Sunteți pe pagina 1din 10

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO.

1, JANUARY/FEBRUARY 2018 895

Conversion of 230 kV Switchyard to Gas-Insulated


Substation in a Gas Plant
Merwyn D’Souza , Senior Member, IEEE, Saud Al-Shammari, and Mghwar Safwa, Member, IEEE

Abstract—Frequent failures and increased maintenance in a 30- operational and maintenance challenges of the 230 kV switch-
year old 230 kV air-insulated switchyard (AIS) of a large gas yard are a major concern in maintaining continuous production
plant caused the existing installation to be unreliable to provide in the gas plant. Any event that would result in a complete loss of
uninterrupted power supply to critical plant operations. The re-
placement parts from original equipment manufacturers became power would be environmentally disconcerting and financially
scarce and expensive. The maintenance activities in severe and impairing. The existing plant will undergo a major expansion,
extremely hot middle-east weather conditions were cumbersome necessitating the addition of four more 230 kV bays to the exist-
and time-consuming. A planned plant expansion with consider- ing switchyard to feed the new loads. The end user has analyzed
able incremental load to the facility provided an opportunity for the ongoing operational problems of the 230 kV system and has
a review of the complete electrical system. After a thorough re-
view, it was decided to convert the main outdoor AIS to an indoor determined that a new indoor 230 kV gas-insulated switchgear
gas-insulated switchgear (GIS) substation to support the existing (GIS) would eliminate the concerns and be able to supply the
and new facilities. However, a total loss of power to the continuous combined loads much more efficiently and reliably.
operation of this critical gas facility was unacceptable. The existing The existing switchyard is fed by radially connected, double
switchyard with an energized 230 kV open bus system had limited circuit, 230 kV overhead transmission lines (OHTL) from two
space to safely perform the demolition and construction activities
for the new GIS. Detailed analysis of the installation options, con- different sources. Each radial feeder is connected to a differ-
struction techniques, safety requirements, and logistical methods ent bus within the same sourcing substation. The main power
was performed to eliminate potential for any total loss of power. source is from the utility-owned power station that is connected
The construction activity involved interfacing with two separate to the national grid via 230 kV OHTLs. The alternative power
redundant power supply sources, with separate transmission line source is from a cogeneration plant. All four incoming 230 kV
protection systems and equipment. The parties involved worked
together in reaching an agreement on engineering, procurement, OHTLs terminate at the gantries within the 230 kV switchyard
installation, testing, and commissioning activities that would suc- of the gas plant. These gantries form the interface points be-
cessfully implement this transition without any loss of power to the tween the incoming OHTLs and the gas plant electrical system.
gas production facilities. No modifications are envisioned on the utility-owned 230 kV
Index Terms—230 kV, air-insulated switchyard (AIS), demoli- OHTLs. The project was tasked with determining the optimum
tion, gas-insulated switchgear (GIS), installation options, transi- method to connect the gantries to the new 230 kV GIS consid-
tion, total loss of power. ering the existing structures, foundations, and clearances based
on a detailed study and site survey. The OHTL control, protec-
I. BACKGROUND tion, and monitoring panels for all incoming lines are currently
HE EXISTING 230 kV air-insulated switchyard (AIS) lo- located in the main substation P1. All control, protection, and
T cated in a large gas plant in Saudi Arabia has been in
operation for more than 30 years. The existing equipment has
control cables to existing coupling capacitor voltage transform-
ers (CCVTs), disconnect switches (DSs), ground switches, and
been experiencing increased maintenance for several years due transformers are required to be reconnected to the new 230 kV
to equipment aging and lack of a robust system to withstand the GIS substation. The project is required to determine if these
harsh middle-east desert weather conditions. Moreover, replace- existing panels could be utilized or new ones are to be installed.
ment parts from original equipment manufacturers (OEMs) are The existing three 13.2 kV double-ended substations (P1, P2,
not easily available and supported raising safety concerns. These and P3) receive power from the 230 kV/13.2 kV step-down
transformers. The transformer 230 kV bushings are connected
Manuscript received June 23, 2016; accepted September 27, 2016. Date of to the 230 kV tubular bus system via DSs. These existing trans-
publication September 12, 2017; date of current version January 18, 2018. formers need to be fed from the new GIS substation. All related
Paper 2016-PCIC-0562, presented at the 2016 Petroleum and Chemical Industry
Conference, Philadelphia, PA, USA, Sep. 19–22, and approved for publication control, protection, and monitoring cables need to be rerouted
in the IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS by the Petroleum or new ones to be installed from the existing equipment to the
and Chemical Industry Committee of the IEEE Industry Applications Society. new GIS substation.
(Corresponding author: Merwyn D’Souza.)
M. D’Souza and M. Safwa are with WorleyParsons, Monrovia, CA 91016 The cogeneration power plant is connected to the national
USA (e-mail: Merwyn.D’Souza@WorleyParsons.com; mghwar.safwa@worley grid via the gas plant with all surplus cogeneration power
parsons.com). being exported. This paper will address the constructability,
S. Al-Shammari is with Aramco Services Company C/O Worley Parsons,
Monrovia, CA 91016 USA (e-mail: saud.shammari@aramcoservices.com). maintainability, and operability of revamping the existing elec-
Digital Object Identifier 10.1109/TIA.2017.2752143 trical system to maintain the gas plant operations at optimum

0093-9994 © 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications standards/publications/rights/index.html for more information.
896 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018

Fig. 3. Planned GIS substation.


