Sunteți pe pagina 1din 59

SLRB @ 2.

850
No. Diameter Spacing No. Of
Sl no. Description of RCC to be Laid Description of bar Of of bar
(M) bars
sides (MM)
BB- 12 dia 2-legged stirrups
1 2 12 150 37
at 150C/C
BB- Distribution 16 no.s, 16
2 M-20 grade cement concrete 2 16 - 16
dia
for BED BLOCKS and DIRT
WALLS of SLRB at KM 2.850 DW- 12 dia 2-legged stirrups
3 2 12 150 37
at 150 C/C
DW- Distribution 10 no.s, 20
4 2 20 - 10
dia

SLRB @ 4.775
BED BLOCK AND DIRT WALL
No. Diameter Spacing No. Of
Sl no. Description of RCC to be Laid Description of bar Of of bar (M) bars
sides (MM)
BB- 12 dia 2-legged stirrups
1 2 12 150 37
at 150C/C
BB- Distribution 8 no.s, 16
2 M-25 grade cement concrete 2 16 8 no.s 8
dia
for BED BLOCKS and DIRT DW- 12 dia 2-legged stirrups
3 WALLS of SLRB at KM 4.775 2 12 150 37
at 150 C/C
DW- Distribution 8 no.s, 16
4 2 16 8 no.s 8
dia

DECKSLAB
No. Diameter Spacing No. Of
Sl no. Description of RCC to be Laid Description of bar Of of bar (M) bars
sides (MM)
TOP MAT- MAIN - 12 dia @
1 1 12 0.3 32
300C/C
TOP MAT- Distribution- 12
2 M-25 grade cement concrete 1 12 0.3 18
dia @ 300C/C
for DECK-SLAB for SLRB at KM
4.775KM is in progress. BOTTOM MAT- MAIN - 12 dia
3 1 12 0.14 68
@ 140C/C
BOTTOM MAT- Distribution-
4 1 25 0.16 33
25 dia @ 160C/C

Kerb
No. Diameter Spacing No. Of
Sl no. Description of RCC to be Laid Description of bar Of of bar (M) bars
sides (MM)
1 2
2 M-25 grade cement concrete 2
for DECK-SLAB for SLRB at KM
3 4.775KM is in progress. 2
M-25 grade cement concrete
for DECK-SLAB for SLRB at KM
4.775KM is in progress.
4 2

Parapet
No. Diameter
of bar Spacing No. Of
Sl no. Description of RCC to be Laid Description of bar Of (M) bars
sides (MM)
1 2
2 M-25 grade cement concrete 2
for DECK-SLAB for SLRB at KM
3 4.775KM is in progress. 2
4 2
SLRB @ 2.850
No. Of Total Unit
No. Of welded cutting weight ( Weight Construction staf Q.C Staf
Remarks
overlaps joints length (KGS) AEE DEE EE AEE DEE EE
KGs)
(M)
2.3 0.889 151.308

5.1 1.58 257.856

2.38 0.889 156.571

5.1 2.469 251.838

SLRB @ 4.775
BLOCK AND DIRT WALL
Total
No. Of cutting Unit Weight Construction staf Q.C Staf
No. Of welded weight ( (KGS) Remarks
overlaps joints length AEE DEE EE AEE DEE EE
KGs)
(M)
2.3 0.889 151.308
5.1 1.58 128.928
2.38 0.889 156.571

5.1 1.58 128.928

DECKSLAB
Total
No. Of cutting Unit Weight Construction staf Q.C Staf
No. Of welded
overlaps joints length weight ( (KGS) Remarks
KGs) AEE DEE EE AEE DEE EE
(M)
5.17 0.889 147.076

9.67 0.889 154.739

5.17 0.889 312.537

9.97 3.858 1269.32

Kerb
Total
No. Of cutting Unit Weight Construction staf Q.C Staf
No. Of welded weight ( (KGS) Remarks
overlaps joints length AEE DEE EE AEE DEE EE
KGs)
(M)
0 0
0 0
0 0
0 0

Parapet
No. Of Total Unit
No. Of welded cutting weight ( Weight Construction staf Q.C Staf
Remarks
overlaps joints length (KGS) AEE DEE EE AEE DEE EE
KGs)
(M)
0 0
0 0
0 0
0 0
Bar bending schedule of SLRB @4.775
Bed block and Dirt wall
Sl No. No. Of sides Date Description of bar Shape of bar Spacing (M)
1 2 BB- 12 dia 2-legged stirrups at 150C/C 0.15
2 2 BB- Distribution 8 no.s, 16 dia —
3 2 DW- 12 dia 2-legged stirrups at 150 C/C 0.15
4 2 DW- Distribution 8 no.s, 16 dia —

