Sunteți pe pagina 1din 106

FIRE SAFETY PLAN

Prepared for:
BANANI DCC UNIQUE COMPLEX
Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213

Prepared by:

.
House – 27, Road – 01, Sector – 06, Uttara, Dhaka – 1230, Bangladesh

Approved By:
Bangladesh Fire Service & Civil Defence
38-46, Kazi Alauddin Road, Dhaka 1000
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
Contents
1. DEFINITIONS .............................................................................................................................................................. 2
2. FIRE SAFETY PLAN OBJECTIVES& PURPOSE ................................................................................................. 6
2.1 Objective ....................................................................................................................................................................... 6
2.2 Purpose.......................................................................................................................................................................... 6
2.3 Assignment of Responsibility ....................................................................................................................................... 7
2.4 Plan Implementation: .................................................................................................................................................... 7
3. BUILDING INFORMATION ...................................................................................................................................... 8
General Description: ........................................................................................................................................................... 8
4. EXISTING ACTIVE FIRE PROTECTION SYSTEMS......................................................................................... 17
5. EXISTING PASSIVE FIRE PROTECTION SYSTEMS ....................................................................................... 21
6. FLOOR PLANS (DRAWING) .................................................................................................................................. 23
7. HUMAN RESOURCES .............................................................................................................................................. 24
8. GENERAL RESPONSIBILITIES ................................................................................................................................ 27
8.1 Management Responsibility ........................................................................................................................................ 27
8.2 Workers Responsibilities ............................................................................................................................................ 28
9. RECORDS OF ELECTRICAL SAFETY, FIRE DRILL AND EVACUATION DRILL ETC. .......................... 31
10. INSPECTION, MAINTENANCE & TESTING ........................................................................................................ 34
11. EVALUATION OF WEEKNESS AND GAPS IN EXISTING FIRE SAFETY PLAN ......................................... 54
12. SUGGESTIONS FOR FIRE PREVENTION, PREPAREDNESS & CONTROL ................................................. 62
13. MAINTENANCE LOG ................................................................................................................................................ 95
14. ANNEX......................................................................................................................................................................... 105

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 1
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Figure: 1.0.0 Site front view

1. DEFINITIONS

Automatic Fire Detection and Alarm System –

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 2
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
Fire alarm system comprising components for automatically detecting a fire, initiating an alarm of fire and initiating
other actions as appropriate.

Automatic Sprinkler System –


A system of water pipes fitted with sprinkler heads at suitable intervals and heights and designed to actuate
automatically, control and extinguish a fire by the discharge of water.

BNBC-
A part of the building code which has requirements applicable for fire protection as per Bangladesh National Building
Code.

Combustible Material –
The material which either burns itself or adds heat to a fire

Emergency Lighting-
Lighting provided for use when the supply to the normal lighting fails.

Emergency Lighting System –


A complete but discrete emergency lighting installation from the standby power source to the emergency lighting
lamp(s), for example, self-contained emergency luminaries or a circuit from central battery generator connected
through wiring to several escape luminaries.

Escape Lighting –
That part of emergency lighting which is provided to ensure that the escape route is illuminated at all material times,
for example, at all times when persons are on the premises, or at times the main lighting is not available, either for the
whole building or for the escape routes.

Fire Door –A fire-resistive door approved for openings in fire separation.

Fire Exit-

A way out leading to an escape route having panic bar hardware provided on the door.

Fire Lift –

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 3
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

The lift installed to enable fire services personnel to reach different floors with minimum delay, having such features
as required in accordance with this Part.

Fire Load –
Calorific energy, of the whole contents contained in a space, including the facings of the walls, partitions, floors and
ceilings.

Fire Load Density-


Fire load divided by floor area.

Fire Resistance Rating –


The time that a material or construction will withstand the standard fire exposure as determined by fire test done in
accordance with the standard methods of fire tests of materials/structures.

Fire Safety Plan –

A plan which provides occupant information for control of fire hazards, maintenance of fire protection systems, and
evacuation procedures for their building.

Fire Separation –
The distance in meters measured from the external wall of the building concerned to the external wall of any other
building on the site, or from other site, or from the opposite side of street or other public space for the purpose of
preventing the spread of fire.

Fire protection systems –

A general term used in this document which includes sprinkler and fire alarm systems, hose stations, portable fire
extinguishers, fire dampers, emergency lights, exit signs, fire doors, smoke control equipment, and voice
communication systems.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 4
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
Roof Exits –
A means of escape on to the roof of a building, where the roof has access to it from the ground. The exit shall have
adequate cut-off within the building from staircase below.

Smoke Detector –

A combined smoke detector and audible alarm device designed to sound an alarm within the room or suite in which it
is located upon the detection of smoke within the room or suite.

Supervisory staff –
Those occupants of a building who have been appointed to take responsibility for some aspect of the fire safety plan
(Fire Safety Director & Deputies).

Ventilation –
Supply of outside air into, or the removal of inside air from an enclosed space.

Venting Fire –
The process of inducing heat and smoke to leave a building as quickly as possible by such paths that lateral spread of
fire and heat is checked, firefighting operations are facilitated and minimum fire damage is caused.

Wet Riser –
An arrangement for firefighting within the building by means of vertical rising mains not less than 100 mm nominal
diameter with landing valves on each floor/landing for firefighting purposes and permanently charged with water from
a pressurized supply.

Wet Sprinkler System –


A fire sprinkler system which has sprinkler supply piping containing water. Such a system cannot be installed in areas
subjected to freezing conditions as water is always in the sprinkler piping.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 5
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
2. FIRE SAFETY PLAN OBJECTIVES & PURPOSE
2.1 Objective
Fire safety planning has 3 primary objectives:
 Fire Hazard Control
 Fire Protection System Maintenance
 Emergency Evacuation
Fire Safety Planning prevents the occurrence of fire by the control of fire hazards in the building, ensures operation of
fire protection systems by establishing maintenance procedures, and provides a systematic method of safe and orderly
evacuation of the building in the event of fire.
A Fire Safety Plan is a detailed document designed to deal with all aspects of fire safety relating to a specific building
or property. The document is intended to be a reference manual outlining the fire safety practices to be routinely used.
Fire Prevention and Control
To prevent the occurrence of the fire through the control of fire hazards and the proper maintenance of the building
safety systems and facilities, establish procedures that will maximize the probability of controlling and extinguishing a
fire in the safest and most efficient manner.
Occupant Safety
To establish a systematic method including Emergency Procedures for safe and orderly evacuation of the building in
the case of a fire or other emergency and training for responsible supervisory staff.

2.2 Purpose
A Fire Safety Plan is designed by the building owner to identify the actions that should be taken by the occupants and
building management in the event of a fire or similar emergency situation. In addition, actions are identified which
must be implemented and documented, where required, in order to maintain fire protection systems and assist in the
prevention of fire on the premises. The Fire Safety Plan therefore covers fire prevention, evacuation and emergency
response. A copy of this plan is to be made available to all supervisory staff and employees. All recipients of this plan
are required to study the procedures outlined and be prepared to follow these procedures in case of fire or any other
emergency.
This Fire Safety Plan has been created to assist building owners and supervisory staff in preparing a Fire Safety Plan,
to achieve compliance with BNBC fire Code. It will be used the enclosed information as a guide only and customize
the information to reflect the property and existing fire protection systems installed and existing fire hazards.
The Fire Safety Plan is a unique document tailored to the individual needs and resources of a building.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 6
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

The purposes consist of:


 Emergency Procedures to provide owners and occupants/users of the building
 With the information they require to safely evacuate the building.
 Appointments and training of Supervisory Staff and provide a useful, organized information source of
responsibilities for Fire Safety.
 Maintenance of Building Facilities procedures including checks, testing and inspection requirements of the
Fire Code.
 Alternative Measures in case of power failures or system failures.
 Providing a guide for emergency responders in the case of an emergency involving the building.

2.3 Assignment of Responsibility


The owner is responsible for ensuring that the plan is correct and complete and that it is implemented and maintained
in order to achieve the above purpose and objectives.

2.4 Plan Implementation:


The implementation of a Fire Safety Plan helps to assure effective utilization of life safety features in a building, to
protect people from fire. The required Fire Safety Plan should be implemented by the resources of each individual
building or complex of the buildings.
If anybody fall under any of the below, it is himself or herself who is responsible for the plan Implementation.
 An employer
 The owner
 Facilities Manager
 Building Manager
 Risk Assessor

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 7
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
3. BUILDING INFORMATION
General Description:

COMMERCIAL BUILDING NAME: BANANI DCC UNIQUE COMPLEX


Address: Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213
Total Building Area: 83,120.33 sqm

Main Commercial building Building:


a. Buildingt Area : 83,120.33 sqm
b. Construction Date: N/A
c. Basic Construction: Rcc Structure
d. Building Height: 45.8 ft.
e. Internal Road Width :14.5 m
f. Internal Road Height: Open to Sky.
g. Number of Stair: 02 Nos
Stair Wide:
Stair-01: 1.5m.
Stair-02: 1.5m.
h. Building Use: commercial building

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 8
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Different Service Locations in Main Building:

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 9
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Layout of Master Plan

Building Name: BANANI DCC UNIQUE COMPLEX


PP Bag Warehouse/
Heat Treatment and Chemical Godown
Building Area: 331,800 ,Sft
Basic Construction: Steel Structure
Number of Storied: 2 Storied
Number of Stair: 4 Stairs
Number of Fire Exit: 4 ways
Building Use: Cement Fibre Manufacture

i. Location:

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 10
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Figure: Location Map

a. Service Location:
Water Reservoir location(s) :
Transformer Room location(s): Beside main building (Separated & Segregated).
Generator Room location(s) : Beside Transformer Room (Separated & Segregated).
Switch Gear Room location(s): Beside Transformer Room.
Compressor Room Location: Beside Transformer Room.

b. Hazard Locations:
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 11
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
 Generator Room: Separated Shed Building
 Sub-Station: Separated Shed Building
 Chemical Store: Separated Shed Building
 Wastage Store Area: Separated Shed Building
 Boiler: Separated Shed Building
 Compressor: Separated Shed Building

c. Exits:
 Number of Exits: Main Building-02
 Locations: Every Floor
(Details Is included in Annex-A)

d. Emergency Power & Lighting

 Emergency generator: Yes


 Fuel: Diesel
 Location: Ground Area
 Automatic Battery Charger: Yes
 Serves: Stand By

(Details Is included in Annex-A)

e. Fire Pathways and Building Service


 Opening in the separating wall: N/A
 Smoke and heat vents: Yes
 Electrical, gas and HVAC Services: Yes
 Surface finishes: General
 Wired glass panels: Yes
 Fire lift: N/A
(Details Is included in Annex-A)

f. Electrical Rooms & Equipment


 Substation location: Ground Floor
 Generator location: Ground Floor
 Transformer location: Ground Floor
 MDB/DB/SDB/SB/MCB BOX/Others: Every Floor
 Low Tension Panel (LT,415/230V), Location: Electrical room
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 12
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
 High Tension Panel (11 KV) Location: Electric room
 Meter Room (HT/LT meter), Location: Electrical room

Figure: Low Tension Panel


g. Electrical and electronic Engineering Installation
 Electrical connection: Every Floor
 Wiring: Every Floor
 Wiring for lights: Every Floor.
 External influence/A
 Selection and erection to minimize spreading of fire: Fire door, Fire separation barriers,
Fire Separation Shaft has been implemented as per fire design.
 Conduits and conduit fittings: PVC, Metallic Tray
 Lighting protection system: Yes
 Earthing-
 Circuit and system of earthing: Yes
 Methods of earthing: Resistance-earthed neutral.
(Details Is included in Annex-B)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 13
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

h. Chemical/Flammable/Combustible Storage
 Location/Quantity: Ground Floor.

j. Transformer
 Location: Basement-1, Basement-1
 03 Nos
 Capacity- 2500 KVA,2000 KVA
 Dry Type
 Segregated and separated.

Figure: Transformer-2000 KVA

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 14
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
j. Generator

 Location: Basement-1 & Ground floor


 Diesel generator.
 Segregated and separated unit.
 Nos-05
 Capacity: 2000KVA,500 KVA
 Three Phase

Figure: Diesel Generator (Sample)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 15
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

k. Fire Control Room:


 Location: FACP ROOM LEVEL-8
 Type: addressable
 Battery Capacity: 24 vot Dc power
 NOS: 05
 Model : 4100 ES

Figure: Sample Fire Alarm Panel (Sample)

l. Interior Decoration Material: N/A

m. Structure: Steel Structure and RCC.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 16
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
4. EXISTING ACTIVE FIRE PROTECTION SYSTEMS

a. Portable Fire Extinguishers


i. Total - 156 pcs Fire Extinguisher. Where- ABC Dry Powder 110 pcs and
CO2 46 pcs.
 Locations: Every Floor

Figure: Fire Extinguisher


(Details Is included in Annex-A)

b. Fire Hydrant
 Type: Class I & II
 Location: Ground Floor (Pump Room)
(Details Is included in Annex-A)

c. Standpipe System
 Type: Class I & II (Wet Riser)
 Riser locations: Ground Floor beside the stairs
 Riser isolation valve locations: Every Floor (Starting Point of Every Riser)
 Hose connection locations: Every Floor
 Siamese connection location: Main Entrance
(Details Is included in Annex-A)
Pressure reducing valves
 Location: Pump Room (Diesel Pump)
 Type: Diaphragm type PRV

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 17
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

d. Sprinklers
 Locations: Warehouse
 Valve type: Wet
 Isolation valve locations: Butterfly
 Main Supply Shut-Off location: N/A
 Siamese location: Ground Floor
 Test valves location: Same Floor
 Air pressure maintenance: Yes

e. Fire Alarm System: Yes

f. Fire Detection System:


 Monitored: Control Room
 Annunciator location: Control Room
 Main Fire Alarm Location: Ground Floor (Control Panel)
 Heat detector locations: Every Floor
 Smoke detector locations: Every Floor
 Smoke alarm locations: Every Floor
 Strobe and Horn location: Every Floor
 Manual pull station locations: Every Floor
 Control Panel location: Ground Floor
 Main Entrance door: Ground Floor
(Details Is included in Annex-A)

Figure: Sample Sounder & Manual Call Point

g. Command Station
 Location: Ground Floor (Control Room)
 (Details Is included in Annex-A)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 18
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
h. Fire Pump: Electrical and Diesel and Jockey Pump:
 Rate of flow: Jockey pump: 20GPM, Electrical & Dassel Pump: 500GPM
 Pressure: 12 bar at pump house and 4.5bar at remote area.
 Location: Ground Floor (Pump House)
(Details Is included in Annex-A)

i. Jockey Pump:
j. Rate of flow: Jockey pump: 20GPM
k. Pressure: 12 bar at pump house and 4.5bar at remote area.
l. Location: Underground Basement (Pump House)

Figure: Fire Hydrant Pump Set (Sample)

m. Means of Exit Signs and illumination


 Location: Every Floor
 Graphics: Electronics
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 19
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
 Illumination: Average More than 50Lux
 Source of power: IPS
 Floor level exit signs: Every Exit
(Details Is included in Annex-A)

n. Fire Department Access Routes


i. Width: 120’-00” Adjacent with Dhaka-Chittagong Highway road.
ii. Marked: Aisles Mark
iii. Locations: Main Entrance with Dhaka-Chittagong Highway road.
(Details Is included in Annex-A)
o. Fire Department Access to Roof
 Location: North-West Corner of the building.
 Key Location: Control Room.
(Details Is included in Annex-A)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 20
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
5. EXISTING PASSIVE FIRE PROTECTION SYSTEMS

Part- Existing Passive Fire Protection Systems


v
Structural Fire Protection System Yes No N/A Remarks
A (Write Details of Material, Rating &
Type)
Fire Rating of Sub-Station Yes 4 Hours Fire Rated
(as per BNBC 4.4.1.)

Fire Rating of Boiler Room No N/C


(as per BNBC 4.4.1.)

Fire Rating of Generator Room Yes 4 Hours Fire Rated


(as per BNBC 4.4.1.)

Fire Rating of Compressor Room Yes 4 Hours Fire Rated


(as per BNBC 4.4.1.)

Fire Rating of Chemical Store Yes 4 Hours Fire Rated


(as per BNBC 4.4.1.)

Fire Rating of Day Care Room No N/C


(as per BNBC 4.4.1.)

Fire Rating of Canteen Yes 2 Hours Fire Rated


(as per BNBC 4.4.1.)

Fire Rating of Prayer Room Yes 2 Hours Fire Rated


(as per BNBC 4.4.1.)

Penetration between Floor to Stair No N/C

Penetration between Floor to Floor No N/C

Penetration between Floor to Exit No N/C

Penetration between Other No N/C

B Fire Stairs

Wall Rating (as per BNBC 4.4.1.)


Yes 4 Hours Fire Rated

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 21
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
Fire Door Rating (as per BNBC 4.4.1.)
Yes 2 Hours Fire Rated

Width of stair and fire door


(as per BNBC 4.4.1.) 5’-00”
Yes
Ventilation System (as per BNBC 4.4.1.)
Yes
Air Pressurized System (as per BNBC
4.4.1.) Yes

Hand Rail Type (as per BNBC 4.4.1.)


