Documente Academic
Documente Profesional
Documente Cultură
TENDER DOCUMENT
FOR
THE DESIGN AND BUILD PROJECT FOR THE BUS RAPID TRANSPORT
(BRT)
FACILITIES ON THIKA SUPERHIGHWAY CORRIDOR
(CLAYWORKS-RUIRU-NAIROBI CBD- KENYATTA NATIONAL HOSPITAL
SECTION)
NOVEMBER , 2019
i|P age
Thika Road BRT Section VIII: Employer’s Requirements
Section VIII
EMPLOYER’S REQUIREMENTS
This Employer’s requirements specifies the particular requirements for the completed Works
on a functional basis, including detailed requirements on quality and scope, and details on
what the Contractor shall supply as consumables or otherwise.
In the preparation of these Employer’s requirements, the following Documents and Manuals
are part of the sources of reference:-
1. Conditions of Contracts for EPC/Turnkey Projects FIDIC, 1999 and the Sub-clauses
therein
2. Standard Specifications for Road and Bridge Construction, 1986 and their Corresponding
Sub Clauses.
3. Road Design Manual, Part I; “Geometric Design of Rural Roads”, January 1979
4. Road Design Manual, Part III; “Materials and Pavement Design for New Roads”, August
1987
5. Road Design Manual, Part IV; “Bridge Design”, August 1993
6. Proposed Manual for Traffic Signs in Kenya,
a. Part I, “Road Markings” and,
b. Part II, Manual for Traffic Signs in Kenya, June1975
7. Standard Specifications for Road and Bridge Construction, 1986
8. NaMATA BRT Design Framework (Feb 2018) or as instructed by NaMATA
8.
ii | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
TABLE OF CONTENTS
1 INTRODUCTION .................................................................................................................................. 1
268,000,000 ................................................................................................................................................... 12
1|P age
Thika Road BRT Section VIII: Employer’s Requirements
2|P age
Thika Road BRT Section VIII: Employer’s Requirements
Employer’s Requirements
THE DESIGN AND BUILD PROJECT FOR THE BUS RAPID TRANSPORT (BRT)
FACILITIES ON THIKA SUPERHIGHWAY CORRIDOR.
1 INTRODUCTION
As a Design & Build Contract (FIDIC EPC/TURNEY: fixed price) with a construction
period of 18 months.
The Works will include all field Works, detailed engineering design and upgrading of the
existing superhighway by introduction of BRT lanes and accompanying facilities in the
innermost lanes of the existing carriageway and as detailed below.
1|P age
Thika Road BRT Section VIII: Employer’s Requirements
2 WORKS DESCRIPTION
2.1. Project Location
The project is located along the existing Thika Superhighway (A2S & A2S R) Corridor from
Ruiru, Membley Junction, Clayworks, Kenyatta University, Githurai, Kasarani, Pangani
Underpass, Murang’a Road, Globe Cinema Overpass, Tom Mboya Street, Moi Avenue, Haile
Selassie Avenue to Kenyatta National Hospital and Back .
Phase I; Clayworks, Kenyatta University, Githurai, Kasarani, Pangani Underpass, Murang’a
Road, Globe Cinema Overpass, Tom Mboya Street, Moi Avenue Approximately 20 Km long.
Phase II: Ruiru, Membley Junction, Clayworks section approximately 3km and Moi Avenue,
Haile Selassie Avenue to Kenyatta National Hospital approximately 4km.
2.2. Existing Route Condition.
Thika Superhighway (Class S) road is currently a bituminous road comprising of, on average,
6 lanes on the main carriageway and 4 lanes on the service road and is generally in good
condition. The Section in the CBD has two lanes most of the way and is in fair condition
which may require immediate strengthening.
2.2.1. Previous Designs
The as built drawings for the Thika Superhighway are available for information purposes
only to enable the bidders prepare the Works designs. Information on the rest of the Corridor
may be obtained on request from Kenya National Highways Authority.
2.2.2. Land use
Land use is characterised by a combination of commercial and residential activities with
several commercial/ residential structures abutting the road reserve. There are several existing
utility lines along the road reserve which may need to be relocated by the Contractor.
2|P age
Thika Road BRT Section VIII: Employer’s Requirements
3.1. General
The summary of the scope of Works to be carried out is as follows;
i. Carry out a detailed traffic impact study and modelling.
ii. Detailed Engineering design for;
a. Modification of Ten (10No.) existing footbridges to serve as access to BRT
picking points and stations as listed below;
i. Kenyatta University
ii. Kahawa Barracks
iii. Githurai (Car wash)
iv. Kasarani/Roysambu
v. Safari Park
vi. Garden City (under construction)
vii. Kenya School of Monetary Studies (under construction)
viii. Utalii/National Youth Service
ix. Muthaiga
x. Ngara
b. BRT picking booths in the median
c. Channelization of both motorized and non-motorized traffic to accommodate
the BRT infrastructure.
d. Three (3) No. elevated U-turn ramps as interchange for feeder Buses and
Matatus
e. Three (3) No. Park and ride Facilities
f. Physical separation of the BRT lanes from general traffic
g. Three (3) No. New footbridges at Ruiru, Membley and Githurai
h. Transfer stations at Ruiru, Githurai and Kasarani.
iii. Detailed Engineering designs for the smooth flow of traffic at the junctions and
accesses.
iv. Construction of the BRT infrastructure and the engineered road facilities as per the
approved Detailed Engineering Designs.
v. Provision and maintenance of offices, laboratory and accommodation for the
Employer’s Representative and /or his staff.
vi. Maintenance of the existing road during construction period.
vii. Management and control of traffic during construction period
viii. Provision and erection of road furniture and road markings and other miscellaneous
Works
ix. Any other Works as may be instructed by the Employer’s Representative or as agreed
between the Contractor and the Employer.
3|P age
Thika Road BRT Section VIII: Employer’s Requirements
The Contractor shall incorporate in the detailed design, the existing services and utility
lines to avoid relocation of the same.
The Contractor shall incorporate in his Contract Price, the unavoidable costs of
protecting, relocating and/or accommodating the existing services and utility lines in the
detailed design.
3.3. Programme and Project Phases
The Contractor shall provide a time Programme as required under Clause 8.3 of the
Conditions of Contract.
The Contractor shall allow in his programme for construction of trial sections and
carrying out tests upon them as directed by the Employer’s Representative in accordance
with the provisions of Clause 129 of the Standard Specification for Road and Bridge
Construction, 1986. The Time for Completion of the Contract shall not be extended
because of the time taken to carry out tests and evaluate trial sections.
The Contractor shall be required to carry out Works in three distinctive phases as follows:
(i) Feasibility Study and Preliminary Design;
(ii) Detailed Engineering Design; and
(iii) Construction.
Construction of permanent Works shall not proceed until the detailed engineering design
of the said work has been approved by the Employer.