SLAB
Sl No. No. Of sides Date Description of bar Shape of bar Spacing (M)
1 1 23.07.19 TOP MAT- MAIN - 12 dia @ 300C/C 0.3
2 1 23.07.19 TOP MAT- Distribution- 12 dia @ 300C/C 0.3
3 1 23.07.19 BOTTOM MAT- MAIN - 12 dia @ 140C/C 0.14
23.07.19 BOTTOM MAT- 160C/C
Distribution- 25 dia @
4 1 0.16

Kerb
Sl No. No. Of sides Date Description of bar Shape of bar Spacing (M)
1 2 23.07.19 TOP MAT- MAIN - 12 dia @ 300C/C 0.14
Parapet
Sl No. No. Of sides Date Description of bar Shape of bar Spacing (M)
1 2 23.07.19 TOP MAT- MAIN - 12 dia @ 300C/C 0.14
LRB @4.775
wall
Diameter No.s Length Unit weight Total weight(KGs) Laid
12 37 2.3 0.889 151.308 151.3078 34 35
16 8 5.1 1.58 128.928 128.928 8 8
12 37 2.38 0.889 156.571 156.5707 34 35
16 8 5.1 1.58 128.928 128.928 8 8
565.735 0.566 MT

Diameter No.s Length Unit weight Total weight(KGs)


12 32 5.17 0.889 147.076 32
12 18 9.67 0.889 154.739 18
12 68 5.17 0.889 312.537 68
25 33 9.97 3.858 1269.321 33
1883.673 1.884 MT

Diameter No.s Length Unit weight Total weight (KGs)


10 69 1.82 0.617 154.966 0.155 MT 69

Diameter No.s Length Unit weight Total weight (KGs)


10 69 0.617 0 0 MT
Total weight (KGs)
143.129
128.928
148.107
128.928
549.092 0.549

147.076
154.739
312.537
1269.321
1883.673 1.884

154.966 0.155
SLRB AT KM 2.850
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 Thursday, 28 March 2019 of structures as per drawings and technical
specifications, for R/S abutments and wings
of SLRB at KM2.850 is in progress.
Earth work excavation in soils for foundation
2 Friday, 29 March 2019 of structures as per drawings and technical
specifications, for L/S abutments and wings of
SLRB at KM2.850 is in progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
3 Saturday, 30 March 2019 specifications, for L/S and R/S abutments and
wings of SLRB at KM2.850 is completed.
Shuttering is done and area kept ready for
laying of concrete.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4 Tuesday, 2 April 2019 size aggregates for FOUNDATION FILLING of
R/S abutments and wings of SLRB at KM
2.850 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5 Wednesday, 3 April 2019 size aggregates for FOUNDATION FILLING of
L/S abutments and wings of SLRB at KM
2.850 is in progress.
Shuttering is in progress for SS/SS
6 Thursday, 4 April 2019 (abutments) concrete for both R/S and L/S of
SLRB at KM2.850.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
7 Monday, 8 April 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/S abutments
and wings of SLRB at KM 2.850 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
8 Tuesday, 9 April 2019 SUPER STRUCTURE works of R/S
abutments and wings and shuttering for
second lift of L/S abutment of SLRB at KM
2.850 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
9 Wednesday, 10 April 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 2.850 is
in completed.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
10 Wednesday, 19 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 2.850 is in
progress.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
11 Thursday, 20 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 2.850 is in
progress.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
12 Friday, 21 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 2.850 is in
progress.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
13 Saturday, 22 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 2.850 is
completed , shuttering is done and area kept
ready for laying of concrete.
Providing and laying insitu vibrated M-20
grade cement concrete using 20 mm down
15 Thursday, 27 June 2019 size aggregates for R/S BED BLOCKS and
DIRT WALLS of SLRB at KM 2.850 is
completed.
16 Friday, 28 June 2019 Curing is in progress
17 Saturday, 29 June 2019 Curing is in progress

