Sunteți pe pagina 1din 3

Project Status Report ‐ 02

Status of Project Work for the Period: December 13,2019 – December 19,2019

Project Name: Enterprise Resource Planning (ERP)


Client: Universal Support Fund (USF)
Implementation
Prepared by: Ora-Tech Project Manager / USF Project Manager
Date: November 28, 2019
Ora-Tech Team USF Team

On‐Site Team On‐Site Team


Munir Ahmd Mansoor Ullah
Yasir Hameed Ahsan Mansoor
Meher Un Nisa All Team Leads
Usman Amjad

Off‐Site Team

Off‐Site Team

Status of Project Work to Date, Including Progress Reported This Period: December 13,2019 – December 19,2019
Project: To-Be document of finance has submitted & is in review status.

Task, Milestone(s) and Deliverables achieved so far:


Planned Revised Actual
Tasks, Milestone or Key Project
Status Completion Completion Completion
Deliverable
Date Date Date
TOBE Finance December
Complete Jan 03,2020
16,2019
TOBE Phase is started In‐Progress Jan 03,2020
(Project TOBE)
(Purchasing & Payroll)
Started on
Time

USF Oracle E-Business Suite Implementation Project Page 1 of 3


Special Problems or Issues to be Addressed:
Issue: Who Will Address: Associated Impact

Plans for Next Period / Week (As Per Baseline Project Plan)
1.
2.
3.
Other Notes and Concerns:
1.
2.

Status Report Forwarded to:

USF Team
Name Role / Position
Project Sponsor
Project Manager
Finance Key Business User
Purchasing Key Business User

Ora-Tech Team
Name Role / Position
Asad Nawaz Khan Project Director
Faisal Khan USF Project Account Manager
Munir Ahmed Project Manager
Yasir Hameed Senior Consultant

Complete Information Now


Name: Signature: Date:
Ahsan Mansoor/ Mansoor Ullah

USF Oracle E-Business Suite Implementation Project Page 2 of 3


Name: Signature: Date:
Munir Ahmed

Indication Legend
Started on time
In‐Progress
Complete on time
Scheduled
Rescheduled
Delayed Start
Delayed End

USF Oracle E-Business Suite Implementation Project Page 3 of 3