JULY 2019

NAME OF ACTIVITY WEEK 1 WEEK2 WEEK 3 WEEK 4


Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa

A. THESIS PROPOSAL

B. CONSULTATION

C. DETERMINE PRICES AND MATERIALS

D. RESEARCHING

E. SEARCH FOR TESTING FACILITY

F. PREPARATION FOR MIDTERM DEFENSE

G. ORGANIZING ACTIVITIES FOR GANTT CHART

H. COST BENEFIT ANALYSIS

I. SUBMISSION OF COST BENEFIT ANALYSIS AND GANTT

J. MIDTERM DEFENSE

K. PROGRESS REPORT

L.

M.
AUGUST 2019
NAME OF ACTIVITY WEEK 1 WEEK2 WEEK 3 WEEK 4
Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa

A. MAKING CONTAINER FOR CIGARETTE BUTTS

B. CONSULTATION

C. PLACEMENT OF CONTAINERS IN SMOKING AREAS

D. VACATION

E. COLLECTION OF CIGARETTE BUTTS

F. THESIS DISCUSSION

G. PROCUREMENT FOR BRICK MATERIALS

H. PROGRESS REPORT

I. FIXING OF REVISIONS

J.

K.

L.
M.

SEPTEMBER 2019
NAME OF ACTIVITY WEEK 1 WEEK2 WEEK 3 WEEK 4
Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa

A. PROCUREMENT OF BRICK MOLDS

B. CONSULTATION

C. COMPLETION OF WRITE UP

D. PROGRESS REPORT

E. THESIS DISCUSSION

F. PROTOTYPE TESTING

G. GATHERING OF DATA

H. DATA ANALYSIS

I. COMPUTATIONS

J. MAKING POWERPOINT PRESENTATION

K. VACATION
L.

M.

OCTOBER 2019
NAME OF ACTIVITY WEEK 1 WEEK2 WEEK 3 WEEK 4
Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa

A. APPROVAL OF PAPER FROM THE ADVISER

B. CONSULTATION

C. FINALIZE PAPER WORKS

D. PRINTING OF PAPERS

E. ADVSISER AND PANELIST SIGNATURES

F. HARDBOUND

F. SUBMISSION OF WRITE-UP

G. FINAL PAPER

H. FINAL EXAMS

I. VACATION
J.

K.

ACTIVITY DETAILS

NAME OF ACTIVITY A. Thesis Proposal


ALLOCATED TIME FRAME Three Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Adviser Rejected Thesis Proposal

SOLUTION: Find Another Thesis Proposal

EXPECTED OUTCOME Approved Topic and Finalized Thesis Title

NAME OF ACTIVITY B. CONSULTATION


ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Not Enough Information To Start.

SOLUTION: Search For More Journals and Other Thesis

EXPECTED OUTCOME Additional Learning About The Thesis

NAME OF ACTIVITY C. DETERMINE THE PRICES AND MATERIALS


ALLOCATED TIME FRAME Four Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: The Materials Prices Are Too Expensive

SOLUTION: Find The Cheapest Alternative Materials Or Compare The Different Prices Of
The Stores And Buy The Cheapest
EXPECTED OUTCOME Knowing The Total Budget For The Thesis

NAME OF ACTIVITY D. REASERCHING


ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


3 pcs. Related Books (Library) COST: PHP 0.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: The Information Is Too Difficult To Find

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME Giving Information That We Can Use

NAME OF ACTIVITY E. SEARCHING FOR TESTING FACILITY


ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser Lab Custodian
Chairperson
MATERIALS AND EQUIPMENT COST: PHP
COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: The School Did Not Allow Us To use The Testing Machine

SOLUTION: Find Another Testing Machine Outside the School

EXPECTED OUTCOME Getting Idea Where To Test Our Prototypes

NAME OF ACTIVITY F. PREPARATION FOR MIDTERM DEFENSE


ALLOCATED TIME FRAME Seven Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser 1 Ce-Proj Prof