SLRB AT KM 3.375
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 Saturday, 30 March 2019 of structures as per drawings and technical
specifications, for R/S abutments and wings
of SLRB at KM3.375 is in progress.
Earth work excavation in soils for foundation
2 Monday, 1 April 2019 of structures as per drawings and technical
specifications, for R/S abutments and wings
of SLRB at KM3.375 is in progress.
Earth work excavation in soils for foundation
3 Tuesday, 2 April 2019 of structures as per drawings and technical
specifications, for L/S abutments and wings of
SLRB at KM3.375 is in progress.
Earth work excavation in soils for foundation
4 Wednesday, 3 April 2019 of structures as per drawings and technical
specifications, for L/S abutments and wings of
SLRB at KM3.375 is in progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
5 Thursday, 4 April 2019 specifications, for L/S and R/S abutments and
wings of SLRB at KM3.375 is completed
shuttering is in progress and area kept ready
for laying of concrete.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
6 Monday, 8 April 2019 size aggregates for FOUNDATION FILLING of
R/S abutments and wings of SLRB at KM
3.375 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
7 Tuesday, 9 April 2019 size aggregates for FOUNDATION FILLING of
L/S abutments and wings of SLRB at KM
3.375 is in progress.
Shuttering is in progress for SS/SS
8 Saturday, 20 April 2019 (abutments) concrete for both R/S and L/S of
SLRB at KM3.375
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
9 Monday, 22 April 2019 SUPER STRUCTURE works of L/S & R/S
abutments and wings ( first lift)is completed
and shuttering for second lift of SLRB at KM
3.375 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
10 Tuesday, 23 April 2019 SUPER STRUCTURE works of L/S and R/S
abutments and wings ( second lift) of SLRB at
KM 3.375 is progress and shuttering is in
progress for third lift .
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
11 Wednesday, 24 April 2019 SUPER STRUCTURE works of L/S &R/S
abutments and wings(third lift) of SLRB at KM
3.375 and shuttering for R/S second lift is in
progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
12 Thursday, 25 April 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/ S R/S
abutments and wings of SLRB at KM 3.375 is
in progress
Shuttering is in progress for SS/SS
13 Friday, 26 April 2019 (abutments) concrete for both R/S and L/S of
SLRB at KM3.375
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
14 Saturday, 27 April 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 3.375 is
completed.
21 Monday, 29 April 2019 Curing is in progress
22 Tuesday, 30 April 2019 Curing is in progress
23 Wednesday, 1 May 2019 Curing is in progress

SLRB AT KM 4.675
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 Thursday, 25 April 2019 of structures as per drawings and technical
specifications, for R/S abutments and wings
of SLRB at KM4.675 is in progress.
Earth work excavation in soils for foundation
2 Friday, 26 April 2019 of structures as per drawings and technical
specifications, for L/S abutments and wings of
SLRB at KM4.675 is in progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
3 Saturday, 27 April 2019 specifications, for L/S and R/S abutments and
wings of SLRB at KM4.675 is completed,
shuttering is in progress and area kept ready
for laying of concrete.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5 Thursday, 2 May 2019 size aggregates for FOUNDATION FILLING of
L/S & R/S abutments and wings of SLRB at
KM 4.675 is in progress.
Shuttering is in progress for SS/SS
6 Saturday, 4 May 2019 (abutments) concrete for both R/S and L/S of
SLRB at KM4.675
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
6 Friday, 24 May 2019 SUPER STRUCTURE works of L/S & R/S
abutments and wings completed and
shuttering for L/S second lift of SLRB at KM
4.675 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
7 Saturday, 25 May 2019 SUPER STRUCTURE works of L/S & R/S
abutments and wings ( second lift) completed
and shuttering for L/S final lift of SLRB at KM
4.675 is in progress
8 Monday, 27 May 2019 Shuttering for SS/SS R/S final lift is in
progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
9 Tuesday, 28 May 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 4.675 is
in completed
16 Curing is in progress
17 Curing is in progress
18 Curing is in progress