Yes
Emergency light available or not (as per
BNBC 4.4.1.)
Yes
Compartmention- Fire Barrier, Fire
C
Wall, Partition & Smoke Barrier:

Fire Stairs
Yes

Substation Room
Yes

Generator Room
Yes

LT & HT Panel Room


Yes

Ceiling
NA

Open Protection Fire & Smoke


D
damper used in Duct system or not.
N/A

Fire stopping materials in Electrical


line, plumber, communication & gas
E
services holes are sealed and protected
with fire stop system or not.
N/A

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 22
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

6. FLOOR PLANS (DRAWING)

a. Active & Passive Fire Protection System (Including Annex-A)


b. Fire Detection & Alarm System (Including Annex-B)
c. Single Line Diagram (Including Annex-C)
d. Lightning Protection System (Including Annex-D)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 23
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

.
7. HUMAN RESOURCES

FIRE SAFETY MANAGEMENT STRUCTURE


The person with the overall responsibility for fire safety: - Responsible Person:
Iftakharul Alam (fire
Planning: Structure of organization safety officer)
Organization: Setting objectives, policy and procedures Position:
Control: Identify person responsible to tasks / actions FIRE OFFICER
Monitoring: Checks and the implementation of standards
Review: Reviews of fire safety performance standards

Responsible Person:
The person with responsibility for fire safety risk assessment: Engr. Md. Nurey Alam
Siddik
 Carrying out fire safety risk assessment Position:
 Review of fire safety risk assessments Head of Engineering

The person with responsibility for the maintenance program: Competent Person:
 Fire detection and warning system Md.Shajahan mondal
 Emergency lighting Position:
 Escape routes Electrical Engineer
 Fire safety signs and notices
 Fire resisting walls, partitions and doors
 Firefighting facilities
 Electrical appliances and premises installations
Competent Person:
The person with responsibility for developing and reviewing the Md.Shajahan mondal
premises Fire Safety Management Plan which details the procedures
Position:
to be taken by all staff, visitors, members of the public, service users
Electrical Engineer
and all relevant person in the event of fire.

The person with responsibility for staff training: Competent Person:


 What to do in the event of fire Ahmed Kamrul Hasan
 What to do upon hearing the fire alarm Position:
 Liaison with the fire service Head of Compliance
 Emergency shutdown procedures
 Firefighting arrangements

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 24
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
PLOT-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Higher Management and key personnel:


Head of HR & Compliance: Ahmed Kamrul Hasan 01713375888
Head of Compliance: Ahmed Kamrul Hasan 01713375888
Head of Engineering Engr. Md. Nurey Alam Siddik 01794706245
Electrical Engineer: Md.Shajahan mondal 01715119688

Building Security: Banani unique Complex

Responsible Person:
Fire Marshal: Md. Abdul Hannan Sarker 01769501461
Fire Marshal: Md. Ruhul Amin Sardar-1 01924151435
Fire Marshal: Md. Abdul Wahid 01751520978

Fire Marshal: Md. Ruhul Amin 01912733841

 Number: Four Person (Fire Marshal)


 Location: Ground Floor
(Details Is included in Annex-A)

Emergency Lighting Units


Emergency lighting units connected to battery pack units are installed in the following areas: Each and Every Floor
To maintain 50 lux at aisle marks.
(Details Is included in Annex-A)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 25
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Main Natural-gas Supply Shut-off


 Location: N/A
(Details Is included in Annex-A)

Heating, Ventilation & Air Conditioning


 Type of heating: N/A
 Ventilation system: N/A
 Mechanical exhaust system: N/A

Water facilities
 Water requirement for interior fire protection: 45000 Gallons (500 GPM*90
Min)
 Water Sources for fire protection: Reserve water
 Individual Water sources: Industrial Water, Industrial potable water.
(Details Is included in Annex-A)

Fire Department Keys


 Location: Control Room.
 Access for: Fire Safety trained persons.
(Details Is included in Annex-A)

Areas of Refuge
 Locations: In Front of Main Building.
(Details Is included in Annex-A)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 26
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

8. GENERAL RESPONSIBILITIES

8.1 Management Responsibility


Responsibilities of Owner
The owner of a building is responsible for preparing a Fire Safety Plan and must ensure that the building
and facilities comply with the provisions of the Fire Code.
 Establishment of emergency procedures to be followed at the time of an emergency.
 Appointment and organization of designated supervisory staff to carry out fire safety duties.
 Instruction of supervisory staff and other occupants so that they are aware of their responsibilities
for fire safety.
 Notification of the Chief Fire Official regarding changes to the Fire Safety Plan.
 Maintenance of building facilities provided for the safety of the occupants.

Chief Officers / Managing Directors Responsibility:


 Ensuring that this Policy and/or any departmental fire safety policies/codes of practice that
complement this Policy are in place properly implemented and reviewed.
 Ensuring that a Responsible Person is appointed for all of their premises to oversee and
implement fire safety arrangements and ensure that they are competent and appropriately trained
to undertake their duties.
 Ensuring that arrangements are in place for the completion of fire risk assessments, including,
where appropriate, technical surveys in respect of fire protection.
 Ensuring that fire, security, and health and safety arrangements at each premise are
complementary.

Managers / Section Heads / Department Managers with responsibility for premises or parts
of premises will:

 Ensuring that fire risk assessments are carried out for all their workplaces, and for specific
activities such as hot working involving welding, cutting, work with bitumen, etc.
 Ensuring in conjunction with the outcome of the fire risk assessment that the optimum number
and type of fire extinguishers are installed in appropriate locations.
 Ensuring that fire alarm and detection systems, emergency lighting and fire extinguishers are
appropriately located and properly maintained.
 Ensuring that a robust and effective emergency plan is in place at each location to safely evacuate
all persons, whether employees, visitors or service users. This emergency plan must take into
account people with mobility, some sensory and some learning impairments, including those with
temporary impairments, which will affect their ability to use stairs or otherwise evacuate premises
promptly. The plan must be internally deliverable and not reliant on the Fire and Rescue Service
to complete the evacuation.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 27
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Arranging for the emergency plan to be issued to their employees, visitors, etc. to inform them
what to do in the event of fire, particularly safe evacuation.
 Arranging for a competent responsible person (who may also be the premises coordinator) to be
nominated to oversee and implement fire safety arrangements at their workplace(s) on their
behalf.
 Ensuring that if there is any doubt about the provision of new or replacement fire extinguishers.
 Ensuring that staffs are appropriately trained in fire safety procedures to reflect the requirements
of the fire risk assessment.
 Ensuring that a copy of the current fire risk assessment for their premises is readily accessible, its
provisions complied with.
 Ensuring that fire risk assessments are reviewed at least annually or whenever there is any
building alteration, change of occupation or use of the premises or following an incident
involving fire.
 Ensuring that effective arrangements are in place for contacting the emergency services.
 Ensuring that the Fire and Rescue Service are aware of any significant hazards associated with
the premises e.g. oxygen cylinders, storage of petrol, etc;
 Confirming that their quarterly premises fire safety inspections address fire safety arrangements;
and
 Liaising with the local trade union safety representative, where appointed, on all aspects of the
above arrangements.

8.2 Workers Responsibilities


The Common Worker Responsibilities:
 Ensuring they are familiar with the emergency plan for their workplace and co–operate by
participating in fire evacuation/drill procedures and by observing practical fire safety
arrangements.
 Knowing and co-operate with, the responsible person for their workplace.
 Reporting to their manager or supervisor any concerns about fire safety.
 Being familiar with all escape routes.
 Not wedge fire doors open, nor block or obstruct them.
 Being aware of the action to be taken on discovering a fire, hearing a fire alarm, for raising the
alarm (including the location of fire alarm call points) and calling the fire and rescue service.
 Promptly evacuate the premises, in accordance with the emergency plan, to a place of safety
without putting themselves and others at risk, and NOT attempt to extinguish a fire unless they
have been specifically trained.
 Complying with the No Smoking legislation.

In the Event of fire:


 Sounding a verbal alarm and/or alert other staff.
 Leaving the fire area immediately and assist anyone in immediate danger to evacuate.
 Communicating clearly and distinctly when giving instructions.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 28
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Closing all doors behind you to confine the fire; turn off or power down heat source equipment
and appliances
 Notifying the Bangladesh Fire service Department. (Doing this from a safe location.) Calling 02-
9555555.
 Meeting the fire crews and inform the Fire Officer regarding conditions in the building.
Providing access and assistance to fire crews as directed.
 Staying clear of the building until the “All Clear” has been given from fire officials.
 If designated with fire emergency duties, carry out pre-planned procedures.

Upon Hearing an Alarm of Fire:


 Leave the building immediately, use the nearest exit.
 Shutdown heat source equipment where applicable.
 Close all doors behind you to confine the fire.
 Ensuring the Bangladesh Fire service Department has been notified. (Do this from a safe
location)
 If designated with fire emergency duties, carry out pre-planned procedures.

NOTE:
 Not to re-enter the building until the “ALL CLEAR” has been given from the fire officials.
 Not to shut off the fire protection facilities until instructed to do so by the Bangladesh Fire service
Department.

Responsibilities of the Designated Staff


 Being in complete charge of the approved Fire Safety Plan and the specific
responsibilities of the personnel.
 Educating and train all building personnel and occupants in the use of the existing fire
safety equipment and in the actions to be taken under the approved Fire Safety Plan
including emergency procedures.
 Knowing the location and number of exits.
 Ensuring that a schematic diagram, showing type, location and operation of all building
fire systems & instructions.
 Controlling of fire hazards in the building.
 Provisioning of alternative measures for safety of occupants during shutdown of the fire
protection equipment.
 Ensuring that fire drills are carried out regularly, as required. Approved location – put up
front. Prepared approval inspection.
 Assuring that checks, tests and inspections as required by the Fire Code are completed on
schedule and records are retained and maintained.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 29
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Assist and support with the preparation and review (at least annually) of fire safety risk
assessments.
 Ensuring compliance with the outcomes of the Fire Risk Assessment and that the
necessary control measures are implemented.
 Preparing and reviewing the emergency plan issued to all staff.
 Ensuring information on fire safety arrangements is available to service users and
visitors.
 Ensuring all staff and, where appropriate, contractors are instructed in the emergency
plan.
 Arranging and review fire drills at a frequency of not less than six months.
 Specifying and rehearse the arrangements for assisting visitors, disabled people or those
with temporary physical impairments to safely evacuate the premises. Where appropriate,
a PEEP must be developed.
 Ensuring Fire Alarms are regularly tested at the recommended frequency e.g. weekly.
 Monitoring that fire alarm systems, detection devices, emergency lighting and fire
extinguishers are appropriately and regularly maintained.
 Keeping the fire log book or equivalent up to date.
 Ensuring that fire action notices (displayed as a minimum at fire alarm call points) and
fire signage are appropriate and kept up to date.
 Ensuring all escape routes are kept clear of obstructions and that access to fire
extinguishers and fire alarms is not impeded.
 Ensuring that the annual testing of portable electrical equipment and periodic testing (5
yearly) of the fixed electrical installations has been carried out, and
 Ensuring that quarterly fire safety inspections of the premises are carried out and that
these address fire safety arrangements.

TRAINING OF STAFF
Designated supervisory staff will conduct training
Training Criteria:
 Being able to implement and carry out the emergency procedures as listed in this fire
safety plan.
 Knowing the location and operation of the fire protection equipment and exits.
 Actions, including responsibilities and duties to be taken by supervisory staff and
occupants upon discovery of a fire and when an alarm is heard.
 Understanding what a fire hazard is and to avoid those situations.
 The method of evacuating occupants to a safe location.
 Procedure for calling the fire department using 02-9555555 whenever assistance is
needed.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 30
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Knowing the correct building address.


 Understanding the contents of the fire safety plan

9. RECORDS OF ELECTRICAL SAFETY, FIRE


DRILL AND EVACUATION DRILL ETC.
a. Earthling Resister Records:

b. Thermography Test Resister Records:


Testing Date Next Testing Condition DB/MDB No Comment Tested By
Date

c. Electrical Safety Training Resister:

e. Fire & Evacuation Drill Resister:

f. Fire Extinguisher Checklist:

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 31
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

g. SLD Test Resister:


Testing Date Next Testing Condition DB/MDB No Checked by
Date
02.05.2019 02.011.2019 Good Every Panel Md.Shajahan
mondal
15.04.2019 11.05.2019 Good Every Panel Md.Shajahan
mondal

10.03.2019 15.04.2019 Good Every Panel Md.Shajahan


mondal

09.02.2019 10.03.2019 Good Every Panel Md.Shajahan


mondal

General Instruction to Occupants


 Following the emergency procedures posted on each floor. Taking the exit routes and
evacuate in an orderly way.
 If smoke presents a hazard, it trying an alternate exit.
 If trapped by smoke or fire, staying in your area; closing the door and seal all openings
against smoke.
 Moving to the most protected room and if possible, partially opening the window for air.
Closing the window if smoke comes in.
 Staying low to the floor if smoke enters the room.
 Trying signaling from windows or call for help.
 If a phone is available, calling the Fire Department, telling the communications operator
exactly where you are located.
 Waiting to be rescued – remain calm. Listening for instructions or searching fire fighters.
 Protecting from smoke at all times.

In the event of discovering a fire Occupants will:


 Leave the fire area; take your keys, if readily available.
 Close all doors behind you tightly, DO NOT LOCK.
 Activate the fire alarm, using nearest safe pull station.
 Use exits or exit stairwells to leave the building immediately.
 Do not use the Elevator
 After leaving the building, call 911 (Never assume this has been done).
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 32
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Know and give correct address and location of the building.


 Everyone must meet and be accounted for at the Meeting Area
 Keep the main entrance and all driveways clear for Fire Fighter Personnel.
 Do not return until it is declared safe to do so by the Fire Department Captain.

If anybody in your office or a room and a fire alarm is heard:


 Before opening door, occupant will feel the doorknob for heat. If it’s not hot, brace him/herself
against door and open it slightly. If occupant feel air pressure or a hot draft, closing the door
quickly.
 If occupant fined no fire or smoke in corridor, closing the door behind occupant, WILL NOT
LOCK and leaving by the nearest exit. After leaving the building, calling the fire brigade.
 If Occupant encounter smoke in the corridor or stairwell, moving down the corridor to the other
side of the building, where another stairwell should be clear, or if it is just too difficult or unsafe
return to own office and remain Calm!

If occupant cannot leave his/her office or room or have returned to it because of fire or
heavy smoke, remain in your office or room:
 Closing the door.
 Unlocking the door for possible entry by the firefighters.
 Dialing fire brigade and tell the operator where the occupant is!
 Sealing any cracking where smoke can get in by using towels, mats or any item that will seal the
doorways that is allowing smoke in, as is necessary. (Rolling of wide strong masking tape is a
useful tool to keep in the drawer.)
 Crouching or crawling low to the floor if smoke has entered the room.
 Moving to the most protected room and partially open the window for air (closing the window
however, if smoke comes in.)
 Waiting to be rescued. Remaining calm. Do not panic or jump.
 Listening for instructions or information, which may be given by authorized personnel?

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 33
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

10. INSPECTION, MAINTENANCE & TESTING

General
The BNBC Fire Code Regulations require that fire protection installations be maintained in
operating condition in accordance with Part 4. In most cases the Fire Code does not specify in
detail the necessary inspection, maintenance, and testing procedures; instead, it references
standards such as those developed by the National Fire Protection Association. Where such
standards are referenced by the code, they have been identified in this plan as Reference
Standard.

Record of Electrical Safety, Fire Drill and Evacuation Drill


Earthing Register:
Name of the Commercial building: BANANI DCC UNIQUE COMPLEX
Testing Date Earth pit No Next Testing Condition Comment Tested By
Date
31.08.2019 28 30.02.2020 Good R cc UCFIL (MGI).
Commercial
building
25.02.2019 28 31.08.2019 Good R cc UCFIL (MGI).
Commercial
building
26.08.2018 28 25.02.2019 Good R cc UCFIL (MGI).
Commercial
building

Responsible Personnel from Commercial building


Md.Shajahan mondal
Electrical Engineer

Thermography Register:
Name of the Commercial building:

Responsible Personnel from Commercial building


Iftakharul Alam (fire safety officer)
Electrical Safety Training Register:
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 34
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Name of the Commercial building: Banani Dncc unique Complex

Commercial building Responsible Personnel

Fire and Evacuation Drill Register:


Name of the Commercial building: BANANI DCC UNIQUE COMPLEX

Commercial building Responsible Personnel


Engr. Md. shajahan mondal
Electrical Engineer

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 35
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Electrical and Electronics Equipment Inspection


Inspection of Substation
Commercial building name: BANANI DCC UNIQUE COMPLEX
Date:
Time:
Inspected By Engr. Md. shajahan mondal (Electrical Engineer)

Oil Leaks for Transformer YES/NO Comments


Value of PFI YES

Transformer Protection YES

Availability of Firefighting YES


Equipment

Checking panel boards for YES


proper overcurrent protection.

Activeness of Fire Detection YES


System

Checking Magnetic Contractors YES

Checking The panel Connections YES

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 36
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Inspection of Medium Voltage& Overhead lines


Commercial building name: BANANI DCC UNIQUE COMPLEX

Date:
Inspected By Engr. Md. shajahan mondal (Electrical Engineer)
Equipment YES/NO Comment

Power Transformer YES

Switchgear Enclosure YES

Medium Voltage Air Circuit Breakers YES

Fused LB Disconnect Switchgear NO

Unfused LB Disconnect Switchgear NO

Fused NLB Disconnect Switchgear NO

Unfused NLB Disconnect Switchgear NO

Induction Disc Relays NO

Overcurrent Relays YES

Solid State Relays YES

Overhead Power Line Insulators YES

Overhead Power Line Connectors YES

Overhead Power Line Wooden Poles YES

Overhead Power Line Metal Tower YES


Structure
Surge Arrestors YES

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 37
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Inspection of Lighting/Electrical Circuits


Commercial building name: BANANI DCC UNIQUE COMPLEX
Date:
Inspected By Engr. Md. shajahan mondal (Electrical Engineer)

ELECTRICAL Yes No N/A Comments

No circuit breakers regularly Yes


tripping?
No extension cords used for a Yes
permanent operation?

Are all plugs and cords in good Yes


condition

Are all extension cords plugged Yes


into a grounded outlet when in
use?

No electrical switches, switch Yes


plates or receptacles, cracked,
broken or have exposed contacts?

Do all electrical panels have a Yes


surrounding space of 3 feet clear?

Are all electrical circuit breakers Yes


identified?

Are there any other electrical


issues that need attention at this
time?

