Lube Oil Piping Schedule

Sr. Description Drawing No. Rev No. of Joints Pipe Size

1 Control Oil Supply Header 673010209-26 - 40 40


2 Control Oil to Return Header 673010209-27 - 10 80
3 Lube Oil from MOT to Cooler 673010209-28 - 11 80
4 Lube Oil Cooler Oil Drain to Centrifuge 673010209-29 - 6 25
5 Lube Oil Filter Drain to Centrifuge 673010209-30 - 13 25

6 LO Supply Header for Users 673010209-31 - 31 80

7 Lube Oil Supply to Turbine Front Bearing 673010209-32 - 15 50


8 Lube Oil Supply to Turbine Rear Bearing 673010209-33 - 14 40
9 Lube Oil Supply to Gear Box 673010209-34 - 20 80
10 Lube Oil Supply to Generator Front Bearing 673010209-35 - 13 25
11 Lube Oil Supply to Generator Rear Bearing 673010209-36 - 15 25
12 Lube Oil Return header from Users 673010209-37 - 21 150
13 Lube Oil Return from Turbine Front Bearing 673010209-38 - 14 150
14 Lube Oil Return from Turbine Rear Bearing 673010209-39 - 14 100
15 Lube Oil Return from Gear Box 673010209-40 - 14 150
16 Lube Oil Return from Generator Front Bearing 673010209-41 - 11 100
17 Lube Oil Return from Generator Rear Bearing 673010209-42 - 14 100
18 EOP Discharge to Supply Header 673010209-43 - 10 50
19 Oil Centrifuge return to MOT 673010209-44 - 17 25
20 MOT supply to Oil centrifuge 673010209-45 - 10 25
21 Coupling guard oil return 673010209-46 - 10 50

22 Lube oil supply to OHT 673010209-47 - 44 50


23 Lube oil return from OHT 673010209-48 - 24 40
Total 391
Joints Inch dia Inch dia
Inch Dia completed Remarks Duration Start Finish
completed balance

64 40 64 0
32 10 32 0
35 11 35 0
6 6 6 0
13 13 13 0

99 31 99 0

30 15 30 0
22 14 22 0
64 20 64 0
13 13 13 0
15 15 15 0
126 21 126 0
84 14 84 0
56 14 56 0
84 14 84 0
44 11 44 0
56 14 56 0
20 10 20 0
17 17 17 0
10 10 10 0

20 0 0 20 shall be done after 2


alignment
88 30 60 28 u/p 7/12/2019
38.4 18 28.8 10 u/p 7/12/2019
1037.2 361 979.6 58
Manpower

1 fitter, 1 Welder
NIBR Piping Schedule
Sr. Description Drawing No. Rev No. of Joints

COOLING WATER SYSTEM


1 ACW PUMP SUCTION LINE - PUMP I 17
ES0163-75050300-ISO-3150 1
2
ACW PUMP SUCTION LINE - PUMP II
2 ES0163-75050300-ISO-3160 1 3
ACW PUMP DISCHARGE LINE - PUMP I 6
3 ES0163-75050300-ISO-3170 1
1
ACW PUMP DISCHARGE LINE - PUMP II 6
4 ES0163-75050300-ISO-3180 1
1
ACW SUPPLY LINE COMMON HEADER 20
5 ES0163-75050300-ISO-3191 1
5
ACW SUPPLY LINE COMMON HEADER
6 ES0163-75050300-ISO-3192 1 14
ACW SUPPLY LINE TO LUBE OIL COOLER I & II
7 ES0163-75050300-ISO-3241 0 30
ACW SUPPLY LINE TO ALTERNATOR COOLER 13
8 ES0163-75050300-ISO-3251 0
14
9 ACW SUPPLY LINE TO BFP ES0163-75050300-ISO-3261 0 40
ACW RETURN LINE FROM LUBE OIL COOLER
10 ES0163-75050300-ISO-3460 0 30
ACW RETURN LINE FROM ALTERNATOR AIR 12
11 ES0163-75050300-ISO-3470 0
COOLER 14
12 ACW RETURN LINE FROM BFP ES0163-75050300-ISO-3480 0 40
ACW RETURN LINE COMMON HEADER TO
13 ES0163-75050300-ISO-3521 1 15
COOLING TOWER
ACW RETURN LINE COMMON HEADER TO
14 ES0163-75050300-ISO-3522 1 24
COOLING TOWER
ACW RETURN LINE COMMON HEADER TO
15 ES0163-75050300-ISO-3530 0 6
DRAIN TRENCH
AUX. COOLING TOWER OVERFLOW & DRAIN
16 ES0163-75050300-ISO-3540 0 10
LINE TO TRENCH
ACW PUMP RECIRCULATION LINE TO AUX.
17 ES0163-75050300-ISO-3560 1 10
COOLING TOWER
CT MAKE UP WATER TRANSFER PUMP SUCTION
18 ES0163-75050300-ISO-3700 0 28
LINE - PUMP I
CT MAKE UP WATER TRANSFER PUMP
19 ES0163-75050300-ISO-3720 0 15
DISCHARGE LINE - PUMP I
CT MAKE UP WATER TRANSFER PUMP
20 ES0163-75050300-ISO-3730 0 15
DISCHARGE LINE - PUMP II
MAKE UP WATER TRANSFER PUMP DISCHARGE
21 ES0163-75050300-ISO-3740 1 27
LINE TO AUX. COOLING TOWER
MAKE UP WATER TRANSFER PUMP DISCHARGE
22 ES0163-75050300-ISO-3780 0 20
LINE TO AUX. COOLING TOWER
MAKE UP WATER TRANSFER PUMP DISCHARGE
23 ES0163-75050300-ISO-3790 0 26
LINE TO AUX. COOLING TOWER
MAKE UP WATER TRANSFER PUMP DISCHARGE
24 ES0163-75050300-ISO-3800 0 23
LINE TO AUX. COOLING TOWER
MAKE UP WATER TRANSFER PUMP DISCHARGE
25 ES0163-75050300-ISO-3810 0 17
LINE TO AUX. COOLING TOWER
MAKE UP WATER TRANSFER PUMP DISCHARGE
26 ES0163-75050300-ISO-3820 1 18
LINE TO AUX. COOLING TOWER
CT MAKE UP WATER TRANSFER PUMP
27 ES0163-75050300-ISO-3750 0 14
RECIRCULATION LINE
28 SOFT WATER TANK OVERFLOW & DRAIN ES0163-75050300-ISO-3760 0 17
29 SOFTENER OUTLET TO SOFT WATER TANK ES0163-75050300-ISO-3770 0 20
ACW SUPPLY TO SAMPLE COOLER IN AQC
30 ES0163-75050300-ISO-3193 0 33
BOILER TP
ACW RETURN FROM SAMPLE COOLER IN AQC
31 ES0163-75050300-ISO-3242 0 15
BOILER TP
ACW RETURN FROM SAMPLE COOLER IN AQC
32 ES0163-75050300-ISO-3820 0 36
BOILER TP
ACW SUPPLY TO SAMPLE COOLER IN PH BOILER
33 ES0163-75050300-ISO-3252 0 20
TP
ACW SUPPLY TO SAMPLE COOLER IN PH BOILER
34 ES0163-75050300-ISO-3262 0 31
TP
ACW RETURN FROM SAMPLE COOLER IN PH
35 ES0163-75050300-ISO-3523 0 32
BOILER TP
ACW RETURN FROM SAMPLE COOLER IN PH
36 ES0163-75050300-ISO-3710 0 21
BOILER TP
Total 761
CONDENSATE WATER PIPING
37 CPH OUTLET HEADER TO DEAERATOR TP ES0163-75050400-ISO-4010 26
38 CPH OUTLET HEADER TO DEAERATOR TP ES0163-75050400-ISO-4020 20
Sub Total 46
DM WATER PIPING
DM WATER TANK - I & II COMMON HEADER
39 ES0163-75050500-ISO-5011 4
DM WATER TRANSFER PUMP SUCTION LINE -
40 ES0163-75050500-ISO-5020 8
PUMP I
DM WATER TRANSFER PUMP SUCTION LINE -
41 ES0163-75050500-ISO-5030 8
PUMP II
DM WATER DISCHARGE LINE PUMP - I
42 ES0163-75050500-ISO-5040 12
DM WATER DISCHARGE LINE PUMP - II
43 ES0163-75050500-ISO-5050 12
DM WATER DISCHARGE COMMON HEADER
44 ES0163-75050500-ISO-5061 44
LINE
DM WATER DISCHARGE COMMON HEADER
45 ES0163-75050500-ISO-5062 27
LINE
DM WATER DISCHARGE COMMON HEADER
46 ES0163-75050500-ISO-5063 30
LINE
47 DM WATER TO HP DOSING (PH) ES0163-75050500-ISO-5080 20
DM WATER DISCHARGE COMMON HEADER
48 LINE TO ACC HOT WELL ES0163-75050500-ISO-5101 38
DM WATER DISCHARGE COMMON HEADER
49 LINE TO ACC HOT WELL ES0163-75050500-ISO-5102 16
DM WATER DISCHARGE COMMON HEADER
50 LINE TO HP DOSING (AQC) ES0163-75050500-ISO-5103 8
51 DM WATER PUMP RECIRCULATION LINE ES0163-75050500-ISO-5120 14