Fig. 1. Existing 230 kV air-insulated switchyard.

plant and the utility. The ILS initiates load shedding in the gas
plant in case of a total loss of power from the utility supply.
The group-operated DSs that are utilized to isolate the SF6
outdoor CBs have been problematic due to malfunctioning
mechanisms. The outdoor tubular buses and their supporting
insulated bushings need frequent maintenance and are a safety
concern in the intense heat and dusty environmental conditions.

III. PLANNED GAS-INSULATED SWITCHGEAR


The planned 230 kV GIS substation shall consist of indoor-
type, double-bus, single-breaker, SF6 GIS. The conceptual con-
figuration for the proposed substation is shown in Fig. 3. The
230 kV interface gantries shall be connected to the GIS incomers
by underground cables or above grade gas-insulated bus (GIB).
Fig. 2. Existing 230 kV air-insulated switchyard. The GIS line up will contain two incoming circuits from cogen-
eration power plant, two incoming circuits from national grid
production levels throughout the demolishing, construction, utility, two bus coupling, and two sectionalizing CBs as part
testing, and commissioning activities. The major objective shall of the main bus arrangement. Feeder CBs will be connected
be to perform all activities in a safe and reliable manner with to the various loads as per project requirements. Each 230 kV
minimum disruption of power supply to the plant existing power incoming or outgoing circuit can be connected to either one of
distribution systems. the two buses in one section. Each incoming/outgoing circuit
bay will be comprised of bus sections, disconnect/grounding
switches, power CBs, current transformers, surge arresters, and
II. EXISTING AIR-INSULATED SWITCHYARD termination bushings.
The existing 230 kV AIS consists of outdoor SF6 circuit Protection, metering, and control systems consist of intelli-
breakers (CB), DSs, grounding switches in an inverted post- gent electronic devices (IEDs) that are integrated with the power
insulator configuration as shown in Figs. 1 and 2. The double system automation system (PSA) and perform protective relay
bus bar arrangement consists of rigid aluminum tubular buses functions such as breaker failure protection, low impedance bus
and is interconnected to the 230 kV outdoor equipment and differential protection, line differential protection, synchroniz-
incoming A-frame gantries by aluminum-clad steel-reinforced ing check relays, as well as integration with the supervisory
aluminum conductors. control & data acquisition (SCADA) system. As the IEDs are
The existing plant facility power consumption is an average interfaced through the PSA interface, there is a much greater
of 210 MW and a maximum of 238 MW. The cogeneration availability of automation, monitoring, and control in the new
power plant has three generation trains with a total capacity of GIS. A 125 Vdc system will be installed within the new GIS
475 MW. An islanding and load shedding system (ILS) located substation building to provide power to the GIS protection,
at substation P1 monitors the power flow from the cogeneration metering, and control systems. The physical location of this
D’SOUZA et al.: CONVERSION OF 230 KV SWITCHYARD TO GAS-INSULATED SUBSTATION IN A GAS PLANT 897