1|P age
Thika Road BRT Section VIII: Employer’s Requirements
Pavement Structure
The following matrix presents the required pavement performance specifications for the
entire road project at the end of 1 year Defect Notification Period after handover by the
Contractor to NaMATA
The matrix sets out key performance indicators for surface deflection (limits will be set
on finalization and approval of design), riding quality, rutting and cracking. The limits
include a condition expected not to be exceeded on the major part of the project
(percentages of major portion indicated), and a supplementary condition related to limit
on out-of-range values. The Contractor is to remedy at his cost any test parameters that
fail to meet the required performance criteria set in the table below
It will be noted that causes of cracking, if occurring in this period, must be identified and
agreed. Suitable repairs shall then be undertaken as approved to remedy any underlying
defects.
Major part of Limit on out-of-
project Supplemen range Test
Parame tary Limi Test Frequenc
ter Units At least Limit condition Less than t Method y
Rebound Every
Maximu
deflection, 50m, each
m
8,200 Kg lane
surface mm 95% < 0.35 AND 2% > 0.4
axle load,
deflecti
near side
on
wheel path
IRI Continuou
roughness s in each
Roughn
m/km with lane
ess
(mm/ calibrated
m) 80% < 4 AND 2% > 5 vehicle
Near side Every
Rutting wheel path 50m, each
mm 90% < 2 AND 2% > 5 lane
There shall be no visible cracks. Any cracks appearing during this monitoring
Crackin
period must be immediately sealed, and reason(s) for cracking identified and
g
suitable repairs undertaken to the Client's approval
2|P age
Thika Road BRT Section VIII: Employer’s Requirements
This section describes the performance specifications for the bridges, foot bridges and the
drainage structures at the end of the Defect Notification Period.
Design Life
The bridges, footbridges and drainage structures design life shall be 100 years.
Minimum cover for reinforcements shall be as specified in the
The design of the structures shall be as defined in BS or its equivalent
Cracks
Cracks in concrete shall not exceed the limits specified in BS 5400 part 4.
Vertical Clearances
The vertical clearances for bridges, footbridges and underpasses shall be minimum 6m above
the road riding surface.
Sleeves
The Contractor shall provide for safe crossing of other service lines including fibre,
underground cables, power lines, pipelines etc within the bridges, footbridges and other
drainage structures
Beams
Simply/continuously supported beams maximum deflections under design loading shall be
L/500 where ‘L’ is the effective length of the span in millimetres as defined in BS 5400 part
4.
Abutments
The maximum allowable deflection of Cantilever members under design loading shall be
L/200 where ‘L’ is the effective length in millimetres as defined in BS 5400 part 4.
For restrained abutments, movement of the restraining tendon shall not be more than 25mm.
Connections
Connection for structural steel members shall be of the same quality and strength as the
mother members preferably by butt welding with cathodes that are of the same quality
material as the mother member.
Connections for non-structural members shall be as per the standard specifications
Where bolts are used, they shall have the same design life as the overall structure under the
prevailing weather conditions.
Bearings
The bearings shall have a guarantee of 100 years with minimal maintenance cost.
The bearing shall be able to accommodate the maximum rotation, maximum direct loading
and any shear deflections.
Barriers
Crush barriers shall be able to resist minimum impact loading specified in BS 5400 part 2:
Specifications for Loads.
Safety barriers shall not be prone to vandalism. Non-motorised safety barriers shall restrain
sliding off and discourage jumping over the facility.
Expansion Joints
Expansion joints shall allow for movements without inducing lateral forces in the members.
The expansion joints shall allow for self-cleansing.
3|P age
Thika Road BRT Section VIII: Employer’s Requirements
The expansion joints shall be properly fixed to last the bridge design life of 100years.
The expansion joints shall have a guarantee of 100years with minimal maintenance cost.
The non-motorised traffic facilities shall be comfortable, safe, adequate and aesthetically
appealing at proper locations suitable for use by normal, elderly, disabled and the children.
The walking surface shall be of adequate traction to avoid sliding.
BRT Facilities
4|P age
Thika Road BRT Section VIII: Employer’s Requirements
5|P age
Thika Road BRT Section VIII: Employer’s Requirements
The Environmental and Social Impact Assessment (ESIA) study will be in accordance with
the Environmental Management and Co-ordination Act (EMCA), 1999 and the
Environmental (Impact Assessment and Audit) Regulations, 2002.
The safety audit shall be carried out in accordance with the Road Safety Audit
Manual/guidelines of the Government of Kenya and any other internationally accepted
standards and as agreed with the Employer.
All the design and construction work undertaken by the Contractor in respect of the Contract
shall comply with these procedures and requirements.
6|P age
Thika Road BRT Section VIII: Employer’s Requirements
7|P age
Thika Road BRT Section VIII: Employer’s Requirements
8|P age
Thika Road BRT Section VIII: Employer’s Requirements
5 CONTRACTUAL REQUIREMENTS
The requirements stipulated herein are to be used in addition to sound engineering
knowledge and good industry practice. A requirement must not be understood as an
"instruction" to the Contractor, who must at all times use his discretion and engineering
expertise to critically evaluate the requirement and, if he decides to deviate from or not
to abide by such requirement, the Contractor must provide motivation or
recommendations to NaMATA substantiating the reason for the required deviation. All
deviations will be subject to approval by NaMATA or its nominated representative. The
approved deviation shall not subject the Authority to additional cost not included in
the Contract price.
The Contractor shall establish a paired (coupled) inter-visible GPS control points at least
5.0Km apart from each other. The location of these Control Points shall be determined by
reviewing existing topographic maps and site conditions of the project route.
a) The monument for each Control Point shall be die-stamped in the field; the Contractor
shall provide a standard canopy drawing to the Engineer for approval before the
establishment of the control points.
b) The Design-Builder shall maintain an accuracy level of 10mm+5pmm for the (x, y)
coordinates of all the control points.
The vertical control points shall be referenced in the field on permanent concrete posts
with an interval of 300m and shall be shown on the plan and profile drawings apart from
list of benchmarks to be provided on a separate sheet accompanied by a photo of each
benchmark.
Differential level methods shall be used to establish elevations for the vertical Control
Points. The closing error of a levelled circuit shall not exceed ±√K cm in height
difference between the forward and reverse levelling of successive permanent survey
stations. K is a distance in Km between two consecutive bench marks.
9|P age
Thika Road BRT Section VIII: Employer’s Requirements
Construction Surveying
The Contractor shall be responsible for all survey necessary to complete the work. All
survey control data, calculations, surveying and measuring required for setting and
maintaining the necessary lines and grades shall be the Contractor’s responsibility.
Detailed survey records shall be maintained, including a description of the work
performed on each shift, the methods utilized and control points used. The record shall be
adequate to allow the survey to be reproduced. This record shall include graphic notes
depicting control points used and relationship to other control points or reference points,
description, coordinates and location description. Bench marks and Temporary bench
marks shall also have graphic notes depicting description, elevation, coordinates and
location description. The Survey Manager shall provide a copy of each day’s record to the
Engineer when requested within three calendar days after the end of the shift.
Use standard field books consistent with those customarily used by the
construction industry
Allow the Engineer to inspect these field books at any time
The books become the Employer’s property once work is completed
5) Correct any errors at the Contractor’s own cost
6) Assume responsibility for all final accuracy of construction
10 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Survey Records
Survey records shall be delivered in hardcopy format and also in electronic file format.