SLRB AT KM 4.775
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 Thursday, 25 April 2019 of structures as per drawings and technical
specifications, for R/S abutments and wings
of SLRB at KM4.775 is in progress.
Earth work excavation in soils for foundation
2 Friday, 26 April 2019 of structures as per drawings and technical
specifications, for L/S abutments and wings of
SLRB at KM4.775 is in progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
3 Saturday, 27 April 2019 specifications, for L/S and R/S abutments and
wings of SLRB at KM4.775 is completed. and
area kept ready for laying of concrete.
Shuttering is in progress for FOUNDATION
Saturday, 25 May 2019 FILLING (abutments) concrete for both R/S
and L/S of SLRB at KM4.775
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4 Monday, 27 May 2019 size aggregates for FOUNDATION FILLING of
R/S abutments and wings of SLRB at KM
4.775 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5 Tuesday, 28 May 2019 size aggregates for FOUNDATION FILLING of
L/S abutments and wings of SLRB at KM
4.775 is in progress.
Shuttering is in progress for SS/SS
6 Tuesday, 18 June 2019 (abutments) concrete for both R/S and L/S of
SLRB at KM4.775
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
7 Wednesday, 19 June 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of R/S abutment
and wings completed of SLRB at KM 4.775 is
in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
8 Thursday, 20 June 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/S abutment
and wings of SLRB at KM 4.775 is in
progress.
9 Friday, 21 June 2019 Shuttering for SS/SS L/S & R/S final lift is in
progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
10 Saturday, 22 June 2019 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 4.775 is
in completed
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
11 Monday, 24 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 4.775 is in
progress.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
12 Tuesday, 25 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 4.775 is in
progress.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
13 Wednesday, 26 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 4.775 is in
progress.
Providing , fabricating and placing in position
reinforcement steel bars for BED BLOCKS
14 Thursday, 27 June 2019 and DIRTWALLS of both R/S and L/S
Abutments of SLRB at KM 4.775 is completed,
shutttering is done and area kept ready for
laying of concrete.
Providing and laying insitu vibrated M-25
grade cement concrete using 20 mm down
16 Monday, 1 July 2019 size aggregates for R/S BED BLOCKS and
DIRT WALLS of SLRB at KM 4.775 is
completed.
Providing , fabricating and placing in position
17 Tuesday, 2 July 2019 reinforcement steel bars for DECKSLAB,
KERBS and PARAPET WALL of SLRB at KM
4.775 is in progress.
Providing , fabricating and placing in position
18 Wednesday, 3 July 2019 reinforcement steel bars for DECKSLAB,
KERBS and PARAPET WALL of SLRB at KM
4.775 is in progress.
Providing , fabricating and placing in position
19 Thursday, 4 July 2019 reinforcement steel bars for DECKSLAB,
KERBS and PARAPET WALL of SLRB at KM
4.775 is in progress.
Providing , fabricating and placing in position
20 Friday, 5 July 2019 reinforcement steel bars for DECKSLAB,
KERBS and PARAPET WALL of SLRB at KM
4.775 is in progress.
Providing , fabricating and placing in position
reinforcement steel bars for DECKSLAB,
21 Saturday, 6 July 2019 KERBS and PARAPET WALL of SLRB at KM
4.775 is completed, shuttering is done and
area kept ready for laying of concrete.
Providing and laying insitu vibrated M-25
22 Wednesday, 24 July 2019 grade cement concrete using 20 mm down
size aggregates for DECK-SLAB for SLRB at
KM 4.775KM is in progress.
23 Thursday, 25 July 2019 Curing is in progress
24 Friday, 26 July 2019 Curing is in progress
25 Saturday, 27 July 2019 Curing is in progress
DROP at KM 4.800
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.800 is in
progress.
Earth work excavation in soils for foundation
2 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.800 is in
progress.
Earth work excavation in soils for foundation
3 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.800 is
completed.
Earth work excavation in soils for foundation
4 of structures as per drawings and technical
specifications, U/S of DROP at KM 4.800 is in
progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
5 specifications, U/S of DROP at KM 4.800 is
completed and area kept ready for laying of
concrete
Shuttering is in progress for D/S for
6 FOUNDATION FILLING ( BED, CISTERN and
CUTOFF WALL) of DROP at 4.800KM is in
progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
7 size aggregates for FOUNDATION FILLING
( BED, CISTERN and CUTOFF WALL) of D/S
of DROP at KM 4.800 is in progress.
8 Shuttering for D/S of DROP at Km 4.800 for
Headwall and retaining walls is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
9 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE ( wings, returns and
headwall) first lift of D/S of DROP at KM 4.800
is in progress.
10 Leanmix
Shuttering is in progress for U/S for
11 FOUNDATION FILLING of DROP at 4.800KM
is in progress.
Providing and laying insitu vibrated M-15
12 grade cement concrete using 40 mm down
size aggregates for FOUNDATION FILLING of
U/S of DROP at KM 4.800 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
13 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE second lift of D/S of
DROP at KM 4.800 is in progress.
14 Shuttering for U/S of DROP at Km 4.800 for
wing walls and return walls is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
