Sunteți pe pagina 1din 10

WHITE PAPER

Schedule Risk Analysis


Simplified1
by David T. Hulett, Ph. D.

Table of Contents Critical Path Method Scheduling On the one hand, the critical path method
- Some Important Reservations (CPM) of scheduling is traditional and well
Critical Path Method The critical path method (CPM) of scheduling accepted. It is essential for developing the
Scheduling - Some
a project is a key tool for project logic of the project work and for managing
Important Reservations.....1
management. A schedule “network” the day-to-day project activities.
Three Steps to a Successful represents the project strategy. Activities,
Schedule Risk Analysis, where the work is accomplished, are linked by On the other hand, the CPM schedule is only
Illustrated by Case 1...........2
relationships (e.g. finish-start, start-start, accurate if every activity is started “as soon
Summary of Schedule Risk finish-to-finish) showing how the work is as possible” and takes just as long as its
Assessment........................ 10 planned. Strings of linked predecessor and duration estimate indicates. Project managers
successor activities constitute “paths” understand that projects do not ever go
through the network. When two or more entirely according to plan, which is one reason
paths are to be done simultaneously, they are for frequent status reviews. Since real projects
described as parallel paths. do not work this way, CPM is just the
beginning of project schedule management.
Some of the most important points in the
project are where several parallel paths Project managers need to understand some
converge. At these merge or join points, the key reservations about the standard CPM, and
paths must all be completed before a how to use a schedule risk analysis to provide
Note 1 David Hulett is milestone is recorded for payment, an information crucial to a project’s success,
Principal of Hulett & Associates inspection can be done, sub-assemblies can before they embark on their project:
of Los Angeles, CA. He can be be integrated for testing or the project can be
reached at (310) 476-7699,
recorded as complete. • The project duration calculated by CPM is
at info@projectrisk.com and
on the web at
accurate only if everything goes
www.projectrisk.com. CPM computes the shortest project according to plan. This is rare in real
This article is reprinted from completion duration and or completion date projects.
the PM Network, July 1996, from the longest path through the network.
pp. 23-30 with permission of The “longest pole in the tent” is called the • In many cases the completion dates CPM
the Project Management
“critical path.” Any delay on the critical path produces are unrealistically optimistic and
Institute, 130 South State
Road, Upper Darby, PA. PMI is will delay the project. Conversely, CPM shows highly likely to be overrun, even if the
a worldwide organization of that paths that are not critical can be delayed schedule logic and duration estimates are
advancing the state-of-the-art or lengthened, if they have enough “float” or accurately implemented.
in project management. scheduling flexibility, without necessarily
(610) 734-3330
delaying the project.
FAX (610) 734-3266.

www.deltek.com info@deltek.com
• The CPM completion date is not even the Three Steps to a Successful
most likely project completion date, in Schedule Risk Analysis,
almost all cases. Illustrated by Case1
The three steps to a successful risk analysis
• The path identified as the “critical path” are described. They are: (1) create the CPM
using traditional CPM techniques may not schedule for the project, (2) estimate the
be the one that will be most likely to uncertainty in the activity durations, and (3)
delay the project and which may need perform a risk analysis of the schedule,
management attention. usually with a Monte Carlo simulation method
available in several software packages.
In a recent article2, Harvey Levine challenged
“the mathematically disinclined” to determine Step 1: CPM Schedule – the
the degree of schedule overrun risk without Foundation of a Risk Analysis
getting confounded by mathematical or CPM analysis of the project schedule is the
statistical terminology. To help achieve this key building block of a quantified risk
goal, three case studies are presented in this assessment. Case 1 presents a very simple
paper. Using simple schedules of two project and a typical schedule risk analysis. It
activities or four activities on two parallel illustrates how the CPM completion date can
paths, these case studies show both the easily be overrun. It shows how a risk analysis
pitfalls of relying on CPM and the benefits of a can illuminate the issues in CPM and point to
schedule risk analysis. their resolution. For the first step, a project
with two activities and a finish milestone is
These case studies show that it may not be shown in Figure 1.
feasible to complete even simple projects by Figure 1
their CPM-determined date, given risk Figure 1
characteristics that are similar to those often Case 1: Project Network with Single Path
Case 1: Project Network with Single Path
found in real, everyday projects. CPM does not
identify these overrun problems very well, or
at all. In fact, CPM shows that the project will A101 A102 F
finish on a certain date. If CPM does not work
Project Manger
Bus. Unit Mgr.

