COMPARATIVE STATEMENT

Laying of cc road at B C Colony kothwalguda(V) of shamshabad( m)


Name of the work
Sl.no Description of item As per sanctioned estimate As per Working estimate Excess less Rremarks

Unit Qty Rate Amount Qty Rate Amount


Excavation for roadway in soil using manual
means for carrying of cut earth to embankment
site with initial lift of 3 mts and lead upto 50 m
1 as per Technical Specification Clause 302.3 1 cum 76.50 232.05 17752 69.06 232.05 16025 1726
MORD

Supplying and filling of 2.36mm HBG Chips


with initial lead in layers not exceeding 15 cm
thick consolidatiing each deposited layer by
2 watering and rampping including cost and 1 cum 30.60 1143.14 34980 30.69 1143.14 35083 103
conveyance of water to work site and all
operational incidental ,labour charges hire
charges and T & O Complete for finished item
Construction of un-reinforced, dowel jointed at
expansion and construction joint only, plain
cement concrete pavement, thickness as per
design, over a prepared sub base, with 43
grade cement or any other type as per Clause
3 1501.2.2 M20 (Grade), coarse and fine 1 cum 57.37 6745.50 386989 57.55 6745.50 388204 1214
aggregates conforming to IS : 383, maximum
in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using
approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing
of 125 mictron
Supplying and thick
filling polythene film, wedges,
gravel in trenches , with
4 steel plates
initial lead inincluding
layers not levelling the formwork
exceeding 15 cm thick as 1 cum 18.54 299.40 5551 18.72 299.40 5605 54
per drawing), spreading
consolidatiing each depositedthe concrete
layer bywith
sholvels,
watering andrakes, compacted
rampping usingcost
including needle,
and
5 Add 12%
scareed VAT
conveyance of water to work site and allin
and plate vibrators and finished 53433.00 53433.00
6 Add 0.50 %operation
continuous
operational Q.C
incidental including provision
,labour charges hireof 2226.00 2226.00
7 Ls Amount
contraction
charges and forTAdjustment
and &expansion,
O Complete construction
for finishedjoints,
item
applying debonding strips, primer, sealant, 50000.00 . 500000.00
dowel bars, near approaches to bridge / culvert
and construction joints, admixtures as As per Sanctioned Estimate 500000.00
approved, curing of concrete slabs for 14-
As per Workdone 500000.00
days, curing compound (where specified) and
water finishing to lines and grade as per `
drawing and Technical Specification Clause
1501 MORD.
Assistant Exicutive Engineer Deputy Exicutive Engineer
PR MPP Shamshabad PRSD Rajendranagar
Rremarks

+
+
AGREEMENT SCHEDULE

Construction of UGD from Yasa Narsimha Reddy House to H.Agam Reddy House at Laxmareedyguda (V) of Shankarpally (M)
. Quantities given herein those upon which the lumpsum tender cost of the work is based but are subjected to alterations ommissions, deduxctions and additions
as approved in the condition of this contract to do not necessarily shown the actual quantities of work to be done. The unit rates not below are those covering the
payment of extras or deductions for ommission according to the conditions of the contract as set forth in the preliminary specification of the APDSS and
other conditions of specifications of this contract.
2) It is to be expressely understood that the measured work is to be taken (not with standing any customer of practice to the contrary ) accordingly to the actual
drawings where in place and finished according to the drawings of as may be ordered from time to time by the Executive Engineer and cost calculated by
measurement or weight and the respective prices, without any additional charges for and necessary or contingent works connected with rates are for
works in site and completed in every respect.
Sl. Probable Description of item to be executed Unit of calculation
No quantity both in figures & words
1 2 3 4
Earthwork in excavation for Pipe Line trench Cutting as per drawing and technical
107.93 specifications Clause 305.1 including setting out, construction of shoring and bracing, removal
1 of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and
Cum bottom and backfilling in trenches with excavated suitable material as per Technical 1 Cum
Specification 305 MORD / 304 MORTH including contractor profit (One cubic meter)

1 Rmt
129.00 Supply and delivery of 8 " Dia SWG SP-1 pipe conforming to ISI 651 - Including cost of pipes and
2 (One running
Rmt transportation charges loading and Unloading Charges etc Complete meter)

Lowering and laying in ready made trench true to alignment and gradient, jointing, and testing of
3
129.00 stone ware pipes including cost of jointing material such as cement mortar (1:1) proportion and 1 Rmt
Rmt hemp yarn but excluding cost and conveyance of pipe. (Reference to specifications BIS No. (One running
6530/72) meter)

Constructon of 0.90 M Circular Sewer Man hole of 0.90 mts x 0.55 m of 1.00 M depth with 2 nd
class bricks in cm 1:6 prop and corbelling too including cc bed ( 1: 4 : 8 ) prop using 40 mm
gauge HG Metal 0.10 mt thick and CC (1:2:4) Prop benching / chanelling,internal plastreng with
4 20 mm thick cm 1:4 and External Plasterng with 12mm thick CM (1:4) with fine rendering
including cost and fixing of CI steps and fixing FC/ CI cover and frame but excluding the cost of
cover and frame, including the cost and conveyance of all materials at site complete and curing
for 21 days complete all taxes seignarage charges as per specification etc complete.

11 1 No
nos 0.80 mt depth (one number only)

3 1 No
nos 0.90 mt depth (one number only)
Manufacture as per BIS:12592 (Part 1&2) Supply & Delivery of manhole covers and frames with ISI
5 14.00 marking anywhere in A.P., F.O.R. destination including, loading, un-loading & stacking at site but
excluding central excise duty, sales tax, octroi and other Govt levies etc., as applicable. I.S.I
1no.
Mark
nos one number only

Total items Five ( 5 ) only

Contractor signature
AGREEMENT SCHEDULE
Est_Cost Rs.2.00 lakh
Grant: MPLADS
eddy House at Laxmareedyguda (V) of Shankarpally (M)
ork is based but are subjected to alterations ommissions, deduxctions and additions
e actual quantities of work to be done. The unit rates not below are those covering the
f the contract as set forth in the preliminary specification of the APDSS and

with standing any customer of practice to the contrary ) accordingly to the actual
be ordered from time to time by the Executive Engineer and cost calculated by
arges for and necessary or contingent works connected with rates are for

Rates As per sanctioned estimated rates Amount


contractor both figures & words
5 6

197.47
(Rs.One Hundred Ninty Seven and paise Four
Seven only) 21313.00

Rs. 485.00
(Rs. Three Hundred Fourteen only) 62565.00

Rs. 189.13
(Rs. one hundred Eighty Nine and paise Thirteen
only) 24398.00

Rs.4897.09
(Rs. Four thousand Eight Hundred Ninty Seven
and paise Nine only) 53868.00
Rs.5395.19
(Rs. Five thousand Three Hundred Ninty Five
and paise Ninteen only) 16186.00
Rs. 1543.00 21602.00

Rs.One thousand Five Hunderd Forty Three only

Total 199932.00