15 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE first lift of U/S of DROP
at KM 4.800 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
16 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE ( second lift) of U/S of
DROP at KM 4.800 is in progress.
17 Shuttering
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
18 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE of D/S and U/S
( tapering section) of DROP at KM 4.800 is in
progress.
Providing and laying insitu vibrated M-20
19 grade cement concrete using 20 mm down
size aggregates for WEARINGCOAT U/S &
U/S of DROP at KM 4.800 is in progress.
20
DROP at KM 4.725
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.725 is in
progress.
Earth work excavation in soils for foundation
2 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.725 is in
progress.
Earth work excavation in soils for foundation
3 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.725 is
completed.
Earth work excavation in soils for foundation
4 of structures as per drawings and technical
specifications, U/S of DROP at KM 4.725 is in
progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
5 specifications, U/S of DROP at KM 4.725 is
completed and area kept ready for laying of
concrete
Shuttering is in progress for D/S for
6 FOUNDATION FILLING ( BED, CISTERN and
CUTOFF WALL) of DROP at 4.725KM is in
progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
7 size aggregates for FOUNDATION FILLING
( BED, CISTERN and CUTOFF WALL) of D/S
of DROP at KM 4.725 is in progress.
8 Shuttering for D/S of DROP at Km 4.725 for
Headwall and retaining walls is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
9 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE ( wings, returns and
headwall) first lift of D/S of DROP at KM 4.725
is in progress.
10 Leanmix
Shuttering is in progress for U/S for
11 FOUNDATION FILLING of DROP at 4.725KM
is in progress.
Providing and laying insitu vibrated M-15
12 grade cement concrete using 40 mm down
size aggregates for FOUNDATION FILLING of
U/S of DROP at KM 4.725 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
13 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE second lift of D/S of
DROP at KM 4.725 is in progress.
14 Shuttering for U/S of DROP at Km 4.725 for
wing walls and return walls is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
15 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE first lift of U/S of DROP
at KM 4.725 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
16 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE ( second lift) of U/S of
DROP at KM 4.725 is in progress.
17 Shuttering
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
18 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE of D/S and U/S
( tapering section) of DROP at KM 4.725 is in
progress.
Providing and laying insitu vibrated M-20
19 grade cement concrete using 20 mm down
size aggregates for WEARINGCOAT U/S &
U/S of DROP at KM 4.725 is in progress.
DROP at KM 4.750
Area passed by Construction staf
Slno. Date Description of work
DEE
Earth work excavation in soils for foundation
1 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.750 is in
progress.
Earth work excavation in soils for foundation
2 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.750 is in
progress.
Earth work excavation in soils for foundation
3 of structures as per drawings and technical
specifications, D/S of DROP at KM 4.750 is
completed.
Earth work excavation in soils for foundation
4 of structures as per drawings and technical
specifications, U/S of DROP at KM 4.750 is in
progress.
Earth work excavation in soils for foundation
of structures as per drawings and technical
5 specifications, U/S of DROP at KM 4.750 is
completed and area kept ready for laying of
concrete
Shuttering is in progress for D/S for
6 FOUNDATION FILLING ( BED, CISTERN and
CUTOFF WALL) of DROP at 4.750KM is in
progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
7 size aggregates for FOUNDATION FILLING
( BED, CISTERN and CUTOFF WALL) of D/S
of DROP at KM 4.750 is in progress.
8 Shuttering for D/S of DROP at Km 4.750 for
Headwall and retaining walls is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
9 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE ( wings, returns and
headwall) first lift of D/S of DROP at KM 4.750
is in progress.
10 Leanmix
Shuttering is in progress for U/S for
11 FOUNDATION FILLING of DROP at 4.750KM
is in progress.
Providing and laying insitu vibrated M-15
12 grade cement concrete using 40 mm down
size aggregates for FOUNDATION FILLING of
U/S of DROP at KM 4.750 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
13 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE second lift of D/S of
DROP at KM 4.750 is in progress.
14 Shuttering for U/S of DROP at Km 4.750 for
wing walls and return walls is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
15 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE first lift of U/S of DROP
at KM 4.750 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
16 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE ( second lift) of U/S of
DROP at KM 4.750 is in progress.
17 Shuttering
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
18 size aggregates for SUB STRUCTURE /
SUPER STRUCTURE of D/S and U/S
( tapering section) of DROP at KM 4.750 is in
progress.
Providing and laying insitu vibrated M-20
19 grade cement concrete using 20 mm down
size aggregates for WEARINGCOAT U/S &
U/S of DROP at KM 4.750 is in progress.
SLRB AT KM 2.850
passed by Construction staf Area passed by Construction staf REMARKS
DOR
EE AEE DEE EE