52 DM TANK OVERFLOW & DRAIN ES0163-75050500-ISO-5170 14

53 MB OUTLET TO DM WATER TANK ES0163-75050500-ISO-5191 26


DM WATER DISCHARGE COMMON HEADER
54 LINE TO LP DOSING (AQC) ES0163-75050500-ISO-5111 26
DM WATER DISCHARGE COMMON HEADER
55 LINE TO LP DOSING (AQC) ES0163-75050500-ISO-5112 20
Sub Total 323
BOILER INITITAL FILL PIPING
BOILER INITIAL FILLING PUMP SUCTION LINE -
56 ES0163-75050500-ISO-5350 8
PUMP I
BOILER INITIAL FILLING PUMP DISCHARGE LINE
57 ES0163-75050500-ISO-5360 16
- PUMP I
BOILER INITIAL FILLING PUMP DISCHARGE
58 ES0163-75050500-ISO-5371 13
COMMON HEADER LINE
BOILER INITIAL FILLING PUMP DISCHARGE
59 ES0163-75050500-ISO-5372 16
COMMON HEADER LINE
BOILER INITIAL FILLING PUMP DISCHARGE
60 ES0163-75050500-ISO-5373 18
COMMON HEADER LINE
BOILER INITIAL FILLING PUMP DISCHARGE
61 ES0163-75050500-ISO-5381 25
COMMON HEADER LINE
BOILER INITIAL FILLING PUMP TO AQC BOILER
62 ES0163-75050500-ISO-5461 23
INITIAL FILLING
BOILER INITIAL FILLING PUMP TO PH BOILER
63 ES0163-75050500-ISO-5491 20
INITIAL FILLING
BOILER INITIAL FILLING PUMP TO PH BOILER
64 ES0163-75050500-ISO-5492 10
INITIAL FILLING
BOILER INITIAL FILLING PUMP TO DEAERATOR
65 ES0163-75050500-ISO-5382 24
INITIAL FILLING
BOILER INITIAL FILLING PUMP TO CONDENSATE
66 ES0163-75050500-ISO-5462 29
STORAGE TANK
SUb Total 202
RAW WATER PIPING
RAW WATER TRANSFER PUMP SUCTION LINE -
67 ES0163-75050600-ISO-6010 8
PUMP I
RAW WATER TRANSFER PUMP SUCTION LINE -
68 ES0163-75050600-ISO-6020 8
PUMP II
RAW WATER TRANSFER PUMP DISCHARGE LINE
69 ES0163-75050600-ISO-6030 15
- PUMP I
RAW WATER TRANSFER PUMP DISCHARGE LINE
70 ES0163-75050600-ISO-6040 15
- PUMP II
RAW WATER TRANSFER PUMP DISCHARGE
71 ES0163-75050600-ISO-6051 35
HEADER LINE TO MGF
RAW WATER TRANSFER PUMP RECIRCULATION
71 ES0163-75050600-ISO-6052 15
LINE
Sub Total 96
SERVICE WATER PIPING
SERVICE WATER TRANSFER PUMP I & II SUCTION
72 ES0163-75050600-ISO-6270 25
SERVICE WATER TRANSFER PUMP DISCHARGE
73 ES0163-75050600-ISO-6300 15
LINE - PUMP I
SERVICE WATER TRANSFER PUMP DISCHARGE
74 ES0163-75050600-ISO-6310 15
LINE - PUMP II
SERVICE WATER TRANSFER PUMP DISCHARGE
75 ES0163-75050600-ISO-6321 50
COMMON HEADER LINE
SERVICE WATER TRANSFER PUMP DISCHARGE
76 ES0163-75050600-ISO-6322 23
COMMON HEADER LINE
SERVICE WATER TRANSFER PUMP DISCHARGE
77 ES0163-75050600-ISO-6330 34
COMMON HEADER LINE
Sub Total 162
NPIT PIPING
N.PIT TRANSFER PUMP SUCTION LINE - PUMP I
78 ES0163-75050600-ISO-6450 8
N.PIT TRANSFER PUMP SUCTION LINE - PUMP II
79 ES0163-75050600-ISO-6460 8
N.PIT TRANSFER PUMP DISCHARGE LINE - PUMP
80 ES0163-75050600-ISO-6470 13
I
N.PIT TRANSFER PUMP DISCHARGE LINE - PUMP
81 ES0163-75050600-ISO-6480 13
II
N.PIT TRANSFER PUMP DISCHARGE LINE TO
82 ES0163-75050600-ISO-6491 19
CLIENT TP
83 N.PIT TRANSFER PUMP RECIRCULATION LINE ES0163-75050600-ISO-6492 6
Sub Total 67
PORTABLE WATER PIPING
PORTABLE WATER TRANSFER PUMP I & II
84 ES0163-75050600-ISO-8721 22
SUCTION
PORTABLE WATER TRANSFER PUMP DISCHARGE
85 ES0163-75050600-ISO-8722 12
LINE - PUMP I
PORTABLE WATER TRANSFER PUMP DISCHARGE
86 ES0163-75050600-ISO-8731 12
LINE - PUMP II
PORTABLE WATER TRANSFER PUMP DISCHARGE
87 ES0163-75050600-ISO-8732 30
COMMON HEADER LINE
Sub Total 76
INSTRUMENT & SERVICE AIR PIPING
INSTRUMENT AIR & SERVICE AIR COMPRESSOR-I
88 ES0163-75050700-ISO-7010 45
& II TO INSTRUMENT AIR DRYER - I & II

