Status of Project Work for the Period: December 13,2019 – December 19,2019
Off‐Site Team
Off‐Site Team
Status of Project Work to Date, Including Progress Reported This Period: December 13,2019 – December 19,2019
Project: To-Be document of finance has submitted & is in review status.
Plans for Next Period / Week (As Per Baseline Project Plan)
1.
2.
3.
Other Notes and Concerns:
1.
2.
USF Team
Name Role / Position
Project Sponsor
Project Manager
Finance Key Business User
Purchasing Key Business User
Ora-Tech Team
Name Role / Position
Asad Nawaz Khan Project Director
Faisal Khan USF Project Account Manager
Munir Ahmed Project Manager
Yasir Hameed Senior Consultant
Indication Legend
Started on time
In‐Progress
Complete on time
Scheduled
Rescheduled
Delayed Start