Monday, 1 April 2019 2

Friday, 5 April 2019 2

Monday, 29 April 2019 2


Monday, 24 June 2019 2

Friday, 28 June 2019 2

2
M 3.375 2
passed by Construction staf Area passed by Construction staf REMARKS
EE AEE DEE EE 2
Friday, 5 April 2019 2

Thursday, 11 April 2019 1


Monday, 29 April 2019 2

2
M 4.675 2
passed by Construction staf Area passed by Construction staf REMARKS
EE AEE DEE EE 2

Monday, 29 April 2019 2

Saturday, 4 May 2019 2


Wednesday, 29 May 2019 2

2
2
2
2
M 4.775 2
passed by Construction staf Area passed by Construction staf
REMARKS
EE AEE DEE EE 2

Monday, 29 April 2019 2

Wednesday, 29 May 2019 2


Monday, 24 June 2019 2

Friday, 28 June 2019 2

Tuesday, 2 July 2019 2


Monday, 22 July 2019 2

Thursday, 25 July 2019 2

M 4.800
passed by Construction staf Area passed by Construction staf
REMARKS
EE AEE DEE EE
M 4.725
passed by Construction staf Area passed by Construction staf
REMARKS
EE AEE DEE EE
M 4.750
passed by Construction staf Area passed by Construction staf
REMARKS
EE AEE DEE EE
CC qty CC per day No. Of tests

15.0085 3

30.017 15.0085 3

18 3

18 3

71 35 3
5.98 5.98 3
18.915 3

37.83 18.915 3

44 3

36 3

28 3

24 3
154.59 22.59 3

27.92 #REF! 3

28 3

12 3
50.64 10.64 3

17.3525 3

34.705 17.3525 3

16 3
16 3

46.49 14.49 3

5.88 5.88 3
32.58 32.58 3

72
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/2/2019 size aggregates for FOUNDATION FILLING of 15.0085 3
R/S abutments and wings of SLRB at KM
2.850 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/3/2019 size aggregates for FOUNDATION FILLING of 30.017 15.0085 3
L/S abutments and wings of SLRB at KM
2.850 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/8/2019 size aggregates for SUB STRUCTURE / 18 3
SUPER STRUCTURE works of L/S abutments
and wings of SLRB at KM 2.850 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/8/2019 size aggregates for FOUNDATION FILLING of 0 3
R/S abutments and wings of SLRB at KM
3.375 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
4/9/2019 SUPER STRUCTURE works of R/S 18 3
abutments and wings and shuttering for
second lift of L/S abutment of SLRB at KM
2.850 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/9/2019 size aggregates for FOUNDATION FILLING of 37.83 18 3
L/S abutments and wings of SLRB at KM
3.375 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/10/2019 size aggregates for SUB STRUCTURE / 71 35 3
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 2.850 is
in completed.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
4/22/2019 SUPER STRUCTURE works of L/S & R/S 44 3
abutments and wings ( first lift)is completed
and shuttering for second lift of SLRB at KM
3.375 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
4/23/2019 SUPER STRUCTURE works of L/S and R/S 36 3
abutments and wings ( second lift) of SLRB at
KM 3.375 is progress and shuttering is in
progress for third lift .
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
4/24/2019 SUPER STRUCTURE works of L/S &R/S 28 3
abutments and wings(third lift) of SLRB at KM
3.375 and shuttering for R/S second lift is in
progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/25/2019 size aggregates for SUB STRUCTURE / 24 3
SUPER STRUCTURE works of L/ S R/S
abutments and wings of SLRB at KM 3.375 is
in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
4/27/2019 size aggregates for SUB STRUCTURE / 154.59 22.59 3
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 3.375 is
completed.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5/2/2019 size aggregates for FOUNDATION FILLING of 27.92 #REF! 3
L/S abutments and wings of SLRB at KM
4.675 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
5/24/2019 SUPER STRUCTURE works of L/S & R/S 28 3
abutments and wings completed and
shuttering for L/S second lift of SLRB at KM
4.675 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
size aggregates for SUB STRUCTURE /
5/25/2019 SUPER STRUCTURE works of L/S & R/S 12 3
abutments and wings ( second lift) completed
and shuttering for L/S final lift of SLRB at KM
4.675 is in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5/27/2019 size aggregates for FOUNDATION FILLING of 25.32 3
R/S abutments and wings of SLRB at KM
4.775 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5/28/2019 size aggregates for SUB STRUCTURE / 50.64 13.32 3
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 4.675 is
in completed
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
5/28/2019 size aggregates for FOUNDATION FILLING of 34.705 13.32 3
L/S abutments and wings of SLRB at KM
4.775 is in progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
6/19/2019 size aggregates for SUB STRUCTURE / 16 3
SUPER STRUCTURE works of R/S abutment
and wings completed of SLRB at KM 4.775 is
in progress
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
6/20/2019 size aggregates for SUB STRUCTURE / 16 3
SUPER STRUCTURE works of L/S abutment
and wings of SLRB at KM 4.775 is in
progress.
Providing and laying insitu vibrated M-15
grade cement concrete using 40 mm down
6/22/2019 size aggregates for SUB STRUCTURE / 46.49 14.49 3
SUPER STRUCTURE works of L/S and R/S
abutments and wings of SLRB at KM 4.775 is
in completed
Providing and laying insitu vibrated M-20
grade cement concrete using 20 mm down
6/27/2019 size aggregates for R/S BED BLOCKS and 5.98 5.98 3
DIRT WALLS of SLRB at KM 2.850 is
completed.
Providing and laying insitu vibrated M-25
grade cement concrete using 20 mm down
7/1/2019 size aggregates for R/S BED BLOCKS and 5.88 5.88 3
DIRT WALLS of SLRB at KM 4.775 is
completed.
Providing and laying insitu vibrated M-25
7/24/2019 grade cement concrete using 20 mm down 32.58 32.58 3
size aggregates for DECK-SLAB for SLRB at
KM 4.775KM is in progress.
Cube strength register