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 38
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Inspection of Generator
Commercial building name: BANANI DCC UNIQUE COMPLEX
Date:
Time:
Inspected By Engr. Md. shajahan mondal (Electrical Engineer)

MON TUE WED THU FRI SAT SUN


Staff doing inspection should initial each box as he/she finds that item is
functioning OK.
Running Hours (checking the hourly OK OK OK OK OK OK OK
guage and entering amount)
Generator is clean and in good OK OK OK OK OK OK OK
condition
Shed is clean and in good condition OK OK OK OK OK OK OK

Fuel tank at least 50% full OK OK OK OK OK OK OK

Temperature of Engine OK OK OK OK OK OK OK

RPM OK OK OK OK OK OK OK

Fuel leaks? NO NO NO NO NO NO NO

Fuel cap on? NO NO NO NO NO NO NO

Motor Oil level is okay? OK OK OK OK OK OK OK

Motor Oil condition? OK OK OK OK OK OK OK

Radiator, no leaks? NO NO NO NO NO NO NO

Radiator coolant level okay? OK OK OK OK OK OK OK

Battery connections good? OK OK OK OK OK OK OK

Battery water level ok? OK OK OK OK OK OK OK

Battery Charger is charging? OK OK OK OK OK OK OK

No Leaks (look underneath generator) NO NO NO NO NO NO NO

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 39
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

MON TUE WED THU FRI SAT SUN


Exhaust system is functioning OK OK OK OK OK OK OK
normally?
Auto-start is working? OK OK OK OK OK OK OK
All Tools and equipment are present OK OK OK OK OK OK OK
and in good condition?
Fire extinguisher present OK OK OK OK OK OK OK

Fire extinguisher working OK OK OK OK OK OK OK

First Aid Kit present? OK OK OK OK OK OK OK

First Aid Kit complete? OK OK OK OK OK OK OK


Water decanter (does it need to be OK OK OK OK OK OK OK
drained?)
Documents: OK OK OK OK OK OK OK

Generator Log present? OK OK OK OK OK OK OK

Daily Check forms present? OK OK OK OK OK OK OK

Manuals present? OK OK OK OK OK OK OK

Start engine: OK OK OK OK OK OK OK

Pre-heating works? OK OK OK OK OK OK OK

Motor starts easily? OK OK OK OK OK OK OK

Oil pressure OK? OK OK OK OK OK OK OK

Battery Charging? OK OK OK OK OK OK OK
No unusual smells, lights, OK OK OK OK OK OK OK
sounds?

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 40
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Fixed Extinguishing System: N/A


Reference: NFPA 17, Dry Chemical Extinguishing Systems
Reference: NFPA 17A, Wet Chemical Extinguishing Systems
Reference: NFPA 12A, Halon 1301 Fire Extinguishing Systems
Monthly Inspection
Responsibility: N/A
Procedure:

 The extinguishing system is in its proper location.


 Manual actuators are unobstructed.
 Tamper indicators and seals are intact.
 Maintenance tag or certificate is in place.
 No obvious physical damage or condition exists that may prevent operation.
 Pressure gauge(s), if provided, are in operable range.
 Nozzle blow off caps are intact and undamaged.

Record Keeping:
Monthly Inspection & Testing Report
Semi-annual Maintenance
Responsibility: N/A
Procedure:
Contractor to perform maintenance in accordance with the reference standard.
Record Keeping:
Semi-Annual Inspection & testing Report

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 41
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Portable Fire Extinguishers


Reference Standard: NFPA 10, Standard for Portable Fire Extinguishers
An inspection of an extinguisher is a quick check that an extinguisher is available and will operate.
It is intended to give reasonable assurance that the extinguisher is fully charged and operable.
Maintenance is a thorough check of an extinguisher which is intended to give maximum assurance
that an extinguisher will operate effectively and safely and will normally reveal the need for
hydrostatic pressure testing. Recharging is the replacement of the extinguishing agent.

Monthly Inspection
Responsibility: Engr. Md. shajahan mondal (Electrical Engineer)
Procedure:

 Check portable fire extinguishers for the following:


 Located in designated place
 No obstruction to access or visibility
 Operating instructions on nameplate legible and facing outward
 Seals and tamper indicators not broken or missing
 Determine fullness by weighing or hefting
 Examine for obvious physical damage, corrosion, leakage, or clogged nozzle
 Pressure gauge reading or indicator in the operable range or position

Record Keeping: Monthly Inspection & Testing Report


 Serial number of extinguishers requiring maintenance should be recorded on report for
qualified contractor.
Fill-out extinguisher tag with following information:

 Date extinguisher was inspected


 Initials of person performing inspection

Annual Maintenance

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 42
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Responsibility: Engr. Md. shajahan mondal


(Electrical Engineer)
Procedure:

 Perform maintenance in accordance with the BNCC Fire Code Regulations and NFPA 10,
including any necessary hydrostatic pressure testing.

Record Keeping: Annual Inspection & Testing Report


Means of Escape
Daily Inspection
Responsibility: Engr. Md. shajahan mondal (Electrical Engineer)
Procedure:

 Doors in fire separations shall be inspected to ensure that they remain closed and latched
unless the door is equipped with an acceptable hold open device that will permit the door
to close and latch automatically in the event of fire.
 Corridors used by the public and exits shall be maintained free of obstructions
 Exterior passageway and exterior exit stairs shall be maintained free of snow and ice
accumulations.

Record Keeping: None


Monthly Inspection
Responsibility: Engr. Md. shajahan mondal
(Electrical Engineer)

Procedure:

 Doors in fire separations shall be operated to ensure that they are properly maintained.
Doors equipped with a hold open device must release automatically in the event of a fire.

Record Keeping: Monthly Inspection & Testing Report

Fire Detection & Alarm System


Reference standard: NFPA 72, Inspection and Testing of Fire Alarm Systems.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 43
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Daily Inspection
Responsibility: Engr. Md. shajahan mondal (Electrical Engineer)

Procedure:

 Check Fire Alarm AC power lamp

 Check Fire Alarm trouble lamps


Record Keeping: None
Monthly Testing
Responsibility: Engr. Md. shajahan mondal
(Electrical Engineer)
Procedure:

 Notify the alarm monitoring company, the fire department and the tenants that you are
testing the system. Notify all parties when you have completed testing.
 Under emergency power, one manual alarm initiating device shall be operated on a
rotation basis and shall initiate an alarm condition
 Intended function of all alarm audible signal appliances shall be ensured
 The annunciator panel shall be checked to ensure that the tested devices annunciate
correctly.
 Intended function of the audible and visual trouble signals shall be insured
 Fire alarm batteries shall be checked to ensure that:
o Terminals are clean and lubricated where necessary -Terminal clamps are clean and
tight where necessary
o Electrolyte level and specific gravity, where applicable, are specified by the
manufacturer

Record Keeping: Monthly Inspection & Testing Report

Annual Service
Responsibility: Iftakharul Alam (fire safety officer)
Procedure:

 Contractor shall perform service in accordance with NFPA 72

Record keeping: Annual Inspection & Testing Report


___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 44
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Emergency Lighting Units


Reference Standard: As per BNBC
Monthly Inspection
Responsibility: Engr. Md. shajahan mondal
(Electrical Engineer)
Procedure:

 Self-contained emergency lighting unit equipment shall be inspected to ensure that:

- pilot lights are functioning and not obviously damaged or obstructed,


- the terminal connections are clean, free of corrosion and lubricated when
necessary,
- the terminal clamps are clean and tight as per manufacturer’s specifications, and
- The battery surface is kept clean and dry.

Record Keeping: Monthly Inspection and Testing Report


Monthly Testing
Responsibility: Monthly Testing
Responsibility Engr. Md. shajahan mondal
(Electrical Engineer)
Procedure:

 Self-contained emergency lighting unit shall be tested at intervals not greater than one
month to ensure that the emergency lights will function upon failure of the primary power
supply.
Record Keeping: Monthly Inspection & Testing Report

Annual Testing
Responsibility: Engr. Md. shajahan mondal
(Electrical Engineer)
Procedure:

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 45
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Self-contained emergency lighting unit equipment shall be tested at intervals not greater
than twelve months to ensure that the unit will provide emergency lighting for duration
equal to the design criterion under simulated power failure conditions.
 After completion of the test, the charging conditions for voltage and current and the
recovery period shall be tested to ensure that the charging system is functioning in
accordance with the manufacturer’s specifications.

Record Keeping: Annual Inspection and Testing Report.

Emergency Generator
Reference Standard: As per BNBC.
Weekly Maintenance Schedule
Responsibility Engr. Md. shajahan mondal
(Electrical Engineer)

 Examine the following:

 Fuel tank level


 Lubricating oil level
 Engine coolant
 Heaters, lubricant and/or coolant
 Engine, generator, fuel tanks and cooling systems for evidence of leakage
 Operation of fuel transfer pump
 Starting system-batteries, etc., for leakage, cleanliness and terminal security
 Air tanks for pressure (air motor system)
 Valves for leakage (air motor system)
 Operation of auxiliary engine and compressor (air motor system)
 Bleed off condensation (air motor system)
 Louvre settings-control panel settings (ensure the unit is ready for start-up)
 Battery electrolyte level
 Battery specific gravity
 Battery electrical connections (tightness, leaks or salvation)
 Battery cleanliness and dryness between terminal posts

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 46
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Charger cleanliness and operation of both float and equalize modes


 Engine governor control linkages and oil level
 Engine fuel pump oil sump
 Engine fan belts and protective devices
 Panel covers are secure and annunciator lamps are operational

Monthly Testing
Responsibility: Engr. Md. shajahan mondal

(Electrical Engineer)
Procedure:

 Have manufacturer’s maintenance manual and manual of instructions available.

 Simulate a failure of the normal electrical power supply, arranged so that:


- an engine-generator set operates under at least 30% of the rated load for 60
minutes;
- all automatic transfer switches are operated under load
 Record readings of all instruments associated with engine and generator and verify
that they are normal.

Procedure to Operate Generator (simulate power failure):

 Engage the emergency power transfer switch


 Disengage the switch after completion of test to ensure generator is in normal
operating condition.

Record Keeping: Weekly Testing and Maintenance Report


Monthly Maintenance and Inspection Schedule
 Include an inspection to assess the correct functioning of all auxiliary equipment such as
the radiator shutter control, coolant pumps, fuel transfer pumps, oil coolers, and engine
room ventilation controls and operation.
 Generator
- check brush operation for sparking
- check for bearing seal leakage
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 47
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Semi-annual Service
Responsibility: Engr. Md. shajahan mondal
(Electrical Engineer)

Procedure: Check/Clean the following:

 Crankcase breathers

 Lubricant governor
 Linkages
Record Keeping: Semi-Annual Testing Report
Annual Maintenance
Responsibility: Qualified Contractor
Procedure:

 Contractor shall perform checking, testing, and servicing of items which require
attention at 1-year intervals as specified in the manufacturers= instructions and CSA
Standard C282.
 Liquid fuel storage tank shall be drained and refilled with a fresh supply of fuel at
intervals not greater than 12 months.

Record keeping: Annual Inspection & Testing Report

Sprinkler System
Reference Standard: N/A
Daily Inspection: N/A
Responsibility: N/A
Procedures: N/A
Record Keeping: N/A
Weekly Inspection: N/A
Responsibility: N/A
Procedures: N/A
Record Keeping: N/A
Monthly Inspection & Tests: N/A

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 48
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Responsibility: N/A
Procedures: N/A
Record Keeping: N/A
Bi-monthly Test and Inspection: N/A
Responsibility: N/A
Procedures: N/A
Record Keeping: N/A
Semi-annual Tests: N/A
Responsibility: N/A
Procedures: N/A
Record Keeping: N/A
Annual Tests & Maintenance: N/A
Responsibility: N/A
Procedures: N/A

Standpipe & Hose System


Reference Standard: NFPA 14, Installation of Standpipe and Hose System.
Alterations - Standpipe systems that have been modified or extended or are being restored to service
after a period of disuse exceeding twelve months, shall be flow and pressure tested at the highest and
most remote hose connection to ensure the availability of the water supply for which the system was
designed.

Monthly Inspection
Responsibility: Iftakharul Alam (fire safety officer)
Procedure:

 Hose cabinets shall be inspected to ensure that the hose is in proper position and that all
of the equipment is in place and in operable condition.
 Hose valves shall be checked to ensure they are tight.
 Main shut off valve shall be checked to ensure that it is open.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 49
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Record Keeping: Monthly Inspection & Testing Report


Annual Inspection
Responsibility: Iftakharul Alam (fire safety officer)

 All portions of the system shall be inspected.


Record keeping: Annual Inspection & Testing Report

Fire Pumps & Reservoirs


Weekly
Responsibility: Iftakharul Alam (fire safety officer)

Procedure:

 The water level in the fire pump reservoir shall be observed at intervals not greater
than 7 days and maintained at the proper level.
 Operate internal combustion engine fire pump at rated speed and observe the discharge
pressure, suction pressure, lubricating oil level, operative condition of relief valve, and
general operating conditions at intervals not greater than 7 days.
 Internal-combustion engine fire pumps shall be operated for a sufficient time to bring the
engines up to normal operating temperatures. The storage batteries and fuel supplies
shall be maintained at the correct levels.

Record Keeping: Weekly Inspection & Testing Report


Monthly Test
Responsibility Iftakharul Alam (fire safety officer)

Procedure:
 Test fire pumps driven by electric motor at rated speed until satisCommercial building
performance of the pump, driver and controller is verified at intervals not greater than
one month. (An indication of the satisCommercial building performance of the controller
can be obtained by starting the pump by reducing the water pressure in the controller
sensing line. The operating conditions of the relief valve, and the discharge and suction
pressures, lubricating oil levels and priming water levels, are further indications of the
performance of the fire pump and related equipment.)
Record Keeping: Monthly Inspection & Testing Report.
Annual Testing
Responsibility: Iftakharul Alam (fire safety officer)
Procedure:

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 50
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

 Fire pumps shall be tested at full rated capacity at intervals not greater than 12 months to
ensure that they are capable of delivering the rated flow.

Record keeping: Annual Inspection & Testing Report.

Fire Dampers & Fire Stops Flaps


Annual Inspection
Responsibility: Iftakharul Alam (fire safety officer)
Procedure:
 Ensure that the fire dampers and fire stops are in place and are not obviously damaged or
obstructed.
Record keeping: Annual Inspection and Testing Report.

Hoods, Ducts & Filters


Weekly Inspection
Responsibility: Iftakharul Alam (fire safety officer)

Procedure

 Hoods, ducts and filters subject to accumulations of combustible deposits shall be


inspected at intervals not greater than 7 days and shall be cleaned if the accumulation of
such deposits creates a fire hazard.
 If necessary hoods and filters shall be cleaned by staff.
 If necessary ducts shall be cleaned by a qualified contractor.

Record Keeping: Weekly Inspection & Testing Report - when equipment is cleaned.
Chimneys, Flues & Flue Pipes
Annual Inspection
Responsibility: Iftakharul Alam (fire safety officer)
Procedure:

 Inspect to identify any dangerous conditions at intervals not greater than


twelve months, after any chimney fire, at the time of addition of any
appliance, clean as often as necessary to keep them free from dangerous
accumulations of combustible deposits.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 51
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Record keeping: Annual Inspection and Testing Report.

Heating Ventilating & Air Conditioning Systems


Annual Testing and Servicing
Responsibility: Iftakharul Alam (fire safety officer)
Procedure: N/A
Record Keeping: N/A
Fire Department Access to Building
Daily Inspection

Responsibility: Iftakharul Alam (fire safety officer)


 Streets, yards and roadways provided for fire department access shall be maintained so as to
be ready for use at all times by fire department vehicles.
o Vehicles shall not be parked to obstruct access of fire department vehicles and
signs shall be posted prohibiting such parking.
o Access panels or windows provided to facilitate access for firefighting operations
shall be maintained free of obstructions at all times.

Record Keeping: None


Fire Hydrants
Semi-annual Inspection
a) Responsibility: Iftakharul Alam (fire safety officer)

(Head of Engineering, Mechanical Dept.)


Procedure:

 Hydrants shall be inspected to ensure that hydrant caps are in place and caps with worn,
rusted or obstructed threads, which might hamper easy removal, are repaired or replaced.
 Hydrant barrels shall be inspected to determine if water has accumulated as a result of a
leaking main valve or a plugged or damaged drain valve.
 Main valves which are leaking and drains which are plugged or damaged shall be
repaired.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 52
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Exception: Where it is not practical to repair faulty drain valves or where


drain valves are intentionally plugged, measures shall be taken to prevent
the freezing of accumulated water.
Record Keeping: Semi-annual Inspection & Testing Report.
Annual Flushing
b) Responsibility: Iftakharul Alam (fire safety officer)

(Head of Engineering, Mechanical Dept.)


Procedure:

 Semi-annual inspection list previously.


 Hydrants shall be flushed at intervals not greater than 12 months with the main valve
and any outlet valves fully opened until the water runs clear.

Record Keeping: Annual Inspection & Testing Report

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 53
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

11. EVALUATION OF WEEKNESS AND GAPS IN


EXISTING FIRE SAFETY PLAN

Findings and Recommendation


1 Sub Header : Existing Active Fire Protection Systems
Question : Does the building have a Standpipe System and Fire Hydrant System?

Description of : Where required?


Requirements Standpipe systems shall be installed throughout all new and existing buildings and
structures where the highest occupied floor is more than 10 m (33 ft.) above grade
or more than 10 m (33 ft.) below grade.
Installation requirements.
All installation and design requirements outlined in BNBC Part 4 Chapter 4 for
combined standpipe and automatic sprinkler systems shall be replaced by the
requirements of NFPA 14 with a minimum pressure of 450 kPa (65 psi) at the
hydraulically most remote hose connection. Standalone standpipe systems shall
meet the BNBC requirements with a minimum 450 kPa (65 psi) pressure at the
hydraulically most remote hose connection, or NFPA 14.