substation is to be optimized based on detailed site survey for D. Advantages and Disadvantages of GIS
space availability and constructability.
The GIS is suitable for a large range of voltages due to its
compact size and modular design that provides flexibility for
many different configurations. The GIS needs less space than
IV. AIR INSULATED VERSUS GAS INSULATED
the AIS (approx. 10% of AIS). Assembly and commissioning at
A brief discussion on AIS and GIS is essential in understand- site is quicker due factory pre-assembly and testing. Segregated
ing their application. The differences, advantages, and disadvan- and enclosed live parts make it a very reliable system (due to
tages of AIS and GIS are discussed in the following paragraphs. reduced disruption of the insulation system). The contact with
the grounded metal enclosure is safer for attending personnel.
GIS has lower maintenance frequency and costs due to totally
A. Air-Insulated Substation enclosed elements. It also has a much higher reliability than
AIS has all switchgear equipment, CBs, DSs, grounding AIS. It can be installed indoors or outdoors in densely popu-
switches, busbars, and other related equipment installed out- lated areas, in areas with heavy rainfall, sandstorms, or snow,
doors exposed to the atmosphere. Due to this condition, the AIS including underground and offshore locations. Environmental
infrastructure and components are always vulnerable to contin- factors such as high humidity, salinity, industrial pollution have
uous degradation in the harsh climate conditions. no major impact on the GIS. With proper maintenance, the op-
erational life of a GIS is estimated to be 40–50 years, compared
to 25–30 years for AIS.
B. Advantages and Disadvantages of AIS The choice between GIS and AIS depends on their pros and
The AIS is best suited for voltages below 230 kV. It requires a cons. Depending on their application, for many projects around
larger space for installation, commissioning, and maintenance. the world, GIS offers the obvious choice due to its technological
However, the equipment can be spaced liberally without any and economic advantages over AIS.
appreciable increase in cost. The cost of construction and in-
stallation is lower due to its outdoor location, easily sourced, V. DESIGN
and simpler equipment. It is also easier to extend in the future, A. Design Criteria
provided ample space is available. The AIS equipment is within
view, and therefore fault location and repair is easier. The end user requirements mandate an elevated building
The disadvantages include utilization of more space than GIS. to house the new 230 kV GIS equipment. The GIS shall be
Regular and more frequent maintenance is required compared built to utility agency’s requirements that contain International
to GIS, therefore resulting in higher maintenance costs. The AIS Electro-technical Commission’s (IEC) specifications. These in-
is vulnerable to faults due to outdoor pollution, saline environ- clude IEC 62271-1 [1], IEC 62271-100 [2], IEC 62271-102 [3],
ment, and other factors such as direct lightning strikes, heavy and IEC-62271-203 [5].The new GIS substation shall contain
winds, rains, and cyclones. Due to these effects, the AIS have all related auxiliary equipment to protect, control, and moni-
lower reliability than GIS. Exposed live parts make working tor the switchgear, incoming power supplies, OHTLs, feeders
around the equipment unsafe for attending personnel. It is nor- connected to downstream equipment at existing 13.2 kV sub-
mally not installed in densely populated areas and is vulnerable stations P1, P2, and P3; and new 13.8 kV substation P5. The
to human intrusion. new GIS will interface with the existing ILS located in existing
substation P1.
The 230 kV incoming gantries shall be the interface point for
C. Gas-Insulated Substation the OHTLs from the two power supply sources to the GIS. The
location of the GIS substation building P4 shall be based on the
The GIS has the high-voltage (HV) buses, CBs, switches,
option selected to connect the OHTLs to the GIS. All activities
current transformers, voltage transformers, and surge protec-
involved in the conversion from AIS to GIS shall be conducted
tors encapsulated within the metal enclosure containing sulfur
in a manner that will sustain the continuity of power supply to
hexafluoride (SF6 ) gas. GISs primarily use SF6 gas as the pri-
the existing plant to operate at full capacity.
mary insulating medium. SF6 is nontoxic, maintains atomic and
Repurposing and expanding the existing switchyard ground
molecular properties even at high voltages, and has high cool-
grid for the GIS required utilizing IEEE Std. 80 [7] and software
ing properties and superior arc quenching properties. It is about
that performed analysis on the ground grid utilizing the finite
five times as dense as air. SF6 is used in GIS at pressures from
element method. Recommendations were made to upgrade the
400 to 600 kPa absolute. The pressure is chosen so that the SF6
grid to maintain the step and touch potentials within acceptable
will not condense into a liquid state at the lowest temperature
safe limits under normal and fault conditions.
(with dew point at or below –35 ˚C) the equipment is subjected
to. The switchgear housings are made of nonmagnetic material
such as aluminum or stainless steel. Its multicomponent units B. Interface Requirements With 230 kV Power Supply Sources
make it very compact in size and highly reliable. The GIS has The OHTL protection, control, and monitoring panels for
a gas detection system that monitors the gas pressure in each the two power supply sources (cogeneration and utility) are lo-
individual compartment. cated in existing substation P1. These panels are connected to
898 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018

system has been upgraded to fiber-optic ground-wire (OPGW).


An additional backup line protection is also provided with
time phase over-current, ground fault, UV/OV, and frequency
relay protection. The protection philosophy limits the use of
automatic reclosing and line restoration in line fault scenarios,
locking out the line until there can be a physical verification
of the line’s integrity. It does not discriminate between single-
or three-phase faults (i.e., no single pole tripping). Status and
alarm signals are provided to the central power monitoring
system through a remote terminal unit.
The 230 kV OHTL protection scheme was evaluated and
recommendations were made to procure new protection pan-
els and update their existing device settings to meet new
microprocessor-based relay requirements based on IEC 61850
[4]. The new protection scheme will be capable of communicat-
ing with the PSA and other equipment connected to the system.
The new panels and protective relaying devices were selected to
meet the requirements and agreed upon with the utility agency.
The new multifunction digital line differential relays shall pro-
vide a simple built-in interface to fiber optic communications
based on IEC 61850 [4]. In addition to line differential pro-
Fig. 4. 230 kV line differential protection. tection, they will include additional functions such as phase
and ground distance elements, directional and nondirectional
existing CCVTs, current transformers (CTs), and potential trans- overcurrent elements, synch check, voltage elements, frequency
formers (PTs), interlocking and signaling contacts located in the elements, and general purpose logic. Two sets of digital line dif-
AIS equipment. They also control the outdoor SF6 breakers and ferential relays must be used, each with dedicated sets of CTs
their related DSs. These panels contain redundant multifunc- and separate optical fibers for communication. Relays shall be
tion protection relays for each circuit and must be in operation reliability proven and be from two different manufacturers.
while the OHTLs are energized to supply power to the gas plant. The protection scheme for the feeders from the AIS to the
The cables connecting the various AIS devices to these control existing substations P1, P2, and P3 was at a short distance (less
panels are installed underground within the switchyard area. than 200 ft.) and only utilized overcurrent relays. However, the
Relocating the existing panels and reutilizing them in the new distance between the GIS and substations P1, P2, P3, and P5 is
GIS substation was evaluated for constructability. The reloca- not insignificant, and after evaluating potential fault scenarios,
tion effort was found to be too complicated and risky, rendering the recommendation was made to utilize line differential pro-
the existing electrical system susceptible to shut down. Recom- tection for the feeders. In addition, a communication interface
mendations were made to procure and install new control panels will be established between the GIS and the feeder substations
in the new substation P4. to coordinate relay protection.
The planned GIS will contain the same functional elements
as the AIS, but will be enclosed in a compartment, making D. 230 kV Tie-In to GIS
the interface with different signals more localized. The power
supply incomers will be connected to the GIS. The incoming A study was conducted to evaluate the best option to connect
power monitoring will be done at the GIS, but needs to be the incoming 230 kV OHTL power sources to the GIS via the
interfaced with the ILS located in existing substation P1. existing gantries. The options were as follows:
1) 230 kV GIB;
2) cross linked polyethylene (XLPE) insulated cables;
C. 230 kV Transmission Line Protection Requirements
3) hybrid of GIB (for incoming lines) and XLPE cables (for
The cogeneration OHTLs are protected by dual primary outgoing feeders).
microprocessor-based type line differential relays as shown in The GIB requires above grade structural steel framework with
Fig. 4. The communication channels between the relays on the a concrete foundation to route the 8-in diameter buses per phase.
sending and receiving sides are achieved via fiber optic cables Installation of six circuits with three-phases per circuit is very
(OPGW) and set of interface converters. The utility-owned cumbersome and unsafe in an energized switchyard. The coor-
OHTLs are protected by dual primary electronic type impedance dination between demolition of existing AIS and construction of
line distance relays (Mho) and set of interface convertors. The the new GIB would not be feasible without prolonged shutdown
communication channel between the distance relays on both of the 230 kV switchyard.
the sending and receiving ends of the lines was achieved via Installation of 230 kV underground cables was carefully an-
line trap and pilot wires when they were initially installed. alyzed taking into consideration the required minimum sep-
However, since then the line trap-pilot wire communication aration between phases and between circuits. Assessment in-
D’SOUZA et al.: CONVERSION OF 230 KV SWITCHYARD TO GAS-INSULATED SUBSTATION IN A GAS PLANT 899

