COAL RUN OFF AND ASH RUN OFF DESIGN BASIS

Timor-1
Coal Fired Steam Power Plant 2 X 50 MW
(Timor-1 CFSPP Project)

Consortium of
PT. IKPT - PT. PP (Persero) Tbk. - ITOCHU Corporation -
Sumitomo Heavy Industries, Ltd. - PT. Medco Power Indonesia
Date: CIVIL
Log
in
Comm No: MECH

ELECT
A ☐ APPROVED
I&C
REVIEW

SUPPPORT
B ☐ APPROVED AS
NOTED
GENERAL

PLN DOC. NO. :


C ☐ NOT APPROVED

PLN UIP NUSRA (HO) 1


I ☐ INFORMATION
PLN UPP TIMOR 1
CONTRACTOR DOC. NO. :
REVIEWED DOES NOT RELIEVE PLN PUSENLIS (JKT)
CONTRACTOR FROM RESPONSIBILITY
FOR ERROR OR DEVIATIONS FROM
JAYA CM (SITE)
T1_PP_000_PRS_DOC_001
DISTRIBUTION

CONTRACT REQUIREMENTS

CONTRACTOR (JKT) 1
By: Date:
CONTRACTOR
(SITE)
CONTRACT NO. :
Log Date: 0389.PJ/DAN.02.01/010000/2019
out Comm No: Note:

0 2019-11-14 Issue for Approval


PREPAR CHECK APPROV AUTHORI
REV DATE PURPOSE OF ISSUE
ED ED ED ZED
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 2 of 8

REVISION HISTORY

REV. NO. DATE DESCRIPTION

0 2019/11/14 Issue for Approval


COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 3 of 8

TABLE OF CONTENT

1. INTRODUCTION .............................................................................................................. 4
2. GENERAL ......................................................................................................................... 4
3. PROJECT DESCRIPTION ................................................................................................ 4
4. SITE CONDITIONS .......................................................................................................... 4
4.1. Site Location ..............................................................................................................4
4.2. Site Condition.............................................................................................................4
5. ENVIRONMENTAL DATA ................................................................................................ 5
5.1. General Climate Condition .........................................................................................5
5.2. Design Condition ........................................................................................................6
6. CODES AND STANDARD ................................................................................................ 7
7. PROCESS DESIGN BASIS OF Coal and Ash Runoff Treatment ..................................... 7
7.1. The Parameter of Coal Runoff and Ash Runoff Water ...............................................7
7.2. Description of Coal Runoff and Ash Runoff Treatment ..............................................7
7.3. Block Flow Diagram & Process Flow Diagram of Coal and Ash Runoff Treatment ....8
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 4 of 8

1. INTRODUCTION
For fulfilling the electricity energy demand in Kupang, PT Perusahaan Listrik Negara (Persero) has
planned to build Timor-1 CFSPP (2 x 50 MW) for supplying the electric power for public use.
The Plant will consist of 2 units, having a minimum Net output of 2 x 50 MW and maximum Net Output
of 2 x (50 MW+10%).

The Plant to be built will be state of the art technology, functional and will designed as well as capable
of continuous, efficient and reliable operation with minimum maintenance under existing environmental
and operation with minimum maintenance under existing environmental and operation condition. All
equipment provided will be of simple robust and conservative design, with generous built in safety
factors and protective systems.

The Plant will be generated by using coal. The coal is transported by barge and unloaded to coal jetty
facilities, then conveyed and stocked to the coal storage area. The type of cooling system shall be once
through cooling using water from the sea.

2. GENERAL
The requirements specified below describe the general design, supply of equipment and materials,
and installation of the electrical system for TIMOR-1 CFSPP (2 x 50 MW) at Kupang, Nusa Tenggara
Timur Province, Indonesia.
3. PROJECT DESCRIPTION
The following words shall have the meaning indicated when used herein:
Owner : PT Perusahaan Listrik Negara (Persero)
Consultant PMC : PUSENLIS
Contractor : PT IKPT – PT PP (Persero), Tbk. – ITOCHU Corporation – Sumitomo
Heavy Industries, Ltd. – PT Medco Power Indonesia
Eng. Consultant : PT REKAYASA ENGINEERING

4. SITE CONDITIONS

4.1. Site Location


The Plant is located on Panaf Village, West Kupang Distric, Kupang Regency, Nusa Tenggara Timur
Province, with coordinates UTM zone 51L:550211 m e and 8855605 m S.