Description of : Commercial building Have a Fire Hydrant and Stand Pipe system .
Existing Status Installation was done by Design and Drawing with Listed (EMACO, UL Listed)
products as per NFPA -14 Guideline.
Approved Design and Drawing is Attach

Suggested Plan / : N/A


Recommendation /
Remarks

2 Sub Header : Existing Active Fire Protection Systems

Question : Does the Commercial building have a Fire Hydrant Pump set?

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 54
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Description of : Where required?


Requirements Standpipe systems shall be installed throughout all new and existing buildings and
structures where the highest occupied floor is more than 10 m (33 ft.) above grade
or more than 10 m (33 ft.) below grade.
Installation requirements.
All installation and design requirements outlined in BNBC Part 4 Chapter 4 for
combined standpipe and automatic sprinkler systems shall be replaced by the
requirements of NFPA 14 with a minimum pressure of 450 kPa (65 psi) at the
hydraulically most remote hose connection. Standalone standpipe systems shall
meet the BNBC requirements with a minimum 450 kPa (65 psi) pressure at the
hydraulically most remote hose connection, or NFPA 14. Pump should be as per
NFPA 20.
Description of : System is Passive. Installed as per standard. Commercial building needs Electrical
Existing Status pump and Diesel pump (Standby) of 500GPM 12BAR Pressure. Jocky pump is
about 20 GPM and 12 BAR .

Suggested Plan / : N/A


Recommendation /
Remarks

3 Sub Header : Existing Active Fire Protection Systems


Question : Does the Commercial building have a Fire Department Connection?
Description of Commercial building Has a centrally Fire hydrant system.
Requirements :

Description of : Commercial building Has a centrally Fire hydrant system.


Existing Status

Suggested Plan / : Shall install and active Fire hydrant system.


Recommendation /
Remarks
Sub Header : Existing Active Fire Protection Systems
04
Question : Does the Commercial building have a Sufficient Fire Extinguisher?

Description of : Commercial building Has an amount of 1,29,094.43 SFT floor area. As per
Requirements FSCD act- Total Extinguisher required Total - 156 pcs Fire Extinguisher. Where-
ABCE Dry Powder will 110 and CO2 will be 46 pcs. Foam will be as per required
at Oil handling area.

Description of Commercial building Total - 156 pcs Fire Extinguisher. Where- ABCE Dry
Existing Status Powder 110 pcs and CO2 46 pcs.
:

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 55
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggested Plan / : Commercial building shall install all required fire extinguisher and keep a checklist
Recommendation / of them.
Remarks

5 Sub Header : Existing Active Fire Protection Systems


Question : Does the Commercial building have a Fire Detection and Alarm System?
Description of : Where required?
Requirements Automatic or manual fire alarm and detection systems shall be installed throughout
all new and existing buildings and structures initiating devices shall include there
smoke or fire detection devices spaced in accordance with NFPA 72. When
complete devices designed to initiate the alarm notification, smoke and fire
detection devices can be eliminated throughout that floor.

Description of : Commercial building Have an Addressable Fire Detection system.


Existing Status

Suggested Plan / N/A


Recommendation /
Remarks :

6 Sub Header : Existing Active Fire Protection Systems


Question : Does Commercial building have Fire Command Station?

Description of : Commercial building need to arrange a Fire Command Station to Guideline the
Requirements people while fire and also increase awareness about fire in scheduled date.

Description of : Commercial building use the fire detection room as there detection panel is
Existing Status present.

Suggested Plan / : Separate Fire Command Station is Required with all required instruments.
Recommendation /
Remarks

8 Sub Header : Means of Egress


Question : Interior exit stairways and ramps terminate at an exit discharge except where
terminating at a rated exit passageway?

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 56
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Description of Interior exit stairways are terminating through rated exit passage ways to exterior
Requirements : discharge.

Description of : Construct required rated walls and slabs for the open exit passageways. Cover the
Existing Status openings in exit passageway by opening protective.

Suggested Plan / : Discharge point of ALL exit and Stair should be in a safe or rated place.
Recommendation /
Remarks

9 Sub Header : Means of Egress


Question : Doors along the path of egress have a minimum width of 0.915 m (36 in) and have
required ratings.

Description of : Doors along the path of egress have a minimum width of 0.8 m (32 in) and have
Requirements required ratings.

Description of : Door widths are more than 0.8m. Visually.


Existing Status

Suggested Plan / : N/A


Recommendation /
Remarks

10 Sub Header : Means of Egress


Question : Aisles are provided with the minimum unobstructed clear width of 0.9 m (36 in)
based on occupant loads.

Description of : Aisles are provided with the minimum unobstructed clear width of 0.9 m (36 in)
Requirements based on occupant loads. And should be clear identification.
Description of : Aisles width is adequate at all floors. But Somewhere aisles Blocked and mark
Existing Status faded away.

Suggested Plan / : Remove existing aisle marking and draw new marking fulfilling the minimum aisle
Recommendation / width requirement. Relocate the machines accordingly if necessary.
Remarks

11 Sub Header : Fire Protection Construction


Question : Does the sufficient Rated construction provided for Boiler, Transformer, Sub-
Station and Generator?

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 57
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Description of : As per BNBC and Fire Act- Boiler Room, Transformer Room, Sub Station Room
Requirements and Generator Room must be 04 (Four)Hour Fire rated around the room / Six side.
Door will be 02 (Two) hour Fire Rated

Description of : Boiler, Generator, Sub- station is 04 Hrs Fire Rated.


Existing Status (10’’ Brick Wall)

Suggested Plan / : Option -1


Recommendation / Shift the Boiler Room min. 20 Feet Away from Main Building, Provide 200 mm
Remarks RCC barrier around the room, Provide 2 Hrs Rated Fire Door.

Option -2
Provide 200 mm RCC Wall Around the room, Provide 200 mm Buffer Wall with
maintain a gap minimum 300 mm between Main Wall and Buffer Wall.

Provide 200 mm RCC wall for Transformer, Substation and Generator with 2 Hrs
Fire Rated Door.

12 Sub Header : Fire Protection Construction


Question : Are separations between hazards provided with fire-resistive rated construction
barriers?
Description of : In-process goods are kept haphazardly in various floors such as 2nd floor,3rd floor
Requirements that does not maintaining the dimensions of the requirement for miscellaneous
store (area 250 sq. ft., height 8 ft., separation from adjacent storage area 10 ft.)
Description of : In-process goods are kept haphazardly in various floors such as 2nd floor,3rd floor
Existing Status that does not maintaining the dimensions of the requirement for miscellaneous
store (area 250 sq. ft., height 8 ft. separation from adjacent storage area 10 ft.)

Suggested Plan / : Provide fire-resistive rated construction barriers between hazard types following
Recommendation / Table 4.4.1 of Alliance Standard or Table 4.1.1 from BNBC Part 4. Consult a
Remarks qualified fire protection engineer to design the required rated construction barrier.
Keep the in-process goods on floors such that storage is maintained with a
maximum area of storage of 250 sq ft, a height of 8 ft, and separation from
adjacent storage areas of 10 ft. Provide fire-resistive rated construction barriers
between hazard types in accordance with Alliance Standard Sections 3.4 and 4.5.
Consult a qualified fire protection engineer to design the required rated
construction barrier.
13 Sub Header : Fire Safety Programs
Question : Fire Drills are conducted at required intervals based on building use type.

Description of : Fire drills are conducted every month.


Requirements

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 58
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Description of : Conduct fire drills on a quarterly basis as outlined in BNBC Part 4 Appendix A for
Existing Status all garment facilities. Fire drills shall be conducted under the direction of a Fire
Safety Director. All other requirements for fire drills shall be conducted in
accordance with BNBC Part 4 Appendix A.
Suggested Plan / : Conduct fire drills on a quarterly basis as outlined in BNBC Part 4 Appendix A for
Recommendation / all garment facilities. Fire drills shall be conducted under the direction of a Fire
Remarks Safety Director. All other requirements for fire drills shall be conducted in
accordance with BNBC Part 4 Appendix A.
14 Sub Header : Means of Egress
Question : All paths of egress are provided with compliant means of illumination.

Description of : Aisles, corridors, exit doors and stairways are provided with required means of
Requirements illumination but emergency power is not provided for a sufficient number of bulbs,
therefore in case of power failure or load shedding, all the paths of egress will not
be illuminated as required. Moreover, illumination signs are insufficient in
number.

Description of : Aisles, corridors, exit doors and stairways are provided with required means of
Existing Status illumination but emergency power is not provided for a sufficient number of bulbs,
therefore in case of power failure or load shedding, all the paths of egress will not
be illuminated as required. Moreover, illumination signs are insufficient in
number.

Suggested Plan / : Install appropriate means of illumination at the noted locations. The means of
Recommendation / egress shall be illuminated at all times the building is occupied. Illumination shall
Remarks be a minimum of 10 lux for all corridors, exit doors, and stairways. Aisles shall be
provided with a minimum 2.5 lux.
15 Sub Header : Fire Protection Systems
Question : Fire extinguishers are inspected, tested, and maintained as required.

Description of : Fire extinguishers are inspected, tested, and maintained as required annual
Requirements maintenance of extinguishers by a servicing agent and ii) annual testing of nozzle
of CO2 extinguisher. These are required as per NFPA 10.

Description of : Extinguishers are inspected monthly by the Commercial building's concerned


Existing Status people, but no document was found in support of i) annual maintenance of
extinguishers by a servicing agent and ii) annual testing of nozzle of CO2
extinguisher. These are required as per NFPA 10.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 59
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggested Plan / : Fire extinguishers are to be inspected, tested, and maintained in accordance with
Recommendation / NFPA 10 Chapter 7.
Remarks

16 Sub Header : Fire Safety Programs


Question : A written housekeeping policy is established and enforced.
Description of : Relevant documents were found although they are not established according to
Requirements Section 13.6.

Description of : The Commercial building have the house keeping policy


Existing Status

Suggested Plan / : N/A


Recommendation /
Remarks

17 Sub Header : Fire Safety Programs


Question : A hot-work permit program has been established?

Description of : Hot-work permit program is not established yet, although it is required. However,
Requirements hot-work is not going on in the Commercial building right now.

Description of : No system is developed


Existing Status

Suggested Plan / : Develop a hot-work permit program. The program must comply with the
Recommendation / requirements of NFPA 51B. In general, this program should address the process of
Remarks request and approval of authorities, necessary checks prior approval, standby fire
watch and fire-fighting equipment, sounding of alarm procedure, duration and
expiry of permit and re-approval procedures, etc.

18 Sub Header : Electrical Safety


Question : Does Commercial building have an Approved Design/ Drawing and
Implementation of SLD?

Description of : Commercial building required a proper designs / drawing of electrification system


Requirements and also that design should Approved by affiliated body

Description of : Commercial building Have Approved Design and Drawing of SLD


Existing Status and also maximum of them are Implemented. Found some mismatch with SLD and
existing

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 60
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggested Plan / : Commercial building Have Approved Design and Drawing of SLD
Recommendation / and also maximum of them are Implemented. Found some mismatch with SLD and
Remarks existing

19 Sub Header : Electrical Safety

Question : Is there all Panels are grouted?

Description of : All electrical panels must be grouted with proper foundation with nuts and bolts.
Requirements

Description of : All electrical panels are not grouted with proper foundation with nuts and bolts.
Existing Status
Suggested Plan / : All electrical panels must be grouted with proper foundation with nuts and bolts.
Recommendation /
Remarks

20 Sub Header : Electrical Safety


Question : Cable Looping is there?

Description of : No looping and Multiple connection, Connection without Lug, Breaker without
Requirements phase separator is not allowed

Description of : Looping and Multiple connection, Connection without Lug, Breaker without phase
Existing Status separator is there

Suggested Plan / : No looping and Multiple connection, Connection without Lug, Breaker without
Recommendation / phase separator is not allowed
Remarks Remedy all those

21 Sub Header : Electrical Safety


Question : Dose Commercial building have a Lightning Protection System (LPS)?

Description of : Calculation the risk factor, Design and Drawing, Taken approval from authority
Requirements and installation the system as std

Description of : Commercial building Have Approved Design and Drawing of LPS


Existing Status and also Implemented the system as per approved design
Found some mismatch with SLD and existing

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 61
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggested Plan / : N/A


Recommendation /
Remarks

12. SUGGESTIONS FOR FIRE PREVENTION,


PREPAREDNESS & CONTROL

Suggestions for Electrical Fire Safety: Wiring

Electrical failure or malfunctions account for almost 34,000 home fires, on average, per year
and result in roughly 440 deaths and 51.3 billion in direct property damage according to the
National Fire Protection Association (NFPA). Understanding the common causes, warning
signs and appropriate safety measures can help prevent an electrical fire. The most common
causes for electrical fires are:
• incorrectly installed wiring
• Overloaded circuits and extension cords
• Defective or improper plugs, switches and outlets
• Misuse and poor maintenance of lighting

The warning signs of faulty Wiring or Electrical Systems include:


• Flickering or dimming lights
• Switches or outlets that are hot to touch and/or emit and acrid odor
• Discolored cords, outlets and switch plates
• Repeatedly blown fuses and tripped circuit breakers

To keep the wiring system safe each Commercial building should be in regular acquaintance
of a licensed engineer who can help to ensure that any electrical modification meets existing
standard.
Electric currents carried by wiring, switches, plugs and appliances generate heat. Excessive
or uncontrolled heat can start fires. To help prevent electrical fires the following precautions
can be taken:
• The cords should not run under carpeting, bedding, or other combustible materials; also
avoid placing cords across doorways or frequently traveled areas
• Discard frayed or broken cords and never splice two cords together.
• Don't overload outlets or use extension cords in place of outlets. Call an electrician to
install additional outlets as necessary.
• Ensure plugs fit snugly in outlets to prevent shock and excess heat.

Suggestions for Electrical Fire Safety: Generator Earthing

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 62
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Grounding/Earthing of Standby Generator: One of the major issues of the safety from the
Generator relates to Grounding. In this case, neutral (star point) is to be connected by
insulated earthing conductor through the neutral earthing link or device to main earthing bar.
Neutral earthing conductor is to be suitably sized to carry maximum earth fault current for
time it takes the system protection to operate with final conductor temperature not exceeding
160 deg. C, but not less than 30 mm2 per 100 kVA of generator rating, with a minimum of 50
mm2.

As general precautions the following guidelines should be followed for installation of


emergency generators.
• The generator should be erected in a well-ventilated room preferably with a ridge
opening. It is not desirably to locate this in the basement.
• The generator should be so erected that the radiator of the engine is facing the opening
for effective heat radiation.
• A minimum clear space of 750 mm should be provided all around the generator.
• The applicable de-rating factors, as recommended by the manufacturer of the generator,
for the de-ration of the capacity of the generator should be given due consideration for
the design of the installation.
• The control panel of the generator should be located away from the generator, but in the
same room. The clearance between the generator and the control panel should be more
than 1 meter, for small sets up to and including 250 KVA. For larger sets, more
separation for proper cooling is the deciding factor.
• When two generators are erected side by side, a minimum clearance of 1500 mm
should be provided between the generators.
• The control panel of the generator should be erected with clearances as applicable to
switch boards.
• The generator shall be complete with control panel, daily service tank, underground
bulk storage tank and transfer pump set with duty/standby pumps.
• The control panel should comprise of means for adequate control and protection for the
generator supply with required meters and indication lamps and should be vermin
proof.
• The control and protection may be as follows:
o Up to and inclusive of 100 KVA: Switch fuse, Fuse Switch or Circuit Breaker
o Above 100 KVA: Circuit Breaker.
• Where fuses are provided as back up protection before the circuit breaker / contactor
and in cases where fuses alone are provided in Control Panels of the Generator, a linked
switch or isolator should be provided before the said fuses for isolation and to facilitate
safe renewal of fuses.
• Tapping of supply to the auxiliaries of Generator should not be taken from the control
panel of generator, if there is no provision made by the manufacturer of the generator
for such tapping.
• A link should be introduced in the neutral circuit of the generator and the neutral
earthling should be done at the outgoing side of the link. The neutral earthing and the

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 63
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

neutral link should be at the control panel. If no provision is available for this in the
control panel, it should be done at the terminal box of the generator.
• The generator should never be run in parallel with the Electricity Supply Authorities'
main grid.

• Double throw knife type change-over switch is not to be normally employed for
change-over of supply.
• On the change-over board, a pair of 4 pole fuse switches mechanically interlocked
should be used for each TPN feeder. However, TP FS is permissible if the outgoing
cable is a three-core cable.
• If automatic change-over arrangement is provided, the interlocked contactors should be
of 4 pole type for TPN supply. If the incoming supply source is far away, suitable
isolator / Fuse switch should be provided before the contactor for each incoming
supply.
• The following remote indications shall be displayed in the control room through
Building Management or Plant Control System:
o Generator status: Run/Stop, Voltage, Load current, Frequency, oil pressure, engine
temperature etc.
o Automatic Transfer Switch Status: Mains/Standby.
o Mains power status: ON/OFF for each switchboard section.
o Generator trouble:
o Fail to start.
o Voltage trouble.
o Frequency trouble.
o High Engine Temperature.
o Low oil pressure.
o Over-speed.
o Alternator low and over voltage.
o High winding temperature.
o Daily Fuel tank:
o High Level
o Low Level
o Bulk Storage tank:
o High Level
o Low Level
o Fuel Oil transfer pump status:
o RUN/STOP
o Trouble.
• In case of HV Generators, if isolator or Circuit Breakers is provided for neutral,
necessary mechanical-interlock should be provided between the neutral isolator / or
Circuit Breaker so that neutral isolator / or Circuit Breaker in the neutral circuit is
closed before closing the main circuit breaker of generator and vice versa.

• All generators with rating of 100 KVA and above shall be protected against earth fault
leakage. All generators of 1000 KVA and above shall be protected against faults
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 64
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

within the generator winding using restricted earth fault protection or differential
protection or by both.
• Fuel more than 500 Gallons must not be stored in a single area.