Accounting
Marketing

well in such simple projects, and those the


Partner
IT Staff

Client

GOLD PHARMACEUTICAL PROJECT


CEO
HR

Project Roadmap and Players’ Involvement

problems are multiplied many times for the Suppose the durations are set at 50 working
1. Gold Pharmaceuticals calls Marketing with an RFP for a laboratory
design project.
2. Marketing and Business Unit Manager make Go/No Go decision and
determine the PM.
3.
complex projects facing project managers
Business Unit Manager, PM, and Marketing determine teaming
arrangements. days for A101 and 80 working days for A102.
4. Marketing, PM, Business Unit Manager, and teaming partners prepare

5. every day, the benefits of conducting a risk


proposal and presentation.
After selection, Business Unit Manager and PM assign staff and flag
staffing needs.
Suppose, further, that this project is
6.
7.
analysis on every project become obvious.3
HR Manager recruits staff as appropriate.
Project begins. Ongoing producti
on and project management.
scheduled to start on June 10, 1996. CPM
shows that this simple project will take 130
8. Ongoing communication with projecteam,
t client, partners, and subs.
9. Ongoing support from IT, accounting, and HR staff.
10. Ongoing oversight by Business Unit Manager and CEO.

Note 2 Harvey A. Levine, “Risk Popular, accessible commercial software is


11. Client raises project issues about HVAC design.
12. Project team, client, Business Unit Manager, and eventually CEO
working days (50 + 80 = 130) and complete
Management for Dummies: used for these case studies to show that
participate in a threaded discussion of the issue and resolve it.
on December 11, 1996.
Managing Schedule, Cost and schedule risk analysis methods are available
Technical Risk and
to anyone. Graphical presentations of the There are several considerations in developing
Contingency,” PMNetwork,
Software Forum, October results illustrate the steps required to conduct a successful risk analysis network. For a risk
1995, p.p. 30- 32. a quantified risk assessment and the results analysis to be successful, the CPM network
without using mathematics or statistics. should be developed at a level of detail that
Note 3 An analytical shows the important project structure, i.e. the
treatment of this subject, with
parallel paths and key merge points where
more implications than are
included here, can be found in
the risk is often increased. There are three
David T. Hulett, “Project features to watch for in determining the
Schedule Risk Assessment,” correct level of a schedule:
Project Management Journal,
March 1995, pp. 21-31.

2 WHITE PAPER: Schedule Risk Analysis Simplified


• First, the network should not be of time needed to complete the work given
developed at too high a level of detail, for the planned resources. Experienced project
instance at a level where most of the managers know that the work might take
activities summarise important more or less time than the estimate they have
underlying detail. Summary activities are assumed for the CPM calculation. These times
often characterised by start-to-start or make up the low and high ranges for a risk
finish-to-finish relationships. analysis.