INSTRUMENT AIR DRIER-I & II TO INSTRUMENT


89 ES0163-75050700-ISO-7020 23
AIR RECEIVER
INSTRUMENT AIR RECEIVER TO COMMON
90 ES0163-75050700-ISO-7030 22
SUPPLY HEADER
INSTRUMENT AIR & SERVICE AIR COMPRESSOR-I
91 ES0163-75050700-ISO-7040 14
& II TO SERVICE AIR RECEIVER
SERVICE AIR RECEIVER OUTLET TO COMMON
92 ES0163-75050700-ISO-7050 17
SUPPLY HEADER
Total 121
Grand Total 1854
8/4/2019
Pipe Size Inch Dia Joints Fitup Welding Inch dia Inch dia Duration Start Finish
Completion Completion completion balance

7/12/2019 8/13/2019
300 204 17 17 204 0 5 7/12/2019 7/16/2019
150 12 2 2 12 0 1 7/16/2019 7/16/2019
300 36 3 3 36 0 1 7/17/2019 7/17/2019
200 48 6 6 48 0 1 7/18/2019 7/18/2019
100 4 1 1 4 0 0 Completed
200 48 6 6 48 0 1 7/19/2019 7/19/2019
100 4 1 1 4 0 1 7/20/2019 7/20/2019
200 160 20 20 160 0 1 Completed
25 5 5 5 5 0 1 7/21/2019 7/21/2019
200 112 14 14 112 0 1 7/22/2019 7/22/2019
150 180 30 30 180 0 Completed
150 78 13 13 78 0 1 Completed
80 44.8 14 14 44.8 0 1 Completed
25 40 40 40 40 0 1 7/23/2019 7/23/2019
150 180 30 30 180 0 7/24/2019 7/23/2019
150 72 12 12 72 0 2 Completed
80 44.8 14 14 44.8 0 1 Completed
25 40 40 40 40 0 1 7/24/2019 7/24/2019
200 120 15 15 120 0 Completed

200 192 24 24 192 0 7/25/2019 7/24/2019

200 48 6 6 48 0 1 7/25/2019 7/25/2019

200 80 10 10 80 0 1 7/26/2019 7/26/2019

100 40 10 10 40 0 1 7/27/2019 7/27/2019

50 56 0 56 1 7/28/2019 7/28/2019

40 24 0 24 1 7/29/2019 7/29/2019

40 24 0 24 1 7/30/2019 7/30/2019

40 43.2 27 27 43.2 0 1 Completed

40 32 20 20 32 0 1 Completed

40 41.6 26 26 41.6 0 1 7/31/2019 7/31/2019

40 36.8 0 36.8 1 8/1/2019 8/1/2019


40 27.2 0 27.2 1 8/2/2019 8/2/2019

40 28.8 0 28.8 1 8/3/2019 8/3/2019

25 14 0 14 1 8/4/2019 8/4/2019
50 34 0 34 1 8/5/2019 8/5/2019
50 40 0 40 1 8/6/2019 8/6/2019
40 52.8 0 52.8 1 8/7/2019 8/7/2019

40 24 0 24 1 8/8/2019 8/8/2019

40 57.6 0 57.6 1 8/9/2019 8/9/2019

40 32 0 32 1 8/10/2019 8/10/2019

40 49.6 0 49.6 1 8/11/2019 8/11/2019

40 51.2 0 51.2 1 8/12/2019 8/12/2019

40 33.6 0 33.6 1 8/13/2019 8/13/2019


2495 406 406 1909.4 585.6
8/1/2019 8/10/2019
100 104 0 104 5 8/1/2019 8/5/2019
100 80 80 5 8/6/2019 8/10/2019
184 0 0 0 184
7/14/2019 8/3/2019
100 16 4 4 16 0
40 12.8 8 8 12.8 0 1 7/14/2019 7/14/2019

40 12.8 8 8 12.8 0 1 7/14/2019 7/14/2019


25 12 0 12 1 7/15/2019 7/15/2019
25 12 0 12 1 7/15/2019 7/15/2019
40 70.4 44 44 70.4 0 5 7/16/2019 7/20/2019

40 43.2 27 27 43.2 0 3 7/16/2019 7/18/2019

40 48 30 30 48 0 3 7/21/2019 7/23/2019

25 20 0 20 2 7/19/2019 7/20/2019

40 60.8 25 25 40 20.8 4 7/24/2019 7/27/2019

40 25.6 0 25.6 2 7/21/2019 7/22/2019

25 8 0 8 1 7/28/2019 7/28/2019
15 8.4 0 8.4 1 7/23/2019 7/23/2019
80 44.8 0 44.8 4 7/29/2019 8/1/2019
80 83.2 26 26 83.2 0 6 7/24/2019 7/29/2019

25 26 0 26 2 8/2/2019 8/3/2019

25 20 0 20 2 7/30/2019 7/31/2019
508 168 168 310.4 197.6
7/16/2019 8/5/2019
100 32 0 32 1 7/16/2019 7/16/2019

80 51.2 0 51.2 2 7/17/2019 7/18/2019

80 41.6 0 41.6 2 7/19/2019 7/20/2019

80 51.2 13 13 41.6 9.6 2 7/21/2019 7/22/2019

80 57.6 18 18 57.6 0 2 7/23/2019 7/24/2019

80 80 25 25 80 0 3 7/25/2019 7/27/2019

80 73.6 15 15 48 25.6 2 7/28/2019 7/29/2019

40 32 0 32 2 7/30/2019 7/31/2019

40 16 0 16 1 8/1/2019 8/1/2019

50 48 0 48 2 8/2/2019 8/3/2019

40 46.4 0 46.4 2 8/4/2019 8/5/2019

530 71 71 227.2 302.4


7/25/2019 8/4/2019
80 25.6 8 8 25.6 0 2 7/25/2019 7/26/2019

80 25.6 8 8 25.6 0 2 7/27/2019 7/28/2019

50 30 0 30 1 7/29/2019 7/29/2019

50 30 0 30 1 7/30/2019 7/30/2019

80 112 20 20 64 48 4 7/31/2019 8/3/2019

40 24 0 24 1 8/4/2019 8/4/2019
247.2 36 36 115.2 132
8/1/2019 8/14/2019
50 50 0 50 2 8/1/2019 8/2/2019

40 24 0 24 2 8/3/2019 8/4/2019

40 24 0 24 2 8/5/2019 8/6/2019

50 100 50 50 100 0 4 8/7/2019 8/10/2019

50 46 15 15 30 16 2 8/11/2019 8/12/2019

50 68 0 68 2 8/13/2019 8/14/2019
312 65 65 130 182
8/16/2019 8/21/2019
50 16 0 16 1 8/16/2019 8/16/2019