Suggestions for Electrical Fire Safety: Substation


The major fire risks and detection difficulties within substations arise because of the
following:
• Electrical arcing and the build-up of static electrical charge within equipment.
• Overheating of electrical control equipment, switchgear and cabling.
• Once initiated, a fire may rapidly spread due to the presence of large amounts of
combustible material in the form of hydrocarbons contained in cabling and insulation.
• The environment within uninterrupted power supply areas (i.e. battery room) may
become explosive from the buildup of high concentrations of hydrogen gas.
• Substations are usually unmanned, thus, early intervention by staff may not be
possible in the event of a fire.
• High air movement caused by air-conditioning dilutes and disperses the smoke.
• Much of the mission critical equipment is housed within equipment cabinets and in
cabinet fires may take some time to be detected by ceiling mounted detection devices,
especially since in-cabinet fires will usually have prolonged incipient (shouldering)
stages.
• Underground cable trenches linking the main areas of the substation are considered
hostile environments. High levels of background pollution present in these areas will
affect the reliable operation of conventional detectors as well as being a source of
false (nuisance) alarms.
A Cable Trench is located under the Switch/Relay Room, Control Room and Battery Room
to house the communication, control and power cables between the substation's operational
areas as well as transport power to external high voltage switching towers.
The most efficient way to protect a Cable Trench is to install sampling pipe network at the
top 10% of the trench's height. Therefore, the most efficient way of fire detection of the
substation room would be using an Air Sampling Fire Detection System.
The fire detection system should detect a fire at its true incipient stage, before the advent of
smoke, to confirm the presence of combustion as early as possible and facilitate the operation
of a fire extinguishing system. The system should alert a control and alarm signaling system
and should also have a monitored detection system for fault and fire. The detection system
should conform fully to an internationally accepted engineering standard.
Where no ceiling is present, and the substation is covered by a sheet metal roof, a system
such as Pyrogen\ could be used inside the electrical cabinets. Fire detection needs to be in the
room and all cable trenches. Should a cable room form part of the risk area, fire detection
needs to be included. All detection systems need to be designed and installed to conform to a
recognized international engineering standard such as NFPA70.
All louvers should be sealed in the event of first detection of a fire and all air conditioning
devices must be tripped. All cable trenches must be properly sealed with a fire rated medium
of at least one-hour or as per local standards and regulations. All detection, alarm and
extinguishing circuits are to be monitored for fire and fault. The substation fire protection
system should operate a local audible and visual alarm system, normally a local sounder on

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 65
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

first detection and a second distinguishing audible sound on second detection. The substation
fire protection system then needs to report to a central 24-hour manned operations security
room, and wherever possible, a local fire brigade.

Suggestions for Electrical Fire Safety: Earthing


The primary purpose of earthing is to avoid or minimize the danger of electrocution, fire due
to earth leakage of current through undesired path and to ensure that the potential of a current
carrying conductor does not rise with respect to the earth than its designed insulation.
Earthing can be classified in two ways:
• System earthing;
• Equipment earthing.
System earthing is essential to the proper operation of the system, whereas equipment
earthing concerns the safety of personnel and plant. A key function of equipment earthing is
to provide a controlled method to prevent the buildup of static electricity, thus reducing the
risk of electrical discharge in potentially hazardous environments. Generally, a resistance to
earth of less than 106 will ensure safe dissipation of static electricity in all situations.
Electrical system grounding is accomplished when one conductor of the circuit is
intentionally connected to earth. This is done to protect the circuit should lightning strike or
other high voltage contact occur. Grounding a system also stabilizes the voltage in the system
so "expected voltage levels" are not exceeded under normal conditions.
The path to ground from circuits, equipment, and enclosures shall be permanent and
continuous. This requirement was extracted from NEC 250-51, Effective Grounding Path,
which is more complete and fundamental to the understanding of electrical safety. It states
that the path to ground:
1. "shall be permanent and continuous." (If the path is installed in such a way that
damage, corrosion, loosening, etc. may impair the continuity during the life of the
installation, then shock and burn hazards will develop.)
2. "shall have capacity to conduct safely any fault current likely to be imposed on it."
(Fault currents may be many times normal currents, and such high currents may melt
or burn metal at points of poor conductivity. These high temperatures may be a hazard
in themselves, and they may destroy the continuity of the ground-fault path.)
3. "shall have sufficiently low impedance to limit the voltage to ground and to facilitate
the operation of the circuit protective devices in the circuit." (If the ground-fault path
has a high impedance, there will be hazardous voltages whenever fault currents attempt
to flow. Also, if the impedance is high, the fault current will be limited to some value
so low that the fuse or circuit breaker will not operate promptly, if at all.)
It is important to remember the following regarding safe grounding paths.-
1. The fault current in A-C circuits will be limited by the sum of resistance and
reactance, and the only low-reactance path is that which closely follows the circuit
conductors.
2. If a metallic raceway system is used, make sure that the metallic system is
continuous and permanent.
3. In cases where a metallic raceway system is not used, provide a green or bare
equipment-grounding conductor close to the supply conductors to assure that all
enclosures are bonded together and to the source.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 66
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggestions for Electrical Fire Safety: Distribution Panel Boards


All Distribution Panel Boards must be correctly selected and erected. The Standard states the
following, along with manufacturer's instructions should be considered:
• Compliance with standards
• Operational conditions
• External influences
• Accessibility
Operational conditions
The electrical designer will need to select distribution boards for operational conditions such
as voltage, current and frequency. In Bangladesh the nominal voltage and frequency is
typically 400/230V and 50Hz. Installations and the distribution boards within them will,
however, have different current requirements. It is required that the equipment is suitable for
the design current and the current likely to flow in abnormal conditions. The latter would
include short circuit and earth faults. The specifier will therefore need to assess the current
demand taking into account diversity. They will also need to assess the prospective fault
current at the distribution board location before selecting the board and the protective
devices.
External influences
All equipment including the distribution board must be suitable for the external influences
that they are likely to encounter. There will be conditions where a suitably IP rated
distribution board will be needed. These installations may include:
• Caravan parks
• Marinas
• Agricultural or horticultural installations
• Temporary electrical installations for structures at fairgrounds, amusement parks and
circuses
• Locations where there is a risk of fire due to the nature of processed or stored
materials
Accessibility
Equipment should be located to facilitate its operation, inspection and maintenance.
Cable Entry
Designers and installers must select a wiring system that avoids damage to the sheath and
insulation of cable during installation, use and maintenance.
Where cables enter a distribution board from trucking, the cables must be protected from any
sharp edges in order to comply with Standard. Common methods of complying include
deburring edges and using grommet strips or manufactured spacers.
The Standard requires that the cores of unsheathed cables from which the sheath has been
removed and non-sheathed cables at the termination of the trucking etc. are enclosed.
Complying with these regulations can be difficult when passing the cables from the trucking
into a distribution board.
The on-site construction of a spacer using material such as paxolin is a common solution.
This is, however, time consuming and produces dust, so appropriate health and safety
protection may need providing. Also, the installer must ensure that the solution fully
complies with the regulations by making a proper seal.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 67
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Isolation & switching


Isolation aims to make dead, for safety reasons, all or a discrete section of the electrical
installation by separating it from every source of electric energy. This is commonly achieved
by switching off an isolation device within the distribution board. It is required that the
device shall isolate all live conductors, subject to the provisions of regulation. The neutral
conductor is also a live conductor. In a TN-S or TN-C-S installation, however, BNBC allows
the neutral conductor to not be isolated where it is reliably connected to earth.

Protection against fault current


The value of prospective fault current will need to be assessed when selecting a distribution
board and devices. For an installation with several distribution boards there will be different
values, so you will need to assess this at different points.

BNBC details the requirements of fault current protection. Only faults belonging to the same
circuit need to be considered. On a three-phase distribution board, where there is a mixture of
three-phase and single-phase circuits we need to look at these individually.

A single-phase (line to neutral) fault will be approximately half that of the three-phase fault
(across all lines). This affects the fault current ratings of individual devices for the
distribution board. For example, if a distribution board has a three-phase 10kA prospective
fault current, then the single-phase devices need to be selected to have a minimum fault
current rating of 5kA, if the line to neutral prospective fault current is equal to or higher than
the prospective earth fault current.

Standard states that the short circuit capacity of devices in the distribution board shall not be
less than the prospective fault current where the device is installed.

A lower breaking capacity is permitted if another device on the supply side has the necessary
breaking capacity. In this case the supply side device provides back up protection for the load
side device. Manufacturer's data should.be sought to obtain the level of back up protection
provided.

Using back up protection can produce a more cost-effective installation with perhaps the
incomer to a TP&N board being a 250A MCCB. 10kA outgoing devices could then be
installed where there is a 20kA fault level at that distribution board, subject to manufacturer's
data.

Distribution board fault current rating


The manufacturer is responsible for ensuring the capability of the equipment between the
incoming and the outgoing terminals of the distribution board, which includes bus bars and
connections as well as incoming and outgoing devices. The manufacturer will have
determined the distribution board fault current rating(s), in accordance with the product
standard.
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 68
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Nuisance tripping
In a commercial installation it is likely that socket outlets will supply computers, printers,
copiers and other electronic equipment. This type of equipment produces small amounts of
protective current.

Cables in walls
It is likely that metal partitions will separate rooms in a commercial installation. If this wall
has a cable inside it then the requirements of 522.6.103 will need to be met. These
requirements are similar to those for socket outlets in that if there is adequate supervision by
'skilled' or 'instructed' persons then you do not need to provide additional RCD protection. If
there is some doubt about this, then the designer could make the decision to apply part (v) of
this regulation and provide 30mA RCD protection. This applies to all circuits, not just socket
outlet circuits.

Suggestions for Electrical Fire Safety: Emergency Power Systems


Mains power can be lost due to downed lines, malfunctions at a sub-station, inclement
weather, planned blackouts or in extreme cases a grid-wide failure. In modern buildings, most
emergency power systems have been and are still based on generators. Usually, these
generators are Diesel engine driven, although smaller buildings may use a gasoline engine
driven generator and larger ones a gas turbine. However, lately, more use is being made of
deep cycle batteries and other technologies such as flywheel energy storage or fuel cells.
These latter systems do not produce polluting gases, thereby allowing the placement to be
done within the building. Also, as a second advantage, they do not require a separate shed to
be built for fuel storage.

The following general guidelines are to be followed in case of Emergency Power Systems
• Electrical supply installations, both temporary and permanent, must be installed in
accordance with national legislation and appropriate standards.
• All electrical work should be undertaken by a competent electrician.
• When considering purchasing a temporary or emergency power generator, a check
should be made that the power supply specified is adequate for all intended purposes.
For economy, eliminate unnecessary applications.
• For a safe and reliable service, a source of supply should be selected that will
maintain power at the required voltage for an adequate period.
• The standby supply should operate independently of the normal source of power so
that it will always be capable of operating in the event of a failure of the normal
source.
• For life safety or business continuity systems to operate in fire conditions, the
generator and any control equipment should be provided with fire protection of
adequate duration. All elements of construction of enclosures for emergency
generators should be of noncombustible material and have a minimum of 1-hour
fire resistance.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 69
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• Equipment shall be designed and installed to facilitate periodic inspection, testing and
maintenance.
• Stocks of fuel for generators should be kept to the minimum consistent with
anticipated running requirements.
• Fuel should not be kept in portable containers in the immediate vicinity of the
generator.
• Smoking should be prohibited near portable generators.
• During the period of the emergency, all equipment not powered by the standby power
supply should be switched off. When normal power supplies are restored, automatic
equipment should be checked, and any time clocks and control mechanisms should be
reset as necessary.
• Even if a UPS is present to cope with failure/variation of the normal power supply for
computers and other business critical equipment, it will still be necessary for certain
systems, such as automatic fire detection and alarm systems, security alarms and
similar installations, to have their own back-up power supplies, as specified in
relevant installation and operating standards.
• While it is important to install a generator with sufficient capacity for all foreseeable
future needs, the cost of power when a generator is only running at a fraction of its
capacity must be considered.
• A design where a diesel emergency generator also acts as a fire pump for the sprinkler
installation should be avoided.

Batteries
• Where batteries are to be used to power life safety equipment in an emergency they
should be suitably protected from the effects of a fire, for example by locating them in
a suitable fire-resistant compartment.
• Ideally, the designated battery room should be located on an outer wall of the building
so that adequate ventilation can be readily provided for the batteries to be charged in
this location. The ventilation should allow for at least two air changes per hour.
• Battery rooms should not be located at low levels which may be prone to flooding or
accumulations of firefighting water.
• Battery charging rooms should be ventilated at high level. Chargers should be
mounted on noncombustible surfaces and hangers should be provided for storing
charging leads when not in use.
• When specifying battery power, it should be remembered that to maximize battery
life, and hence minimize costs, batteries should not be allowed to discharge
completely before recharging.
• There should be no combustible material stored within 2m of the charger(s) or
batteries. In areas where wet cells are charged, safe means must be provided for
checking electrolyte levels and topping up the cells when necessary.
• Charging facilities should also include means for mopping up and neutralizing any
spilled electrolyte.
• Where necessary, barriers should be provided to protect charging apparatus from
damage by vehicle movements.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 70
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• Processes which produce open flames, sparks or electric arcs must be excluded from
battery charging areas.

Suggestions for Lightning Protection System (LPS)


The ideal Lightning Protection System for a structure or its connected services would be to
enclose the structure within and earthed and perfectly conducting metallic shield (Box), and
in addition provide adequate bonding of any connected services at the entrance point into the
shield. This would prevent the penetration of the lightning current and the induced
electromagnetic field into the structure.

Air Termination System has been applied in case of the IPS of TEB Fashion Intl. Ltd. The
role of an air termination system is to capture the lightning discharge current and .dissipate it
"harmlessly to earth via the down condZuctor and earth termination system.
Suggestions for Fire Prevention from Boilers
A fired boiler utilizes fuels which are flammable and potentially explosive. Extreme care should
be exercised when making fuel-piping connections. Use the correct gasket, bolts, thread
lubricants, and tightening torque to prevent leaks. It is recommended that drain valve and/or vent
piping be channeled to safe locations. Valve packing should be periodically tightened, and a
rigorous leak check program be implemented as part of the Owner's preventative maintenance
program.
Sometimes unconventional fuels need to be burned in boilers. When this is done, attention should
be paid to the hazards that can result. Theses may from characteristics in the fuels, toxic
chemicals in the fuel, and Toxic chemicals produced through combustion. Persons knowledgeable
in the use of such unconventional fuels should be consulted concerning the problems that may be
encountered.

Hazards In Gas Firing Boilers:


Operating Cause Effect Prevention
Hazard
Gas Line Excessive Explosion, Fire, Color-code piping. Adequate ventilation.
Leaks pressure. Asphyxiation Keep
Improperly All piping, valves and fittings in good
Assembled repair. Test for leaks before placing
joints. Damage equipment in operation. Avoidance of use
to piping, of pipes for supporting other equipment or
valves and walking on. Warning personnel o hazards
fittings carrying so they will report leaks promptly. Insure
fuel. Leaking safety devices are operative
gasket.
Gas relief Excessive Normal Vent discharge Explosion. Fire. Loss of life or injury.
valve or Pressure, Property damage. Pipe all relief valves and
atmospheric Diaphragm vents to point of safe discharge.
vent discharge. rupture in
regulators
Gas line repair. Damaged Explosion. Fire. Loss Use accepted methods for purging and
piping or valves Of life or -injury. recharging gas lines. Follow NFPA 54
Property damage
Wet gas Presence of Flameout and re- Follow NFPA 54 for wet gas supply
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 71
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

distillate in gasignition. Explosion. system


Fire. Loss of life or
injury. Boiler and
property damage
Significant Multiple gas Poor combustion. Appropriate alarms. Use combustion
change in BTU sources with Explosion. Fire. Boiler controls that compensate for BTU changes
rating of gas different or property damage.
heating values Loss of life
I or injury.
High Gas Defective gas Fuel rich mixture. Monitor for regulator operation.
pressure pressure Fireside explosion. Check operation and setting of pressure
regulator Fire. Loss of injury. switch periodically. Repair or replace
I Boiler or property defective : regulators and switches
Damage
Hazards due to Steam Leaks
Steam Leaks Damaged or I Severe Burn Keep all joints and pipes tight. Warn personnel of
corroded pipes hazards of invisibility of: superheated steam
and/or other leaks.
pressure parts

Hazards of Steam Explosion


Operating Cause Effect Prevention
Hazard
Defective Obstruction between boiler Will not lift to Replace or repair safety valve.
safety and valve. Valve damaged or release excess Remove obstructions. Periodically
valves corroded (internal). Lever tied pressure. Impose test valve per ASME code.
down. Obstruction on valve excess pressure on
outlet the boiler. Rupture
the boiler. Cause
loss of life and/or
injury to personnel.
Cause property
damage
Defective Broken gauge. Gauge is not in Gauge is not Calibrate gauge regularly. Replace
steam, calibration. Blockage in line showing the correct defective gauges. Inspect gauge
pressure from boiler to gauge. Gauge pressure. Boiler connection and piping to boiler for
gauges cock is closed. Multiple may be under blockage and/or closed cock.
gauges not in agreement. excessive pressure.
Prevents operator
from being aware
of true operating
conditions.
Low water Defective low water cutoff. Overheated boiler Verify operation of boiler water
level Low water cutoff bypassed. surfaces. Ruptured feed system periodically. Prove
Improper water column boiler. Loss of life low water cutoff operation
blowdown procedure. and/or injury to periodically. Use proper water
Equalizing lines restricted or personnel. Property column blow down procedures.
plugged. Tampering with low damage. Train boiler operators. Do not
water control. Defective boiler tamper with low water controls.
water feed system. Operator Replace defective low water
error. Defective or inoperative controls. Inspect equalizing line

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 72
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

gauge glass. (especially the lower line).