• Second, the schedule should show clearly Duration ranges for each activity are the low
the parallel paths that could cause the (optimistic) and high (pessimistic) durations
project to be late if not coordinated. Case that the work on the activity might take
2 below shows the merge bias that occurs under different possible extreme scenarios.
when parallel paths converge. High ranges, for instance, can be determined
by examining the various things that could go
• Third, the network should not be wrong such as technical problems, site
developed in such great detail that it conditions, supplier delays, and permitting
requires too much information, since that issues - - factors which are often called “risk
would be unworkable and overly drivers.”
burdensome.
Risk drivers are identified and explored in
When building the risk analysis network, the interviews with the managers or team leaders
temptation is to schedule only those paths of the project’s activities who are the most
assessed as the “longest poles in the tent.” knowledgeable people on risk in the work
This is a dangerous practice that should be under their management and control. They
avoided. It is best to show more paths rather are most familiar with the risk issues in each
than fewer, since the shorter poles might activity and can best assess their impact on
actually have more risk than the long poles the possible duration of each activity.
identified by CPM. Case 3, below, shows that a Experienced guidance is often needed to
shorter path with more risk can actually be develop the duration ranges.
the highest risk path, i.e. the path most likely
to actually delay the project. If shorter paths The risk interview starts with a description of
are not included in the network to begin with, what could go wrong with the work in an
their risk might not be explored at all. activity. It then turns to the likelihood of that
scenario and how long the activity might take
If there are scarce resources that make if everything goes wrong. This duration is the
scheduling some activities in parallel high-range duration for that activity. A
Note 4 A 1960’s government infeasible, they ought to be identified and serious and honest airing of the issues
manual on PERT included in the schedule risk analysis. If involved in doing an activity will soon uncover
recommended that the
constraints are included in the CPM network, possible, though perhaps unlikely, pessimistic
high-range pessimistic
estimate should include
however, these must be deleted in the risk scenarios.4
failure and making a fresh analysis. These points are discussed in more
start if the likelihood of such detail below. Conversely, exploring with the managers what
an event was at least 1%. could go right should yield an optimistic
See; US Department of Step 2: Determine the Activity scenario and the low estimate of duration for
Defense, “PERT
Fundamentals: POTC
Duration Ranges each activity. Sometimes, with aggressive or
Textbook,” Bolling AFB, PERT The activity durations that are used to “success-oriented” schedule estimation, the
Orientation and Training calculate the critical path are often thought of CPM duration for many activities are already
Center (date unknown), p. as the “best guess” or “most likely” amount the shortest possible durations conceivable.
3.28.

3 WHITE PAPER: Schedule Risk Analysis Simplified


Often the CPM duration is viewed as the most reveals important problems that had not been
likely duration for most of the activities in the appreciated or communicated fully before the
project. This may not be true, however. The gathering of the duration range data.
risk analyst should, with the project manager,
seek to describe the most likely scenario and Sometimes projects have many activities,
determine if the CPM duration, or some other perhaps thousands. How should the ranges be
duration, will accommodate it. developed for such a large project? In this
case, “risk banding” is often used. The project
The ranges of longer (Max Dur) and shorter manager organises the activities into groups
(Min Dur) activities for the two Case 1 with common risk characteristics. For each of
activities are shown in Figure 2, below. The these “risk types” the low and high duration
table in that figure shows that there is a ranges would be expressed in percentages,
greater risk of overrun than opportunity for e.g. minus 15%, plus 25%, from the CPM
underrun in these two activities.5 The barchart duration. With large networks there is little
shows the CPM completion date of December alternative but to use CPM durations as the
11, 1996. most likely in the activity distributions.

There may be problems in collecting data Once the ranges, often called “3-point
about project schedule risk. For instance, estimates,” are determined, the project
project managers may be reluctant to commit manager must adopt a probability distribution
their activity managers’ time to develop the shape for each risky activity. A probability
information needed for a risk analysis, since distribution takes the three possible durations
they are the very people who are most busy (low, most likely and high) and expresses the
managing the project itself. Alternatively, relative likelihood of alternative outcomes
some project managers avoid examining risk within that overall range. That is, there are
at all because it poses difficult issues, some possible durations which are more likely
highlights bad news, exposes embarrassing than others.
problems or raises issues that would have to
be disclosed to the owner or customer. Triangular distributions are often used in risk
analysis because they are easy to specify (just
Even if a project manager wants to explore needing three points and a straightedge) and
risk honestly, it is often challenging to develop to use in analysis. Also, the project managers
realistic ranges, particularly for unlikely but may not know enough to specify any other
possible extreme events. But, gathering distribution type, although other distribution
duration range data has the major benefit of shapes are often available in the software.
Note 5 Asymmetrical making everyone aware of the problems
distributions are quite facing the project. A risk analysis usually
common. The CPM durations
are often optimistic scenarios
that do not work out in
Figure 26
practice. Sometimes the CPM Figure 26
duration is the low or most Case 1:Case
Simple
1: Simple2-Activity Project
2-Activity Project
optimistic duration as well.

