Documente Academic
Documente Profesional
Documente Cultură
Timor-1
Coal Fired Steam Power Plant 2 X 50 MW
(Timor-1 CFSPP Project)
Consortium of
PT. IKPT - PT. PP (Persero) Tbk. - ITOCHU Corporation -
Sumitomo Heavy Industries, Ltd. - PT. Medco Power Indonesia
Date: CIVIL
Log
in
Comm No: MECH
ELECT
A ☐ APPROVED
I&C
REVIEW
SUPPPORT
B ☐ APPROVED AS
NOTED
GENERAL
CONTRACT REQUIREMENTS
CONTRACTOR (JKT) 1
By: Date:
CONTRACTOR
(SITE)
CONTRACT NO. :
Log Date: 0389.PJ/DAN.02.01/010000/2019
out Comm No: Note:
REVISION HISTORY
TABLE OF CONTENT
1. INTRODUCTION .............................................................................................................. 4
2. GENERAL ......................................................................................................................... 4
3. PROJECT DESCRIPTION ................................................................................................ 4
4. SITE CONDITIONS .......................................................................................................... 4
4.1. Site Location ..............................................................................................................4
4.2. Site Condition.............................................................................................................4
5. ENVIRONMENTAL DATA ................................................................................................ 5
5.1. General Climate Condition .........................................................................................5
5.2. Design Condition ........................................................................................................6
6. CODES AND STANDARD ................................................................................................ 7
7. PROCESS DESIGN BASIS OF Coal and Ash Runoff Treatment ..................................... 7
7.1. The Parameter of Coal Runoff and Ash Runoff Water ...............................................7
7.2. Description of Coal Runoff and Ash Runoff Treatment ..............................................7
7.3. Block Flow Diagram & Process Flow Diagram of Coal and Ash Runoff Treatment ....8
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project
1. INTRODUCTION
For fulfilling the electricity energy demand in Kupang, PT Perusahaan Listrik Negara (Persero) has
planned to build Timor-1 CFSPP (2 x 50 MW) for supplying the electric power for public use.
The Plant will consist of 2 units, having a minimum Net output of 2 x 50 MW and maximum Net Output
of 2 x (50 MW+10%).
The Plant to be built will be state of the art technology, functional and will designed as well as capable
of continuous, efficient and reliable operation with minimum maintenance under existing environmental
and operation with minimum maintenance under existing environmental and operation condition. All
equipment provided will be of simple robust and conservative design, with generous built in safety
factors and protective systems.
The Plant will be generated by using coal. The coal is transported by barge and unloaded to coal jetty
facilities, then conveyed and stocked to the coal storage area. The type of cooling system shall be once
through cooling using water from the sea.
2. GENERAL
The requirements specified below describe the general design, supply of equipment and materials,
and installation of the electrical system for TIMOR-1 CFSPP (2 x 50 MW) at Kupang, Nusa Tenggara
Timur Province, Indonesia.
3. PROJECT DESCRIPTION
The following words shall have the meaning indicated when used herein:
Owner : PT Perusahaan Listrik Negara (Persero)
Consultant PMC : PUSENLIS
Contractor : PT IKPT – PT PP (Persero), Tbk. – ITOCHU Corporation – Sumitomo
Heavy Industries, Ltd. – PT Medco Power Indonesia
Eng. Consultant : PT REKAYASA ENGINEERING
4. SITE CONDITIONS
c. Bathymetry
Bathymetry survey area that was conducted by Owner is approximately 36 Ha.
5. ENVIRONMENTAL DATA
5.1. General Climate Condition
Climatic conditions based on data from the project site Climatology Meteorology and Geophysics
Agency (BMKG) on Lasiana Station Kupang, within 10 (ten) years (2003 to 2012):
a. Relative Humidity
Relative humidity varies about 46% to 98% and manual average is about 76%.
b. Air Temperature
The annual average temperature is 27.30C
The maximum temperature is 31.70C
The minimum temperature is 22.70C
c. Wind
Dominant wind blows from East to West. Maximum wind speed 32.5 knot.
d. Atmospheric Pressure
Maximum : 1015.3 mm Bar.
Minimum : 998.9 mm Bar.
Average : 1009.4 mm Bar.
COAL RUN OFF AND ASH RUN OFF
DESIGN BASIS FOR
Timor-1 CFSPP 2 X 50 MW Project
e. Evaporation
The annual average for evaporation is 5.8 mm/day.
f. Rainfall
Maximum (Year) 2385 mm
Maximum (Monthly Mean) 882 mm
Average Rain Fall (Yearly Mean) 1633 mm
Greatest Rainfall in a Day 203 mm
Rainy Season Month December until April
b. Relative humidity
- Mean maximum 76%
- Design humidity 83%
j. Wind load
The design wind load calculation shall be referring to ANSI – A58.1 or “Peraturan Muatan
Indonesia (Indonesian Standard)”.
National Standard
The Regulation of Minister of Environment No.8 year 2009, Sheet II, point D.
1 pH - 6-9
3 Fe mg/L 5
4 Mn mg/L 2
7.3. Block Flow Diagram & Process Flow Diagram of Coal and Ash Runoff Treatment
The block flow diagram of Coal and Ash Runoff Treatment unit can be seen Figure 3.
Stockyard / Dead Coal Runoff
Coal Yard WWTP
Pond
Figure 3. Block Flow Diagram of Coal and Ash Runoff Treatment Unit