Scaled or Poor maintenance procedures. Ruptured boiler. Proper maintenance. Regular
corroded : Inadequate inspection. Loss of life and/or inspections by competent inspector
boiler Improper chemical cleaning. injury to personnel. Keep inspection log. Proper boiler
internal Contaminated boiler water. Property damage. water treatment.
Surface. Poor feed water control. Boiler overheating.
Improper water treatment.
Bypassed Defective electrical wiring. Controls will not Verify proper operation of controls
Controls Tampering with controls and function. Boiler periodically. Correct electrical
electrical wiring. may rupture. May wiring defects immediately. Do not
cause furnace tamper, with controls.
explosion. Loss of
life. Property
damage.
Tampering Deliberate action by personnel. Improper operation Read and follow manufacturer's
with Lack of knowledge on the part of boiler. Boiler |instructions. Prevent access by
Controls of the personnel. Inadequate may rupture. May unauthorized personnel by locking
training cause furnace equipment cabinet. Properly train
explosion. Loss of operators
life. Property
damage
Poor No definite maintenance Danger to personnel Establish a definite maintenance
maintenance policy and procedure. Lack of and property. Low Policy and procedure. Assign i
interest of the boiler owner. operating maintenance responsibility. Insist
Poorly or inadequately trained efficiency. on
personnel. No one assigned the Eventually high Performance of maintenance,
maintenance responsibility repair and functions. Keep maintenance log
replacement costs.
Poor operation
Condensate Improperly vented tank. Vent Tank pressure may Eliminate traps in vent line.
tank too small. Vent is trapped. exceed design Eliminate restrictions in vent line.
explosion Frozen condensate in trapped pressure. Tank may Vent to be full size (no valves).
vent explode. Loss of Vent to be run vertically from tank
life. Property
damage

Hazards of Steam Explosion


Operating Cause Effect Prevention
Hazard
Equipment being Equipment not Physical injury or Place the equipment if zero energy state
serviced or locked out, not death or zero mechanical state. Establish and
repaired. tagged out, not comply with lockout and tag out
Unexpected placed in zero procedures. Train and alert personnel.
starting of mechanical state, or Warning signs. Use blocking devices or
remotely not placed m zero ties to prevent movement of equipment
controlled energy state
equipment.
Movement of
equipment.
Release of
electrical energy.
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 73
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Release of fluid
pressure.
Activities related Failure to observe Potential injury or Observe operating and maintenance
to cleaning safety procedures death to personnel. instructions for maintenance cleaning.
applicable to Observe all safety regulations and
maintenance normal safety precautions. Provide a
cleaning safe means of access for maintenance
cleaning. Provide personnel with
protective clothing and equipment.
Establish a routine procedure to clean
and remove residue (ash, soot, slag)
frequently to prevent excessive
accumulation. Report all unsafe
Entering a Extremely Potential danger to Observe all safety regulations and
confined or hazardous life and health normal safety precautions. Provide
enclosed space environment I.e. sufficient ventilation to assure fresh air
(includes but not toxic or quality and quantity to maintain the
limited to furnace, inflammable health and safety of personnel. Test for
drums, shell, gas oxygen deficient oxygen deficiency with field type
passes, ducts, atmosphere, hot oxygen analyzers or other suitable
flues, bunkers, material, darkness. devices. Develop stand-by emergency
hoppers, tanks) Temporary plans and procedures. Report all unsafe
internal conditions and/or unsafe practices.
access provisions Work with a partner. Test for toxic or
flammable gas. Provide lights before
entering a confined space
Airborne Leakage. Potential danger to Operate ventilation and exhaust
contaminants I.e. Inadequate life and health systems. Wear; approved respiratory
gases, vapors, ventilation or protective equipment. Wear ' protective
fumes, dust, and exhaust clothing, observe all safety regulations
mist and normal safety precautions. Report
all unsafe conditions and/or unsafe
practices
Fire at burner Electrical or Potential injury or Operate equipment in accordance
deck, fuel mechanical death to personnel. with manufacturers recommended
stations, or other component failure. Potential equipment procedures. Locate: fuel, combustible
areas adjacent to Fuel leaks or property damage materials, and controls away from:
the boiler boiler surfaces. Report all unsafe
conditions and/or: practices. Train and
drill operators in emergency firefighting
and extinguishing procedures, Use fire
protection systems. Repair leaks
promptly
Wet steam during Steam wet from Poor atomization. Insulate all steam lines. Check proper
atomizing source. Steam line Dirty or smoky trap operation: periodically. Follow
not insulated. Steam fires. Sparkles in manufacturer's instructions
traps not working. flame. Discharge of
Explosion unburned oil in
furnace. Fireside
explosion or puff.
Boiler damage.
Property damage.
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 74
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Loss of life and/or


injury to personnel
Worn or damaged Abrasive material Fire. Incomplete or Check tips regularly. Use copper tools
atomizer (sprayer in oil. Normal wear. smoky combustion. to clean tips. Follow manufacturer's
plate) Leaving out of Flare back instructions. Replace gaskets when
service burner tip in cleaning or replacing tips. Do not use
hot furnace. Tip copper tools for cleaning stainless steel
abuse. Explosion parts

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 75
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggestions on fire Propagation:


Fire propagates through openings, such as ducts, vents, windows, doors etc. Dividing up a
building into different sections creates barriers that slow the speed at which flames spread.
Each section should be sealed with a self-closing fire door that is activated automatically by
the fire alarm being triggered. Special door and window frame seals that are activated by heat
can help prevent smoke getting through openings, giving more time to people inside a
burning building.
For this purpose, each holes, gaps and openings must be identified and sealed by the means of
Fire stops. Fire Propagation should be simulated with the existing building structure and
checked for possible measures to strengthen fire/smoke compartmentalization. At present we
can identify the following openings and their consecutive corrective measures in the existing
structure,
1. Holes: each of the hole must be addressed to seal off completely with structural
members (Concrete), which were caused by the Installation of Sprinkler and Steam
Pipeline.
2. Ducts: each of the duct penetration through the walls must be addressed to seal off
completely with Fire Dampers.
3. Shafts: In the Commercial building. There are 4 (four) vertical shafts running all
through from Ground Floor to Top Floor. Each penetration has been identified and
fire stops have been applied on each floor to prevent the vertical propagation of Fire
& Smoke.

Suggestions on Fire Suppression:


The Fire suppression is being done with Standpipe Wet Riser Hose System and Portable Fire
Extinguishers. The following issues must be addressed and kept in scrutiny always.
• Fire Department Connections: Each floor fs equipped with three Fire Department
Connections, which are basically 65mm Landing Valves. It must always be kept in
vigilance if the landing valve coupling is compatible with the hose pipe couplings
used by the Fire Service.
• Risers: There are three vertical Wet Riser pipes with three staircases of the building
with Diameters 4" (2 risers) and 6". A hydraulic calculation was performed to identify
the flow and pressure at different nodes. The system has been designed to maintain a
minimum pressure of 4.5 bar at the most remote sprinkler point with adequate flow.
• Pumps: Three Pumps, (Diesel Engine Driven Fire pump, Electric Motor Driven fire
pump and a jockey Pump) are installed in the Fire Pump Room at Ground Floor to
provide adequate pressure and flow in the sprinkler system. The pumps are being
controlled by the means of three individual control panels. The pumps are activated
by the means of a pressure switch, which makes the Primary Fire Pump (Diesel
engine Driven) start within 30 seconds of a significant pressure drop sensed by the
pressure switches.

Extinguishers:
A portable fire extinguisher can save lives and property by putting out a small fire or
containing it until the fire department arrives; but portable extinguishers have limitations.
Because fire grows and spreads so rapidly, the primary priority for residents is to get out

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 76
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

safely. Fire extinguishers are one element of a fire response plan, but the primary element is
safe escape.
Portable fire extinguishers shall be maintained in a fully charged and operable condition and
shall be kept in their designated places at all times when they are not being used. Fire
extinguishers shall be conspicuously located where they will be readily accessible and
immediately available in the event of fire. Preferably, they shall be located along normal
paths of travel, including exits from areas.
Portable fire extinguishers shall be installed throughout all new and existing facilities in
accordance with BNBC Part 4 Section 4.10 and NFPA 10.
• Spacing: Extinguishers shall be placed so that maximum travel distance to the nearest
unit shall not exceed 30m (100 ft).
• Mounting height: Fire extinguishers having a gross weight not exceeding 18.14 kg (40
Ib) shall be installed so that the top of the fire extinguisher is not more than 1.53 m (5
ft) above the floor (NFPA 10 6.1.3.8). Fire extinguishers having a gross weight
greater than 18.14 kg (40 Ib) (except wheeled types) shall be installed so that the top
of the fire extinguisher is not more than 1.07 m (316 ft) above the floor (NFPA 10
6.1.3.8).
• Portable fire extinguishers shall readily available in different type. These are Portable
Fire
• Extinguishers are of Gaseous types, Dry Chemical types, Water types, Film-Forming
type, and Foam types. For proper operation persons with adequate knowledge and
familiar with their operation must be available.
• Portable fire extinguishers shall be adequately protected from impact, vibration, and
adverse environment and shall not be exposed to temperatures outside the listed
temperature range shown on the fire extinguisher label.
• Portable fire extinguishers mounted in cabinets or wall recesses shall be placed so that
the fire extinguisher operating instructions face outward. The location of such fire
extinguishers shall be marked conspicuously.
• The owner or designated agent or occupant of a property in which fire portable
extinguishers are located shall be responsible for inspection, maintenance, and
recharging. The procedure for inspection and maintenance of fire extinguishers varies
considerably. Monthly "quick check" or inspection in order to follow the inspection
procedure as outlined in NFPA 10 shall be done.
• Maintenance, servicing and recharging shall be performed by trained persons having
available the appropriate servicing manual(s), the proper types of tools, recharge
materials, lubricants, and manufacturer's recommended replacement parts or parts
specifically listed for use in the fire extinguisher. These extinguishers shall be
maintained as per NFPA 10, at intervals of not more than one year.
• All rechargeable-type fire extinguishers shall be recharged after any use or as
indicated by an inspection or when performing maintenance or as per the
recommendations of the manufacturer.
• For personal safety during approach with extinguishing equipment it shall be
remembered that most fires produce toxic decomposition products of combustion and
some materials can produce highly toxic gases. Fires can also consume available

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 77
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

oxygen or produce dangerously high heat. All of these can affect the degree to which
a fire can be safely extinguished.

FHC (Fire Hose Connections)


A fire hose is a high-pressure hose that carries water or other fire retardant (such as foam) to
a fire to extinguish it. Outdoors, it attaches either to a fire engine or a fire hydrant. Indoors, it
can permanently attach to a building's standpipe or plumbing system.
The1 usual working pressure of a fire hose can vary between 8 and 20 bars (800 and 2,000
kPa; 116 and 290 psi), After use, a fire hose is usually hung to dry, because standing water
that remains in a hose for a long time can deteriorate the material and render it unreliable or
unusable. Therefore, the typical fire station often has a high structure to accommodate the
length of a hose for such preventative maintenance.
Modern fire hoses use a variety of natural and synthetic fabrics and elastomers in their
construction. These materials allow the hoses to be stored wet without rotting and to resist the
damaging effects of exposure to sunlight and chemicals. Modern hoses are also lighter weight
than older designs, and this has helped reduce the physical strain on firefighters. Various
devices are becoming more prevalent that remove the air from the interior of fire hose,
commonly referred to as fire hose vacuums. This process makes hoses smaller and somewhat
rigid, thus allowing more fire hose to be packed or loaded into the same compartment on a
firefighting apparatus.
Hose connections are often made from brass, though hardened aluminum connections are
also specified. The hose connections/couplings must be checked regularly for compatibility
with the ones that Fire Department use.
As per BNBC Part 4, Chapter 4 The minimum pressure for standpipes supplying a 50mm or
larger hose shall be at least 300 kPa (4.2.3.3). For standpipe supplying first aid hose (38 mm
nominal) may have a minimum pressure of 200 kPa. The maximum pressure at any point of
the system shall not exceed 2434.1 kPa, if the hose connection at 40mm outlet exceeds 700
kPa approved pressure regulating device shall be installed to maintain the above maximum
limits.
The hose shall be connected to the standpipe within a height not more than 1.5 m from the
finished floor level. Hose stations shall be easily accessible for inspection and testing (BNBC
4.2.3.10).

Hydrant
Fire protection in land-based buildings, offshore construction or onboard ships is typically
achieved via all of the following:
• Passive fire protection - the installation of firewalls and fire rated floor assemblies to
form fire compartments intended to limit the spread of fire, high temperatures, and
smoke.
• Active fire protection manual and automatic detection and suppression of fires, such
as fire sprinkler systems and (fire alarm) systems.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 78
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

The existing fire safety System in the Commercial building. Engages both active and passive
Fire protection. The standpipe wet riser hose systems are the means of Passive Fire Protection
which is the most commonly used in the Ordinary Hazard (Class G II) industries in
moderately high-rise buildings.
The Hydrants used in the premises of the Commercial building. Is of a "Wet-Barrel" design,
i.e. the hydrant is connected directly to the pressurized water source.

The user attaches a hose to the fire hydrant, then opens a valve on the hydrant to provide a
powerful flow of water, on the order of 350 kPa (50 pounds per square inch gauge (psig)).
This user can attach this hose to a fire engine, which can use a powerful pump to boost the
water pressure and possibly split it into multiple streams. A user should take care not to open
or close a fire hydrant too quickly, as this can cause a water hammer, which can damage
nearby pipes and equipment. The water inside a charged hose line causes it to be very heavy
and high water pressure causes it to be stiff and unable to make a tight turn while pressurized.
When a fire hydrant is unobstructed, this is not a problem, as there is enough room to
adequately position the hose.

Automatic configurations of three Pumps, (Diesel Engine Driven Fire pump, Electric Motor
Driven fire pump and a jockey Pump) are installed in the Fire Pump Room at Ground Floor
to provide adequate pressure and flow in the sprinkler system. The pumps are being
controlled by the means of three individual control panels. The pumps are activated by the
means of a pressure switch, which makes the Primary Fire Pump (Diesel engine Driven) start
within 30 seconds of a significant pressure drop sensed by the pressure switches.

The most important suggestion of maintaining an efficient Fire hydrant system is to run it at a
regular interval, which is mentioned in the Inspection, Testing & Maintenance section in Part
IX.
The details of hydrant system are provided in the drawings for reference.

Automatic Sprinkler System:


A fire sprinkler system is an active fire protection method, consisting of a water supply
system, providing adequate pressure and flow rate to a water distribution piping system, onto
which fire sprinklers are connected. Fire sprinkler systems are extensively used worldwide,
with over 40 million sprinkler heads fitted each year. In buildings completely protected by
fire sprinkler systems, over 96% of fires were controlled by fire sprinklers alone.

By a wide margin, wet pipe sprinkler systems are installed more often than all other types of
fire sprinkler systems. They also are the most reliable, because they are simple, with the only
operating components being the automatic sprinklers and (commonly, but not always) the
automatic alarm check valve. An automatic water supply provides water under pressure to the
system piping.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 79
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

The Sprinkler System employed in the Commercial building. Building is of "Wet Pipe" type.
The system is always kept in certain water pressure so that water supply at the most remote
sprinkler point can have a minimum pressure of 4.5 bar. The system has been designed using
an area & density approach as per the guidelines & standards of NFPA 13 and BNBC Part 4
Chapter 4. Identifying the Hazard Class (Ordinary Hazard Group 2) the design area and
density* has been determined by referencing the table in NFPA 13.

The design area is a theoretical area of the building representing the worst-case area where a
fire could burn. The design density is a measurement of how much water per square foot of
floor area should be applied to the design area.

The suggestions for an efficient sprinkler operation should include:


• A plan of action is required should a sprinkler system fail to work properly for more
than 10 hours in a 24-hour period. A sprinkler system could include, but not limited
to, sprinkler heads, sprinklers, branch lines, water mains and water supply.
• Where a sprinkler system is out of service for more than 10 hours in a 24-hour period,
the authorities having jurisdiction (Bangladesh Fire Service & Civil Defense
authority) shall be notified, and the building shall be evacuated, or an approved fire
watch shall be provided for all parties left unprotected by the shutdown until the
sprinkler system has been returned to service.
• Sprinkler valves shall be open and sealed; gauges should indicate normal pressures
and sprinkler heads must be unobstructed.
• Sprinkler system outages can occur during construction, utility failures
The details of Sprinklers are provided in the drawings for reference.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 80
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Alarm System
The details of Sprinklers are provided in the drawings for reference.
In the Commercial building premises, a suitable electrically operated fire warning system,
with manual call points positioned both on exit routes and adjacent to final exits have been
installed. The suggestions include but not limited to:
• This should have sufficient sounders for the warning to be clearly heard throughout
the workplace. The sound used as a fire warning should be distinct from other sounds
in the workplace and, where background noise levels are high, or an employee has a
hearing impairment, it may also be necessary to install a visual alarm such as a
distinctive flashing or rotating light.
• Where a public-address system is used in conjunction with a fire warning system,
both should over-ride any other function of the equipment (such as playing music).
The public-address element of the system should give clear verbal instructions and
should over-ride the fire warning signal - this should be distinct from other signals
which may be in general use.
• If an automatic fire detection system and a manually operated electrical alarm system
are installed in the same workplace, they should normally be incorporated into a
single integral system. Voice evacuation systems should be similarly integrated to
prevent confusion.
• Fire safety measures an-d equipment in the workplace must be kept in effective
working order. This includes all fixtures and fittings such as fire doors, staircases,
corridors, fire detection and alarm systems, fire-fighting equipment, notices and
emergency lighting. Regular checks, periodic servicing and maintenance must be
carried out, whatever the size of the workplace. Any defects should be put right as
quickly as possible.
• The Fire Alarm System must be integrated with:
o The mechanical exhaust system
o Active & Passive Fire Protection System
o Fire Doors
o Fire Department Notification
o Manual Call Points

Detection System
The suggestion for proper working of the Addressable Fire Detection & Alarm System might
include:
• The system should be capable of immediate operation at all times.
• The system should be capable of fire detection based on testing conducted in
accordance with internationally recognized standards or as prescribed by the
Administration.
• The system and its components should be suitably designed to withstand ambient
• Temperature changes, vibration, humidity, shock, corrosion and impact normally
encountered on the building. External components should additionally be designed to
withstand sun irradiation, ultraviolet exposure, water ingress and corrosion normally
encountered.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 81
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• If detectors are not remotely and individually identifiable dedicated to Lobby area
only, the detectors should be grouped into sections. The system indicating units
should, as a minimum, denote the section in which a detector has been activated.
• The location and spacing of the detectors should be within the limits tested.
• There should be not less than two sources of power supply for the electrical
equipment used in the operation of the fixed fire detection and fire alarm system, one
of which should be an emergency source. The supply should be provided by separate
feeders reserved solely for that purpose. Such feeders should run to an automatic
change-over switch situated in or adjacent to the control panel for the fire detection
system.
• Detectors should be operated by heat, smoke or other products of combustion, flame,
or any combination of these factors. Detectors operated by other factors indicative of
incipient fires may be considered by the Administration provided that they are no less
sensitive than such detectors.
• All detectors should be of a type such that they can be tested for correct operation and
restored to normal surveillance without the renewal of any component.
• The activation of any detector should initiate a visual and audible fire signal at the
control
• Panel and indicating units. If the signals have not received attention within 2 min an
audible alarm should be automatically sounded throughout the crew accommodation
and service spaces, control stations and machinery spaces of category A. This alarm
sounder system need not be an integral part of the detection system.
• The control panel should be located on the navigation bridge or in the onboard safety
center.
• At least one indicating unit should be so located that it is easily accessible to
responsible members of the management at all times.
• Clear information should be displayed on or adjacent to each indicating unit about the
spaces covered and the location of the sections.
• Power supplies and electric circuits necessary for the operation of the system should
be monitored for loss of power or fault conditions as appropriate. Occurrence of a
fault condition should initiate a visual and audible fault signal at the control panel
which should be distinct from a fire signal.
• Suitable instructions and component spares for testing and maintenance should be
provided, considering any special requirements for detectors located in external areas.
Detectors should be periodically tested using equipment suitable for the types of fires
to which the designed to respond.