Qtr 2, 1996 Qtr 3, 1996 Qtr 4, 1996 Qtr 1, 1997 Qtr 2, 1997 Qtr 3, 1997
Note 6 Figure 2 shows a view
of the Case 2 network and risk ID Task Name Min Dur Duration Max Dur Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
ranges that were developed in 1 Total Project 0d 130c 0d
Microsoft Project v. 4.1 from
2 A101 40c 50c 100c
Microsoft Corporation and
Risk+ v. 1.5, a MS Project 3 A102 70c 80c 100c
addin, from Program
4 Finish 0d 0d 0d
Management Solutions, Inc. 12/11

4 WHITE PAPER: Schedule Risk Analysis Simplified


Suppose that the analyst in Case 1 chooses a simple • Is December 11 even the “most likely” duration of this
triangular distribution for each activity, using the data in simple project?
Figure 2. The distributions are shown in Figure 3. They make
it clear that both CPM durations are optimistic, and that the • How many days are needed for a contingency to reduce
A101 duration of 50 working days is quite optimistic.7 the overrun risk exposure to an acceptable level?

Figure
Figure 33 The method, usually used is called Monte Carlo simulation,
has several steps:
Case 1: Probability Distributions
Case 1: Probability Distributions
• Each iteration begins by selecting a duration for each
A ctivity A 101 A ctivity A 102 risky activity at random from its range and distribution
probability probability like those in Figure 3.

• The total project and key milestone completion dates for


that iteration are calculated using CPM for that
particular configuration of durations. Those are only
possible dates for completion of the project and its
milestones, and they may not be representative of all
40 50 100 70 80 100
Working days Working days possible solutions.

• To determine the entire pattern of possible completion


Note 7 One measure of how optimistic these durations are is a dates for the project and its important milestones, the
comparison of the CPM duration to the average that would occur if the risk analyst iterates the project many times. At the end
activities were to be done many times. The average durations that
of each iteration, the completion dates for the total
correspond to the given ranges and triangular distributions are
computed by (low + most likely + high) / 3. For A101, an average project and for any important milestone are collected
overrun is calculated as (40 + 50 + 100) / 3 = 190 / 3 = 63.3 working and stored. The programme also records which activities
days. An overrun from the CPM duration of 50 days is 13.3 working were on the critical path for that iteration.
days, almost 3 weeks.
• At the end of the entire simulation, project completion
Step 3: Simulate the Project Schedule and important milestone dates computed from all
Once the activities’ duration ranges and distributions have iterations are collected and arrayed in graphs and tables
been determined, the schedule risk analysis can determine showing the probability distribution, or relative
how risky the entire project schedule is. The most common frequency, of all possible dates.
method of determining schedule overrun risk is to simulate
the project by solving (or iterating) it hundreds or thousands Suppose that the risk analyst examining Case 1 determines
of times on the computer. that 2,500 iterations will be sufficient for the accuracy
needed.8 The result of that simulation is a cumulative
Q3 ‘05 Q4 ‘05 Q1 ‘06 Q2 ‘06 Q3 ‘06 Q4 ‘06 Q1 ‘07 Q2 ‘07 Q3 ‘07 Q4 ‘07
The simulation results for Case 1, for instance, will answer likelihood distribution that represents the likelihood of the
such important project management questions as: project completing on or before each possible date. This
distribution is shown in Figure 4 above:
• Is the completion date estimate of December 11
reasonable?

