6th International Workshop on Concrete in the Americas

Load Transfer at Existing República


Station During Construction of São Paulo
Subway Line 4 – Yellow
Dr. Nelson Lúcio Nunes
Civil Design Department
São Paulo Subway Company
SUMMARY

 SÃO PAULO – GENERAL INFORMATION


 SÃO PAULO SUBWAY SYSTEM
 LINE 4 – YELLOW
 REPÚBLICA STATION CONCEPT FOR LINE 4
 DESIGN MODELING FOR LOAD TRANSFER
 EXECUTIVE SEQUENCE FOR LOAD TRANSFER AND TBM DRAGGING
 INSTRUMENTATION OF TRANSFER LOADS

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
SÃO PAULO – GENERAL INFORMATION

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
São Paulo Metropolitan Area

Brazil
São Paulo State

São Paulo Metropolitan Area - Pop.: 16,3 M


Area: 8051 km²

City of São Paulo – Population: 11 M


Area: 1509 km²
Downtown
Chicago – Population: 2,8 M
Area: 606 km²
City of São Paulo
6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
DOWNTOWN SÃO PAULO
SÃO PAULO SUBWAY SYSTEM

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
SÃO PAULO SUBWAY SYSTEM – 2010
Present:
Total length: 62,3 km
Stations: 56
Passengers: 3,3 Million / day
LINE 1 – Blue
LINE 3 – Red
LINE 2 – Green

LINE 4 – Yellow
(Under Construction)
LINE 2 Extension
(Under Construction)

LINE 5 – Lilac

Line 5 – Future Extension


(Design Under Development)
Logo ACI

LINE 4 – GENERAL FEATURES


 Total Length = 12,8 km
Shield tunnels = 6,4 km
NATM tunnels = 5,5 km
Cut and Cover tunnels = 0,9 km
Surface = Maintanance Yard 111.400 m2
 Number of stations = 11
Cut and Cover: 3 (Faria Lima, Fradique Coutinho and
República)
NATM: 8 (Vila Sônia, Morumbi, Butantã, Pinheiros, Oscar
Freire, Paulista, Higienópolis and Luz)
 Some numbers
Passengers: 900.000 per day (Ridership estimated for 2012)
24 trains with 6 cars each

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
Republica Station
REPÚBLICA STATION
CONCEPT
FOR LINE 4

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
Line 3
(Operating) República
Square

Existing Station Line 4


(Built in 1982) (Under Construction)

Block for Line 4


Built in 1982

Block for Line 4


Under Construction
Single NATM Existing Block
Tunnels
Single NATM
Tunnels

Hilton Shaft Existing


New Block 24 de Maio Shaft
Block

ORIGINAL CONCEPT:
•Tunnel Boring Machine Arrives at Hilton Shaft
• TBM is disassembled at Hilton Shaft
• TBM is assembled at 24 de Maio Shaft
• TBM departures from 24 de Maio Shaft

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
Single NATM Existing Block
Tunnels
Single NATM
Tunnels

Hilton Shaft Existing


New Block 24 de Maio Shaft
Block

ORIGINAL CONCEPT:
• Construction of Shafts demands detours and street
interdictions, causing severe traffic jams and disturbing
neighborhood
• Conception abandonned.

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
Existing Block

Block 5
New Block (Existing)

NEW CONCEPT:
• Tunnel Boring Machine arrives at Station
• TBM is dragged through Station
• TBM depatures from Station
• Shafts are not necessary

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
SÃO PAULO LINE 4 TUNNEL BORING MACHINE

• Earth Pressure Balance

• Outer diameter: 9,50 m

• Inner diameter: 8,43 m

• 30 m Tunnel / day

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
SITUATION FOR LINE 4 WITH
12 13 14 15 15A
ORIGINAL CONCEPT:
LEVEL A - ROOF