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION Problem: Lack OF Information To Consider

SOLUTION: Polish The Whole Thesis

EXPECTED OUTCOME Knowing The Little Mistake That We Can Improve

NAME OF ACTIVITY G. ORGANIZING ACTIVITIES FOR GANTT CHART


ALLOCATED TIME FRAME FOUR DAYS
PERSONNEL INVOLVED 1 Ce-Proj Adviser 1 Ce-Proj Prof

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: What To Consider on Making Gantt Chart

SOLUTION: Search On How To Make a Gantt Chart

EXPECTED OUTCOME Learn The Flow Of The Thesis That We Will Do

NAME OF ACTIVITY H. COST BENEFIT ANALYSIS


ALLOCATED TIME FRAME Four Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser 1 Ce-Proj Prof

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Cost Are Not Accurate
SOLUTION: Double Check The Price Of Each Materials

EXPECTED OUTCOME Knowing The Budget That We Will Use

NAME OF ACTIVITY I. SUBMISSION OF COST BENEFIT ANALYSIS AND GANNT CHART


ALLOCATED TIME FRAME One Day
PERSONNEL INVOLVED Ce-Proj Adviser

MATERIALS AND EQUIPMENT COST: PHP


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: We Make A Mistake On Making The Two Quizzes

SOLUTION: Improve The Gannt Charge And Cost Benefit

EXPECTED OUTCOME Polish The Two Quizzes

NAME OF ACTIVITY J. MIDTERM DEFENSE


ALLOCATED TIME FRAME One Day
PERSONNEL INVOLVED 1 Ce-Proj Adviser Ce-Proj Prof
3 Panel
MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00
COST: PHP 0.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: The Panel Revised Some Part Of The Thesis

SOLUTION: Polish The Revised Data/Information


SOLUTION: Polish The Revised Data/Information

EXPECTED OUTCOME Proceeding To Second Phase of The Thesis (Making Prototype)

NAME OF ACTIVITY K. PROGRESS REPORT


ALLOCATED TIME FRAME Four Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser 1 Ce-Proj Prof

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: How To Start The Prototype

SOLUTION: Consult The Ce-Proj Adviser

EXPECTED OUTCOME Start Making Process on the Prototype

NAME OF ACTIVITY L. MAKING CONTAINER FOR CIGARETTE BUTTS


ALLOCATED TIME FRAME Four Days
PERSONNEL INVOLVED

MATERIALS AND EQUIPMENT 1 pcs. Used Paint Container COST: PHP 0.00
3 pcs. Plastic Bags COST: PHP 9.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 9.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Expensive Trashcan

SOLUTION: Making Alternative Trashcan For Cigarette Butts Only

EXPECTED OUTCOME Collecting Cigarette Butts In A Proper Way


NAME OF ACTIVITY M CONSULTATION
ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Progress Is Not That Much

SOLUTION: Double The Effort To Make More Progress

EXPECTED OUTCOME Knowing The Current Status Of Our Thesis

NAME OF ACTIVITY N. PLACEMENT OF CONTAINERS IN SMOKING AREAS


ALLOCATED TIME FRAME Three Days
PERSONNEL INVOLVED People On The Smoking Areas
Owner Of The Smoking Area
MATERIALS AND EQUIPMENT COST: PHP 0.00
COST: PHP 0.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Smoking Areas Did'nt Allow Us to Place a Trashcan For Cigarette Butts

SOLUTION: Keep Finding Smoking Areas

EXPECTED OUTCOME Collecting Cigarette Butts on a Proper Way


NAME OF ACTIVITY O. COLLECTING CIGARETTE BUTTS
ALLOCATED TIME FRAME Two Days
PERSONNEL INVOLVED Owner of The Smoking Area

MATERIALS AND EQUIPMENT COST: PHP


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: The Cigarette Butts Is Not Enough

SOLUTION: Find Another Way On Collecting Cigarette Butts.