5 WHITE PAPER: Schedule Risk Analysis Simplified


Figure9 49
Figure 4
Probability Distribution of Total Project Completion
Proability Distribution of Total Project Completion
Case 1: Simple Two-Activity Project
Case 1: Simple Two-Activity Project
Date: 01/26/96 06:54:15 PM Completion Std Deviation: 14.7d
Number of Samples: 2500 95% Confidence Interval: 0.6d
Unique ID: 6 Each bar represents 4d.
Name: Total Project

300 1.0 Completion Probability Table


270 0.9 Prob Date Prob Date

Cumulative Probability
0.05 12/05/96 0.55 01/07/97
240 0.8
0.10 12/10/96 0.60 01/09/97
210 0.7 0.15 12/12/96 0.65 01/14/97

Sample Count
180 0.6 0.20 12/17/96 0.70 01/16/97
0.25 12/19/96 0.75 01/21/97
150 0.5
0.30 12/23/96 0.80 01/24/97
120 0.4 0.35 12/24/96 0.85 01/30/97
90 0.3 0.40 12/27/96 0.90 02/06/97
60 0.2
0.45 12/31/96 0.95 02/13/97
0.50 01/03/97 1.00 03/14/97
30 0.1
0 0
11/19/96 01/07/97 03/14/97

Completion Date
1-path Project Illustrating Path Risk

Figure 4 includes a likelihood distribution • Suppose a conservative schedule is


(bell-curve) and a cumulative distribution required, one that has an 80% likelihood
(Scurve) shown in both pictures and a table of success. The results show that January
for the total project completion date. From the 24 has such a success likelihood. Hence, a
Note 8 More iterations will chart we can see: 6- week contingency is needed to reduce
provide more accuracy and
the risk of overrun to an acceptable level
smoother output graphs. More
complex models will require • The CPM completion date of December 11 for this conservative company.
more iterations to produce is only 10% - 15% likely to be adequate
accuracy. If different scenarios for this simple project. Placing confidence CPM clearly establishes December 11 as the
are embedded in the model in completion by December 11 is very project end-date. Just as clearly, the risk
(e.g. 20% chance of failing a
likely to get the contractor and customer analysis establishes that December 11 is
test and starting over), more
iterations will be needed.
in trouble. highly optimistic. Any owner/customer or
Often iterations will take contractor that agrees to that date is in
computer time, especially with • A look at the bell-shaped distribution trouble now on this project. Without a risk
complex projects and resource reveals that the most likely completion analysis, the existence or degree of trouble is
leveling, so there is a practical date is close to December 24, not unknown.
side to how many iterations to
December 11. The common sense notion
use. Try a number of iterations
on the specific schedule, using that adding “most likely” durations along Monte Carlo is a well-established method to
different “seed values” to a critical path will result in the most likely represent risk. Several commercial scheduling
start the Monte Carlo, until the project completion date that is simply programmes have a schedule risk analysis
results do not change wrong, in most cases. module. For some others, third-party software
materially as the number is
companies may have provided such capability.
increased.
• The average completion date is January Not all network programmes have risk analysis
Note 9 Figure 4 shows the 7. If this simple project were done 100 packages, however. The risk analyst using a
simulation results in a table times, its average completion would be a network programme that lacks the risk package
that summarises the about a 3-week overrun of the CPM will have to load the schedule into a network
cumulative distribution shown duration, providing for the holidays. programme that does.
in the chart. The printout is
from Risk+ software.
Two issues common to scheduling should be
resolved before the simulation is begun.
These are the handling of constraint dates
and limited resource requirements.