CENTRAL PLATFORM

TWO SINGLE TRACKS


LEVEL B

NATM NATM
LEVEL C - LINE 4 PLATFORM Tunnel Tunnel
LEVEL C

11

LEVEL D

LEVEL E - LINE 3 PLATFORM

LEVEL E
SITUATION FOR LINE 4 WITH NEW
CONCEPTION:
12 13 14 15 15A
LEVEL A - ROOF
DOUBLE TRACK SHIELD TUNNEL

TBM ARRIVES AT STATION

DRAGGING OF TBM LEVEL B

LEVEL C - LINE 4 PLATFORM

Tunnel LEVEL C

Boring
Machine
11

COLUMNS ON THE LEVEL D

TBM WAY

????
LEVEL E - LINE 3 PLATFORM

LEVEL E
TBM ARRIVING AT REPUBLICA STATION (NEW BLOCK)
SHIELD TUNNEL FROM TBM ARRIVED AT STATION
WHAT IS NECESSARY TO DRAG TBM
THROUGH EXISTING STATION ?
• BUILD NEW COLUMNS
• TRANSFER LOADS FROM EXISTING COLUMNS TO NEW
ONES
• DEMOLISH EXISTING COLUMNS
• DEMOLISH CENTRAL PLATFORM
• DEMOLISH LEVEL C SLAB
• DRAG TBM THROUGH STATION
• REBUILD LEVEL C SLAB
• BUILD NEW PLATFORMS

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
WHAT IS NECESSARY TO DRAG TBM
THROUGH EXISTING STATION ?
• BUILD NEW COLUMNS
THE CHALLENGE:
• TRANSFER LOADS FROM EXISTING COLUMNS TO NEW
TO PERFORM ALL THESE
ONES
STEPS WITHOUT
• DEMOLISH EXISTING COLUMNS
INTERRUPTING LINE 3
• DEMOLISH CENTRAL – 59,000
PLATFORM
OPERATION
PEOPLE
• DEMOLISH LEVEL AT STATION PER
C SLAB
DAY
• DRAG TBM THROUGH STATION
• REBUILD LEVEL C SLAB
• BUILD NEW PLATFORMS

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
DESIGN MODELING FOR LOAD TRANSFER

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
DESIGN AND ANALYSIS MODELING
• Software: SAP 2000 (Computers & Structures, Inc.)
• Staged Construction Analysis
• Considers overlaping effects in structures
• Each Stage considers accumulated effects in structure
until last stage
• Load Transfer and TBM dragging: Nine Stages of
Structural Modifications
• Staged Construction Outputs:
• 3D Perspective Graphical Displays
• Force Diagrams and Stress Contours

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
3D
6th Perspective Display
International Workshop of 1stinStage
on Concrete the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
3D
6th Perspective Display
International Workshop of 2ndin Stage
on Concrete the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
FORCE DIAGRAMS

A
STAGE 2 - AXIS C :

B INTRODUCTION OF NEW
STRUCTURES (COLUMNS AND
STEEL BEAMS AT LEVELS A and
B)

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
FORCE DIAGRAMS

Aa
AFTER STAGES 3 AND 4 – AXIS C

B 3 - PARTIAL LOAD TRANSFER


FROM EXISTING COLUMNS
BETWEEN LEVELS A and B

4 - DEMOLITION OF COLUMNS
C BETWEEN LEVELS A and B

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
FORCE DIAGRAMS

AFTER STAGES 5 AND 6 – AXIS C


B
5 - COMPLETION OF LOAD
TRANSFER FROM EXISTING
COLUMNS BETWEEN LEVELS B
and D

C 6 - DEMOLITION OF COLUMNS
BETWEEN LEVELS B and D AND
PARTIAL DEMOLITION OF LEVEL
D C STRUCTURE

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
FORCE DIAGRAMS

A
AFTER STAGES 7 AND 8 – AXIS C

B 7 - RECONSTRUCTION OF LEVEL
C STRUCTURES AFTER TBM
DRAGGING.