The electronic format shall be in ASCII, DWG or DXF format. They shall be delivered at
the time of substantial completion unless requested by the Engineer at an earlier time.
As-Built Records
The Contractor shall produce reports documenting the location of the as-built alignments,
profiles, drainage structure locations, and survey control monuments placements. These
reports shall include descriptive statements for survey methods used to determine the as-
built location of the features being surveyed. The Contractor’s as-built data shall include
the coordinate types (x, y and/or z) and feature codes in the format acceptable to the
Employer.
Performances requirements
The design and construction documents shall be prepared by (or under the direction of) a
professional highways engineer.
Design Criteria
The Contractor shall design and construct the Works to meet the following requirements:
i. Class of Highway: Class A2S/A2S R
ii. Maximum Highway Design Speed: 120 Km/hr
iii. Min. Radius of Hor. Curve: 600m (Design speed 100km/h),100m(Design
Speed in town 50km/h)
iv. Carriage way normal camber: 2.5%, shoulder fall: 4%. Maximum super-
elevation: 6%. For super-elevated sections, the shoulder fall shall be the same as
the super-elevation.
v. The Contractor shall coordinate and ensure that the project design
accommodates and allows for the design of technically and environmentally sound
project.
vi. BRT System:-
o station saturation shall be < 40%
o facilities shall be in accordance with the NaMATA BRT design
framework (2018) or as instructed by NaMATA
1|P age
Thika Road BRT Section VIII: Employer’s Requirements
Road Cross-Section
Minimum road cross-section shall be as specified in the Road Design manual and the
NaMATA BRT design framework (2018).
Embankment slopes
i. 1:4 for fills less than 1m
ii. 1:2 for fills over 1m but less than 4m and,
iii. 1:1.5 for fills greater than 4m.
iv. Pavement widening, Side ditches, cut off ditches and service lanes shall be designed
as per Road Design Manual, Part I.
v. Culvert outfall drains shall be designed to have the same cross section as a cut off
ditch Type 2.
Junctions
i. Minor Junction Type (minimum): As provided for in the Road Design Manual, Part I;
“Geometric Design of Rural Roads”, January 1979
ii. Extent of Improvement of the off road at the junctions (minimum): Major road Km
0.5, minor roads Km 0.05 into the off road.
The minimum number of new footbridges shall be 1 No., however, the Contractor
shall assess the adequacy and where necessary provide for more footbridges in his bid
to ensure adequacy of the facilities.
The footbridges design criteria shall include;
(i) The vertical clearance above the road riding surface to be min.6.0m
(ii) The substructure of the footbridge should be in such a way as not to cause
obstruction to storm water drain or space for other services e.g. fibre underground
cables power lines, pipes lines etc.
The footbridge shall preferably be of composite structural members i.e concrete
substructure, steel superstructure and appropriate roofing material.
The footbridges design and workmanship shall be aesthetically appealing and user
friendly to all pedestrians (including people with disability), cyclists and motorcycles.
3|P age
Thika Road BRT Section VIII: Employer’s Requirements
Moisture ingress into the fill and pavement layers shall be limited through the appropriate
engineering designs including appropriate surface and sub-surface drains.
The potential of collapsible soils and active sub-grades shall be investigated and
appropriate actions for treatment implemented.
The Contractor shall take all necessary steps to rehabilitate the quarry / borrow site, in
accordance to the NEMA licence and including landscaping, grassing and planting of
trees.
4|P age
Thika Road BRT Section VIII: Employer’s Requirements
5.1.5 Hydrology/Hydraulics
General
A hydrological study shall be carried out to establish the hydraulic condition and
adequacy of the existing structures along the road, and identifying places where
additional new structures are required.
5|P age
Thika Road BRT Section VIII: Employer’s Requirements
iv. Box culverts of opening greater than 5 m2 shall be designed to pass a 25 year flood with a
minimum free board of 1.0m.
v. Box / pipe culverts of opening less than 5 m2 shall be designed to pass a 10 year flood.
5.1.6 Drainage
i. The Contractor shall provide a safe and well-drained corridor for use and maintenance of
the road.
ii. The design and construction of all drainage structures and appurtenances shall adequately
address functionality, durability, ease of maintenance, maintenance access, safety,
aesthetic and protection against vandalism according to Contract specifications and
standards.
iii. In fulfilling the requirements for drainage, the Contractor shall abide by and fulfil the
requirements related to drainage features while at the same time meeting requirements of
other required design elements on the project. Drainage The primary objective shall be:
• Maintain drainage pattern
• Provide culvert opening for natural drainage channels
• Prevent undue accumulation and retention of water upon and adjacent to the roadway
• Provide the roadway against storm and subsurface water damage
iv. Providing a safe driving surface for the traveling public
v. The Contractor shall be responsible for the drainage system along the project. All design
work shall comply with the Drainage Manual including the engineering analysis
necessary to design any drainage structures.
vi. Drainage design should achieve the most effective and economical methods by which
runoff water can be passed through and removed from the roadway.
vii. The designer shall check all stages of design for accuracy, completeness and compliance
with the Brief and relevant Standards.
viii. A design Summary Sheet shall be prepared for all road bridges on completion of the
design, and shall be included in the set of design drawings. The Design Summary Sheet is
an important feature of the design as it contains a summary of all major features of the
design. The main items to include on the Design Summary Sheet are:
Details of the span configuration.
The design cross-sections used in the analysis at critical positions, eg support and
mid-span.
Details of the reinforcement and/or prestress and the section capacities at the critical
sections.
The serviceability design moments and resulting stresses at the critical sections.
Live Load Distribution Factors for different loadings.
Design Live Load.
The available live load capacity at the critical sections, for use in checking heavy load
movements.
Foundation information, i.e. design bearing pressures for spread footings and design
pile loads for piled foundations.
Design Scour allowance.
Drainage Submittals/Plans
The Contractor must prepare plan sheets, notes, and details to include the following inter-
alia:
- Drainage structure sheets
- Ditches and outfall sheets
- Ditch and outfall cross section sheets
- Pipe and Box/ slab culvert tabulation
- Erosion control details and plan
6|P age
Thika Road BRT Section VIII: Employer’s Requirements
5.1.7 Culverts
Minimum size
Access pipe culvert minimum Diameter size: 600mm
Cross culvert minimum Diameter size: 900mm
Multiple box culverts: cell number should not exceed six (6) cells.
Culvert Material
Reinforced concrete shall be used for all cross and access culverts. Alternative Materials
for culvert shall be subject to employer’s approval.
Culvert Documentation
The Contractor must supply the following for culvert documentation:
For minor culvert: Culvert Design Sheet
For Major culvert: Design computation
7|P age
Thika Road BRT Section VIII: Employer’s Requirements
Demolition
The Contractor shall demolish if there is substandard structures such as fords, drifts,
vented causeways, and any insufficient structures (structurally and hydraulically) along
the project. The Contractor shall design and construct appropriate structures in place of
those who would be demolished.
Design and Performance Requirement
New Bridges
For structure site(s) identified provide a Structure Selection Report as part of the Draft
Structural Report. Prepare the selection report with supporting drawings, tables, and
discussion as needed. Include the following (as a minimum):
Review the structure site data to determine the requirements that will control the structure
size, layout, and type.