6 WHITE PAPER: Schedule Risk Analysis Simplified


The first issue is the treatment of constraint dates such as Case 2: Project Schedule Risk with Parallel Paths --
“not later than” or “must finish on” dates. Constraints are the “Merge Bias”
often implemented in the CPM schedule to represent key The three steps of a schedule risk analysis can be used in
dates contained in a contract or some other requirement. more complicated cases than Case 1. For instance, most
Constraints are used to highlight key contract dates because projects have activities planned simultaneously along
these dates must be met or the project is in trouble. parallel paths. At the end of the project, and often at
important internal milestones, these paths converge.
Constraint dates have no place in a risk analysis, however.
One main goal of a risk analysis to determine whether the At path convergence (or merge) points, projects can be
important contract dates, those established in the network delayed if the probability distributions of the converging
with constraint dates, are in jeopardy. If constraint dates paths’ durations overlap because a delay on any one of the
were implemented in the simulation, each iteration would be paths will delay the work. Examples include; (a) several
forced to meet those dates. Simulation with constraints types of construction work that must be completed before
operating during each iteration cannot possibly investigate an inspection can be conducted, or (b) several components
the feasibility of meeting the dates because success is that must be finished before integration and testing can be
enforced. Constraints must be taken off the schedule before done.
doing a risk analysis because they invalidate a risk analysis.
Of course, some merge points have several paths converging,
The second issue is the treatment of limited resources. If and the opportunity for delay at such points is thus
several activities using the same resource are potentially magnified. Clearly, path merge points can never be good
scheduled at the same time, they may require more of that news for a risk analysis. The increase in project risk at merge
resource than is available. Resource leveling in CPM pushes points, called the “merge bias,” is the subject of Case 2.
one or another resource using activity out in time so that a
resource’s usage does not exceed its availability in any time In Case 2, a simple parallel path project is assumed. Suppose
period. B101 is exactly like A101 and B102 is exactly like A102 in
all respects; CPM durations and low and high ranges, as
Because each solution in a risk analysis must at least be illustrated in Figure 5.
feasible, it should not violate any resource limitations that
exist. Each iteration must be resource-leveled if some The CPM result for this schedule is exactly the same as Case 1;
resource(s) is (are) limited. The risk analysis software 130 working days to a completion date scheduled at
package should be able to level resources as it is iterating. December 11. Both Path A and Path B are identified as “critical
This increases run time substantially. paths”
by CPM.

Figure 5
Figure 5
Case 2: Project Network with Parallel Paths
Case 2: Project Network with Parallel Paths

Qtr 2, 1996 Qtr 3, 1996 Qtr 4, 1996 Qtr 1, 1997 Qtr 2, 1997 Qtr 3, 1997

ID Task Name Min Dur Duration Max Dur Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

1 Total Project 0d 130d 0d

2 A101 40d 50d 100d

3 A102 70d 80d 100d

4 B101 40d 50d 100d

5 B102 70d 80d 100d

6 Finish 0d 0d 0d
12/11

7 WHITE PAPER: Schedule Risk Analysis Simplified


Figure 6
Figure 6
Proability Distribution of Total Project Completion
Probability
Case 2:Distribution
Four Activitiesof
inTotal Project
Two Parallel Completion
Paths
Case 2: Four Activities in Two Parallel Paths
Date: 01/26/96 06:02:47 PM Completion Std Deviation: 12.8d
Number of Samples: 2500 95% Confidence Interval: 0.5d
Unique ID: 6 Each bar represents 3d.
Name: Total Project

220 1.0 Completion Probability Table


198 0.9 Prob Date Prob Date

Cumulative Probability
176
0.05 12/18/96 0.55 01/21/97
0.8
0.10 12/24/96 0.60 01/23/97
154 0.7 0.15 12/30/96 0.65 01/24/97

Sample Count
132 0.6 0.20 01/02/97 0.70 01/28/97
110 0.5
0.25 01/06/97 0.75 01/31/97
0.30 01/08/97 0.80 02/04/97
88 0.4 0.35 01/10/97 0.85 02/07/97
66 0.3 0.40 01/13/97 0.90 02/12/97
44 0.2 0.45 01/15/97 0.95 02/19/97
0.50 01/17/97 1.00 03/12/97
22 0.1
0 0
11/29/96 01/17/97 03/12/97