8 - INPUT OF LIVE AND


PERMANENT LOADS, AS WELL
C
LOADS FROM LINE 3 AND LINE 4
TRAINS.
D

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
EXECUTIVE SEQUENCE FOR LOAD TRANSFER
AND TBM DRAGGING

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
12 12A 13 14 14A 15 15A

LEVEL A - ROOF

CONSTRUCTION 3 3
OF NEW
COLUMNS LEVEL B

3 3
• CONSTRUCTION
LEVEL C - LINE 4 PLATFORM

OF FUNDATION
LEVEL C
BLOCKS,
INCLINED
PILLARS AND
3 3
TIE MEMBERS
LEVEL D

2
2
2
LEVEL E - LINE 3 PLATFORM

LEVEL E
TIE MEMBER

INCLINED PILLAR
12 12A 13 14 14A
15 15A

LEVEL A - ROOF

LEVEL B

ASSEMBLING OF STEEL
BEAMS WHICH WILL
LIFT EXISTING
STRUCTURES BETWEEN
LEVEL C - LINE 4 PLATFORM

LEVELS A & B LEVEL C

LEVEL D

LEVEL E - LINE 3 PLATFORM

LEVEL E
TRENCHES WHERE BEAMS
WILL BE POSITIONED
PREPARING STEEL BEAMS TO BE LIFTED
LIFTING OF LEVEL A STEEL BEAMS
VERTICAL TENDONS DUCTS
LEVEL A SLAB

LOAD TRANSFER VERTICAL TENDONS

NEW COLUMN EXISTING COLUMNS


CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

6 7

LEVEL C - LINE 4 PLATFORM

PARTIAL LOAD
TRANSFER TO NEW LEVEL C

COLUMNS, BY
PRESTRESSING OF 8
VERTICAL TENDONS,
WHICH LINKS LEVEL D

EXISTING CONCRETE
STRUCTURE TO STEEL
BEAMS ASSEMBLED AT
LEVEL E - LINE 3 PLATFORM
LEVEL A
LEVEL E
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

DEMOLITION OF EXISTING
COLUMNS AT AXES 13
AND 14, BETWEEN 9
8

9
9
LEVELS A and B
LEVEL C - LINE 4 PLATFORM

LEVEL C

10

LEVEL D

LEVEL E - LINE 3 PLATFORM

LEVEL E
LOAD TRANSFER VERTICAL
TENDONS

DEMOLITION OF EXISTING COLUMN BY DIAMOND WIRE SAW CUTTING


CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

9 9
9
LEVEL C - LINE 4 PLATFORM

LEVEL C

10 Assembling of level B steel


beams at axes B, C and D
LEVEL D

LEVEL E - LINE 3 PLATFORM

LEVEL E
PREPARING STEEL BEAMS FOR LIFTING
LIFTING OF STEEL BEAMS
JACK

JACK BASE JACK BASE

STEEL BEAM POSITIONED OVER CORBELS


ASSEMBLING OF JACK BASE FINISHED
POT BEARING

CORBEL

JACK BASE JACK BASE


CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

9 9
9
LEVEL C - LINE 4 PLATFORM

LEVEL C

10

LEVEL D

execution of load transfer


from existing columns at LEVEL E - LINE 3 PLATFORM

the axes 13 and 14 for new LEVEL E

columns at axes 12A and


14A
25690

50 POT BEARING
SUPPORT CORBEL

100
920

50

D
P.T
920

CONCR
6376 3700 5280 4385 5949

ETE BE
50
PLAN

AM FAC
200

E
SECTION
1700 ou 1840

CONCRETE FILLING UNDER SLAB JACK


EXISTING SLAB
700

EXISTING BEAM
970

20
STEEL BEAM STEEL BEAM
130

SHEET STIFFENER 25.0

PLATE 25.0 x 450


200 200
PS 450 x 450 x 31.5 x 25 PLATE STIFFENER 25.0
1700 ou 1840

CONCRETE FILLING UNDER SLAB JACK


EXISTING SLAB
700

EXISTING BEAM
970

20
STEEL BEAM STEEL BEAM
130

SHEET STIFFENER 25.0

PLATE 25.0 x 450


200 200
PS 450 x 450 x 31.5 x 25 PLATE STIFFENER 25.0

Jack action over concrete


structure near to existing
columns
1700 ou 1840

CONCRETE FILLING UNDER SLAB JACK


EXISTING SLAB
700

EXISTING BEAM
970

20
STEEL BEAM STEEL BEAM
130

SHEET STIFFENER 25.0

PLATE 25.0 x 450


200 200
PS 450 x 450 x 31.5 x 25 PLATE STIFFENER 25.0

Reaction over steel


beams
STEEL BEAM

JACK
STEEL WEDGE

JACK BASE
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

LEVEL C - LINE 4 PLATFORM

LEVEL C

12
LEVEL D

Demolition of existing
columns at axes 13 and 14, LEVEL E - LINE 3 PLATFORM

between levels B and D.