Consider restrictions due to site access and transport limitations, and local material
availability.
Recommend proposed adjustments to profile alignment and grade necessary to
accommodate bridge location and freeboard requirements.
The Contractor will provide a summary of the detailed structural design criteria and
submit to the Engineer for approval.
Structural Drawings
Prepare structural drawing(s) that show all details necessary for construction of the
bridge.
The following (as a minimum) is an estimate of the Contract plan sheets required for
typical simple span structure:
8|P age
Thika Road BRT Section VIII: Employer’s Requirements
Performance Requirements
The Contractor shall design, furnish and construct retaining walls for the project.
Gravity walls and Cast-in-place cantilever walls shall constitute acceptable retaining
walls for permanent applications provided they are done to applicable standards.
Performance Requirements
The Contractor shall design & install pavement markings that will be uniform in type,
colour, dimensions, location & reflectivity as provided in Standard technical
Specification.
9|P age
Thika Road BRT Section VIII: Employer’s Requirements
and provide such guidance & warnings as may be needed to ensure the safe & informed
operation of the traffic stream.
Sign Construction
The Contractor shall:
Furnish and install all signs, posts, foundations & associated materials.
Install and construct the signs to conform to the requirements of Standard
Specifications
Provide positive guidance to the traveling public at all times during construction
by the use of new signing to ensure safe & informed operation while traffic is
maintained on the roadway.
Guardrails shall be provided in accordance with the requirements of the Road Design
Manual, Part I; “Geometric Design of Rural Roads”, January 1979, but incorporating
steel posts for box culverts and reinforced concrete posts at high embankment locations.
The Contractor shall provide for retro-reflective studs on the guardrails every 4 meters.
The road reserve boundary post shall be provided at 100m interval and at the major
junctions.
Street lights
The Contractor shall provide for street lighting of the additional BRT infrastructure with
minimal maintenance and operation cost and shall be required to reinstate any street
10 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
11 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
13 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
(v) As the project proceeds, the Contractor shall present to NaMATA alternatives for
improvement in alignment of the road and for improvements where the road passes
through villages and settlements.
(vi) Road drawings to include:
a) Plan drawings at a scale of 1:2000 or other agreed scale to show alignments,
vegetation type, main drainage elements, right of way and clearly show areas
of land take
b) Profile drawings to scale 1:2000/1:200 or other agreed scale, to include the
existing road surface or natural ground level and proposed vertical alignment.
(vii) The Contractor shall undertake the geometric design of the road using a modern and
comprehensive (Computer Aided Design and Drafting) CADD package. This CADD
software must be capable of allowing the designer to assess different alignments along
the proposed route and also for preparation of a visual 3D representation of the
designed roads. All topographical and design data shall be supplied in a format
suitable for input to Civil 3D design software or similar. The design shall be
referenced to a line or string which shall contain details of chainage (or station),
horizontal and vertical geometry information.
(viii) Preliminary Pavement design: The Contractor shall divide the road into homogenous
sections in terms of traffic loading and strength, and propose at least two alternative
pavement options in terms of layer type, quality and thickness of pavement
considering the project traffic loadings for each section. The Contractor shall take
into account availability of suitable construction materials along the route.
(ix) Preliminary Design of Structures. The Contractor shall carry out topographic survey,
geotechnical investigation, hydrological study and others that are necessary to prepare
structurally sound and cost effective design layouts for major structures in the project
road.
a) Topographic survey for preliminary design of structures:- The Contractor shall
carry out topographic surveys of the sites of the proposed structures extending
500m to either side. Cross-sections of stream beds shall also be taken. These
surveys shall be presented on drawings at a scale of 1:1,000 in plan view
together with a longitudinal section along the anticipated axis of the structures.
The drawings shall indicate the location of the geotechnical investigations made
during the geotechnical study referred to below.
b) Geotechnical investigations for preliminary design of bridges:- The Contractor
shall carry out a geotechnical survey by drilling boreholes until he establishes a
stable ground, analyse and present the findings in a comprehensive geotechnical
report.
c) Hydrological and hydraulic design of bridges:- Hydrological and hydraulic
studies shall determine flood characteristics of the streams crossed, including the
elevation of the water surface, the velocity of flow, for a recurrence interval of
100 years.
d) Preliminary geometric design of bridges and drawings.
Location plans for bridge / structure and approaches
Longitudinal sections of approaches
Elevation of the structure
General arrangement to show type of foundations, abutments, piers and
deck
14 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Short report on main issues in building the bridge and how these will be
mitigated e.g. wide fast flowing river
The Contractor shall pay particular attention to the following specific issues and shall
consider the following aspects:
(i) Speed and Delay survey. This survey would be done separately for the traffic stream
and for buses, both peak and off peak period to assess the journey and running speeds
along with delays along the entire length of the corridor.
(ii) Road Network Inventory Surveys of entire length of corridor including all
Intersections and service roads in the influence area;
(iii) Boarding / alighting survey of passenger at major bus stops. This survey shall
provide an estimate of bus stop loads as well as total bus passenger demand on the
corridor;
(iv) Origin / Destination cum Opinion Survey both for bus and Intermediate Public
Transport / private modes (auto-rickshaws and two-wheelers) at all major bus stops
and intersections respectively during peak periods on sample basis. The O-D survey
for bus passengers shall be conducted at all the bus stops on the selected corridors and
shall provide an estimate of distance wise bus passenger demand on the respective
corridor. The O-D cum opinion survey for other users shall in addition provide the
potential shift to the new system;
(v) Direction-wise Classified Traffic Volume Survey All types of modes will be
counted separately and Passenger Occupancy survey at all intersections. This survey
will provide information on section wise daily and peak hour traffic volume and
composition on the corridors;
(vi) Traffic Signal time and saturation flow survey at all signalized intersections for
morning, midday and evening peaks as well as off peak period.
(vii) Parking survey (on-street and off-street) would be carried out along the entire
length of the corridor to collect the details about parking accumulation and parking
duration for peak period. The parking demand assessment would enable to plan for
providing alternate parking facility; and
(viii) Pedestrian Survey at all major intersections for peak periods. Both along and across
movements will be counted to gauge the Intensity of pedestrian Traffic for provision
of requisite pedestrian facilities as well as minimizing pedestrian vehicular conflicts.
(ix) Traffic Forecasts: the Contractor shall quantify both the direct and indirect impact of
the road development and the analytic approach must include appropriate forecasting
techniques/models and be supported by appropriate survey instruments, including:
a) Population and Settlement survey,
b) Economic and market survey; and
c) Transport survey (for motorized and non-motorized transport (NMT), including
pedestrians).
The traffic forecasts should include the generated, diverted and induced traffic. The
forecasts should include best estimate of likely demand (based on economic activity,
15 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
past growth trends, growth in vehicle population, etc) and the more critical variables
should be subjected to sensitivity analysis. The forecasts should also include the
impact on the project area during the construction period.