Completion Date
2-path Project Illustrating Merge Bias

A project with parallel paths like Case 2 is • The conservative company requiring an
almost always more likely to be overrun than 80% likelihood of success now requires a
the simple single-path schedule such as that in completion date of February 4, not
Case 1. The cause of this pessimistic result is January 24 as in Case 1.
the “merge bias” which has been known for
some 25 years.10 The CPM schedule did not reveal these
Note 10 MacCrimmon, K. R.
and Ryavec, C. A. “An problems at all. Even with parallel critical
Analytical Study of the PERT The distribution of possible completion dates paths, the CPM analysis forecasted the same
Assumptions,” in R. Archibald from a Monte Carlo simulation of Case 2, completion date of December 11 in both
and R. Villoria, Network-Based shown in Figure 6 below, reflects the impact cases. The risk analysis showed that the risk
Management Systems (PERT/
of the merge bias: of overrun and necessary schedule
CPM), New York, Wiley, 1967,
Appendix C. Also described in
contingency were materially higher in Case 2
Hulett, op. cit., pp. 24-26. • The CPM date, which is still December 11, over those in Case 1.
is now not even 5% likely to occur.
This paper has shown that two simple
• The most likely completion date is about projects, one with 2-activities and another
January 7, not December 24, 1996 as in with 4- activities on 2 parallel paths, can be in
Case 1. trouble. It follows that real projects, which are
infinitely more complex, are even more likely
• The average completion date is January to be infeasible because they have more
17, not January 7 as in Case 1. This parallel paths and merge points. A risk
project has an average or “expected” analysis identifies and quantifies the
overrun of 5 calendar weeks from the difficulties faced by the project manager.
CPM estimate.

8 WHITE PAPER: Schedule Risk Analysis Simplified


Case 3: Risk Management and the “Highest Risk But, is Path A the most likely to delay the project? Is it the
Path” “highest risk path?” A risk analysis is now required not only
Suppose the project manager who received these risk to estimate the possible durations of this project after risk
analysis results took steps to mitigate the risk forecasted in management but also to identify the highest risk path.
Case 2, above. Several steps might be taken.
As mentioned above, the simulation software identifies
• First, the project manager might reduce the risk in which activities are on the critical path for each iteration. At
activities A101 and A102, perhaps through different the end of the simulation, the percentage of the iterations in
strategies, e.g. buy rather than make a tricky component which the activities were critical indicates the relative
or utilize a different supplier thought to be more likelihood that delays in their completion will delay the
reliable. project, their relative criticality.

• Second, the project manager could shorten the duration In Case 3, path A may be the critical path using CPM
of activity B101 by 5 days, to 45 working days, perhaps durations, but that is not the end of the story. In the
by adding a second shift to part of the work. For Case 3, software display shown in Figure 7, relative criticality for
it is assumed that the risk ranges around both activities’ each activity is indicated by the numbers to the left of the
durations in Path B are the same as in Case 2, perhaps bars in the bar chart. These results indicate that Path B is the
reflecting geological conditions or the technological highest risk path, the one with the greatest likelihood to
challenges which remain. delay the project, with a 69% likelihood, even though its CPM
duration is 5 days shorter than Path A. The risk management
Suppose that the new risk ranges resulting from these steps steps taken on the CPM critical Path A succeeded; Path A is
are shown in Figure 7. forecasted to delay the project only 31% of the time. In this
way a risk analysis helps identify the highest risk path for
Experienced schedulers will recognise that shortening risk management.
activity B101 makes Path B a “near-critical” path which has
a CPM duration of 125 days and a float of 5 working days.
Path A is now the only “critical path” with a total CPM
duration of 130 working days. The completion date is still
scheduled for December 11.

