widening to four lane divided highway from Km 120+000 to Km 228+000 of NH-11 (Jaipur – Mahua
Section).
CHAPTER 13
The Concessionaire shall comply with the O&M requirements set out in Schedule –L
of CA during the entire concession period.
The Concessionaire has consistently been in default in maintaining the Project
Highway as per requirements of the CA and Maintenance programme and IC has
recommended recovery of damages by NHAI on account of non- fulfillment of
contractual obligation in respect of O&M.
Further strengthening of Concessionaire’s team is required, for proper execution of
operation & maintenance works in future. It would be appropriate to deploy a team of
well qualified and experienced staff minimum as mentioned in the Organizational
Structure proposed on dated 27th July 2011 during the meeting of the PD,PIU-Jaipur.
To enhance capacity building of the Concessionaire’s engineers in O&M, it would be
useful to provide opportunities to them to have regular and refresher on job trainings
on O&M of Highway Projects which would be helpful in updating their technical
know-how, administrative and management skills during implementation of the O&M
programme of the Project Highway.
Any change in design or specifications of work, if needed during execution, requires to
be appraised well in advance, requisite variation orders also prepared if required,
and got approved before executing the work (variation item).
Timely mobilization of all necessary resources including men and material; proper
planning of maintenance work, consistent review of work program showing recovery
plans of delayed maintenance of works if any, preparation of a separate work
program for maintenance of the works as per approved work program, is vital for
completion of the works in time.
Regular progress review meetings in O& M period will also be very effective to sort out
bottle necks which help the concessionaire to resolve them timely. Such meetings,
preferably, should be held, once a month at site level.
Continuous effort is required for effective implementation of O&M plan, from
Concessionaire side, throughout the O&M period. Proper attention is sought to
conduct all requisite quality control tests to ensure that the material (both local and
manufactured) used at site in works done fully comply with design, drawings and
technical specifications.
The road is designed for 20 years. However, in view of movement of heavily loaded
vehicles carrying 40-50 tons of sand, distresses on road surface have been noticed
in some stretches of the Project Highway very early. To sustain the road to a required
service level in Operation period, appropriate measures are required to be taken by
the Concessionaire to carry out the preventive maintenance and Periodic
6. Patrolling:-
The system of patrolling is incompetent and inefficient. No timely action is taken for
implementing the duties assigned to the patrolling team.