cluded the maximum current carrying capacities of individual 4) All personnel risk and safety factors related to working
circuits under contingency conditions, including the ability of within an energized 230 kV switchyard were evaluated
one 230 kV utility circuit to carry the plant load (that includes based on ANSI/IEEE C2-2012, National Electrical Safety
existing, planned, and future loads). Thermal capacity calcula- Code (NESC) [6], and recommendations made to be incor-
tions for directly buried XLPE cables were performed to select porated into the project constructability and safety plans.
adequate conductor size for safely transmitting the maximum Substation modifications and new expansion buildings have
power to existing and future demand load that the plant is ex- been limited to areas within the security fence lines and do not
pected to consume. present any appreciable security risk.
A comparison of these two options included equipment costs,
lead time, constructability, and reliability. The lead time for VII. PATH TO EXECUTION
cables is about half the lead time for GIB. The installation
time is about the same. However, the AIS tubular structures A. Project Requirements
in close proximity need shutdown and demolition to facilitate The project requirements include the design, materials, fabri-
installation of GIB structures. The GIB needs manufacturer’s cation, inspection, testing, commissioning, and documentation
supervision during installation and commissioning. The GIB based on end user requirements. Compliance to end user spec-
foot print will require a significant portion of the switchyard ification requires all electrical equipment to be installed as per
plot and will limit future expansion. The XLPE cables have NEC (NFPA 70) [12]. The reinforcement bars in GIS substa-
the lowest cost, shorter lead time, and an equivalent overall tion foundation shall be connected to the grounding grid at two
reliability and maintainability when compared with GIB. The locations to act as additional ground rods. To avoid damage to
XLPE cables have the lowest risk to project time line. The reinforced concrete foundation, the actual current in steel bars
XLPE cables have a clear advantage based on constructability must be less than the value of short time current loading ca-
and costs. Based on the results of the study, the end user decided pability ICE of the concrete enclosed electrode, calculated as
to proceed with the underground XLPE power cable option to per IEEE Std. 80 [8], and clause 14.6. Safety measures as per
connect the 230 kV OHTLs and the load feeders to the GIS. IEEE Std. 80 [8] shall be taken to limit the undesirable effects
caused by circulating currents and transient grid potential rise.
Insulation coordination study of the GIS shall be performed to
ensure adequacy of protective margin considering power fre-
VI. POTENTIAL RISKS AND MITIGATION quency over voltages, switching over voltages, lightning over
The 230 kV AIS conversion to GIS is a complex undertaking voltages, and very fast transients.
involving interface with many entities. The most significant risks The cable installation shall be a combination of direct-buried
include the following. and concrete encased duct bank in a single layer arrangement
1) Interference of underground cabling with existing as per end user standard details. All cable risers shall be ad-
underground utilities: The construction drawings shall be equately supported. The GIS incoming 230 kV cables shall
followed to ensure that specified safety clearances and terminate outdoors at the incoming gantries, and indoors at the
separation between circuits are maintained. Any modifi- GIS through elevated building floor. The cable risers shall be
cations to existing utilities shall be coordinated and carried adequately protected by steel structural supports.
out in a timely manner. All 230 kV GIS cable terminations shall be done under manu-
2) Coordination of demolition, installation, and transition facturer’s supervision utilizing personnel certified in accordance
activities for uninterrupted plant operation: The plant with manufacturer’s procedures. The 230 kV cable termination
operations need to perform the necessary configuration installation and testing shall follow the guidelines in IEEE 1300
of existing electrical equipment to isolate the electrical [11] and IEEE 48 [13], respectively.
lines and equipment during demolition and tie-in activi-
ties. This will require a comprehensive list of motors and B. GIS Testing
loads that need to remain energized during the transition
The end user, their engineer, the OEM, and the third party
process, considering operation from a single-ended bus
inspector shall witness the specified tests of the GIS at the man-
in all existing substations. A detailed procedure must be
ufacturer’s facilities. The factory testing confirms functionality,
prepared, agreed upon, and approved to implement these
operability, and reliability of the design. It also establishes the
activities.
baseline data and that the switchgear is suitable for the speci-
3) Modifications to existing 230 kV incoming A-frame
fied application. Routine tests shall be as prescribed in relevant
gantries to terminate the new underground cables need
standards and shall include partial discharge tests on all PTs, de-
removal of existing CCVTs and replacement of surge ar-
termination of knee point voltage (VK ), and excitation limiting
resters. The cable terminators will need their own struc-
secondary voltage (UAL ) on CTs.
ture with new foundations. The 230 kV cable termination
is a specialized activity that must be carefully planned
C. Cable Testing
and coordinated with the cable terminator manufacturers.
Testing and inspection of this interface involves multiple The field testing of HV power cable along with all acces-
entities and may add significant time to each activity. sories ensures capability to meet design requirements, detect
900 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018

