PROJECT : B-4 L-2 DIANA

OWNER : MS. MARIBETH MAGANTE


DATE : MARCH 09 ,2019

Subject : WORK SCHEDULE


WK 1 WK 2 WK 3
MAR 4 - 9 MAR 11 - 16 MAR 18 - 23
WORK DESCRIPTION M T W TH F S M T W TH F S M T W TH F S

1.0 Lay out / staking Excavation

2.0 Gravel Bedding

B 3.0 Rebars Fabrication wall footing / footing / Column


and Installation
4.0 Form Works Footing

5.0 Concreting footing / wall footing

6.0 Form works Columns Up to Bot. Beams

7.0 Concreting Columns

8.0 CHB Laying Perimeter Wall up to Ground Level

9.0 Back filling and compaction Ground Floor

10.0 Gravel Bedding S O G

Electrical Roughing - in to fixtures


PlumbingRoughing - in to fixtures

Soil Poisoning

Rebars S O G

Concreting S O G

Scafolding/Formworks Second Floor Beams / Slab

Rebars Beams /Columns / Slab/ Dowels

Concreting Second Floor

Scafolding Installation ford columns and roof beams

Columns rebars to roof beams

Concreting Columns

Roof beams Rebars

Roof beams Form works

Roof beam Concreting

Forms removal second floor

CHB Laying Ground Floor


Door Jamb Installation

Plastering Ground

Forms removal Roof Beams

CHB Laying Second Floor

Door Jamb Installation

Plastering Second Floor

Fabrication of Roof Truss/Iron works/Railings

Installation of roof Truss

Installation Facia Board

Roof Covering

Ceiling Works

Painting Interior wall

Painting Exterior wall

Painting Ceiling

Doors Installation
Tiles C R

Tiles Second Floor

Stairs

Tiles Ground Floor and Garage

Cabinet and Counter top

Septic Tank

Painting of doors and door jamb/ counter top

PREPARED BY ;
ENGR. RENZO A. NAVARRO
WK 4 WK 5 WK 6 WK 7 WK 8 WK 9
MAR 25 - 30 APR 1 - 6 APR 8 - 13 APR 15 - 20 APR 22 - 27 APR 29 - MAY 4
M T W TH F S M T W TH F S M T W TH F S M T W TH F S M T W TH F S M T W
WK 9 WK 10 WK 11 WK 12
APR 29 - MAY 4 MAY 6 - 11 MAY 13 - 18 MAY 20 -25
TH F S M T W TH F S M T W TH F S M T W TH F S