MRP Explosion
Week
Item Parameters 1 2 3 4 5 6 7 8
VH1-234 Gross requirements 34 45 48 48
On Hand= 85 Scheduled receipts
Lead Time= 1 week Projected available balance 51 51 51 6 6 158 158 110
Safety Stock= 0 Net requirements 42
Q= 200 Planned order receipts 200
Planned order releases 200
VH2-100 Gross requirements 104 155 140 145
On Hand= 358 Scheduled receipts
Lead Time= 1 week Projected available balance 254 254 254 99 99 359 359 214
Safety Stock= 0 Net requirements 41
Q= 400 Planned order receipts 400
Planned order releases 400
Socket Gross requirements 600
On Hand= 425 Scheduled receipts
Lead Time= 3 week Projected available balance 405 405 405 405 305 305 305 305
Safety Stock= 20 Net requirements 195
Q= 500 Planned order receipts 500
Planned order releases 500
Scenario III: Capacity Management
Caculation
Avoidable loss- 58
Effective capacity
hours per week