50 16 0 16 1 8/17/2019 8/17/2019

40 20.8 0 20.8 1 8/18/2019 8/18/2019

40 20.8 0 20.8 1 8/19/2019 8/19/2019

40 30.4 0 30.4 1 8/20/2019 8/20/2019


25 6 0 6 1 8/21/2019 8/21/2019
110 0 0 0 110
8/22/2019 8/25/2019
25 22 0 22 1 8/22/2019 8/22/2019

25 12 0 12 1 8/23/2019 8/23/2019

25 12 0 12 1 8/24/2019 8/24/2019

15 18 0 18 1 8/25/2019 8/25/2019
64 0 0 0 64

50 90 0 90 2 7/18/2019 7/19/2019

50 46 0 46 2 7/20/2019 7/21/2019

50 44 0 44 2 7/22/2019 7/23/2019

40 22.4 0 22.4 2 7/24/2019 7/25/2019

40 27.2 0 27.2 3 7/26/2019 7/28/2019


229.6 0 0 0 229.6
4679.4 746 746 2692.2 1987.2
Group

G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6
G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6
G5 & G6

G5 & G6

G5 & G6
G5 & G6
G5 & G6
G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G5 & G6

G4
G4

G1
12.8
G2
G1
G2
G1

G2

G1

G2

G1

G2

G1
G2
G1
G2

G1

G2

G3

G3

G3

G3

G3

G3

G3

G3

G3

G3

G3
20 20

20
G7

G7

G7

G7

G7
32.8 20 20
IBR Piping Schedule 7/10/2019
Sr. Description Drawing No. Rev No. of Joints Pipe Size Inch Dia Start Finish Group S
t
a
IBR PIPING 7/17/2019 8/14/2019
t
u
MAIN STEAM PIPING 7/17/2019 8/3/2019 s

MAIN STEAM FROM AQC BOILER MSSV TO


1 ES0163-75050100-ISO-1011 0 20 250 200
TURBINE 7/17/2019 7/21/2019
G1 & G2
MAIN STEAM FROM AQC BOILER MSSV TO 17 250 170 7/22/2019 7/24/2019
2 ES0163-75050100-ISO-1012 0
TURBINE 8 100 32 7/25/2019 7/25/2019
HP STEAM TURBINE WARMUP VENT PIPING 1 250 10 7/23/2019 7/24/2019 G3
3 ES0163-75050100-ISO-1061 0
9 150 54 7/25/2019 7/27/2019 G3
LP STEAM TURBINE WARMUP VENT PIPING
4 ES0163-75050100-ISO-1062 0 11 150
66 7/23/2019 7/26/2019 G4
5 MAIN STEAM TO HP DUMP TUBE ES0163-75050100-ISO-1071 0 15 150 90 7/26/2019 7/28/2019 G1
2 350 28 7/26/2019 7/27/2019 G2
6 MAIN STEAM TO HP DUMP TUBE ES0163-75050100-ISO-1072 0 4 300 48 7/28/2019 7/30/2019 G2
2 150 12 7/31/2019 7/31/2019 G2
7 MAIN STEAM TO HP DUMP TUBE ES0163-75050100-ISO-1073 0 6 300 72 7/27/2019 7/31/2019 G4
MAIN STEAM TO EJECTOR & GLAND
8 ES0163-75050100-ISO-1111 0 23 50
SEALING 46 7/29/2019 8/1/2019 G1
MAIN STEAM TO EJECTOR & GLAND 1 80 3.2 8/1/2019 8/1/2019 G2
9 ES0163-75050100-ISO-1112 0
SEALING 13 50 26 8/2/2019 8/3/2019 G2
1 80 3.2 7/28/2019 7/28/2019 G3
MAIN STEAM TO EJECTOR & GLAND
10
SEALING
ES0163-75050100-ISO-1113 0 11 50 22 7/29/2019 7/31/2019 G3
1 40 1.6 8/1/2019 8/1/2019 G3
Sub Total 145 884
LP STEAM PIPING 8/1/2019 8/14/2019
LP STEAM FROM AQC BOILER TO LP STEAM
11 HEADER ES0163-75050100-ISO-1421 0 8 150 48 8/1/2019 8/3/2019 G4
LP STEAM FROM PH BOILER TO LP STEAM
12 HEADER ES0163-75050100-ISO-1431 0 12 250
120 8/8/2019 8/13/2019 G2
LP STEAM FROM PH BOILER TO LP STEAM 11 250 110 8/6/2019 8/10/2019 G4
13 HEADER ES0163-75050100-ISO-1432 0
1 100 4 8/13/2019 8/14/2019 G3
LP STEAM FROM PH BOILER TO LP STEAM
14 HEADER ES0163-75050100-ISO-1433 0 14 250
140 8/9/2019 8/14/2019 G1
LP STEAM FROM HEADER TO TURBINE
15 ES0163-75050100-ISO-1441 1 16 250
INLET 160 8/2/2019 8/8/2019 G1
LP STEAM FROM HEADER TO TURBINE 6 250 60 8/3/2019 8/4/2019 G3
16 ES0163-75050100-ISO-1442 1
INLET 6 200 48 8/4/2019 8/4/2019 G2
LP STEAM FROM HEADER TO DEAERATOR
17 ES0163-75050100-ISO-1451 0 6 100
TP 24 8/5/2019 8/5/2019 G2
2 350 28 8/5/2019 8/6/2019 G3
LP STEAM FROM HEADER TO LP DUMP
18
TUBE
ES0163-75050100-ISO-1461 0 5 250 50 8/4/2019 8/5/2019 G4
2 150 12 8/6/2019 8/7/2019 G2
LP STEAM FROM HEADER TO LP DUMP
19 ES0163-75050100-ISO-1462 0 6 350
TUBE 84 8/7/2019 8/12/2019 G3
Sub Total 95 888
SPRAY WATER SYSTEM 8/7/2019 8/14/2019
SPRAY WATER FROM BFP OUTLET TO
20 EJECTOR & GLAND SEALING PRDS DSH - 01 ES0163-75050200-ISO-2021 0 27 15 16 8/7/2019 8/9/2019 ###