Date of Testing
Sl no. Description of work Grade of concrete Date of casting
7 Days
1 FF @2.850 M15 - 40MSA Tuesday, April 02, 2019 Tuesday, April 09, 2019

2 FF @2.850 M15 - 40MSA Wednesday, April 03, 2019 Wednesday, April 10, 2019

3 Ss/ss abut@ 2.850 M15 - 40MSA Monday, April 08, 2019 Monday, April 15, 2019

4 FF @3.375 M15 - 40MSA Monday, April 08, 2019 Monday, April 15, 2019

5 FF @3.375 M15 - 40MSA Tuesday, April 09, 2019 Tuesday, April 16, 2019

6 Ss/ss abut@ 2.850 M15 - 40MSA Tuesday, April 09, 2019 Tuesday, April 16, 2019

7 Ss/ss abut@ 2.850 M15 - 40MSA Wednesday, April 10, 2019 Wednesday, April 17, 2019
8 Ss/ss abut@ 3.375 M15 - 40MSA Monday, April 22, 2019 Monday, April 29, 2019

9 Ss/ss abut@ 3.375 M15 - 40MSA Tuesday, April 23, 2019 Tuesday, April 30, 2019

10 Ss/ss abut@ 3.375 M15 - 40MSA Wednesday, April 24, 2019 Wednesday, May 01, 2019

11 Ss/ss abut@ 3.375 M15 - 40MSA Thursday, April 25, 2019 Thursday, May 02, 2019

12 Ss/ss abut@ 3.375 M15 - 40MSA Saturday, April 27, 2019 Saturday, May 04, 2019

13 FF @4.675 M15 - 40MSA Thursday, May 02, 2019 Thursday, May 09, 2019

14 Ss/ss abut@4.675 M15 - 40MSA Friday, May 24, 2019 Friday, May 31, 2019

15 Ss/ss abut@4.675 M15 - 40MSA Saturday, May 25, 2019 Saturday, June 01, 2019
16 FF @4.775 M15 - 40MSA Monday, May 27, 2019 Monday, June 03, 2019

17 FF @4.775 M15 - 40MSA Tuesday, May 28, 2019 Tuesday, June 04, 2019

18 Ss/ss abut@4.675 M15 - 40MSA Tuesday, May 28, 2019 Tuesday, June 04, 2019

19 Ss/ss abut@4.775 M15 - 40MSA Wednesday, June 19, 2019 Wednesday, June 26, 2019

20 Ss/ss abut@4.775 M15 - 40MSA Thursday, June 20, 2019 Thursday, June 27, 2019

21 Ss/ss abut@4.775 M15 - 40MSA Saturday, June 22, 2019 Saturday, June 29, 2019

22 BB&DW at 2.850 M20 - 20MSA Thursday, June 27, 2019 Thursday, July 04, 2019
23 BB&DW at 4.775 M25 - 20MSA Monday, July 01, 2019 Monday, July 08, 2019