(x) Axle load survey and traffic engineering: The Contractor shall use appropriate
techniques to verify and adjust the existing unrepresentative sample data from
KeNHA weigh stations and data from their axle load surveys and Equivalent Standard
Axle (ESA) and preliminary pavement design. The Contractor shall use this data to
analyse traffic and specify the design of the required traffic features, including
alignment and junction design. Based on traffic analysis, the Contractor shall
determine the location of signs and markings, guardrails and guide posts, as well as
rest areas, bus stops, and pedestrian facilities, in accordance with standards and
guidelines provided by NaMATA.
(xi) Any other Survey as required.
The above traffic data shall be compiled into a Traffic impact report.
The Contractor shall include a draft sampling and testing programme (to include numbers of
each type of test for testing work) for the road, borrow areas and quarries. This shall be
refined and updated once the assignment commences.
The Contractor shall consider issues in retaining existing embankments and cut areas,
widening of existing embankments and cut areas as well as the design of new embankments,
cut areas, areas of weak subgrade, swamps etc. Calculations showing the proposals are safe,
16 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
The Detailed Design of the Road shall include, but will not be limited to, the
following:
(i) Design Base Statement.
(ii) All working drawings, schedules and designs required for the Construction Works in
accordance with the applicable standards and codes of procedure listed herein.
(iii) Project specifications and other provisions required for the Construction Works.
(iv) Design changes to the drawings, to comply with the Engineering Requirements or as
agreed by NaMATA.
(v) A detailed geotechnical report.
(vi) A detailed topographical survey report.
(vii) Hydrology, hydraulic and Drainage design report.
(viii) A detailed materials report.
(ix) Road Safety Audit report.
(x) Design drawing(s) for bridges consisting of a general arrangement drawing shall be
submitted for approval prior to the commencement of the Detail Design. All approval
requirements of other relevant authorities shall be adhered to.
(xi) Requirements for land acquisition related to borrow areas and temporary
accommodation of traffic and details of negotiations with land owners if applicable,
according to the procedures as agreed to from time to time.
(xii) Traffic analysis and traffic loading.
(xiii) Environmental and Social Impact Statement (compliance with environmental
requirements).
(xiv) Resettlement Action Plan and valuation Report
Design Drawings
The Contractor shall prepare and submit Contract drawings as specified below. For
bidding purposes the drawings shall be reduced in scale as indicated in the section on
preparation of bidding documents or to any other scale agreed to with NaMATA. The
Contractor shall submit and obtain approval from NaMATA the layout of all drawings
prior to preparation of any drawings.
The amount of detailing produced on the drawings shall be sufficient to convey in an
unambiguous manner the intentions of the designer and to facilitate construction of the
structure. No major or significant details shall be left to the discretion of the party
responsible for the supervision of the Works or to the Contractor.
All details drawn and dimensions shown on the drawings shall be to scale, however, in
circumstances where this is not the case, it shall be clearly stated on the drawings that
they are not to scale (NTS). To all such dimensions the abbreviation “NTS” shall be
added.
(i) Standard of draughting shall comply with the requirements of BS 5070 : Part 1;
(ii) The line thicknesses used shall not be less than the following:
Dimension drawings – 0,50 mm preferably with 0,35 mm minimum thickness in the
case of small or intricate detailing, and 0,25 mm for dimension lines;
Reinforcement detail drawings – 0,50 mm preferably with 0,35 mm minimum
thickness in the case of small or intricate reinforcing steel, 0,35 mm for structure
outlines and 0,25 mm for dimension or indicator lines;
Bending schedules – 0,50 mm thickness for sketches and 0,25 mm for dimension
lines.
18 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
(iii) The size (height) of letters for titles shall not be less than 5 mm, and for notes,
dimensions, etc., not less than 2,5 mm. The drawings shall be in black ink with the
writing on the drawing either stenciled or machine printed.
Standardized draughting practices shall be used for the arrangement of details on the
drawings, development and detailing of sections, presentation of details, dimensioning
and identification of items.
The information to be provided in the title block shall include the name of the bridge,
number of the structure, name of the watercourse, description or number of the road on
which the structure is located, kilometer distance.
Bridge drawings
For each bridge the set of working drawings shall consist of:
(i) Site plan
(ii) Longitudinal sections
(iii) Subsurface data
(iv) General arrangement drawing
(v) Foundation layout
(vi) Concrete drawing
(vii) Pre-stressing detail drawing
(viii) Reinforcement detail drawing
(ix) Parapet drawing
(x) Miscellaneous detail drawing
(xi) Bending schedules.
19 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Longitudinal Section:
Original Ground Level
Existing Road Level
Final Road Level
Vertical Alignment data
Horizontal Alignment data
Final Levels (L,C,R) At 20m intervals
Ground Level on c/l.
Camber and Super elevation.
Cross Sections Hor: 1:2000
Cross sections are to be provided at 100 m Vert:1:200
intervals and at significant changes in cross section
Typical Cross Sections
Benching Details for Cut and Fill and Specification
Subgrade Preparation and Specification
Pavement Layer details
20 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Drainage Schedules
Longitudinal Section through Culverts
Dimensions and Levels
Hydraulic Data
Culvert Type.
21 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
5.4 Construction
Works shall be carried out in accordance with the provisions of the Conditions of
Contract, Standard Specification for Road and Bridges Construction 1986 Edition
Published by the Ministry of Transport and Communication and the special
specifications in Appendix B
The final layout of the Works at 1:500 scale or other approved scale
Finished ground levels for the whole of the in the form of spot levels on a 5 m
square plan grid for all earthworks/landscape slopes within the extent of the
Works undertaken, and, for carriageways and other paved areas, spot levels on
cross sections at maximum 20 m centres.
As-built records of all drainage systems including pipe class and levels,
bedding/surround details. etc.
All variations instructed by the Engineer;
Full pavement details;
1|P age
Thika Road BRT Section VIII: Employer’s Requirements
Earthworks details including capping layer thicknesses and any special treatment
necessary at or below sub-grade level;
Drainage details showing all drainage runs, culverts and outfalls. If levels are not
indicated on drawings, schedules should be prepared and included as part of the
as-built records;
Structures details
Types of pipes and geotextiles used by the Contractor. Pollution traps, petrol
interceptors and flap valves, including access routes or arrangements and the
location of surface water drainage and channels shall also be indicated;
The precise location and depth of spare Utility ducts and their intended future use.
Depths and locations should be recorded relative to fixed reference points;
Road lighting, including column positions and electrical details;
Road signs, including legend, size and locations;
Road markings, Safety fences, including types, anchorages etc;
Kerbing, kerb types and paved verges.
Rock fall protection;
Details of sightlines/visibility splays; and
Areas of topsoil placing, including depth, and landscaping and planting (if any).
Electrical installations
2|P age
Thika Road BRT Section VIII: Employer’s Requirements
3|P age
Thika Road BRT Section VIII: Employer’s Requirements
4|P age
Thika Road BRT Section VIII: Employer’s Requirements
1. The original (master) set of full size drawings, on a durable medium suitable for
reproducing copies, showing full details of the Works as constructed at an appropriate
scale;
2. A design calculations report. The Contractor’s designer shall prepare the design
calculations report which shall include, for each major element of the Works, design
the following information:
A description of the design philosophy, referring to principal standards employed
and
The various design parameters, and loadings used during design;
A schedule of principal calculations (including checks) required to define the
design details of the Contractor’s proposals forming the scheme; and
Copies of selected principal calculations, and records of checking procedures as
required by the Engineer;
3. Photographs of each structure. The photographs should show the general structural
elevations together with particular details such as bearing shelves (showing access for
inspection) and abutment inspection chambers. The photos should show good and bad
details with a note suggesting how the detail might be usefully improved in the future.