SPRAY WATER FROM BFP OUTLET TO


21 EJECTOR & GLAND SEALING PRDS DSH - 01 ES0163-75050200-ISO-2022 0 37 15 22 8/7/2019 8/9/2019 ###

SPRAY WATER FROM BFP OUTLET TO


22 EJECTOR & GLAND SEALING PRDS DSH - 01 ES0163-75050200-ISO-2023 0 2 80 6 8/8/2019 8/8/2019 ###

SPRAY WATER PIPE COMMON HEADER


23 ES0163-75050200-ISO-2461 0 14 40 22 8/10/2019 8/11/2019 ###
24 CEP OUTLET TP TO HP DUMP TUBE DSH - 02 ES0163-75050200-ISO-2471 0 22 40 35 8/10/2019 8/12/2019
###
25 CEP OUTLET TP TO HP DUMP TUBE DSH - 02 ES0163-75050200-ISO-2472 0 2 80 6 8/9/2019 8/9/2019
###
26 CEP OUTLET TP TO LP DUMP TUBE DSH - 03 ES0163-75050200-ISO-2481 0 28 15 17 8/10/2019 8/12/2019
###
27 CEP OUTLET TP TO LP DUMP TUBE DSH - 03 ES0163-75050200-ISO-2482 0 2 80 6 8/13/2019 8/14/2019
###
Total 134 132
Grand Total 374 1904
SCHEDULE FOR AQC INLET AND OUTLET DUCTING
Description QTY (MT) Assembly Erection
Sr.No
AQC Inlet Ducting & Hopper Start Finish Start
1 Bottom Hoppers 02 nos 7/23/2019 7/24/2019 7/25/2019
2 Supports: FSII 7/26/2019
3 Part 8+Dummy piece+9+10+11 7/22/2019 7/24/2019 7/26/2019
4 Support FS-III 7/25/2019
5 Support SS-I and FS-IV 7/26/2019
6 FGE-002+Part-7+6+FGE-001 7/31/2019
7 FGD-104
8 FGD-102
9 Part-5+4
10 Part-3+2
11 Part -1
AQC Outlet Ducting
1 Top Transition piece 5 completed 7/24/2019
2 Bellow: FGE004 0.58 7/24/2019

3 Ducting: Part-2+3+4 2.59 7/28/2019 7/31/2019 8/1/2019

4 Supports: FS-I 7/24/2019 7/31/2019 8/2/2019


5 Support: FSII (Damper support) 5.9 7/26/2019 8/1/2019 8/2/2019
6 Damper: FGD103 8/6/2019
7 Ducting: Part-5+6 0.65 8/7/2019
8 Supports: SSI & FSIII 7/25/2019 8/4/2019 8/5/2019
9 Ducting: FGE005+7+8+FGE006 5.44 8/7/2019
10 Part-9 8/10/2019
OUTLET DUCTING
Erection Alignment +Welding Remarks
Finish Start Finish
7/25/2019 7/26/2019 7/31/2019
7/26/2019
7/26/2019 7/26/2019 7/27/2019
7/25/2019
7/26/2019
7/31/2019

DURING SHUTDOWN
DURING SHUTDOWN
DURING SHUTDOWN

7/24/2019
7/24/2019
DAMPER DISTANCE PIECE
8/2/2019 SHOULD BE FABRICTED.
8/2/2019 Supports to be fabricated
8/2/2019 Supports to be fabricated
8/6/2019
8/8/2019
8/6/2019 Supports to be fabricated
8/9/2019
8/11/2019 Shutdown required
updated on 20/7
SL. NO PIPING DETAILS No. of Dia. in Total Inch Start
Field Weld Location Drawing Number SIZE BUTT Inches Dia.
JOINTS
OD (mm)
AQC INTEGRAL PIPING FOR HYDRO 7/20/2019
1 219.1 2 8 16 7/20/2019
2 JB1104-50090101-ISO- 219.1 18 8 144 7/21/2019
HP Down Comer 0014 & 0015 Rev.0 219.1
3 2 8 16 7/22/2019
219.1
219.1
4 4 8 32 7/20/2019
219.1
219.1
5 2 8 16 7/21/2019
219.1
219.1
6 2 8 16 7/20/2019
219.1
HP Evaporator O/L JB1104-50090101-ISO- 273
7 to HP Drum Riser 0016 & 17 Rev.0 2 10 20 7/21/2019
piping 273
219.1
8 2 8 16 7/22/2019
219.1
273
9 16 10 160 7/22/2019
273
273
10 2 10 20 7/22/2019
273
60.3
11 4 2 8 7/23/2019
60.3
60.3
12 1 2 2 7/24/2019
60.3
88.9
13 1 3 3 7/24/2019
88.9
HP Economiser I/L JB1104-50090101-ISO- 60.3
14
Piping 0003 Rev.0
3 2 6 7/25/2019
60.3
88.9
15 2 3 6 7/25/2019
88.9
88.9
16 3 3 9 7/25/2019
88.9
88.9
17 3 3 9 7/25/2019
88.9
60.3
18 4 2 8 7/23/2019
60.3
60.3
19 6 2 12 7/23/2019
60.3
88.9
20 1 3 3 7/23/2019
88.9

HP Economiser JB1104-50090101-ISO-
O/L to HP Drum 0004 & 5 Rev.0
60.3
21 3 2 6 7/23/2019
60.3
HP Economiser
22 JB1104-50090101-ISO- 88.9 2 3 6 7/23/2019
O/L to HP Drum 0004 & 5 Rev.0 88.9
piping
88.9
23 9 2 18 7/24/2019
88.9
88.9
24 1 3 3 7/25/2019
88.9
114.3
25 1 4 4 7/26/2019
114.3
88.9
26 1 3 3 7/26/2019
88.9
168.3
27 2 6 12 7/23/2019
168.3
168.3
28 1 6 6 7/23/2019
168.3
168.3
29 1 6 6 7/23/2019
168.3
219.1
30 3 8 24 7/24/2019
219.1
31 HP Steam Drum to JB1104-50090101-ISO- 168.3 1 6 6 7/24/2019
HP PSH I/L Piping 0018 Rev.0 168.3
168.3
32 1 6 6 7/24/2019
168.3
168.3
33 7 6 42 7/25/2019
168.3
168.3
34 1 6 6 7/25/2019
168.3
168.3
35 1 6 6 7/25/2019
168.3
168.3
36 2 6 12 7/26/2019
168.3
168.3
37 1 6 6 7/26/2019
168.3
168.3
38 2 6 12 7/27/2019
168.3
39 HP Attemperator JB1104-50090101-ISO- 219.1 5 8 40 7/27/2019
Piping 0020 Rev.0 219.1
219.1
40 2 8 16 7/27/2019
219.1
168.3
41 2 6 12 7/27/2019
168.3
168.3
42 2 6 12 7/27/2019
42 2 6 12 7/27/2019
168.3
168.3
43 2 6 12 7/27/2019
168.3
168.3
44 2 6 12 7/27/2019
168.3
168.3
45 2 6 12 7/28/2019
168.3
168.3
46 1 6 6 7/28/2019
168.3
273
47 2 10 20 7/29/2019
HP Main Steam JB1104-50090101-ISO- 273
Piping 0022 Rev.0 273
48 2 10 20 7/29/2019
273
273
49 1 10 10 7/30/2019
273
168.3
50 1 6 6 7/30/2019
168.3
168.3
51 1 6 6 7/30/2019
168.3
273
52 1 10 10 7/30/2019
273

Sub Total 146 - 900

AQC INTEGRAL PIPING FOR SYNCHRO 7/26/2019

60.3
4 2 8 7/26/2019
60.3
60.3
3 2 6 7/27/2019
60.3
60.3
1 2 2 7/28/2019
JB1104-50090101-ISO- 60.3
CPH I/L Piping 0001 Rev.0 60.3
1 2 2 7/29/2019
60.3
60.3
3 2 6 7/30/2019
60.3
114.3
1 4 4 7/31/2019
114.3
60.3
4 2 8 7/26/2019
60.3
60.3
3 2 6 7/27/2019
60.3
60.3
2 2 4 7/28/2019
60.3
JB1104-50090101-ISO-
CPH O/L Piping 0002 Rev.0
JB1104-50090101-ISO- 60.3
CPH O/L Piping 0002 Rev.0
1 2 2 7/29/2019
60.3
114.3
3 4 12 7/30/2019
114.3
114.3
2 4 8 7/31/2019
114.3
114.3
1 4 4 8/1/2019
114.3
Sub Total 29 72