EXPECTED OUTCOME The Cigarette Butts Is Enough To Start The Prototype

NAME OF ACTIVITY P. Thesis Discussion


ALLOCATED TIME FRAME Ten Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Mistake On Some Part

SOLUTION: Fixing The Problem

EXPECTED OUTCOME Know The Progress Of The Thesis


NAME OF ACTIVITY Q. PROCUREMENT FOR BRICK MATERIALS
ALLOCATED TIME FRAME Five Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 6kgs.Water, Carbon Dioxide, Sulphur TrioxideCOST: PHP 30.00
6kgs. Silica (Sand) COST: PHP 90.00
6kgs. Alumina (Clay) COST: PHP 60.00
TOTAL COST FOR ACTIVITY: PHP 180.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Where To buy this Materials

SOLUTION: Consult Ce-Proj Adviser

EXPECTED OUTCOME Start The Prototype

NAME OF ACTIVITY R. PROCUREMENT FOR BRICK MATERIALS


ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 6 kgs. Lime, Feric Oxide COST: PHP 120.00
6 kgs. Alkaslis, Magenesia COST: PHP 120.00
------ kgs. Recycled Cigarette Butts COST: PHP 0.00
TOTAL COST FOR ACTIVITY: PHP 240.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Where To buy this Materials

SOLUTION: Consult Ce-Proj Adviser

EXPECTED OUTCOME Start The Prototype


NAME OF ACTIVITY S. FIXING OF REVISION
ALLOCATED TIME FRAME Three Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


----- pcs. Related Books (Library) COST: PHP 0.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: The Information Is Too Difficult To Find

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME Improve The Thesis

NAME OF ACTIVITY T. PROCUREMENT OF BRICK MOLDS


ALLOCATED TIME FRAME Three Days
PERSONNEL INVOLVED

MATERIALS AND EQUIPMENT 3 pcs. Brick Molds COST: PHP 600.00


COST: PHP 0.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 600.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Where To Buy This Kind Of Molds?

SOLUTION: Ask Adviser Where To Buy or Make An Alternative Mold For Bricks

EXPECTED OUTCOME Start The Prototype


NAME OF ACTIVITY U. Consultation
ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP 0.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Delay on Making The Progress

SOLUTION: Making the More Time To Do The Progress

EXPECTED OUTCOME Knowing The Current Status of the Thesis

NAME OF ACTIVITY V. COMPLETION OF WRITE UP


ALLOCATED TIME FRAME Three Days.
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Having Difficulty With The Current Information

SOLUTION: Recalling The Probable Mistake That We have

EXPECTED OUTCOME Giving Information That We Can Use


NAME OF ACTIVITY W. PROTOTYPE MAKING
ALLOCATED TIME FRAME FIFTEEN DAYS
PERSONNEL INVOLVED Lab Custodian
Chairperson
MATERIALS AND EQUIPMENT ---- pcs. Lab Equipments (School Provided) COST: PHP 0.00
2 pcs. Scoop COST: PHP 140.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 140.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Did Not Finish The Three Samples In Time

SOLUTION: Add Another Days To Complete The Samples

EXPECTED OUTCOME Finish The Samples

NAME OF ACTIVITY X. PROTOTYPE TESTING


ALLOCATED TIME FRAME Two Days
PERSONNEL INVOLVED Lab Custodian
Chairperson
MATERIALS AND EQUIPMENT Compressive Testing Machine
1 pcs. COST: PHP 0.00
(School Provided)
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Prototype Missing

SOLUTION: No Choice Remake The Samples

EXPECTED OUTCOME Giving Data Next


NAME OF ACTIVITY Y. GATHERING OF DATA
ALLOCATED TIME FRAME Six Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


2 pcs. PAPER COST: PHP 2.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 2.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Not Accurate Data

SOLUTION: Picture The Process Of Testing

EXPECTED OUTCOME Giving The Data We Can Used For Solving

NAME OF ACTIVITY Z. COMPUTATIONS


ALLOCATED TIME FRAME Five Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser 1 Ce-Proj Prof

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


10 pcs. Papers COST: PHP 10.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 10.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: What to Compute

SOLUTION: Consult on our Thesis Adviser

EXPECTED OUTCOME Finishing All The Data Needed


NAME OF ACTIVITY A1. MAKING POWERPOINT PRESENTATION
ALLOCATED TIME FRAME Two Days
PERSONNEL INVOLVED None

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Summarizing the thesis paper

SOLUTION: Read the manuscript repeatedly.