LEVEL E
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

LEVEL C - LINE 4 PLATFORM

LEVEL C

12
LEVEL D

Demolition of existing
boarding platform at level
C and part of slab and
LEVEL E - LINE 3 PLATFORM

beams of this level, at


LEVEL E
T.B.M. Clearance area.
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

LEVEL C - LINE 4 PLATFORM

LEVEL C

12
LEVEL D

Construction of Tunnel
Boring Machine dragging
cradle.
LEVEL E - LINE 3 PLATFORM

LEVEL E
DEMOLITION WORKS
LEVEL B STEEL BEAMS

EXISTING COLUMNS CUT OFF

TBM

LEVEL C DEMOLISHED

TBM WAITING CONSTRUCTION OF DRAGGING CRADLE


CONSTRUCTION OF DRAGGING CRADLE
DRAGGING CRADLE FINISHED
DRAGGING CRADLE FINISHED
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

LEVEL C - LINE 4 PLATFORM

DRAG OF
TUNEL BORING MACHINE LEVEL C

13

LEVEL D

Dragging of Tunnel Boring


Machine

LEVEL E - LINE 3 PLATFORM

LEVEL E
TBM DRAGGING
TBM SHIELD TBM BACKUP
LEVEL D SLAB

UNDERPINNING

LINE 3 PLATFORM

UNDERPINNING OF LEVEL D SLAB DURING PASSAGE OF TUNNEL


BORING MACHINE
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

17
LEVEL C - LINE 4 PLATFORM
TOP OF
16
RAILHEAD

LEVEL C

Disassembling of Tunnel
Boring Machine dragging LEVEL D

cradle

Reconstruction of slabs and


beams of the level C. LEVEL E - LINE 3 PLATFORM

LEVEL E

Constructiion of new
platforms at level C.
RECONSTRUCTION OF LEVEL C SLAB AND PLATFORMS
CONCRETE COVER
12A 13 14 14A
12 15 15A

LEVEL A - ROOF

LEVEL B

LEVEL C - LINE 4 PLATFORM


TOP OF
RAILHEAD

LEVEL C

LEVEL D

LEVEL E - LINE 3 PLATFORM

LEVEL E
INSTRUMENTATION OF TRANSFER LOADS

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
ISTRUMENTATION
• VIBRATION WIRE STRAIN GAGES
• Arc Weldable Strain Gage
• Concrete Embedment Strain Gage
• Fiber Optic Rebar Strainmeter
• Temperature Strain Gages
• IMPLEMENTATION AND OPERATION
• LPC LATINA (BRAZIL)
• EQUIPMENT
• GEOKON, Inc. (New Hampshire – USA)
• SOFTWARE
• Vista Data Vision database - Vista Engineering (Iceland)

6th International Workshop on Concrete in the Americas

Load Transfer at Existing República Station During Construction of São Paulo Subway Line 4 – Yellow
SG "ST
VIBRATING WIRE STRAIN GAGE
C

P SETTLEMENT
PI CONTROL
ST "ST
TEMPERATURE STRAIN GAGE
SB "ST
FIBER OPTIC REBAR STRAINMETER
D
85

PILARES EXISTENTES
Arc Weldable Strain Gage
Concrete Embedment Strain Gage Fiber Optic Rebar Strainmeter

Data Acquisition:

10 Multiplexers
2 Dataloggers
2 Computers
AUTHORS
• São Paulo Subway Company
• Civil Conception Department
• Roberto Yazbek Junior (Coordinator)
• Danton Soares Junior (Supervisor)
• Nelson Lúcio Nunes (PhD, Specialized Engineer) – SPEAKER
• Rafaelle Tiboni Fioranelli (MsE, Civil Design Engineer)
• Helder José Ribeiro Soares (Civil Design Engineer)
• Line 4 Construction Department
• Alberto Benedito de Lima Junior (Chief )
• Sérgio Renato de Arruda Leme (Coordinator)
• Yasushi Uema (Senior Engineeer)
• Via Amarela Consortium
• Walter de Almeida Braga (PhD Senior Structural Designer )
• João Rocha (Senior Structural Designer )
• Milton Carvalhal (Construction Coordinator )
6th International Workshop on Concrete in the Americas

THANK YOU