Total 175 972

Total groups in PH
updated on 20/7
Finish Group Group 25-Jul 26-Jul 27-Jul
Day Night
Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding
Dia Inch Dia Dia Inch Dia Dia Inch Dia
7/30/2019
7/20/2019
7/22/2019 16 24
G1 & G2 G3 & G4
7/22/2019

7/20/2019 24

7/21/2019

7/20/2019

7/21/2019 G5 & G6 G7 & G8 10 10

7/22/2019

7/22/2019 10

7/22/2019

7/23/2019

7/24/2019 2

7/24/2019

7/25/2019 G1 & G2 - 6

7/25/2019

7/25/2019 3

7/25/2019

7/23/2019

7/23/2019

7/23/2019

G5 & G6 G7 & G8
7/23/2019

7/23/2019 G5 & G6 G7 & G8

7/25/2019

7/25/2019

7/26/2019

7/26/2019

7/23/2019

7/23/2019

7/23/2019

7/24/2019

7/24/2019 G1 & G2 G3 & G4

7/24/2019

7/26/2019

7/25/2019

7/25/2019

7/26/2019

7/26/2019

7/27/2019

7/28/2019 G1 & G2 G3 & G4

7/27/2019

7/27/2019

7/27/2019
7/27/2019

7/27/2019

7/27/2019

7/28/2019

7/28/2019

7/29/2019
G5 & G6 G7 & G8
7/29/2019

7/30/2019

7/30/2019

7/30/2019

7/30/2019

71 34 0 0 0 0

8/1/2019

7/26/2019 G3

7/27/2019 G3

7/28/2019 G3

7/29/2019 G3

7/30/2019 G3

7/31/2019 G3

7/26/2019 G2

7/27/2019 G2

7/28/2019 G2
7/29/2019 G2

7/30/2019 G2

7/31/2019 G2

8/1/2019 G2

al groups in PH 8 nos.
28-Jul 29-Jul 30-Jul 31-Jul 1-Aug
Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding
Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia
0 0 0 0 0 0 0 0 0 0
2-Aug 3-Aug 4-Aug 5-Aug Cumulative
Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding
Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia

24 24
56 48
8 0
0 0

40 16

16 16

8 8

20 20

16 16

90 90

20 20

4 2

2 0

3 3

6 0

6 6

6 3

0 0

8 8

0 0

3 3
6 0

6 6

0 0

3 3

4 4

3 3

18 12

0 0

0 0

0 0

0 0

0 0

0 0

0 0

0 0

18 6

0 0

0 0

24 24

0 0

0 0

0 0
0 0

12 12

12 12

12 12

0 0

0 0

0 0

0 0

0 0

0 0

0 0

0 0 0 0 0 0 0 0 454 377
NTS FOR AQC BOILER (LP) PRESSURE PARTS & INTEGRAL PIPING (M/s. Bharathi Cement Corpo
PIPE/TUBE DETAIL No. OF
SL. Dia. in Total
BUTT
NO Field Weld Location Drawing Number Inches Inch Dia.
JOINTS

1 JB1104-50090101-ISO-0006 Rev.0 1 2 2

2 JB1104-50090101-ISO-0006 Rev.0 1 2 2
LP Drum I/L Piping
3 JB1104-50090101-ISO-0006 Rev.0 2 2 4

4 JB1104-50090101-ISO-0006 Rev.0 1 2 2

JB1104-50090101-ISO-0009 & 0010


5 Rev.0 4 6 24

JB1104-50090101-ISO-0009 & 0010


6 Rev.0 4 6 24

JB1104-50090101-ISO-0009 & 0010


7 Rev.0 4 6 24
LP Riser piping
JB1104-50090101-ISO-0009 & 0010
8 Rev.0 10 8 80

JB1104-50090101-ISO-0009 & 0010


9 Rev.0 8 8 64

JB1104-50090101-ISO-0009 & 0010


10 Rev.0 2 8 16

JB1104-50090101-ISO-0007 & 0008


11 Rev.0 2 6 12

JB1104-50090101-ISO-0007 & 0008


12 LP Downcomer piping Rev.0 2 6 12

JB1104-50090101-ISO-0007 & 0008


13 Rev.0 2 6 12

14 JB1104-50090101-ISO-0011 Rev.0 1 6 6

15 JB1104-50090101-ISO-0011 Rev.0 5 6 30

16 LP Drum to PSH I/L piping JB1104-50090101-ISO-0011 Rev.0 4 6 24

17 JB1104-50090101-ISO-0011 Rev.0 3 4 12

18 JB1104-50090101-ISO-0011 Rev.0 2 4 8

19 JB1104-50090101-ISO-0012 Rev.0 2 4 8
19 JB1104-50090101-ISO-0012 Rev.0 2 4 8

20 JB1104-50090101-ISO-0012 Rev.0 3 4 12

21 JB1104-50090101-ISO-0012 Rev.0 2 6 12

22 JB1104-50090101-ISO-0012 Rev.0 2 6 12
LP Main Steam Piping
23 JB1104-50090101-ISO-0012 Rev.0 1 6 6

24 JB1104-50090101-ISO-0012 Rev.0 3 3 9

25 JB1104-50090101-ISO-0012 Rev.0 1 3 3

26 JB1104-50090101-ISO-0012 Rev.0 1 6 6

27 JB1104-50090101-ISO-0025 Rev.0 1 3 3

28 JB1104-50090101-ISO-0025 Rev.0 1 3 3

29 JB1104-50090101-ISO-0025 Rev.0 2 3 6
Common Drain header
30 JB1104-50090101-ISO-0025 Rev.0 1 3 3

31 JB1104-50090101-ISO-0025 Rev.0 1 2 2

32 JB1104-50090101-ISO-0025 Rev.0 1 2 2

Total 80 - 445

175

900
updated on 21/7
Start Finish Group Day Group Night Group Night

7/20/2019 8/1/2019

7/20/2019 7/21/2019

7/20/2019 7/20/2019
G1 - -
7/20/2019 7/20/2019

7/20/2019 7/20/2019

7/20/2019 7/20/2019

7/20/2019 7/20/2019

7/21/2019 7/21/2019
G1 & G2 - G3
7/22/2019 7/22/2019

7/23/2019 7/23/2019

7/23/2019 7/23/2019

7/20/2019 7/20/2019

7/20/2019 7/20/2019 G2 - -

7/20/2019 7/20/2019

7/24/2019 7/24/2019

7/25/2019 7/25/2019

7/26/2019 7/26/2019 G1 & G2 -

7/27/2019 7/27/2019

7/28/2019 7/28/2019

7/29/2019 7/29/2019
7/29/2019 7/29/2019

7/29/2019 7/29/2019

7/29/2019 7/29/2019

7/30/2019 7/30/2019
G1 & G2 -
7/30/2019 7/30/2019

7/31/2019 7/31/2019

8/1/2019 8/1/2019

8/1/2019 8/1/2019

7/24/2019 7/24/2019

7/24/2019 7/24/2019

7/25/2019 7/25/2019
G3 -
7/26/2019 7/26/2019

7/26/2019 7/26/2019

7/26/2019 7/26/2019

Cumulative for HP & LP


Completed 20-Jul 21-Jul 22-Jul 23-Jul
Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Inch Fitup Inch Welding Fitup Inch
Dia Inch Dia Dia Inch Dia Dia Dia Dia Inch Dia Dia

