JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 5-Sep-19 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS
C MASONRY WORKS
11

External Plastering

A/ 2-4 m2 1.0 10.350 5.800 60.03

A/1-2 & 4-5 m2 2.0 0.5*(5.80+5)*4.525 48.87

A-C /1 & 5 m2 2.0 10.400 5.000 104.00

Cement rendering for Gate m2 24.600


Actuator Room
237.500

Converting to ft2 ft2 10.764 237.5 2,556.45


-

Total ft2 2,556.45


JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 5-Sep-19 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH(m) WIDTH HEIGHT QTY TOTAL QTY REMARKS

CF -
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 5-Sep-19 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS
-
A-C/3 1.0 2.0 9.980 5.400 107.784

A-C/4 1.0 2.0 10.070 5.400 108.756 216.540 216.54

Sub station

Foundation m2 1.0 1.0 13.700 0.600

Wall two sides 2.0 1.0 3.000 3.375 20.250

Wall two sides 2.0 1.0 3.450 3.375 23.288

Wall front and back 2.0 1.0 4.200 3.375 28.350

2.0 1.0 4.650 3.375 31.388 103.28

Total 319.815
BOQ NO
BOQ NO

BOQ NO
BOQ NO
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 29/07/2019 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH HEIGHT WIDTH QTY TOTAL QTY REMARKS
C MASONRY WORKS
11 m2

Formwork

A-C/1
Stiffner beam 2.0 2.0 4.675 0.225 4.208

Stiffner columns 2.0 2.0 4.250 0.225 3.825

stiffner column 1.0 2.0 2.390 0.225 1.076

A/1-2
Stiffner column (4.65-0.225) 1.0 2.0 4.425 0.225 1.991

stiffner beam 1.0 2.0 4.175 0.225 1.879

A/2-3
stiffner columns 2.0 3.0 2.2 0.225 2.970

stiffnerbeams 1.0 2.0 4.65 0.225 2.093

Add for bottom 1.0 1.0 1.20 0.225 0.270

stiffnerbeams 1.0 2.0 4.65 0.100 0.930


Add for bottom 1.0 3.0 0.760 0.225 0.513

Total 19.754
29/07/2019 SHEET NO

BOQ NO TOTAL QTY REMARKS


19.754
A/3-4
stiffner column 1.0 2.0 5.05 0.225 2.273

stiffner column 1.0 2.0 2.65 0.225 1.193


-
stiffnerbeams 1.0 2.0 4.65 0.225 2.093

Add beam bottom 1.0 1.0 1.00 0.225 0.225

A/4-5

Stiffner column (4.65-0.225) 1.0 2.0 4.425 0.225 1.991

stiffner beam 1.0 2.0 4.175 0.225 1.879

Add beam bottom 1.0 1.0 2.753 0.225 0.619

A-C/15

Stiffner beam 2.0 2.0 4.675 0.225 4.208

Stiffner columns 2.0 2.0 4.25 0.225 3.825 18.304


CF 38.058
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 29/07/2019 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS
38.058
C/2-3

Stiffner beam 1.0 2.0 3.490 0.225 1.571

Add bottom 1.0 1.0 2.815 0.225 0.633

Stiffner columns 2.0 4.0 2.460 0.225 4.428

1.0 2.0 2.650 0.225 1.193

1.0 3.0 2.650 0.225 1.789

A-C/1a
Stiffner beam 1.0 2.0 5.740 0.225 2.583

Stiffner beam 1.0 2.0 3.040 0.225 1.368

Add beam bottom 2.0 1.0 0.700 0.110 0.154 13.718

Total 51.776
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 26-Jul-19 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS
51.776
Stiffner columns 4.0 2.0 4.830 0.225 8.694

Stiffner columns 4.0 1.0 2.200 0.110 0.968

A-C/2 cont..

Stiffner beam 1.0 2.0 9.160 0.225 4.122

Stiffner column 1.0 2.0 5.050 0.225 2.273

Stiffner columns 3.0 2.0 5.400 0.225 7.290

Stiffner columns 2.0 1.0 5.400 0.110 1.188

A-C/3

Stiffner beam 1.0 2.0 9.200 0.225 4.140

Add beam bottom 1.0 1.0 0.880 0.110 0.097

Stiffner column 2.0 2.0 5.050 0.225 4.545 33.316

Total 85.092
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 26-Jul-19 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS
m2 85.092
Add column 1.0 1.000 2.150 0.110 0.237

A-C/4

Stiffner beam 2.0 2.0 10.070 0.225 9.063

Stiffner column 2.0 2.0 5.400 0.225 4.860

Total 85.092
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 26-Jul-19 SHEET NO


BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS
85.092
SUB STATION
Stiffner beam 1.0 2.0 4.2 0.225 1.890

Add for beam bottom 1.0 1 2.8 0.225 0.630 2.520

Total 87.612
JFE EC PROJECT MPS

MEASUREMENT SHEETS DATE 26-Jul-19 SHEET NO

BOQ NO DESCRIPTION UNIT NO NO LENGTH WIDTH HEIGHT QTY TOTAL QTY REMARKS

Total -