damages during shipping and installationand defects or er- tions of the 230 kV switchyard equipment energized in order
rors in workmanship in splices and terminations. Since the to maintain plant operations. Preventative safety measures must
installation will be directly buried, cable tests shall be performed be followed during construction works to avoid any loss of life,
with a minimum 150 mm backfill cover over the cables. The test property, and gas production.
site shall have proper protective barriers and warning signs as The 230 kV OHTL connection to the GIS shall follow the
per company safety procedures. Cables testing shall include con- following sequence:
ductor continuity and phasing tests with minimum of 1000 Vdc; 1) utility line-A;
insulation tests prior to and after performing the HV tests; cable 2) utility line-B and cogen line-2;
profile test by radar prior to HV test; HV ac tests at 20–300 Hz 3) cogen line-1.
frequency with pure sine-wave shape voltage with test voltages Prior to commencing any work, the following steps shall be
selected as per IEC 60840 [14]; cable jacket test to confirm in- taken to ensure complete understanding of the construction work
tegrity of outer jacket; cable impedance measurement for relay process and execution methods.
setting determination; and conductor and shield resistance tests.
A. Preparatory Activities and Safety Planning
D. Site Acceptance
1) Approved work permit shall be obtained as per end user
The GIS equipment shall be installed, all interconnections be-
procedures.
tween various interfaces completed and inspected prior to final
2) All detailed drawings, documents, and vendor data per-
functional check out. Site acceptance is required to establish that
taining to 230 kV switchyard/GIS shall be final and is-
the electrical equipment is safe, free of electrical shock and fire
sued for construction.
hazard, and suitable for the purpose for which it is intended to
3) All new equipment and materials required for installa-
be used. The high voltage ac (HVac) system shall be tested and
tion shall be readily available at the site complete with
operational prior to performing any testing on the GIS and pro-
installation, testing, and operating procedures.
tective relay panels. All visual, mechanical, and electrical tests
4) All test forms and procedures shall be available prior to
shall be performed as per end user’s specifications. The GIS test-
the scheduled activities.
ing shall be performed as per IEC 62271-203 [5]. All functional
5) Existing conditions at the 230 kV switchyard and 13.2 kV
checks for GIS operation; alarm, interlocking, indication from
substations P1, P2, and P3 shall be verified prior to ini-
GIS to local, and remote control panels shall be performed.
tiation of any work.
The utility requires a confirmation letter from the end user
6) Construction of new substations P4 and P5 shall be me-
that all tests required as per their construction standards have
chanically complete and ready for energization.
been completed and documented. All deficiencies found shall
7) The existing switchyard grounding grid shall remain in
be documented and categorized in the deficiency register. All
place and shall be extended to cover the substations P4
deficiencies shall be corrected prior to energization. A joint
and P5. All temporary grounding systems shall meet
final inspection shall be carried out to confirm compliance with
IEEE Std. 1246-2011 [10].
interface requirements as per the memorandum of understanding
8) Installation of new control, metering, protective relay
between the end user and utility. After successfully meeting
panels, and communication interfacing devices related
the utility and end user requirements, the installation shall be
to 230 kV OHTLs shall be mechanically complete and
signed off by the inspection group and Readiness of Energization
ready for commissioning and start-up.
Report approved for energization.
9) 230 kV cable feeders and the intertrip control wires at
both sides of new substations P4 and P5 shall be installed,
VIII. TRANSITION PLAN
tested, and terminated.
The conversion from existing AIS to new GIS involves careful 10) All protection, control, metering, signal, load shedding,
planning of demolition, construction, testing, and re-energizing and communication cables within GIS substation P4;
activities. This section addresses the various issues involved and between GIS and existing 13.2 kV and new 13.8 kV
with the coordination of demolishing the existing electrical substations shall be installed, tested, and ready for
equipment with its associated structures and the installation termination.
of new equipment, structures, supports, various cable trenches, 11) Testing and precommissioning of all equipment and pro-
and ducts in a safe manner. tective devices within substations P4 and P5 shall be
Failure to plan and to obtain prior approvals or agreements carried out and accepted by the end user.
with the involved parties will cause major delays in the seam- 12) Cable trenches shall be prepared and ready for installa-
less transfer of power supply from the AIS to GIS. Dismantling tion of 230 kV XLPE cables and associated protection
or demolishing of existing structures/equipment in the 230 kV and communication cables from GIS building to utility
switchyard shall be performed concurrently with the installation lines A and B, and cogeneration lines 1 and 2.
of new 230 kV XLPE cables and cable terminators (including 13) The new 230 kV cables and associated communication
its associated steel structures). The installation contractor shall cables related to OHTL protection and 230 kV cable
submit a risk assessment report prior to performing any work feeders from GIS to existing substations P1, P2, and P3
within the switchyard. All work will be performed with por- shall be partially installed and coiled at a safe distance
D’SOUZA et al.: CONVERSION OF 230 KV SWITCHYARD TO GAS-INSULATED SUBSTATION IN A GAS PLANT 901