16 8 8 16 16 16

64 64

16

12 12

12 6

12 6

6 6

6 6 12 12

6 6

4 4 8
4 4 8

92 80 52 0 32 8 42 40 30

193 175 92 30 54 18 152 108 92

Saturday Sunday
23-Jul 24-Jul 25-Jul 26-Jul 27-Jul
Welding Inch Fitup Inch Welding Inch Fitup Inch Welding Inch Fitup Inch Welding Fitup Inch Welding
Dia Dia Dia Dia Dia Dia Inch Dia Dia Inch Dia

24 24

18 18

24 24

16

6 12 12

12

8
8

12 12

12 6

38 0 0 90 86 46 18 0 0

126 48 52 161 120 46 18 0 0


28-Jul 29-Jul 30-Jul 31-Jul 1-Aug
Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding
Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
2-Aug 3-Aug 4-Aug 5-Aug Cumulative
Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Dia
Dia Inch Dia Dia Inch Dia Dia Inch Dia Dia Inch Dia

24

18

24

56

64

16

12

12

12

30

24

12

12
12

12

12

0 0 0 0 0 0 0 0 384

0 0 0 0 0 0 0 0

Cumulative HP & LP 838

Balance HP & LP 507

Days Balance -154.00

Asking Rate -3
Cumulative
Welding Inch
Dia

24

18

24

40

64

12

18

12
12

12

270

647

698
1/5/2020

-5
PIPING WORK SUMMARY
Area Total Inch Dia Completed Balance No of Gang Start Finish
Lube Oil Piping 1037 980 58 1 u/p 7/12/2019
NIBR Piping 4679 2692 1987 7 7/12/2019 8/13/2019
ACC Piping 558 344 214 1 u/p 7/18/2019
Sub Total 6275 4016 2259 9
IBR Piping 1904 0 1904 4 7/17/2019 8/14/2019
AQC Integral 1345 193 1152 6 7/20/2019 7/30/2019
AQC BHP 1251 1251 3 7/17/2019 8/10/2019
PH Integral 2215 2215
PH BHP 734 734
Sub Total 7449 193 7256 13
Total 13724 4209 9515 22
Duration Avail @14/7 To be added
2 VT-1
32 Ambica-1 Turbotech-1 VSR-1 3 1 Turb
8 Ambica-1 1

28 Reco-2 2 2 Reco
10 Mechno-4 LES-2 6
24 3 Les
12
WTP Commissioning
Sr. Activity Area Start Finish
1 Softner to MGF tank piping connection Mech 7/15/2019 7/18/2019
2 MGF tank to UF piping connection Mech 7/15/2019 7/18/2019
3 Motor trial Mech 7/17/2019 7/21/2019
4 Backfilling in degasser area Civil u/p 7/13/2019
Pump foundation casting - BIF, DM, Service Civil u/p 7/13/2019
5 water, Potable water
Pump installation - BIF, DM, Service water, Mech 7/14/2019 7/15/2019
6 Potable water
7 Sheeting Civil 7/13/2019 7/19/2019
8 Instrumentation work E&I
9 Pumps electrical connection E&I
10 Chemicals Mech
11 Flooring & tiles Civil
12

Motor trials 7/18/2019 7/23/2019


Back flushing of MGF vessel 7/19/2019 7/20/2019
Charging upto UF 7/21/2019 7/22/2019
Installation of RO Membrane 7/23/2019 7/25/2019
Charging of Chemicals 7/26/2019 7/28/2019
DM water generation 7/29/2019 8/1/2019
Charging & Commissioning of DCS 7/25/2019 7/27/2019
Taking Dm Plant on auto thru DCS 7/28/2019 8/2/2019
Sr. Item Vendor Location of Expected Expected
Dispatch Dispatch date Arrival at site
1 ACC
1.1 Gear Box Premier Kolkata 7/22/2019 7/29/2019
1.2 Motors Crompton Ahmednagar
1.3 ACC E & I related cables Received at site on 13/7/19
1.4 ACC JB's Received at site on 13/7/19
1.5 ACC Field Instruments in transit 7/19/2019
2 AQC Boiler Integral Piping YNR in transit
3 AQC Dampers Bachman
4 UPS system Vertix Pune
5 Motors
5.1 BFP
5.2 ACC
5.3 CEP
6 Roof sheeting GEE AAR Delhi
7 Boiler house piping (12 MT) Flash Point Pune
Erection completion
as per schedule

7/25/2019
7/25/2019
Sl. No Tag No Description

97 1BD406 STEAM DRUM CBD BYPASS ISOLATION VALVE

111 1DD409 1PI-404 ISOLATION VALVE


147 1FF401 MAIN STEAM LINE VENT ISOLATION VALVE
152 1FF406 1PI-409 ISOLATION VALVE
153 1FF407 1PT-402 ISOLATION VALVE
154 1FF408 STARTUP LINE UPSTREAM ISOLATION VALVE
156 1FF410 STARTUP VENT LINE DRAIN ISOLATION VALVE

157 1FF411 MAIN STEAM SAMPLING LINE ISOLATION VALVE

158 1FF412 MAIN STEAM SAMPLING LINE ISOLATION VALVE

159 1FF413 1PI-410 ISOLATION VALVE


160 1FF414 MSSV AT MAIN STEAM LINE
MSSV INTEGRAL BYPASS VALVE AT MAIN STEAM
161 1FF415
LINE
229 1FF509 STARTUP VENT ISOLATION VALVE
233 1FF513 MSSV VALVE
234 1FF514 INTEGRAL BYPASS VALVE FOR MSSV
ISOLATION VALVE FOR HP DOSING LINE IN LP
236 1QQ502
STEAM DRUM
Location Expected
Medium Vendor of arrival at
Dispatch site

BLOWDOWN

MEDIUM PRESSURE STEAM


MEDIUM PRESSURE STEAM
MEDIUM PRESSURE STEAM
MEDIUM PRESSURE STEAM
MEDIUM PRESSURE STEAM
MEDIUM PRESSURE STEAM

MEDIUM PRESSURE STEAM

MEDIUM PRESSURE STEAM

MEDIUM PRESSURE STEAM


MEDIUM PRESSURE STEAM

MEDIUM PRESSURE STEAM

LOW PRESSURE STEAM


MEDIUM PRESSURE STEAM
LOW PRESSURE STEAM

HIGH PRESSURE DOSING


AQC BHP PIPING SCHEDULE
PIPE DETAIL
SL. NO
Field Weld Location

ISOMETRIC FOR BOILER FEED


SUCTION PIPING FROM
1 DEAERATOR TO SUCTION HEADER
ISOMETRIC
INLET FOR INDIVIDUAL
2 SUCTION PIPING FROM BFP
SUCTION HEADER TO BOILER-1
ISOMETRIC
FEED PUMPFOR INDIVIDUAL
INLET.
SUCTION PIPING FROM BFP
3 SUCTION HEADER TO BOILER-2
FEED PUMP INLET.
ISOMETRIC FOR INDIVIDUAL
4 DISCHARGE PIPING FROM BFP 1 &
2 TO DISCHARGE HEADER I/L.