A general view of the bridge/structure in the surrounding landscape is also required.
Photographs must be in colour and to be a good standard. The colour prints should be
175 mm by 125 mm in size or any other agreed size and should be mounted and titled,
either in one album or in A4 loose leaf plastic wallets. The title should include, as a
minimum, the following information:
Structure;
Description;
Contract Name;
Designer;
Contractor;
Date; and
Photograph Reference; and
4. Fully detailed information necessary for a bridge management system.
5|P age
Thika Road BRT Section VIII: Employer’s Requirements
a) Sufficient as-built information and test certificates to enable any electrical equipment
to be operated on a day to day basis
b) The installation shall be commissioned and substantially completed so that no part of
the installation shall need to be de-commissioned for either electrical or civil remedial
Works. Adequate access shall be provided to the appropriate standard and shall be
compliant with the health and safety regulations;
c) As-built drawings details including site details, electrical circuits and electrical loads.
Any lines of demarcation between the Employer and local authorities must be clearly
identified. Details of mechanical equipment and labels;
d) An inventory of spare equipment held, quantities and where stored shall be provided
to the Employer;
e) An electrical certificate of compliance shall be handed to the Engineer.
6|P age
Thika Road BRT Section VIII: Employer’s Requirements
The Contractor shall be required to submit the following reports/documents to the Employer's
Representative during the project and at the completion of the Works for approval or
otherwise as a routine submission.
The Contractor is advised that there shall be project monitoring site meetings.
The Contractor shall include in the Contract Price costs related to Employer’s personnel
attending scheduled and ad hoc site related meetings where necessary. The costs shall cover
road and air travel, accommodation allowances, meals, among others.
7|P age
Thika Road BRT Section VIII: Employer’s Requirements
A progress narrative;
Quality certifications;
Monthly baseline progress schedule update;
Monthly subContract report;
Quantity calculations;
Statement of materials and labour request
Order on Contract status report;
That all work, including that of the Designer, subContractor, suppliers, etc has been
checked and/or inspected by the Quality Control staff and that all work, except as
specifically noted in the certification, conforms to the requirements of the Contract; and
That the quality plan and all measures and procedures therein are functioning properly
and are being followed, except as specifically noted in the certification.
8|P age
Thika Road BRT Section VIII: Employer’s Requirements
9|P age
Thika Road BRT Section VIII: Employer’s Requirements
The report should be sufficiently detailed to provide the supervision consultant and the
Contractor with adequate and easily referenced survey information during the
construction stage.
5. Hydrological and Hydraulic Report
This report shall detail all assumptions, standards and criteria used in the calculation of
peak run off from each catchment, and such calculations shall be submitted in full.
Hydraulic calculations shall be submitted for each existing or additional drainage
structure.
The condition of each existing structure shall be summarized and reasons stated for its
abandonment, extension or enlargement. The need for erosion or scour protection for
each structure shall be evaluated and quantified.
Full details of identified geotechnical problems along the road alignment, such as weak
sub-grade and slope stability problems, shall be documented and calculations provided.
Remedial measures options shall be proposed and evaluated and quantified.
10 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
The report shall include a list, in each section, the relevant design standards followed and
a Departures Report identifying all instances where these standards have been deviated
from and the reason for such deviation.
The report shall include the estimated Construction Quantities and Economic Analysis of
the presented design.
The report shall include a provisional traffic management plan detailing how motorized
and non-motorized traffic and pedestrians shall be accommodated during the construction
phase.
9. Road Safety Audit Reports
The reports for safety audits at each stage of the design process shall be prepared in
accordance with the Road Safety Audit Manual. The Contractor shall also prepare the
Responses Report to demonstrate how each item raised in the audit reports has been
addressed.
10. Environmental and Social Impact Assessment Report
The Contractor shall prepare the status of implementation of the EMP contained in the
Environmental and Social Impact Assessment Report (ESIA) prepared by NaMATA.
The Contractor shall therefore review the General Specification and recommend specific
options, or possibly additional options, which shall be incorporated into the Works after
approval by NaMATA.
11 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
6 QUALITY ASSURANCE
6.1 Requirements
The Contractor shall operate a quality management system complying with ISO 9001:
2001 for the duration of the Contract.
The quality management system shall describe the management, organisation,
responsibilities, procedures, processes, resources and programme for the Works and
shall cover all stages of the Contract including design, procurement, execution,
construction, completion, testing, commissioning and activities during the Defects
Notification Period. The quality management system shall be contained in:
12 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
• A copy of a current certificate from an accredited certification body showing that the
Contractor, and any associated or subContracted parties, operates a quality management
system complying with ISO 9001:2001;
• Identification of key personnel, with CV's;
• A list of Subcontractors to be employed;
• A list of quality procedures and method statements to be provided (paying particular
attention to control of Subcontractors' Work);
• Description of specialist activities and personnel;
• Description of arrangements for quality control of purchased products and materials;
• Description of control of workmanship;
• Identified hold points; and
• The Contractor’s designer's key personnel for examination of the Works, with CV's. The
Contractor shall provide an organisational chart showing the interrelationship between
these staff, design office staff and the Contractor’s staff for construction.
The Contractor shall afford full opportunity for the Engineer to examine and audit his
quality management system and quality plans and those of its Subcontractors and
suppliers to ensure that the requirements of the Contract are being met. These quality
audits will be undertaken on a regular basis but reasonable notice shall be given to the
Contractor by the Engineer of the date of any such audit.
The Contractor shall rectify all non-compliances notified as a result of the audit by the
Engineer within the timescale set for such notification.
It is expected that the frequency of audits will be as follows:
a. Contractor and Contractor’s designer - no more than 2 audits per year; and
b. Supplier - 1 audit per year of a sample percentage.
In the event of specific problems arising, special audits, over and above the stated routine
audits may also be performed.