4) Remove CCVTs pertaining to phases A, B, and C of


utility line-A.
5) Install foundations, steel structures, and 230 kV XLPE
cable terminators at utility line-A gantry.
6) Dismantle 230 kV horizontal tubular-bus between utility
line-A gantry and D706.
7) Remove CB A702 and DS D706, D707, and D724.
8) Remove/demolish all related control wires, conduits,
junction boxes, steel structures, concrete foundations,
and communication interfacing devices.
9) Perform all necessary cable testing before connecting to
utility circuits.
10) Connect 230 kV cables to utility phases A, B, and
C of line-A gantry through cable terminators and bus
drops. Also, connect pilot wires from utility gantry
to line protection equipment in GIS as shown on
drawings.
11) Ensure structural steel frame of all new structures and
equipment metal frame are connected to the substation
Fig. 5. Utility line-A and cogen line-2 de-energized. ground grid.
12) Ensure all incoming and outgoing feeder breakers on
near the existing interface gantry structures as shown on 230 kV GIS are de-energized and LOTO has been
construction drawings. achieved. The bus-sectionalizer and bus-coupler break-
14) All dismantled materials shall be stored at a clean ers shall remain open.
and safe location and delivered to end user’s ware- 13) Connect 230 kV cables to the new 230 kV incoming
house/storage. breakers.
15) Manpower and tools pertinent to the planned activities 14) Perform testing on OHTL protection, control, and com-
shall be available. Measuring and testing devices shall munication systems.
be calibrated prior to any activities. 15) Dismantle conductors/ horizontal tubular bus sections
16) Lock out/tag out (LOTO) procedures as per NFPA 70E among D706, D707, and D712. Demolish steel structures
[12] and NESC [6] safety codes and recommendations and foundations of all related supports.
shall be followed on activities that involve disconnection 16) Dismantle conductors/tubular bus sections between
of energized equipment. All elements of control shall be D724 and D716 including any extensions to D712 and
actively in place. In addition, the safety precautions on D714.
hazards which must be controlled shall be followed as 17) Remove DS D706, D707, D712, D714, D716, and D724.
per approved work permit. Demolish associated foundations and structural sup-
17) Barricades/barriers and safety signs shall be installed ports.
as per end user safety procedures prior to commence- 18) Install foundations, steel structures, and 230 kV XLPE
ment of construction activities. NFPA 70E [12] Table cable terminators at T702, T704, and T706 interface
130.4(D)(a) lists the limited approach boundary as 4.0 m gantries.
(13 ft.) and restricted approach boundary as 1.7 m (5 ft. 8 19) Perform all cable acceptance tests prior to connecting
in) for 230–242 kV phase-phase alternating current (ac) the cables to cable terminators at T702, T704, and T706
systems. interface gantries.
18) All construction personnel shall be qualified for the tasks 20) Install all necessary cables and wires associated with pro-
and wear proper personal protective equipment when tective devices, control, load shedding system, commu-
working in the vicinity of energized equipment. nication, and PSA between the new GIS and CB control
panels in existing and new 13.8 kV substations. Caution
B. Transition Plan for Utility Line-A shall be exercised and all connections shall be made only
1) Isolate/de-energize utility line-A and cogen line-2. See on de-energized equipment.
Fig. 5. 21) Test all monitoring, control, and communication circuits
2) Disconnect CCVTs from 230 kV utility line-A gantry, related to existing transformers T702, T704, and T706
vertical drop-bus on phases A, B, and C. for continuity and functionality.
3) Disconnect all power, control cables, and metal 22) All exception items related to this activity shall be closed.
frame grounding wires in the CCVT junction boxes, 23) Energization package shall be submitted along with en-
switchgears, protective devices, metering, and load shed- ergization form.
ding panels related to utility line-A equipment. 24) Interface to SCADA system shall be in operation.
902 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018