Figure 7
Figure 7
Case 3: Assessing
Case Risk
3: Assessing Risk Management
Management

Qtr 2, 1996 Qtr 3, 1996 Qtr 4, 1996

ID Task Name Min Dur Duration Max Dur May Jun Jul Aug Sep Oct Nov Dec Jan

1 Total Project 0d 130d 0d

2 A101 45d 50d 60d 31

3 A102 75d 80d 90d 31

4 B101 35d 45d 95d 69

5 B102 70d 80d 100d 69

6 Finish 0d 0d 0d
12/11

9 WHITE PAPER: Schedule Risk Analysis Simplified


Figure 88
Figure
Proability Distribution of Total Project Completion
Probability Distribution of Total Project Completion
Case
Case 3:3:Effect
Effectof
ofRisk
Risk Management
Management
Contact
Deltek Date: 01/26/96 06:15:48 PM Completion Std Deviation: 12.0d
Number of Samples: 2500 95% Confidence Interval: 0.5d
Unique ID: 6 Each bar represents 3d.
Name: Total Project

www.deltek.com 360 1.0 Completion Probability Table


324 0.9 Prob Date Prob Date
info@deltek.com

Cumulative Probability
0.05 12/11/96 0.55 12/31/96
288 0.8
0.10 12/13/96 0.60 01/03/97
252 0.7 0.15 12/16/96 0.65 01/08/97

Sample Count
Deltek® is a leading 216 0.6 0.20
0.25
12/18/96
12/19/96
0.70
0.75
01/10/97
01/14/97
180 0.5
provider of enterprise 144 0.4
0.30
0.35
12/20/96
12/23/96
0.80
0.85
01/20/97
01/23/97
applications software 108 0.3 0.40 12/24/96 0.90 01/29/97
72 0.2
0.45 12/26/96 0.95 02/05/97
designed specifically for 36 0.1
0.50 12/30/96 1.00 03/03/97

project-focused 0
12/03/96 01/03/97 03/03/97
0

businesses. For more Completion Date


than two decades, our Risk Management and the Highest Risk Path

software applications
have enabled
organisations to Case 3 simulation results are presented in developing the three-point activity duration
automate mission-critical Figure 8, above: estimates to use in a schedule risk analysis.
business processes
around the engagement, Figure 8 shows that the risk management The simple examples shown above highlight
execution and delivery of actions have reduced the risk of the total the benefits of risk assessment and the
projects. More than project. The average completion date is now pitfalls of relying on a CPM analysis alone.
12,000 customers January 3, not January 17 as in Case 2 before Some of these benefits are: (1) finding out
worldwide rely on Deltek risk management. how likely the CPM completion date is, (2)
to measure business determining the contingency needed to
results, optimise Will the project complete “on time” after reduce the overrun risk to an acceptable level,
performance, streamline these risk management actions? The CPM (3) identifying the highest risk path for
operations and win new date of December 11 is still less than 5% project risk management, and (4) evaluating
business. likely and further risk management steps are the effect of risk management actions.
needed to reduce the risk to an acceptable
World Headquarters:
level. Those steps might most profitably be The risk analysis has the potential of
applied to Path B, the highest risk path, at providing key information for project
United States
13880 Dulles Corner Lane this time. Certainly, the project manager managers in advance so that risk mitigation
Herndon, VA 20171 should look closely at the progress in B101 plans can be developed and implemented
800.456.2009 and B102 for those are high-risk activities. now. The experience with risk analysis shows
also that developing the data and reviewing
International Sales
Headquarters: Summary of Schedule Risk the results enables the participants to
Canada
Assessment understand and to manage their project
110 Sheppard Ave. East, Suite 620 Risk assessment of a project requires three better.
Toronto, ON M2N 6Y8 steps; (1) create the CPM schedule, (2) gather
416.769.6565
risk information such as optimistic and There is risk in every project. Ignoring risk
United Kingdom pessimistic durations and probability doesn’t make it go away. A three-step risk
3 Hanover Square
distributions, and (3) simulate the network analysis should be conducted for every
London, W1S 1HD
+44 (0) 20 7518 5010 using a Monte Carlo approach. The greatest important project.
amount of effort and judgment goes into
Australia
65 Henley Beach Road,
Mile End, South Australia 5031
+61 8 8150 5500

10 © 2007 Deltek, Inc. All rights reserved. All referenced trademarks are the property of their respective owners.

S-ar putea să vă placă și