Fire Pump
The Fire Pumps installed in the Commercial building. Ltd premises have the construction,
installation & Commissioning as per the guidelines of NFPA 20. As per the guidelines of
BNBC Part 4 Chapter 4, the following guidelines must be followed:
• The firefighting equipment shall be directly feed by automatic main fire pump.
Centrifugal Pump, turbine-type pump (submerged or with vertical shaft) or positive
displacement pumps with adequate supply pressure and flow capacity shall be used

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 82
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

for water supply during demand. Centrifugal pumps shall not be used where a static
suction lift is required.
• Once the pump starts, it shall run continuously until stopped manually. The pump
shall be fully operational within 30 seconds after starting. There shall be provision for
manual starting where priming is necessary. Automatic priming equipment is
necessary to ensure priming at all times. The fire pump shall not be used for other
purpose.
• Fire pumps shall have the rated capacities as shown in Table 4.4.2. The pump shall be
rated at net pressure of 272.70 KPa or more as per requirement of the firefighting
system demand. For pump installation procedure and fittings NFPA 20 shall be
followed.
• The pump shall be housed in a readily accessible position in a building of non-
combustible construction. The pump shall be adequately protected against mechanical
damage.
• There shall be a provision for secondary fire pump which can be operated by
dedicated generator or by an alternate power supply source with adequate control
system and incompliance with safety operation during fire. Quality of the pump
assembly shall comply with the specification of International Association of Fire.
From these generator and alternative power supply source power cannot be utilized
for regular use other than (i) fire lift, (ii) stretcher lift, (Hi) emergency light, (iv) alarm
system.

Priming:
The Fire pumps are recommended to have a positive suction orientation. But in case of the
Commercial building premises the fire pumps are located above the Water Reservoir,
resulting in a negative suction. But priming is being ensured by drain valves which provide a
means to supply water from the discharge header to suction pipes. Moreover, the pipeline is
connected to the overhead tanks along with Non-Return Valves, which ensures a provision to
provide water from overhead tank through the vertical riser pipes to the pump suction pipe.

Water Reservoir
The water requirement as per Table 4.4.1 or BNBC Part 4 Chapter 4 states a flow of 2650
Liters/minute water for Ordinary hazard class I, which would have a duration of 75 minute. The water
requirement becomes 1,98,750 Liters calculating the stated flow rate. The building is equipped with
an Underground Water Reservoir of 2.50 lac Liters. Besides an overhead water tank with capacity
1,00,000 Liters is also connected using an Overhead Connection.
It is suggested that:
• One or more connections from a reliable public water system of proper pressure and adequate
capacity furnish a satisCommercial building supply. A high static water pressure shall not,
however, be the criterion by which the efficiency of the supply is determined.
• If this cannot be done, the post indicator valves shall be placed where they will be readily
accessible in case of fire and not liable to injury. Where post indicator valves cannot readily
be used, as in a city block, underground valves shall conform to these provisions and their
locations and direction of turning to open shall be clearly marked. Adequacy of water supply

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 83
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

shall be determined by flow tests or other reliable means. Where flow tests are made, the flow
in (L/min.) together with the static and residual pressures shall be indicated on the plan.
• Public mains shall be of ample size, in no case smaller than 15 cm (6 in).
• No pressure regulating valve shall be used in water supply except by special permission of the
authority concerned. Where meters are used they shall be of an approved type.
• Where connections are made from public waterworks systems, it may be necessary to guard
against possible contamination of the public supply. The requirements of the public health
authority shall be determined and followed.
• Connections larger than 50.8 mm to public water systems shall be controlled by post indicator
valves of a standard type and located not less than 12.2 m from the buildings and units
protected.

"Fire Vehicle Road & Vertical Clearance


The Main Gate with a width of 10 feet provides the access to the Commercial building. For
Fire Vehicles. The clearance height is 11ft which is also the height of the Ground Floor.
There would be the following recommendations:
• There should be vehicle access for a pump appliance to buildings to either:
o 15% of the perimeter;
Or
o Within 45m of every point on the projected plan area (or 'footprint') of the
building; whichever is less onerous.
• Any elevation to which vehicle access is provided should have a suitable door, not
less than 750mm wide, giving access to the interior of the building.
• All access roads for Fire Service appliances should be kept clear of any obstructions.
It may, however, be considered necessary to restrict unauthorized entry and various
arrangements are set out below.
• Before any obstructions are installed the proposed arrangements should be agreed with the
local Fire Station Commander.
• A clearly defined fire path at least 3.7m wide and capable of supporting the weight of a Fire
Service pumping appliance, i.e. maximum 24 tones, is required through a pedestrianized area.
(This may be indicated by the use of different colored concrete or different paving patterns.)
Where tall buildings abut, the fire path will need to be 6m wide for use by high reach
appliances with a working width of 8m and capable of taking a maximum weight of 24 tons.

Fire Brigade Connection


The Fire Department Connection (FDC), also known as the Siamese Connection, is an important
component found on most sprinkler and standpipe systems. When a sprinkler system activates, the fire
department connects hose lines from a pumper truck to the fire department connection. This
connection allows the fire department to supplement the fire protection system in the event of a fire.
In a recent Comment on Proposal, the NFPA 13 technical committee stated, "The purpose of the Fire
Department Connection is to supplement the water supply, but not necessarily provide the entire
sprinkler system demand. Fire Department Connections are not intended to deliver a specific volume
of water."
• The fire department connection can be thought of as only consisting of the inlet body,
however, the FDC is actually made up of the inlet, check valve, and piping connecting to the
sprinkler system riser or main.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 84
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• FDC shall be on the system side of the water supply check valve. This provision refers to the
inlet, piping, check valve, etc. as being one unit. The sizing of all these components from the
connection to the sprinkler system to the inlet shall be determined by 13(99) 5-15.2.2.
• The piping between the exterior FDC and the check valve be hydrostatically tested in the
same manner as the balance of the system. The test is to confirm that the piping is properly
installed and will not leak or come apart. The required number of inlet connections varies
depending on the type and demand of the system being served. For fire sprinkler systems,
NFPA 13(99) 5-15.2.2 requires a 4" pipe size for fire engine connections.
• Exception allows a single-outlet FDC where piped to a 3" or smaller riser. These criteria
indicate that unless the riser of the sprinkler system is 3" or smaller, the FDC must have a
minimum of two connections. There is no other criterion in NFPA 13 requiring more than two
connections.
• For standpipe systems, NFPA 14(00) 2-8, 2 requires each FDC to have at least two 2-1/2"
internal threaded swivel fittings. Further 14(00) 5-7 requires standpipe systems to be designed
so that the system demand can be supplied by both the attached water supply, where required,
and fire department connections.
• Fire Department Connections must be compatible with the fire hose couplings used by
Bangladesh Fire Service & Civil Defense.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 85
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Fire Brigade Connection in each floor


Fire Department Connections on each floor of the building is Class I service of the standpipe
system equipped with 2.5" diameter outlets. There are three such connections at each floor of
the building adjacent to three staircases, with a branch pipe from the vertical risers.
• It is to be ensured that the coupling system is compatible with the fire hose couplings
used by Bangladesh Fire Service & Civil Defense.
• Cabinets used to contain fire hose shall be of sufficient size to permit the installation
of the necessary equipment at those stations, and so designed as not to interfere with
the prompt handling of the hose valve, hose, and equipment at time of fire. They shall
be used for fire equipment only. Each hose cabinet shall be conspicuously identified.
• Hose outlets shall be within easy reach of a person standing on the floor and in no
case shall be over six (6) feet from the floor. Hose stations shall be located
conspicuously within the immediate area and where not likely to be obstructed. Hose
may be located at one side of the standpipe and supplied by short lateral connections
to the standpipe where necessary to avoid obstructions.
• Maintenance on standpipe systems shall be performed by a trained person who has
undergone the training necessary to reliably perform the required maintenance
procedures. Standpipe maintenance shall be accomplished in accordance with NFPA
14, UFC Appendix 3-C, and appropriate manufactures service manuals
Fire Control Room
The Fire Control Room is a room dedicated for special purposes related to the Fire Safety.
The following recommendations apply for a Fire Control room.
room Size. The fire command center for high-rise buildings shall not be less than 100 square
feet of floor area with no dimension less than 10 feet. The minimum clear ceiling height shall
not be less than eight feet.
• Emergency Power Circuits. The required electrical supply circuits for the equipment
in the fire command center shall be supplied from the building's emergency standby
power system and these circuits shall supply no other outlets, devices, or equipment.
• Room Illumination. The fire command center shall be provided with permanent
lighting, adequate to see all life safety equipment. The illumination for the fire
command center shall be supplied from the building's emergency standby power
system, and these circuits shall supply no other outlets, devices, or equipment.
• Remote Annunciator Panel. A remote fire alarm annunciator panel shall be required at
ground floor entrances into all enclosed stairways in locations approved by the fire
department.
• Identification of Cabinets and Controls. Identification of all cabinets, controls, and devices
shall be clearly and legibly marked and visible at all times and shall be subject to the approval
of the fire department.
• Telephone. A non-toll, non-restricted telephone shall be installed in the fire command center.
This shall be a private line connected directly to the telephone system. The telephone number
shall be clearly displayed on the telephone.
• Dry Marker Board. A dry marker board with a minimum size of three feet by four feet with
all necessary accessories shall be installed and maintained.
• Work Surface. A work surface that is a minimum of 30 inches wide by 60 inches long shall be
located in the fire command center.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 86
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• Air Conditioning. The fire command center shall be conditioned to maintain a temperature
between 70 degrees Fahrenheit and 78 degrees Fahrenheit under normal and emergency
conditions.
• Labeling. All equipment supplied by the building's emergency standby power system shall be
permanently labeled. Labels shall include the origin of their supply circuits.
• Log Book. The building owner shall maintain a logbook in the fire command center. All
alarms, trouble conditions, maintenance and repairs shall be recorded with the date, time, and
location from which the signal originated. Maintenance and repairs shall be logged showing
reason for, date, time, name, and the time the system was restored.
• Equipment and Controls. The fire command center shall contain the following equipment:
• Standby and emergency power system status indicators. This shall include but not be limited
to the following:
o Low fuel indication,
o Generator status,
o A generator control switch shall be installed so as to allow the generator to be manually
started from the fire command center when the building is in alarm mode;
o Controls necessary to automatically notify the fire alarm monitoring company in the event
of a fire alarm or trouble condition. The interconnections required shall also comply with
the raceway requirements;
o A labeled cabinet containing spare sprinkler heads (all types used in the building) and the
proper tools needed for their removal and installation. The number of spare fire sprinkler
heads shall be determined by NFPA 13;
o Clear instructions for the operation of all equipment located in the fire command center;
o Indicators showing the status of the fire pump(s). This shall include, but not be limited to:
power available, pump operating, low fuel, low auxiliary water supply, or other condition
as required by the fire department;
o Three spare fuses for all life safety equipment located in the fire command center shall be
provided. Fuse holders shall be labeled with the size, type, and use of the fuse;
o Data processing equipment required for the life safety system;
o Trouble indicator for pressure drop in the fire department breathing air system;
o Annunciator visually indicating the location of the elevator cars and whether they are
operational;
o Controls for unlocking stairway doors simultaneously.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 87
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Suggestions on Hot Working

Hot working is a major source of Fire hazard in Industrial applications. The following
preventive measures are necessary for hot working.

• Before Beginning
o Evaluate the decision to perform hot work. The first step of the hot work
management process is to determine whether the hazard can be avoided or
minimized. Where practical:
• Avoid hot work if possible.
• Relocate the object requiring hot work outdoors or to specially designated areas that
have been designed and constructed to minimize fire risk. Good housekeeping should
be maintained, and the area routinely audited to ensure it remains safe for hot work.
• Schedule hot work during shutdowns if it cannot be avoided or relocated.
• If it is determined that hot work is necessary, and the object cannot be relocated to a
designated hot work area, the persons requesting and those who will be performing
the hot work should contact a Hot Work Permit Issuing Officer and begin the permit
process.
• Utilizing a Permit System
• While many standards, including NFPA 51B, Standard for Fire Prevention During
Welding, Cutting, and Other Hot Work, require a permit only under certain
conditions, such as being unable to secure a 35- foot radius clear of combustibles, it is
a best practice and highly advisable to use a hot work permit system for all hot work
operations outside the designated area.

Use of Welding & Grinding Machines


Fires occurring in machines using oil-based coolant can cause significant damage within
seconds, potentially spreading throughout the facility and causing extensive damage. Even
with the operator standing by, machines have been destroyed by fire in a matter of minutes.
The following guidelines can reduce the risk of fire while using welding & Grinding
Machines.
Welding
• Electrode holders should be in good repair and rated for the maximum capacity of
equipment used.
• All cables and connectors should be in good repair, tightly attached, fully insulated,
and rated for the maximum capacity of the work.
• The welding lead will have a safe current capacity equal to, or greater than, the
specified maximum output of the arc welding or cutting unit which it serves.
• When a single work lead services more than one unit, its safe current carrying
capacity should equal or exceed the total specified maximum output capacities of all
the units which it services.
• All electrical equipment (welding machines) and work should be properly grounded.
The welding lead is not a ground lead. It is used only to complete the electrical circuit.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 88
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

A separate connection may be required to ground the work piece. Do not mistake the
work lead for ground.
• Pipelines containing gases or flammable liquids, or conduits containing electrical
circuits, should not be used as a ground.
• Equipment for loose connections or bare or damaged wires. Do not use faulty
equipment.
• Have workers turn off the welding machine at the end of the shift or when they will
not be using it for an extended period.

Fire
• Sparks or spatter from welding or arc gouging may ignite burnable items in the area.
Always be sure hot work areas have a minimum 35-foot clear area free of combustible
materials.
• Burnable materials should be removed from the area where welding or arc gouging is
to take place or protected with flame-retardant materials. Use a fire watch as
appropriate.
• When welding on decks, walls, or overhead, be sure to take the necessary precautions
to prevent fire or heat damage in adjacent rooms. Use a fire watch in the other
affected room(s) when appropriate.
• Sparks and spatter from arc gouging travel considerable distances. Whenever
possible, orient the spark stream to minimize concern for fire or damage resulting
from the spark stream. Use fire-retardant shielding and/or fire watch as appropriate.
 Be sure to have full knowledge of the location and use of all fire extinguishing
equipment in the area.
Grinding
• Always use proper protective equipment.
• Use guards whenever they can be used. If you must remove a guard for any reason,
get authorization from your Officer, and replace it as soon as possible.
• Use flash screens or nonflammable poly sheeting to confine flying particles whenever
anyone else is exposed.
• Inspect grinding wheels before using them. Use only wheels that are rated (RPM) for
the
• Machine you are using.
• On bench grinders, keep tongue guards no more than 1/4" and work rest no more than
1/8" away from grinding wheel.

Machinery Friction

When one object comes in contact with another, energy is dissipated in the form of heat,
sound and/or light. The main causes of excessive friction are bearings, equipment damage,
imbalance, slippage and jamming. Electric motors can be found in almost every building as
part of building services, equipment, appliances and tools. Within motors and the equipment,
they drive are bearings which, unless in good order and appropriately lubricated, can generate
excessive heat. While motors are generally regarded as extremely reliable they are subject to
wear, changing environmental and load conditions. Eventually they will fail.
___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 89
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Evacuation
During an emergency, a fire alarm will sound, and all occupants will exit the building via a
safe exit. Persons with disabilities should proceed with their assistants (if available) to the
nearest safe exit. The Fire Safety Director should be available to respond to the premises after
being contacted by the fire department.
The instructions for occupants In Case of Fire, posted prominently on each floor area, provide
quickly read information on procedures to follow in the event of a fire. Use of this concept
should/will ensure a systematic method of safe and orderly evacuation of the building in the
event of fire.