13 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Appendix A:
1|P age
Thika Road BRT Section VIII: Employer’s Requirements
Appendix A:
2|P age
Thika Road BRT Section VIII: Employer’s Requirements
3|P age
Thika Road BRT Section VIII: Employer’s Requirements
4|P age
Thika Road BRT Section VIII: Employer’s Requirements
5|P age
Thika Road BRT Section VIII: Employer’s Requirements
6|P age
Thika Road BRT Section VIII: Employer’s Requirements
7|P age
Thika Road BRT Section VIII: Employer’s Requirements
No Item No Item
1 Hydraulic Sample Ejector
Heavy Duty Solution
2 Balance, 20 Kg Capacity ± 1
g
1 Soil Mortar
8-12 Kg Capacity Electronic
1
Balance, ± 0.1 g
1 Soil Pestle
5-8 Kg Capacity Electronic
1
Balance, ± 0.1 g
1 Paraffin Warmer (2 qts.)
200-300 g Capacity
1
Electronic Balance, ± 0.01 g
1 Sealing Paraffin (50 lbs.)
Buoyancy Balance, 6 Kg x
2
0.1g
1 Cone Mould and Tamping Rod, set
Classification Equipment (BS1377)
No Item 1 Density Basket
2 Complete Liquid Limit Set Aggregates (BS 812-Complete set)
(Casagrande )
2 Plastic Limit Set Complete No Item
1 Pocket Penetrometer 2 Flakiness Gauge
1 Shrinkage Troughs 30 Sodium/Magnesium Sulfate salt, Kg
2 Shrinkage Limit Device 1 Los Angeles Abrasion Machine
8|P age
Thika Road BRT Section VIII: Employer’s Requirements
9|P age
Thika Road BRT Section VIII: Employer’s Requirements
(Schmidt Hammer or
equivalent)
Sand Equivalent Test 1 Quality of Water Test, complete Set
No Item Sampling Bituminous Materials
1 Sand Equivalent Test Set No Item
10 Sand Equivalent Stock 24 1Qt. Sample Can
Solution 1 kg Bottle
Moisture - Density Test (BS 1377) 24 1 Qt. Small Mouth Can
No Item 6 Hubbard - Carmick Specific Gravity
testing Bottles
1 CBR Loading Machine, Mechanical Analysis of Soils
electrical
5 Heavy Compaction Rammer No Item
(4.5 Kg)
45 CBR Mould with all 1 Hydrometer, ASTM 151 H
accessories
2 Slotted Surcharge Weight 4 Stopwatch 30 min., 1/5 sec.
24 Surcharge Weight 1 Beaker Glass, 250 ml.
2 Filter Screen 6 Graduated Cylinder, 100 ml
2 Trimming Knife, 6” Blade 1 High Speed Stirrer
4 Plastic Graduated Cylinder, 3 Dispersing Agent, Kg
100 ml.
4 Plastic Graduated Cylinder, Penetration of Bituminous Materials
200 ml.
4 Plastic Graduated Cylinder, Bitumen Penetrometer (Automatic
1000 ml and Hand Operated)
10 Wash Bottle 12 Needles-Stainless steel or brass
Grade 440c
4 Small Sand Scoop Containers-Metal or glass cylindrical
flat bottom (tin boxes) 90ml capacity
4 Flexible Spatula 6”. Blade Water Bath
1” wide
2 Sample Extruder Transfer dish for container
3 Collar, Detachable Thermometers for water bath
3 Tripod Stop watch or electric timer
2 Spacer Disc Heater-oven or hot plate
Asphalt Concrete Testing Viscosity of Bituminous Materials
No Item No Item
1 Bitumen extraction machine 1 Kinematic Viscometer (Complete)
(SMM type)
6 Beakers for above As 2 Thermometers
required solvent
2 Extractors 1 Water Bath (Thermostatical)
100 Cartridges for extractors 1 Timer
2 Bi-metal thermometer (0 – Time of Setting of Hydraulic Cement
300 0c) 100 and 300mm
2 Electrical thermometer (0 – No Item
300 0c)
1 0.10m core drilling machine Scales
10 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
11 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
12 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
13 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
All the survey equipment shall be of a make and quality approved by the Employer and shall
be supplied to the Employer within one month of the Notice to Commence the Works. If not
supplied on time, the Contractor shall hire equipment at his own expense for use by the
Employer as a temporary measure. All the above survey equipment shall revert to the
Employer at the end of the Contract.
Number
Item
Equipment to be Remarks and accessories
No.
Supplied
1 Total Station Leica 1 No. Plus accessories including on board,
TC 1201 or downloading and processing Software, internal
approved equal battery and charger with connection cables.
Hard cover carrier case for the Total Station
2 Data Recorder 1 No. With charger unit, including downloading and
data processing software
3 External batteries 2 No. For the Total Station supplied.
and charger
4 Car Charger for 1 No. Including 4m long cables for connecting to the
external battery 12V car battery
5 Digital Level 2 No. Plus accessories including tripods, internal and
Instrument external batteries and chargers, hard cover
carrier case.
6 Prisms 6 No. Compatible Tilting Super Prisms and carrier
bags
7 Traverse targets 3 No. With adopters for the prism
8 UHF FM 2-way 2 pairs Plus accessories including batteries and charger
Portable Radios
9 Optical Square 3 No. With carrier case
10 Tribrachs 4 No. With optical plumb, circular level bubble and
rotating adaptors
11 Prism Poles 4 No. 3.6m telescopic detail pole with attached bubble
and carrier cases
12 Metal Levelling 4 No. Aluminium 5m-Invar Staves with bubble and
Staves - 5m long canvas covers
13 Ground plate 2 No. Ground plates for stable positioning of the
levelling staves
14 Tripods 4 No. Compatible adjustable Tripods
15 Vertical Bubbles 6 No. Universal levelling bubble
16 Precision Measuring 1 No. Precision measuring wheel with folding grip for
Wheel distance measuring in the field. Shockproof
counting mechanism fitted over the measuring
14 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Number
Item
Equipment to be Remarks and accessories
No.
Supplied
wheel.
17 Steel Tape 50m 3 No. Nylon Clad steel open-reel tapes
18 Steel Tape 30m 4 No. Nylon Clad steel open-reel tapes
19 Metal Pocket steel 20No.
tapes (5m)
20 Steel tape repair kit 1No. With carrying case punch and eyeleting tool,
long and short eyelets and assortment of un-
graduated steel tape pieces.
21 Ranging Rods 2.0m 18No. 0.5m Red and White coloured point- jointed
long rods. Metallic and joinable
22 Pole and staff stand 2 No. Tripod like stand capable of holding poles and
(holder) staves vertically
23 Collapsible Safety 10 No. For road safety
Traffic Cones
24 Compass 2 No. with a highly resistant case
25 Steel Hammers (4kg 3 No. 2 No. Sledge hammers 2kg weight and 1No.
and 2kg) 4kg sledge hammer
26 Reflective Road 12 No.
Safety Vests
27 Vehicle mountable 1 No. With adapters and cable
Flashing road light
28 Scientific Calculator 4 No.
29 First Aid Kit 2 No. With first aid stuffs
30 Marking Paint 1doz White spray paint in cans(inverted marking
paint)
31 Survey Field Books 50 No. With Hard Cover
32 Marking Chalk To be supplied when required
33 Surveying Umbrella 3 No. Umbrella for protecting of the level from
obstructing light. Large diameter with carrying
bag, dismountable poles and guy ropes.
34 Pangas 6 No. Normal garden pangas or Machete
35 Gum Boots 8 pairs
36 12" Triangular 3 No. Scale to be determined by the Engineer
Architects’ Scale,
Plastic
37 Permanent Markers Red and Blue Markers. To be supplied when
Pens and Colour required
Roll Flagging tape.
38 Safety Hard Hat 10No.
15 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Number
Item
Equipment to be Remarks and accessories
No.