2) Disconnect CCVTs on utility line-B and cogen line-2 at


vertical drop buses on phases A, B, and C.
3) Disconnect all cables, wires, and pilot wires in the CCVT
junction boxes and switchgear terminals related to utility
line-B and cogen line-2.
4) Dismantle all junction boxes and conduits of the utility
line-B and cogen line-2 CCVTs. Store them in a safe
place.
5) Demolish CCVT related steel structures and foundations
related to utility line-B and cogen line-2.
6) Remove DS D704 and 230 kV horizontal tubular bus.
7) Install foundations, steel structures, and 230 kV XLPE
cables terminators at utility line-B and cogen line-2
gantries.
8) Continue the trenches and install 230 kV XLPE and
associated communication cables from GIS building to
utility line-B and cogen line-2 gantries. Also, install ca-
Fig. 6. GIS energized via utility line-A. bles related to cogen line-1 in the same trench.
9) Perform activities as per steps 8–12 presented in
25) Prior to energizing utility line-A, ensure synchronizing Section VIII-B for utility line-B and cogen line-2.
check relays on utility line-A and cogen lines 1 and 2 are 10) Connect 230 kV cables to the new 230 kV GIS incoming
active and working correctly. breakers.
26) Energize utility line-A, and monitor incoming cable from 11) Perform testing on OHTL protection, control, and com-
gantry to GIS incomer CBs for 24 h. Confirm safe oper- munication systems.
ation. 12) All exception items related to this activity shall be closed.
27) Energize incoming breaker on GIS connected to utility 13) Energization package shall be submitted along with en-
line-A circuit. The GIS shall be hot soaked for 24 h, or ergization form.
as per vendor recommendation prior to energizing any 14) Interface to SCADA system shall be in operation.
other GIS breaker. 15) Synchronize and energize utility line-B and cogen
28) Verify that the sync-check relays on GIS bus coupler and line-2. Monitor incoming cables from the gantries to
sectionalizing breakers are active and working correctly. GIS incomer CBs for 24 h. Confirm safe operation.
Close bus coupler breaker to energize GIS bus 1A. 16) Energize GIS incoming breaker connected to utility line-
29) Monitor GIS control, communications, and protective B and cogen line-2 circuits. Exercise bus-sectionalizer
devices for any unusual operational issues under un- and bus-coupler breakers for synchronism and function-
loaded conditions. ality.
30) Energize 230 kV GIS feeder breakers to new transform- 17) The 230 kV GIS will now be on double ended operation
ers T707 and T708. Ensure all transformers are operating via utility line-A, utility line-B, cogen line-2, and cogen
normally and are ready for loading. line-1 power supplies. See Fig. 7.
31) Close the main incomers on 13.8 kV switchgear at new
substation P5 and monitor for safe operation. D. Transition Plan for Cogen Line-1
32) Energize 230 kV GIS feeder CBs to existing transform-
ers T702, T704, and T706. Ensure all transformers are 1) Isolate/de-energize Tihama line-1.
operating normally and are ready for loading. 2) Disconnect all wires including OPGW in the CCVT junc-
33) Ensure synchronism is achieved between utility and tion boxes and switchgear terminals related to cogen
cogen line-1. Close bus-2 main incoming breakers on line-1.
13.8 kV switchgears in substations P1, P2, and P3 (B303, 3) Disconnect CCVTs on cogen line-1 from the vertical
B304, B370, and B391). Now, all switchgears are oper- drop bus on all phases A, B, and C.
ating in parallel with three (3) sources of power supplies 4) Dismantle all junction boxes and conduits of the cogen
(from utility line-A, utility line-B, and cogen line-1). line-1 CCVTs. Store them in a safe place.
This will ensure continuity of power supply to UGP op- 5) Demolish steel structure and foundations related to co-
erations without any interruption. See Fig. 6. gen line-1 CCVT.
34) After energizing all 13.8 kV switchgear, monitor for safe 6) Disconnect and remove all cables, control wires from
operation as per design. CTs, and power supplies in the junction box terminals
related to CBs A703 and A704; DSs D721, D722, and
D725.
C. Transition Plan for Utility Line-B and Cogen Line-2
7) Dismantle 230 kV horizontal tubular bus between cogen
1) Isolate/de-energize utility line-B and cogen line-2. line-1 gantry and D721 (including extensions to D725).
D’SOUZA et al.: CONVERSION OF 230 KV SWITCHYARD TO GAS-INSULATED SUBSTATION IN A GAS PLANT 903

20) All exception items related to this activity shall be closed.


21) Energization package shall be submitted along with en-
ergization form.
22) Interface to SCADA system shall be in operation.
23) Prior to energizing cogen line-1, ensure synchronizing
check relays on GIS bus are working correctly.
24) Energize cogen circuit line-1 and monitor incoming ca-
ble from gantry to GIS incomer CB for 24 h.
25) Monitor GIS control, communications, and protective
devices for any unusual operational issues.
26) Energize 230 kV GIS feeder breakers feeding existing
transformers T701, T703, and T705. Ensure all trans-
formers are operating normally and are ready for loading.
See Fig. 3.
27) After energizing transformers T701, T703, and T705,
normalize 13.8 kV switchgear and monitor for safe op-
eration as per design.
Fig. 7. GIS energized via utility line-B and cogen line-2. 28) The OHTL control and protection panels in the existing
substation P1 substation shall be removed or mothballed
after ensuring that the new 230 kV system in GIS build-
8) Dismantle 230 kV tubular bus between D722 and D715 ing is operating safely.
(including extensions to D705, D711, and D713).
9) Remove CBs A701, A703, A704, and A705; and DSs
D705, D721, D722, D723, D725, D726, D711, D713, IX. CONCLUSION
and D715. Remove/demolish all related control wires, Conclusions drawn in this paper are based on past experi-
conduits, junction boxes, steel structure, and concrete ence, good engineering practice, and proven construction meth-
foundations. ods. Careful planning with strong project management will be
10) Install foundations, steel structures, and 230 kV XLPE required to execute this conversion. Procurement of engineered
cables terminators at cogen line-1 gantry as shown on equipment must start early during the detailed design phase. Site
installation drawing. preparation and remediation activities, if necessary, should be
11) Prepare trenches and continue installation of 230 kV completed to facilitate quicker installation of the substation and
XLPE and associated communication cables from GIS underground utilities. Functional testing of all major equipment
building to cogen line-1 gantry. at the factory shall be witnessed by the installation contractor
12) Perform activities as per steps 8–12 presented in and end user to pre-empt any operational discrepancies. The
Section VIII-B for cogen line-1. new GIS, all related auxiliary equipment, new OHTL protec-
13) Connect 230 kV cables to the new 230 kV GIS incoming tion, and control panels with all interconnection wiring shall
breakers. be installed, inspected, certified to be mechanically complete,
14) Perform testing on OHTL protection, control, and com- functionally tested, and ready to be energized, prior to shutdown
munication systems. of any existing electrical equipment.
15) Continue trenching and install 230 kV XLPE cables from Since the construction activities of the power system transi-
GIS outgoing feeder CBs to 230 kV cable terminators at tion from AIS to GIS need to be performed while the gas plant is
D711, D713, and D715 interface gantries. in operation, maintainability and reliability factors of all activ-
16) Install foundations, steel structures, and 230 kV XLPE ities must remain high. Contingency scenarios were developed
cable terminators at T701, T703, and T705 interface and mitigating actions were approved by the end user to en-
gantries as shown on drawings. able a safe partial or complete plant shutdown. These scenarios
17) Install all necessary cables and wires associated with considered immediate restoration of power supply to restart the
protective devices, control, load shedding system, com- plant.
munication, and PSA between the new GIS and CB con-
trol panels in existing 13.2 kV substations. Caution shall
be exercised and all connections shall be made only on REFERENCES
de-energized equipment.
18) Perform all cable acceptance tests prior to connecting [1] High-Voltage Switchgear and Controlgear: Common Specifications, IEC
Std. 62271-1, 2007.
the cables to cable terminators at T701, T703, and T705 [2] High-Voltage Switchgear and Controlgear: Alternating-Current Circuit-
interface gantries. Breakers, IEC Std. 62271-100, 2008.
19) Test all monitoring, control, and communication circuits [3] High-Voltage Switchgear and Controlgear: Alternating Current Discon-
nectors and Earthing Switches, IEC Std. 62271-102, 2001.
related to existing transformers T701, T703, and T705 [4] Communication Networks and Systems for Power Utility Automation, IEC
for continuity and functionality. Std. 61850, 2010.
904 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 54, NO. 1, JANUARY/FEBRUARY 2018

