Sunteți pe pagina 1din 10

SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.

00 31-Mar-18
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Foamed Asphalt Stabilization SATIP-Q-006-03 14-May-18 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
RECORD CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Contractor - "RH" of Documents and "H" for Material


Material Sampling, Testing & Review of Sampling and Testing.
Engineering Properties of Foamed SAIC-Q- S.ARAMCO - "RH" of Documents and "H" for Material
1.1
Stabilizing Agents and Subbase
SAIC-Q-1057
1057 RH/H RH/H Sampling and Testing on Mega Projects for the first
Materials two production days and "W" on the remaining days
and on other Projects.

RECEIVING
2.0
INSPECTION

2.1 Not Applicable

3.0 INSTALLATION

Stabilization Equipment Set-up SAIC-Q- S. ARAMCO - Witness the first 2 occurences, and
3.1
Inspection
SAIC-Q-1058
1058 W W once every 5 occurences thereafter.

Placement, Compaction and Quality SAIC-Q-


3.2
Control of Foamed Stabilized Materials
SAIC-Q-1059
1059 W S

SAIC-A-
3.3 Compaction Testing SAIC-A-1005
1005 I W

4.0 PRE-COMMISSIONING

4.1 N/A

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.00 31-Mar-18
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Foamed Asphalt Stabilization SATIP-Q-006-03 14-May-18 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
RECORD CNTRCTR
ARAMCO

Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.03.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.03.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use

S-ar putea să vă placă și