4.2. Site Condition


a. Site Plant
Site plant will be located in Kupang, the nearest airport is El Tari International Airport which can
reach about 1 (one) hour by road trip from the project site.
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 5 of 8

Figure 1. Site Plant


b. Topography
Condition of the location is varies from 0.00 m to +39.00 m LLWL. Topography area approximately
50 Ha.

c. Bathymetry
Bathymetry survey area that was conducted by Owner is approximately 36 Ha.

5. ENVIRONMENTAL DATA
5.1. General Climate Condition
Climatic conditions based on data from the project site Climatology Meteorology and Geophysics
Agency (BMKG) on Lasiana Station Kupang, within 10 (ten) years (2003 to 2012):
a. Relative Humidity
Relative humidity varies about 46% to 98% and manual average is about 76%.

b. Air Temperature
The annual average temperature is 27.30C
The maximum temperature is 31.70C
The minimum temperature is 22.70C

c. Wind
Dominant wind blows from East to West. Maximum wind speed 32.5 knot.

d. Atmospheric Pressure
Maximum : 1015.3 mm Bar.
Minimum : 998.9 mm Bar.
Average : 1009.4 mm Bar.
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 6 of 8

e. Evaporation
The annual average for evaporation is 5.8 mm/day.

f. Rainfall
Maximum (Year) 2385 mm
Maximum (Monthly Mean) 882 mm
Average Rain Fall (Yearly Mean) 1633 mm
Greatest Rainfall in a Day 203 mm
Rainy Season Month December until April

g. Wind rose Diagram


The wind rose diagram is attached for information only.

Figure 2. Wind Rose (BID document)

5.2. Design Condition


a. Design temperature 300C

b. Relative humidity
- Mean maximum 76%
- Design humidity 83%

c. Intensity of rainfall 203 mm

d. Design wind velocity 120 km/h


The design wind velocity shall be minimum 120 km/h and also the design wind load calculation shall
be referred to ASCE 7-10.

e. Design seismic force. Peak base acceleration


The design seismic calculation shall refer to the latest version of Indonesian Standard for Design
Guide Line of Seismic Restrain of Building and Non Building Construction (SNI).

f. Cooling water supply


The water for once through cooling water system will be sea water.
g. Sea water temperature
The sea water temperature site condition is 290C. Design point 300C
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 7 of 8

h. Sea water level


Design of HHWL +3.395 LLWL
Design of MSL +1.697 LLWL
Design of LLWL +0.00

i. Final ground level


- Jetty and CW pump house area +8.00 m LLWL
- Power plant area +15.00 m LLWL
- Ash yard area +20.00 m LLWL

j. Wind load
The design wind load calculation shall be referring to ANSI – A58.1 or “Peraturan Muatan
Indonesia (Indonesian Standard)”.

6. CODES AND STANDARD


All materials, equipment and installations shall be in accordance with the applicable portions of the latest
edition of the national and international standards and as per available standards in country of origin of
equipment.

American Standard Testing and Material for Open Channels


a. ASTM Cast Iron A126 Class B for Valve
b. ASTM A307 Gr B Carbon Steel for Nut, Stud, and Bolt

National Standard
The Regulation of Minister of Environment No.8 year 2009, Sheet II, point D.

7. PROCESS DESIGN BASIS OF Coal and Ash Runoff Treatment


7.1. Coal Runoff and Ash Runoff Water Specification
The quality of coal runoff and ash runoff water must be filled quality standard in the regulation of
minister of environment No.8 year 2009.

Table 1. Coal Stockpile Source


No Parameter Units Maximum

1 pH - 6-9

2 TSS mg/L 200

3 Fe mg/L 5

4 Mn mg/L 2

7.2. Description of Coal Runoff and Ash Runoff Treatment


Runoff water from Stockyard will be transport via open channels to coal runoff pond. After that, this
water will be transported to waste water treatment plant to fulfil the quality standard before reject
to the environment/sea. Ash runoff water also is treated similar with coal runoff treatment process.
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project

Issued 2019-11-14 Project Document No: T1-IK-000-PJM-PRC-0003 REV. 0 Page 8 of 8

7.3. Block Flow Diagram & Process Flow Diagram of Coal and Ash Runoff Treatment
The block flow diagram of Coal and Ash Runoff Treatment unit can be seen Figure 3.
Stockyard / Dead Coal Runoff
Coal Yard WWTP
Pond

Figure 3. Block Flow Diagram of Coal and Ash Runoff Treatment Unit