
elapsed time after placement of concrete as specified by the consultant.
c. Obtain approval of stripping sequence and reshoring layout before beginning to start
the operations.
d. Provide barricade and warning signs on the perimeter of the area where stripping and
reshoring will take place.

Page 4
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Formworks

Execution

a. Start removing forms and shoring following the sequence of stripping and reshoring as
per approval of the Consultant.
b. Take care in removing the forms as not to damage the concrete surfaces as well as the
forms for future use.
c. Install shores based on the approved layout of reshorings. Use preshores whenever
necessary. Install additional shores when circumstances required.
d. Store removed formworks and excess shoring on a safe provided area or an area away
from obstructing the progress of other construction works.

6- RESPONSIBILITY AND SUPERVISION

6. 1 Project Engineer

a. Responsible for controlling all civil activities and overall coordination.


b. Ensure that adequate facilities and equipment are provided to the work to avoid injury,
health impairment or damage and to ensure providing quality works within the planned
time frame.
c. Organize the site so that work is carried out in accordance with the specifications with a
minimum risk to men, equipment and materials.

6. 1 QA/QC Engineer

a. Responsible for work entire quality assurance, quality control and inspection programs.
b. Witness the inspections, sampling, and testing of materials.
c. Review and issue the test results the day after test completion.
d. Produce all quality related documents and reports as necessary.
e. Provide written procedures and method statements in coordination with the project
manager describe the job specific work for each stages / activities.
f. Review tests results for all quality control matters.

6. 2 Safety Officer

a. Ensure that all workers have a safe place of work, advice safe system of work and provide
adequate instructions, training and supervision to enable employees to work in safety.
b. Provide instructions to establish safe working methods outline potential hazards at each
stage and indicate precautions to be adopted.
c. Carry out site survey on daily basis to ensure that the HSE methods of working are in
operation and that all regulations are being observed.

Page 5
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Formworks

d. Report, determine and analyze the cause of any accident or dangerous occurrence and
recommend measures for preventing recurrence.

6. 3 Construction Supervisors

a. Adheres to the project specific method statements, procedures, inspection programs and
HSE instructions to get the activities performed as required.

6. 4 Surveyors

a. Ensure that setting out points, levels, and plumb relevant to approved drawings and
reference points.

7- HEALTH AND SAFETY

1. Protective and Safety Equipment

a. Safety Shoes
b. Safety Helmets
c. Safety Glasses
d. Hand Gloves (as required)
e. Dust Masks (as required).

2. Information to Personnel

A pre task briefing will be carried out detailing the following information:
a. Tasks assigned to each personnel
b. Traffic Management / Safety
c. What to do in the event of a first aid injury or other incident
d. Heat stress advice / warning.

Page 6
Sub-
: ‫اﻟﻣﺎﻟك‬ : CONSULTANT / ‫اﻻﺳﺗﺷﺎري‬ : CONTRACTOR / ‫اﻟﻣﻘﺎول‬

‫وزارة اﻟداﺧﻠﯾﺔ‬

‫وﻛﺎﻟﺔ اﻟوزارة ﻟﻠﺗﺧطﯾط واﻟﺗطوﯾر اﻷﻣﻧﻲ‬

PROJECT NO / 1370 PROJECT NAME: South Border Infrastructure Project (Roads and Buildings)
Method Statement for Concrete Formworks

3. Emergency Procedures

In the event of an accident or incident, the following procedure shall be followed:


a. Immediately send first aider to the scene.
b. Stop all other activities in the vicinity.
c. Remove or isolate any immediate dangers ONLY if safe to do so.
d. Inform the emergency services regarding the location, type and nature of the incident including
casualty details.
e. Cordon the area to prevent the scene being further disturbed (to aid investigation).
f. Give assistance as requested to the emergency services.
g. Photograph the scene.
h. Take statements from witnesses.
i. Carry out incident investigation.

8- Quality Assurance:

8. 1 Critical Works

a. Ensure that setting out and survey works are done in accordance with the relevant
drawings, utilizing survey instruments having valid calibration certificates.
b. Ensure that concrete protective cover is attained using concrete spacer.
c. Ensure that all electrical, plumbing and mechanical items are completely installed and
inspected according to specifications and relevant drawings before commencement of
concrete pouring.

8. 2 Inspection & Testing

a. Refer to the inspection and test plan.