[5] High-Voltage Switchgear and Controlgear: Gas-Insulated Metal- Saud Al-Shammari received the graduate degree
Enclosed Switchgear for Rated Voltages Above 52 kV, IEC Std. 62271-203, in electrical engineering from the King Fahad Uni-
2011. versity of Petroleum and Minerals, Dhahran, Saudi
[6] National Electrical Safety Code (NESC), ANSI/IEEE C2-2012, 2012. Arabia, in 2001.
[7] IEEE Standard for High Voltage Gas-Insulated Substations Rated Above He has been with Saudi Aramco, Monrovia, CA,
52 kV, IEEE Std. C37.122-1993, 1993. USA, since 2002 and has led design reviews and
[8] IEEE Guide for Safety in AC Substation Grounding, IEEE Std. 80-2013, electrical power system commissioning activities on
2013. mega power projects. He is in a supervisory position
[9] IEEE Guide for Substation Fire Protection, IEEE Std. 979-2012, 2012. with the Power Systems Engineering Department,
[10] IEEE Guide for Temporary Protective Grounding System Used in Substa- Saudi Aramco, and is currently on a project man-
tions, IEEE Std. 1246-2011, 2011. agement assignment on mega oil and gas projects.
[11] IEEE Guide for Cable Connections for Gas-Insulated Substations, IEEE He has co-authored several published IEEE-International Conference on Har-
Std. 1300-2011, 2011. monics and Quality of Power articles.
[12] National Electric Code (NEC), NFPA 70, 2014.
[13] Standard for Electrical Safety in the Workplace
R
, NFPA 70E-2015, 2015.
[14] Test Procedures and Requirements for Alternating-Current Cable Termi-
nations Used on Shielded Cables Having Laminated Insulation Rated
2.5 kV Through 765 kV or Extruded Insulation Rated 2.5 kV Through 500
kV, IEEE Std. 48-2009, 2009.
[15] Power Cables With Extruded Insulation and their Accessories for Rated
Voltages Above 30 kV (Um = 36 kV) Up To 150 kV (Um = 170 kV) – Test
Methods and Requirements, IEC Std. 60840-2011, 2011.
[16] M. D’Souza, S. Al Shammari, and M. Safwa, “Conversion of 230 KV
switchyard to gas insulated substation in a gas plant,” in Proc. 2016
Petroleum Chem. Ind. Tech. Conf., Philadelphia, PA USA, 2016, pp. 1–10,
doi: 10.1109/PCICON.2016.7589212.

Mghwar Safwa (M’05) received the B.S. degree in


Merwyn D’Souza (M’85–SM’14) received the B.S. electrical engineering from the University of Aleppo,
degree in electrical engineering from the National In- Aleppo, Syria, in 1989.
stitute of Technology Karnataka, India, in 1975. He is currently with WorleyParsons, Monrovia,
He is currently a Senior Engineering Manager CA, USA, as a Technical Consultant in a supervisory
with WorleyParsons, Monrovia, CA, USA. He au- role. He has worked on electric power generation and
thored two IEEE Petroleum and Chemical Industry distribution projects for more than 20 years in project
Committee papers. He has been involved in mining, management, design, start-up, commissioning, facili-
oil, and gas industry major projects worldwide for ties maintenance, and operations management capac-
more than 30 years in various aspects of electrical ities. He has performed complex analytical studies
engineering design, procurement, construction, start- on onshore and offshore electrical systems on several
up, and commissioning. large projects worldwide.
Mr. D’Souza is a registered Professional Engineer in the state of California. Mr. Safwa is a member of the International Society of Automation.

S-ar putea să vă placă și