ID Task WBS Task Name Duration Start Finish Predecessors Resource Names

22 Dec '13 05 Jan '14 19 Jan '14 02 Feb '14 16 Feb '14 02 Mar '1416 Mar '1430 Mar '1413 Apr '14 27 Apr '14 11 May '1425 May '14
Mode F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
1 1 RED EAGLE MINING - DFS PROPOSAL - 90 days Mon Fri 16/05/14
HIGH LEVEL SCHEDULE 13/01/14
2 1.1 KICK-OFF MEETING 0 days Mon 13/01/14Mon 13/01/14 REM/GOLDER 13/01
3 1.2 GEOTECHNICAL FIELD SUPERVISION 25 days Mon Fri 14/02/14
AND FIELD DATA GATHERING 13/01/14
4 1.2.1 Drillers On Site and ready to start 0 days Mon 13/01/14Mon 13/01/14 REM 13/01
5 1.2.2 Geotechnical Field Supervision And 20 days Mon Fri 07/02/14 4,2 GOLDER GOLDER
Field Data Gathering 13/01/14
6 1.2.3 Draft Technical Memorandum issuance0 days Fri 07/02/14 Fri 07/02/14 5 GOLDER 07/02

7 1.2.4 Logs issuance 0 days Fri 07/02/14 Fri 07/02/14 5 GOLDER 07/02
8 1.2.5 Deliverable Feedback Meeting 0 days Fri 14/02/14 Fri 14/02/14 6FS+5 days,7FS+5
REM/GOLDER
days 14/02
9 1.3 TAILINGS AND ROCK MANAGEMENT 25 days Mon Fri 28/03/14
PLAN 24/02/14
10 1.3.1 Tailings And Rock Management Plan 20 days Mon 24/02/14Fri 21/03/14 8FS+5 days
11 1.3.2 Draft Drawing Set issuance 0 days Fri 21/03/14 Fri 21/03/14 10 GOLDER 21/03
12 1.3.3 Draft Report issuance 0 days Fri 21/03/14 Fri 21/03/14 10 GOLDER 21/03
13 1.3.4 Deliverable Feedback Meeting 0 days Fri 28/03/14 Fri 28/03/14 11FS+5 days,12FS+5 days 28/03
14 1.4 PLANT SITE GEOTECHNICAL 15 days Mon Fri 14/03/14
ASSESSMENT AND FOUNDATION 24/02/14
DESIGN
15 1.4.1 PLANT SITE GEOTECHNICAL 10 days Mon Fri 07/03/14 8FS+5 days
ASSESSMENT AND FOUNDATION 24/02/14
DESIGN
16 1.4.2 Draft Drawing Set issuance 0 days Fri 07/03/14 Fri 07/03/14 15 GOLDER 07/03
17 1.4.3 Draft Report issuance 0 days Fri 07/03/14 Fri 07/03/14 15 GOLDER 07/03
18 1.4.4 Deliverable Feedback Meeting 0 days Fri 14/03/14 Fri 14/03/14 16FS+5 days,17FS+5 days 14/03
19 1.5 PORTAL ACCESS DESIGN (OPTIONAL) 15 days Mon 24/02/14Fri 14/03/14
20 1.5.1 PORTAL ACCESS DESIGN (OPTIONAL) 10 days Mon 24/02/14Fri 07/03/14 8FS+5 days
21 1.5.2 Draft Drawing Set issuance 0 days Fri 07/03/14 Fri 07/03/14 20 GOLDER 07/03
22 1.5.3 Draft Report issuance 0 days Fri 07/03/14 Fri 07/03/14 20 GOLDER 07/03
23 1.5.4 Deliverable Feedback Meeting 0 days Fri 14/03/14 Fri 14/03/14 21FS+5 days,22FS+5 days 14/03
24 1.6 SITE WIDE WATER BALANCE 60 days Mon 13/01/14Fri 04/04/14
25 1.6.1 SWWB 55 days Mon 13/01/14Fri 28/03/14 2
26 1.6.2 Draft Report issuance 0 days Fri 28/03/14 Fri 28/03/14 25 GOLDER 28/03
27 1.6.3 Deliverable Feedback Meeting 0 days Fri 04/04/14 Fri 04/04/14 26FS+5 days 04/04
28 1.7 PROJECT MANAGEMENT AND CONTROL 90 days Mon 13/01/14Fri 16/05/14 GOLDER GOLDER
29 1.8 MATERIAL QUANTITY TAKE-OFFS 10 days Mon 07/04/14Fri 18/04/14
30 1.8.1 MTOs 5 days Mon 07/04/14Fri 11/04/14 9,14,19,24
31 1.8.2 Draft Report issuance 0 days Fri 11/04/14 Fri 11/04/14 30 GOLDER 11/04
32 1.8.3 Deliverable Feedback Meeting 0 days Fri 18/04/14 Fri 18/04/14 31FS+5 days 18/04

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Schedule rev A Split External Tasks Inactive Summary Manual Summary Progress
Date: Thu 26/12/13 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names
22 Dec '13 05 Jan '14 19 Jan '14 02 Feb '14 16 Feb '14 02 Mar '1416 Mar '1430 Mar '1413 Apr '14 27 Apr '14 11 May '1425 May '14
Mode F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
33 1.9 FINAL EXCEC SUMMARY 20 days Mon 21/04/14Fri 16/05/14
34 1.9.1 FINAL EXCEC SUMMARY 15 days Mon 21/04/14Fri 09/05/14 29
35 1.9.2 Draft Report issuance 0 days Fri 09/05/14 Fri 09/05/14 34 GOLDER 09/05
36 1.9.3 Deliverable Feedback Meeting 0 days Fri 16/05/14 Fri 16/05/14 35FS+5 days 16/05

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Schedule rev A Split External Tasks Inactive Summary Manual Summary Progress
Date: Thu 26/12/13 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only