24 Deck slab at 4.775 M25 - 20MSA Wednesday, July 24, 2019 Wednesday, July 31, 2019

25 M15 - 40MSA 1/6/1900

26 M15 - 40MSA 1/6/1900

27 M15 - 40MSA 1/6/1900

28 M15 - 40MSA 1/6/1900

29 M15 - 40MSA 1/6/1900

30 M15 - 40MSA 1/6/1900


31 M15 - 40MSA 1/6/1900

32 M15 - 40MSA 1/6/1900


Cube strength register
Compressive
Date of Testing Load in KN Strength (N/mm^2) Avg Compressive strength(N/mm^2)
28 Days 7 Days 28 Days 7 Days 28 Days
286 12.71
295 13.11 13.02
298 13.24
Tuesday, April 30, 2019 394 17.51
420 18.67 18.13
410 18.22
293 13.02
0 4.34
0
Wednesday, May 01, 2019 0
0 0
0
0
0 0
0
Monday, May 06, 2019 0
0 0
0
0
0 0
0
Monday, May 06, 2019 0
0 0
0
0
0 0
0
Tuesday, May 07, 2019 0
0 0
0
0
0 0
0
Tuesday, May 07, 2019 0
0 0
0
0
0 0
0
Wednesday, May 08, 2019 0
0 0
0
0
0 0
0
Monday, May 20, 2019 0
0 0
0
0
0 0
0
Tuesday, May 21, 2019 0
0 0
0
0
0 0
0
Wednesday, May 22, 2019 0
0 0
0
0
0 0
0
Thursday, May 23, 2019 0
0 0
0
0
0 0
0
Saturday, May 25, 2019 0
0 0
0
0
0 0
0
Thursday, May 30, 2019 0
0 0
0
0
0 0
0
Friday, June 21, 2019 0
0 0
0
0
0 0
0
Saturday, June 22, 2019 0
0 0
0
0
0
0
Monday, June 24, 2019 0
0
0
0
0
0
Tuesday, June 25, 2019 0
0
0
0
0
0
Tuesday, June 25, 2019 0
0
0
0
0
0
Wednesday, July 17, 2019 0
0
0
0
0
0
Thursday, July 18, 2019 0
0
0
0
0
0
Saturday, July 20, 2019 0
0
0
0
0
0
Thursday, July 25, 2019 0
0
0
0
0
0
Tuesday, July 30, 2019 0
0
0
0
0
0
Wednesday, August 21, 2019 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
0
0
0
1/27/1900 0
0
0
For 7 days D/s U/s For 28 days D/s U/s
M15 Loading 224 302 Loading 345 465
Strength (9.945-13.45) Strength (15.3-20.7)
For 7 days U/s For 7 days U/s D/s For 28 days U/s D/s
M15 Loading 302 M15 Loading 302 224 Loading 465 345
M20 M20
For 7 days U/s D/s For 28 days U/s D/s
11.7 13.455 9.945 18 20.7 15.3
24
Acceptance criteria for cubes
Acceptance
Sl.no. Grade of Greater of
concrete C or D
Fck+(3or4) Fck+(0.825*Sd)
M10 14 10
M15 19
M20 24
M25 29
M30 34
M35 39
M40 44
M45 49
M50 54
Grade Sd
M10 3.5
M15 3.5
M20 4
M25 4
M30 5
M35 5
M40 5
M45 5
M50 5
Sl no. Date and time Mix proportion W/C ratio Slump
Construction staf Q.C Staf
AEE/DEE/EE AEE/DEE/EE Remarks
CA (Kg)
Sl no. Item of Work Grade Sand (Kg) Cement SD (req)
(Kg)
40 20 10
1 FF 15 190
2 SS/SS 15 692 280 628 315 315 3
3 Pier, BB&DW 20 768 300 0 697 464 4
4 Deck Slab, BB&DW 25 666 380 0 646 430 4
Approach Slab, WC
5 30 625 420 0 728 481 5
on Deck Slab
6 WC on Deck Slab 35
For 2 CuM AJAX considering 1.9 CuM
SD Target Sand (KG) Coarse aggregate
(consider mean Cement
ed) strength (bags)
40 20 10
15 8 0 0 0 0
4 21.6 11 1314.8 1193.2 598.5 598.5
4 26.6 12 1459.2 0 1324.3 881.6
5 33.25 15 1265.4 0 1227.4 817
5 38.25 16 1187.5 0 1383.2 913.9
35 0 0 0 0 0
Density Loose Compact Avg.

Sand 1546 1669 1607.5


CA - 40 1427 1570 1498.5
CA - 20 1407 1532 1469.5
CA - 10 1371 1495 1433

S-ar putea să vă placă și