The best way is to prepare to respond to an emergency before it happens. Few people can
think clearly and logically in a crisis, so it is important to do so in advance, when there is
time to be thorough. When developing your emergency action plan, it's a good idea to look at
a wide variety of potential emergencies that could occur in your workplace. It should be
tailored to the worksite and include information about all potential sources of emergencies.
Developing an emergency action plan means that a hazard assessment is done to determine
what, if any, physical or chemical hazards in the workplace can cause an emergency. If there
are more than one worksite, each site should have an emergency action plan. At a minimum
an emergency action plan must include the following:
• A preferred method for reporting fires and other emergencies;
• An evacuation policy and procedure;
• Emergency escape procedures and route assignments, such as floor plans, workplace
maps, and safe or refuge areas,
• Names, titles, departments, and telephone numbers of individuals both within and
outside your company to contact for additional information or explanation of duties
and responsibilities under the emergency plan;
• Procedures for employees who remain to perform or shut down critical plant
operations, operate fire extinguishers, or perform other essential services that cannot
be shut down for every emergency alarm before evacuating; and
• Rescue and medical duties for any workers designated to perform them.
When preparing emergency action plan, it is important to designate primary and secondary
evacuation routes and exits. To the extent possible under the conditions, it is to be ensured
that evacuation routes and emergency exits meet the following conditions:
• Clearly marked and well it;
• Wide enough to accommodate the number of evacuating personnel;
• Unobstructed and clear of debris always; and
• Unlikely to expose evacuating personnel to additional hazards.
The drawings prepared to show evacuation routes and exits must be posted prominently for
all employees to see
Accounting for all employees following an evacuation is critical. Confusion in the assembly
areas can lead to delays in rescuing anyone trapped in the building, or unnecessary and
dangerous search-and-rescue operations. To ensure the fastest, most accurate accountability
of the employees, you may the following steps must be considered to
• Designate assembly areas where employees should gather after evacuating;

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 90
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• Take a head count after the evacuation. Identify the names and last known locations
of anyone not accounted for and pass them to the official in charge;
• Establish a method for accounting for non-employees such as suppliers and
customers; and
• Establish procedures for further evacuation in case the incident expands. This may
consist of sending employees home by normal means or providing them with
transportation to an offsite location.

The employees need to be educated about the types of emergencies that may occur and
trained of the proper course of action. The size of the workplace and workforce, processes
used, materials handled, and availability of onsite or outside resources will determine the
training equipment. It is to be ensured that all employees understand the function and
elements of the emergency action plan, including types of potential emergencies, reporting
procedures, alarm systems, evacuation plans and shutdown procedures. The special hazards
are also to be discussed, such as onsite flammable materials, toxic chemicals, radioactive
sources, or water-reactive substances. It is to be clearly communicated among the employees
who will be in charge during an emergency so that confusion can be avoided.

Fire Preparedness
Industrial fires are one of the foremost threats to the people and property of any organization.
Injuries, deaths and loss of business result from fires each year. It is estimated that 45% of
businesses never reopen after a minor fire. Such losses are avoidable by applying basic fire
prevention controls and being prepared for emergencies. Good management practices require
the development and implementation of policies and procedures to protect employees and
property by preventing and/or controlling fires and preparing for emergencies.
The effectiveness of a fire prevention and emergency preparedness program is directly related
to management's commitment and involvement. Management must establish policy,
procedures and actively participate in fire drills, training, and inspections. Failure to do so
can mean that the lives of employees, and the business itself, are at risk.
• Management should establish an overall written program to address fire hazard and
preparedness for emergencies.
• Managers, Officers, and employees must be knowledgeable and informed of fire
prevention procedures. Fire protection procedures for employees should include (See
sections for more information):
o Hot work permits
o Storage and handling of combustible materials
o Housekeeping
o Fire extinguisher
o Fire hazard identification
 All employees must understand basic emergency action plans:
o Alarms
o Emergency shutdown
o Evacuation routes
o Assembly areas

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 91
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

• Emergency drills test the effectiveness of the emergency preparedness plan.


Management and employees must rehearse their emergency action plans. At a
minimum, an annual drill should be conducted in each department.
• Emergency preparedness drills and inspections of facility emergency alarms, exit
doors, emergency lighting, and other equipment must be conducted on a routine basis.
• Fire protection must be audited to assess their effectiveness procedures (e.g., hot work
and storage and handling of flammable materials).
• A coordinator should be designated to assist management in assuring that all elements
of the fire protection and emergency preparedness program are in place and working.
The coordinator should understand emergency preparedness planning and all elements
of the facility's fire protection plan.
• All fires must be investigated to identify causes and a strategy for preventing
recurrence.
• Management must enforce all policies and procedures as necessary to maintain
compliance.
• Consideration must be given to all personnel that are on site.

Incendiary/Arson Fire
An incendiary fire is a fire that was started intentionally. It must be remembered though, that
not all incendiary fires are a crime. An incendiary fire that was started to burn property of
another, or to fraud, etc., is called arson. Any fire that is determined or suspected of being
arson needs a complete fire investigation done. If the arson fire is of significant monetary fire
loss, high profile fire, etc., the fire department can investigate.

Fire & Smoke Compartmentation

This is fire separation of. Non-combustible, construction that separates or subdivides a


building. A firewall must have a certain fire resistance rating (spelled out in the Bangladesh
National Building Code) and must maintain structural stability during a fire for a certain
period of time.
• Opening in the separating wall: The opening in the separating walls of the three
Staircases are provided with Fire rated Door Single Leaf with Staircase 1 & 3 and
Double Leaf Fire Door with Staircase 2. There are means for Positive Pressure in the
Staircases through Exhaust Fans, which are interfaced with Fire Detection System.
• Vertical Risers: There are four Vertical Risers in the Building being used for the
purposes mentioned below
o Electrical Cable Riser: Fire Propagation through the electrical cable riser is being
avoided using Fire stoppers on each floor,
o Plumbing Riser: Fire Propagation through the Plumbing riser will be avoided
using Fire stoppers on each floor.
o Steam Riser: Fire Propagation through the Steam riser is being avoided using Fire
stop person each floor.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 92
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

o Communication Cable Riser: Fire Propagation through the communication cable


riser is being avoided using Fire stoppers on each floor.
• Each penetration in the Fire separation walls will be provided with Fire Stoppers
• Ducts: There are no ducts for HVAC or other utilities systems.
• Surface finishes: Paint
• Wired glass panels: Not Available
• Fire lift: Attached to Main Lobby

Fire & Safety Team


The Fire Safety Team's objective is to constantly improve and maintain a high level of safety
standard in the Commercial building premises. The primary goal is to eliminate or reduce the
risks of injuries to occupants working in the building. The second goal is to prevent damage
to property.

To achieve these goals, the Fire Safety Team works together with the other safety teams and
building occupants to establish a safe working environment by planning and implementing
effective preventive measures. These measures include stepping up vigilance via routine
building inspections and educating and increasing the awareness of the individual on fire
safety through training programs organized by Bangladesh Fire Service & Civil Defense
authority.

Safety cabinets and only small volumes are allowed to be kept on the working benches,
provided that a proper labeling system is in place and is according to guideline.
The Fire Safety Plan provides many useful information and is highly recommended for all occupants
to read. Approach any member of the Fire Safety Team if there are any queries.
Below are some useful tips and preventive measures to reduce fire-related risks and hazards:
1. Major contributing factors of electrical fires:
a. Power overloading
b. Short circuits
c. Poor condition or quality of equipment and product
2. Common fire hazards:
a. Items discarded along fire escape route
b. Blocking of fire exits
c. Obstructions to fire-fighting equipment (e.g. fire extinguisher, hose reel)
3. The 3 elements responsible for igniting and maintaining combustion (A fire will not ignite/not
be able to sustain combustion if any of the below elements are absent or in insufficient
amount):
a. Fuel
b. Heat
c. Oxygen
4. Take note of the location of the below fire-fighting equipment:
a. Fire extinguishers
b. Fire blankets
c. Fire hose reels

Upon physical discovery of fire, break the nearest call point to activate the fire alarm to alert everyone
in the building. Inform the Fire Officer immediately.

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 93
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Fire Drill
A fire drill is a method of practicing how a building would be evacuated in the event of a fire or other
emergencies. In most cases, the building's existing fire alarm system is activated, and the building is
evacuated as if the emergency had occurred. Generally, the evacuation is timed to ensure that it is fast
enough, and problems with the emergency system or evacuation procedures are identified to be
remedied.
As per Bangladesh National Building Code the regulations suggest that:
• Fire drill shall be conducted as per design scenarios in presence of the representative of the
authority having jurisdiction (Bangladesh Fire Service & Civil Defense authority).
• The essence of a fire drill is orderly evacuation training not the time of evacuation.
• Training of first aid firefighting is a part of fire drill.
• Log book shall be maintained where each and every fire drill shall be recorded and duly
signed by the representative of the authorities having jurisdiction (Bangladesh Fire Service &
Civil Defense)
• Frequencies of fire drills shall be decided by the authorities having jurisdiction (Bangladesh
Fire Services-Civil Defense)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 94
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

13. MAINTENANCE LOG

Inspection,
Testing and
Scope Action Taken
Maintenance:
Weekly
Visual Inspection
Tank level YES/NO
Checking
Tank float Visual Inspection
YES/NO
switch Testing
Solenoid valve Visual Inspection
YES/NO
operation Testing
Checking
Water in system YES/NO
Cleaning
Flexible hoses
Visual Inspection YES/NO
and connectors
Visual Inspection
Oil level YES /NO
Checking

Lube oil heater Checking YES /NO

Level (Cooling Visual Inspection


Diesel Engine System YES /NO
system) Checking
Adequate
cooling water to Checking YES /NO
heat exchanger
Water pump (s) Visual Inspection YES /NO
Condition of
Visual Inspection
Flexible hoses YES /NO
Checking
and connections
Jacket water
Checking YES /NO
heater
Leakage
Visual Inspection
(Exhaust YES /NO
Checking
system)
Drain
Checking YES /NO
condensate trap
Electrolyte level
Checking YES /NO
(Battery system)
General
Visual Inspection YES /NO
inspection

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 95
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Pump house
heating Visual Inspection
YES /NO
ventilating Checking
louvers

Inspection,
Testing and
Scope Action Taken
Maintenance:
Monthly
Electrical System
Exercise
isolating switch Visual Inspection
YES /NO
and circuit Checking
breaker
Case exterior
clean and dry Testing YES /NO
(Battery system)
Specific Gravity
or state of
Visual Inspection YES /NO
charge (Battery
system)
Charger and
Diesel Engine System charge rate Checking YES /NO
(Battery system)
Equalize charge
Checking YES /NO
(Battery system)
Circuit breaker
of fuses
Visual Inspection YES /NO
(Electrical
system)

Inspection,
Testing and
Scope Action Taken
Maintenance:
Quarterly
Strainer, Filter,
or dirt leg, or
Cleaning YES /NO
combination
there of
Crankcase
Diesel Engine System Visual Inspection
breather
Changing YES /NO
(Lubrication
Cleaning
system)
Water strainer
(Cooling Cleaning YES /NO
system)
Insulation and
fire hazards Visual Inspection YES /NO
(Exhaust

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 96
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

system)

Terminals clean
Visual Inspection
and tight YES /NO
Checking
(Battery system)
Wire chatting
where subject to
Visual Inspection
movements YES /NO
Checking
(Electrical
system)

Inspection,
Testing and
Scope Taken Action
Maintenance:
Electrical system Semiannually
Operate manual
starting means Testing YES /NO
(electrical)
Antifreeze
protection level
Testing YES /NO
(Cooling
system)
Flexible exhaust
section (Exhaust Visual Inspection YES /NO
system)
Operation of
Diesel Engine system
safeties and
alarms Checking Testing YES /NO
(electrical
system)
Boxes, panels
and cabinets
Cleaning YES /NO
(electrical
system)
Inspection,
Testing and
Scope Action Taken
Maintenance:
Annually
Lubricate pump
Changing YES /NO
bearings
Pump System
Check pump
Checking YES /NO
start and play
Check accuracy
of pressure Checking
YES /NO
gouges and Changing
sensors

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 97
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Check pump
coupling Checking YES /NO
alignment
Lubricate
Changing YES /NO
coupling
Mechanical Transmission
Lubricate right-
Changing YES /NO
angle gear drive
Trip circuit
breaker (if
Testing YES /NO
mechanism
provided)
Inspect and
operate
emergency
YES /NO
manual starting
means (Without Visual Inspection
power) Testing
Tighten
electrical
Checking YES /NO
connections as
Electrical System
necessary
Lubricate
mechanical
moving parts
Checking YES /NO
(excluding
starters and
relays)
Calibrate
pressure switch Checking YES /NO
settings
Grease motor
Grease motor Changing YES /NO
bearings
Water and
foreign material Cleaning YES /NO
in tank
Tank vents and
overflow piping Checking Testing YES /NO
unobstructed

Diesel Engine System Piping Visual Inspection YES /NO

Rad out neat


Cleaning YES /NO
exchanger
Inspect duct
work clean Visual Inspection
YES /NO
louvers Checking
(combustion Changing

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 98
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

air)(cooling
system)

Excessive back
pressure
Testing YES /NO
(Exhaust
system)
Exhaust system
hungers and
supports Visual inspection YES /NO
(Exhaust
system)
Clean terminals
Cleaning YES /NO
(Battery system)
Tighten control
and power
wining Checking YES /NO
connections
(Battery system)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 99
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

HAMEEM DENIM LIMITED

Fire Pump Check List


APPENDIX-D (FIRE PUMP SYSTEM INSPECTION
CHECK LIST)
To be completed by the Inspector at the time of Inspection. Attach additional shoots, data or calculation
as necessary to provide a complete record.

COMMERCIAL BUILDING
INFORMATION
Commercial building Name : BANANI DCC UNIQUE COMPLEX

Address: Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213


Bangladesh.

a) Representative Name: Iftakharul Alam (fire safety officer)

Designation: Head of HR and Compliance.


Phone: 01711085216

INSTALLATION, SERVICE AND TESTING CONTRACTOR


INFORMATION

Contractor Name:

Address:

Inspector or Tester Name:

Qualification of Inspector or Tester:


A Contract for Inspection and testing in accordance with NFPA is in effect as of:
……………………………

WITNESS BY

Company Name HAMEEM DENIM LIMITED

Address: Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213, Bangladesh.

Representative Name: Iftakharul Alam (fire safety officer)


___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 100
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Inspection,
Testing and
Scope Action Taken
Maintenance:
Weekly
Visual Inspection YES/NO
Tank level
Checking
Tank float Visual Inspection YES/NO
switch Testing
Solenoid valve Visual Inspection YES/NO
operation Testing
Checking YES/NO
Water in system
Cleaning
Flexible hoses YES/NO
Visual Inspection
and connectors
Visual Inspection YES/NO
Oil level
Checking
YES/NO
Lube oil heater Checking

Level (Cooling Visual Inspection YES/NO


Diesel Engine System system) Checking
Adequate YES/NO
cooling water to Checking
heat exchanger
YES/NO
Water pump (s) Visual Inspection
Condition of YES/NO
Visual Inspection
Flexible hoses
Checking
and connections
Jacket water YES/NO
Checking
heater
Leakage YES/NO
Visual Inspection
(Exhaust
Checking
system)
Drain YES/NO
Checking
condensate trap
Electrolyte level YES/NO
Checking
(Battery system)
General YES/NO
Visual Inspection
inspection

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 101
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

Pump house YES/NO


heating Visual Inspection
ventilating Checking
louvers

Inspection,
Testing and
Scope Action Taken
Maintenance:
Monthly
Electrical System
Exercise YES/NO
isolating switch Visual Inspection
and circuit Checking
breaker
Case exterior YES/NO
clean and dry Testing
(Battery system)
Specific Gravity YES/NO
or state of
Visual Inspection
charge (Battery
system)
Charger and YES/NO
Diesel Engine System charge rate Checking
(Battery system)
Equalize charge YES/NO
Checking
(Battery system)
Circuit breaker YES/NO
of fuses
Visual Inspection
(Electrical
system)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 102
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

UNIQUE CEMENT FIBRE INDUSTRIES LTD.

Fire Alarm & Detection System Check List

To be completed by the Inspector at the time of Inspection. Attach additional shoots, data as necessary to provide a compl

COMMERCIAL BUILDING INFORMATION

Commercial building Name : BANANI DCC UNIQUE COMPLEX

Address: Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213, Bangladesh.

Representative Name: Iftakharul Alam (fire safety officer)

Designation: Head of HR and Compliance.

INSTALLATION, SERVICE AND TESTING CONTRACTOR INFORMATION

Contractor Name:

Address:

Inspector or Tester Name:

Qualification of Inspector or Tester:

Phone:

Standpipe and Hose System Check List

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 103
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

APPENDIX C (STANDPIPE SYSTEM INSPECTION CHECK


LIST)
To be completed by the Inspector at the time of Inspection. Attach additional shoots, data or
calculation as necessary to provide a complete record.

COMMERCIAL BUILDING
INFORMATION

Commercial building Name : BANANI DCC UNIQUE COMPLEX

Address: Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213, Bangladesh.

Representative Name: Iftakharul Alam (fire safety officer)


Designation: DGM HR & Compliance

INSTALLATION, SERVICE AND TESTING CONTRACTOR


INFORMATION

Contractor Name:

Address:

Inspector or Tester Name:

Qualification of Inspector or Tester:

Phone:

WITNESS BY

Company Name: BANANI DCC UNIQUE COMPLEX

Address: Plot-44, Kemal Ataturk Avenue, Banani, Dhaka-1213, Bangladesh.

Representative Name: Iftakharul Alam (fire safety officer)

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 104
FIRE SAFETY PLAN
BANANI DCC UNIQUE COMPLEX
Plot-44, KEMAL ATATURK AVENUE, BANANI, DHAKA-1213

14. ANNEX

a) Fire Protection System.


b) Fire Detection and Alarm System.
c) Fire Safety Master Plan
d) Lightning Protection System
e) Fire Safety Plan Floor Wise

___________________
Safety Source Ltd
H # 27, R # 01, S # 06 Uttara, Dhaka, Bangladesh Page 105

S-ar putea să vă placă și