DECEMBER 3, 2019

6,000 psi

283 cu.m.
ROOF DECK SLAB
Location: GL.: 1-2, G-J

DECEMBER 5, 2019
4,000 psi

355 cu.m.
SLAB ON GRADE
Location: GL:9-12,A-C
DECEMBER 4, 2019
6,000 psi
12 cu.m.
First Lift Column & Second Lift Column
(2nd Flr. Suspnd. Slab)
Location: 1st Lift Column: A2, D1, E1 2nd Lift Column: B1, C1

DECEMBER 6, 2019
6,000 psi
312 cu.m.
SECOND FLOOR SUSPND. SLAB
Location: GL: 4-6, A-C
DECEMBER 7, 2019
6,000 psi

37 cu.m.
First Lift Column & Second Lift Column (2nd Flr. Suspnd. Slab),
First Lift Column (Ground Floor)
Location: 1st Lift Column: A2, A3, B3, B2, C2 2nd Lift Column: D2, E2 (2nd Floor)
, & 1st Lift Column: H9, G10, H10, J10, H11, J11, H12 (Ground Floor)

DECEMBER 9, 2019
6,000 psi

248 cu.m.
SECOND FLOOR SUSPND. SLAB
Location: GL: 4-6, C-G
DECEMBER 10, 2019
6,000 psi

22 cu.m.
First Lift Column & Second Lift Column (2nd Flr. Suspnd. Slab),
First Lift Column (Ground Floor)
Location: 1st Lift Column: A2, D1, E1 2nd Lift Column: B1, C1 (2nd Floor) , & 1st
Lift Column: J12 (Ground Floor)

DECEMBER 11, 2019


6,000 psi

233 cu.m.
ROOF DECK SLAB
Location: GL.: 1-2, E-G
DECEMBER 12, 2019
4,000 psi

713 cu.m.
SLAB ON GRADE
Location: GL: 9-12/E-J

DECEMBER 13, 2019


6,000 psi
10 cu.m.
First Lift Column & Second Lift Column
(2nd Flr. Suspnd. Slab)
Location: 1st Lift Column: E3, F3, 2nd Lift Column: G3,H3,J3
DECEMBER 14, 2019
6,000 psi

18 cu.m.
First Lift Column & Second Lift Column
(2nd Flr. Suspnd. Slab)
Location: 1st Lift Column: D3, F4, 2nd Lift Column: D2,C3,G4,H4,J4

DECEMBER 14, 2019


6,000 psi

286 cu.m.
SECOND FLOOR SUSPND. SLAB
Location: GL.: 4-6, F-J
AUGUST 26, 2019
6,000 psi

27 cu.m.
FIRST LIFT COLUMN & PEDESTAL
Location: 1st Lift Column : A/1,B/1,C/1,D/1,A/2,B/2,C/2,A/3 Pedestal :
F/1,G/1,H/1,J/1,J/2,H/2,G/2,F/2,E/2,F/3

AUGUST 24, 2019


1,500 psi
12.5 cu.m.
PILE CAP
Location: A/7, D/7, E/7, F/7, H/7, J/7

6,000 psi
12 cu.m.
PEDESTAL
Location: E/3, G/3, H/3, J/3, F/4, E/5, F/5, G/5, D/6, E/6, F/6, G/6
AUGUST 24, 2019
4,000 psi

54 cu.m.
PILE CAP
Location: G/4, J/4, J/5, H/5, G/5, F/5, E/5, D/5

AUGUST 25, 2019


4,000 psi

84 cu.m.
TOWER CRANE FOUNDATION 1
AUGUST 22, 2019
4,000 psi

42 cu.m.
PILE CAP
Location: E/2, F/2, G/2, E/3, F/3

AUGUST 23, 2019


4,000 psi

75 cu.m.
PILE CAP
Location: F/4, G/3, H/3, J/3, H/4, J/6, G/6 F/6, E/6, D/6
AUGUST 16, 2019
6,000 psi

10 cu.m.
PEDESTAL
Location: A/1, A/2, A/3,A/5, B/1, B/2, B/3, C/1, C/2, C/3, C/4, D/1, D/2, D/3, E/1

AUGUST 21, 2019


4,000 psi

30 cu.m.
PILE CAP
Location: F/1, G/1, H/1, J/1, J/2, H/2
AUGUST 13, 2019
4,000 psi

90 cu.m.
PILE CAP
Location: A1, A2, A3, A5, B1, B2, C1, C2, D1, D2

AUGUST 14, 2019


4,000 psi

92 cu.m.
PILE CAP
Location: A4, A6, B3, B4, B5, C3, C4, C5, C6, D3, E1, B6