EXPECTED OUTCOME Detailed Presentation

NAME OF ACTIVITY B1 APPROVAL OF PAPER FROM THE THESIS ADVISER


ALLOCATED TIME FRAME Two Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Adviser Revised Some Part Of the Thesis

SOLUTION: Polish The Revised Parts

EXPECTED OUTCOME Improving The Thesis Paper


NAME OF ACTIVITY C1 PRINTING OF PAPERS
ALLOCATED TIME FRAME One Day
PERSONNEL INVOLVED

MATERIALS AND EQUIPMENT 200 pcs. Bond Papers COST: PHP 200.00
200 pcs. Ink COST: PHP 200.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 400.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Didn't Make In Time

SOLUTION: Make The Paper Works Overnight If Needed

EXPECTED OUTCOME Ready The Powerpoint Next

NAME OF ACTIVITY D1 SUBMISSION OF THE WRITE UP


ALLOCATED TIME FRAME Three Days
PERSONNEL INVOLVED

MATERIALS AND EQUIPMENT 3 pcs. Hard Copy/ Soft Copy/ Book Bind COST: PHP 500.00
COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 500.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Late Submission Due To Traffic Or Heavy Rain

SOLUTION: Early In School Or Provide Private Vehicle

EXPECTED OUTCOME Ready For Passing The Papers To The Panels


NAME OF ACTIVITY E1 PRESENTING THE POWERPOINT TO THE PANEL
ALLOCATED TIME FRAME Five Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser 3 panel

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


COST: PHP
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 0.00
POSSIBLE PROBLEMS AND SOLUTION PROBLEM: Panel Saw An Error On Our Study

SOLUTION: Solve The Error By Improving The Thesis

EXPECTED OUTCOME Ready For Final Paper

NAME OF ACTIVITY F1 FINAL PAPER


ALLOCATED TIME FRAME Three Days
PERSONNEL INVOLVED 1 Ce-Proj Adviser 1 Ce-Proj Prof

MATERIALS AND EQUIPMENT 1 pcs. Own Laptop COST: PHP 0.00


1 pcs. Book Bind COST: PHP 300.00
COST: PHP
TOTAL COST FOR ACTIVITY: PHP 300.00
POSSIBLE PROBLEMS AND SOLUTION N/A

N/A

EXPECTED OUTCOME Prepared For Passing


NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser
MATERIALS AND EQUIPMENT 1 pcs.
3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis


EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME

NAME OF ACTIVITY B.
ALLOCATED TIME FRAME
PERSONNEL INVOLVED 1 Ce-Proj Adviser

MATERIALS AND EQUIPMENT 1 pcs.


3 pcs. Relat

TOTAL COST
PROBLEM: The Information Is Too Difficult To Find
POSSIBLE PROBLEMS AND SOLUTION

SOLUTION: Try To Find Information On Internet And Read Past Thesis

EXPECTED OUTCOME
REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser
Own Laptop COST:
Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:
Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis
Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use

REASERCHING
Six Days
viser

Own Laptop COST:


Related Books (Library) COST:
COST:
TOTAL COST FOR ACTIVITY:

Thesis

Giving Information That We Can Use


COST: PHP 0.00
COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00
COST: PHP 0.00
COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00
COST: PHP 0.00
COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00
COST: PHP 0.00
COST: PHP 0.00
COST: PHP
PHP 0.00

COST: PHP 0.00


COST: PHP 0.00
COST: PHP
PHP 0.00