Supplied
39 3 metre straight 3 No
edge and wedges
Equipment Specification
A set of Dual Frequency Rapid static (phase) Not more than
GPS receivers (1 Base Static mode after initialization Horizontal: 5mm + 0.5 ppm
and 2 Rovers) with (rms)
accessories and Vertical: 10mm + 0.5 ppm
software, RTK facilities (rms)
and accessories. Kinematic (phase) Not more than
Onboard, downloading Moving mode after initialization Horizontal: 10mm + 1 ppm
and processing (rms)
Software, internal and Vertical: 20mm + 1 ppm (rms)
external battery and
Not more than
chargers with
connection cables. Hard Static (phase) with long Horizontal: 5mm + 0.5 ppm
cover carrier cases observations (rms)
Vertical: 10mm + 0.5 ppm
(rms)
Not more than
Static and rapid static (phase) Horizontal: 5mm + 0.5 ppm
(rms)
Vertical: 10mm + 0.5 ppm
(rms)
Not more than
Kinematic (phase) Horizontal: 10mm + 1 ppm
(rms)
Vertical: 20mm + 1 ppm (rms)
16 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
finished and fully habitable condition not later than 30 days after the Engineer’s Order to
Commence Work and such buildings shall be to the entire satisfaction of the Employer.
Upon completion of the Contract, the office and laboratory if not rented and all furniture,
fixtures and equipment shall revert to the Employer and the Contractor shall clear the site
to the satisfaction of the Employer. All furniture and equipment to be transported to the
facilities of the Employer as instructed by the Employer."
"The power supply to all the facilities of the Employer to be made available 24 hours a
day. Generators should be made available at all the facilities. Emergency lighting to be
supplied at each facility."
a) General
"Upon completion of the Contract, the Employer’s Personnel office, buildings, furniture,
equipment, survey instruments, fixtures and services specified herein shall revert to the
Employer. At the end of the Project the Contractor shall be responsible for transportation
of office contents to the facilities of the Employer as directed."
"The Engineer’s office shall have a minimum and internal floor area of 150 m2. The
office shall be completely separate from that of the Contractor shall be fenced with a 2 m
high barbed wire fence and gate, with padlock and chain."
b) Documents
“Original documents of FIDIC Conditions of Contract for EPC/Turnkey Projects, First
Edition 1999, two copies for Employer.”
c) Furniture and Equipment
“All equipment, furniture, fixtures and surveying instruments to be provided as listed in
table 2 with additional attached list and survey instruments to be provided as listed in
table 3 to be approved by the Employer.
17 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
18 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
19 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
20 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
(a) General
The Contractor shall provide accommodation by renting the houses described below for
the entire Contract duration of the Contract for use by the Employer’s site personnel.
Upon completion of the Contract, furniture, equipment and fixtures as specified in the
design drawings and in Table 1 shall revert to the Contractor. All furniture, equipment
and fixtures to be transported to the facilities of the Employer as instructed."
(b) Upon completion of the Contract, the houses listed below shall revert to the Contractor ".
“The Type I house shall be furnished and equipped and in addition shall at least have
three bedrooms, two bathrooms (one en-suite), kitchen, dining room, living room and
store room/lock-up garage.”
“The Type II house shall be furnished and equipped and in addition shall at least have two
bedrooms, two bathrooms (one en-suite), kitchen, dining room, living room and store
room/lock-up garage.”
“The Type III house shall be furnished and equipped and in addition shall at least have
two bedrooms, one bathroom, kitchen, dining room, living room and store room.”
“The Type IV and V house shall be furnished and equipped and in addition shall at least
have one bedroom, one bathroom, kitchen, living room.”
Housing Units
I 4
II 5
III 5
IV 10
V 10
21 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Dining chairs 6 4 4 4
22 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Kitchen table 1 1 2 2
23 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Dustbin 1 1 2 2
24 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
25 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
All vehicles to be supplied by the Contractor shall be brand new, right hand drive, diesel
powered and fitted with air-conditioner and power steering as described below.
2 No. Type 1: Minimum 2.8 -litre 4-wheel drive, or equivalent approved, 5 door Sports
Utility Vehicle or similar approved, fitted with air bags, mobile telephone hands-free headset
and 2-way radio.
3 No. Type 2: Minimum 2.8 -litre 4-wheel drive, or equivalent approved, twin-cab pick-up,
fitted with mobile telephone hands-free headset and 2-way radio. .
2 No. Type 3: Minimum 2.7 -litre 4-wheel drive, or equivalent approved, single cab pick-up
(with canvas back and seat), fitted with mobile telephone hands-free headset and 2-way radio.
A minimum of 1 No. of either Type of vehicles above shall be for the Employer’s use on the
project and will be supplied and maintained by the Contractor throughout the Operations
Service Period. Payment will be made as for the vehicles to be supplied during the Design-
Build period.
The Contractor shall replace any vehicle by a similar new vehicle after it has completed
150,000Km.
Ownership of these vehicles will revert to the Contractor upon completion of the Contract.
The ash content of penetration grade bitumen shall not exceed 0.5% by weight.
26 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Reference pegs shall be 50mm x 50mm in section, 600mm long driven 400 mm firmly into
ground and painted white above ground level. The offset from the centreline shall be
indicated by a small nail 20-25mm long with its head driven flush with the top of the peg.
Chainage, offset and reference elevation shall be clearly indicated on the sides of the peg to
the satisfaction of the Employer.
The Contractor shall take care not to uproot or damage trees which are within the road
reserve but outside the construction width. After the Contractor has staked out the extent of
the road, the Employer, with the assistance of the Contractor, shall mark out the trees to be
removed. After removal, the trunks and branches of these trees shall be cut up into pieces
not more than 2.0 m in length, transported and neatly stored at the nearest Ministry of Roads
and Works camp at a position to be indicated by the Employer.
Section 5:Earthworks
No mass haul diagram has been provided with the Contract documents. The Contractor
shall locate suitable materials for constructing earthworks along the alignment and
elsewhere.
“Fill material which is required in addition to that provided by excavation shall be obtained
from borrow pits to be located and provided by the Contractor but to the approval of the
Employer.”
The Employer will not make available to the Contractor any land for quarries, borrow pits,
stockpile and spoil areas, except for those in the road reserves and specifically approved by
him.
The Contractor will be entirely responsible for locating and proving suitable sources of
materials complying with the Standard and Special specifications and for procurement,
winning, haulage to site of these materials, rehabilitating the borrow pits, quarries, stockpile
and spoil areas, and all costs involved therein. Similarly the Contractor will be responsible
for provision of areas for stockpiling materials and disposal of spoil, as well as the costs
thereof. Should there be suitable areas for spoil dumps or stockpiling within the road
reserve, the Contractor may utilise them, subject to the approval of the Employer.
27 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
No additional payment will be made to the Contractor to cover costs arising from the
requirements of this clause. The Contractor shall include the costs of complying with this
clause in the rates.
Minor
drainage 816 Replace UF1 with F1
structures
28 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Appendix A:
29 | P a g e
Thika Road BRT Section VIII: Employer’s Requirements
Appendix B: Other Design Data
The following data, will be provided by the client to all bidders within a period of one month
from the date of issue of bidding documents for information purposes only. Bidders should
however further appraise themselves of the project conditions through appropriate means to aid
in the preparation of their bids.
30 | P a g e