ISOMETRIC FOR BFP DISCHARGE


5 PIPING FROM BFP DISCHAGRE
HEADER OUTLET TO FLOW
CONTROL VALVE INLET (1FCV401)
ISOMETRIC FOR BFP DISCHARGE
PIPING FROM CONTROL VALVE
6 OUTLET (1FCV401) TO
ECONOMISER INLET( AQC BOILER)
ISOMETRIC FOR BFP DISCHARGE
7 PIPING FROM CONTROL VALVE
OUTLET (1FCV401) TO
ECONOMISER INLET( AQC BOILER)

8 ISOMETRIC FOR AQC BOILER CPH


OUTLET TO DEA. 1TP501

9 ISOMETRIC FOR CPH INLET FROM


CEP DISCHARGE TP1502
9 ISOMETRIC FOR CPH INLET FROM
CEP DISCHARGE TP1502

10 ISOMETRIC FOR CPH BYE PASS


LINE

ISOMETRIC FOR DEAEARATOR


11 OVER FLOW AND DRAIN PIPING
TO 1TP-203
ISOMETRIC FOR HP SUPERHEATER
12 STEAM PIPING FROM MSSV
OUTLET TO FOR
1TP304
ISOMETRIC LP SUPERHEATER
13 STEAM PIPING FROM MSSV
OUTLET TO 1TP503

ISOMETRIC FOR AUXILIARY STEAM


14 PIPING FROM 1TP202 TO
DEAERATOR

ISOMETRIC FOR HP STEAM MAIN


15 STEAM LINE START UP VENT
EXHAUST PIPING TO SLIENCER

ISOMETRIC FOR LP STEAM MAIN


16 STEAM LINE START UP VENT
EXHAUST PIPING TO SLIENCER

17 ISOMETRIC FOR AQC BOILER CPH


OUTLET TO DEAERATOR
17 ISOMETRIC FOR AQC BOILER CPH
OUTLET TO DEAERATOR

18 ISOMETRIC FOR AQC BOILER CPH


OUTLET TO DEAERATOR

19 ISOMETRIC FOR AQC BOILER CPH


OUTLET TO DEA. 1TP501

20 ISOMETRIC FOR CPH INLET FROM


CEP DISCHARGE TP1502
ISOMETRIC FOR BFP DISCHARGE
21 PIPING FROM CONTROL VALVE
OUTLET (1FCV401) TO
ECONOMISER INLET( AQC BOILER)
22 HP steam MS Line safety valve -1 to
23 Boiler initial filling line from 1TP 30
24 CBD tank Vent piping to ATM
25 CBD tank drain piping upto trench
26 Common drain HDR to CBD tank I/L
27 Deaerator tank safety valve exhaust
28 LP steam MS Line safety valve -1 to
AQC BHP PIPING SCHEDULE
PIPE DETAIL No. OF Dia. in Total FITUP
SIZE BUTT
Drawing Number Inches Inch Dia. COMPLETED
OD (mm) JOINTS

219.1
JB1104-50090401-ISO-0001 Rev.1 4 8 32 0
219.1
219.1
JB1104-50090401-ISO-0002 Rev.1 8 8 64 0
219.1
219.1
JB1104-50090401-ISO-0003 Rev.1 7 8 56 0
219.1
73
2 3 6 0
73
JB1104-50090401-ISO-0004 Rev.1
168.3
10 6 60 10
168.3
88.9
1 3 3 3
88.9
JB1104-50090401-ISO-0005 Rev.1
168.3
13 6 78 32
168.3
88.9
JB1104-50090401-ISO-0006 Rev.1 8 3 24 0
88.9

88.9
14 3 42 0
88.9
JB1104-50090401-ISO-0007 Rev.1
60.3
2 2 4 0
60.3
114.3
JB1104-50090401-ISO-0012 Rev.0 11 4 44 0
114.3
114.3
JB1104-50090401-ISO-0013 Rev.0 8 4 32 0
JB1104-50090401-ISO-0013 Rev.0 8 4 32 0
114.3
114.3
JB1104-50090401-ISO-0014 Rev.0 6 4 24 0
114.3
88.9
7 3 21 0
88.9
JB1104-50090401-ISO-0015 Rev.0
219.1
11 8 88 0
219.1
273.1
JB1104-50090401-ISO-0016 Rev.2 3 10 30 0
273.1
168.3
JB1104-50090401-ISO-0017 Rev.1 8 6 48 0
168.3
88.9
2 3 6 0
88.9
114.3
JB1104-50090401-ISO-0018 Rev.1 9 4 36 0
114.3
168.3
8 6 48 0
168.3
168.3
4 6 24 0
168.3
273.1
JB1104-50090401-ISO-0020 Rev.1 2 10 20 0
273.1
323.9
7 12 84 0
323.9
88.9
3 3 9 0
88.9
JB1104-50090401-ISO-0022 Rev.1
168.3
5 6 30 0
168.3
114.3
JB1104-50090401-ISO-0028 Rev.0 11 4 44 0
JB1104-50090401-ISO-0028 Rev.0 11 4 44 0
114.3
114.3
JB1104-50090401-ISO-0029 Rev.0 9 4 36 0
114.3
114.3
JB1104-50090401-ISO-0030 Rev.0 5 4 20 0
114.3
114.3
JB1104-50090401-ISO-0031 Rev.0 14 4 56 0
114.3
88.9
JB1104-50090401-ISO-0032 Rev.1 10 3 30 0
88.9
JB1104-50090401-ISO-019 5 8 40 0
JB1104-50090401-ISO-027 11 3 33 0
JB1104-50090401-ISO-008 3 3 9 0
JB1104-50090401-ISO-009 15 2 30 0
JB1104-50090401-ISO-010 9 3 27 0
JB1104-50090401-ISO-011 1 4 4 0
JB1104-50090401-ISO-021 5 8 40 0
Total 261 - 1282 45
WELDING COMPLETION Duration Start Finish No of Suports Group
NO. OF INCH %
JOINTS DIA COMPLETION

24 7/17/2019 8/10/2019

0 0 0.00 4 7/30/2019 8/3/2019 G4

0 0 0.00 5 7/30/2019 8/4/2019 G5

0 0 0.00 4 7/30/2019 8/3/2019 G6

0 0 0.00 1 7/17/2019 7/17/2019 G1

4 24 40.00 3 7/17/2019 7/19/2019 G2

1 3 100.00 1 7/18/2019 7/18/2019 G3

0 0 0.00 4 7/18/2019 7/21/2019 G1

0 0 0.00 1 7/20/2019 7/20/2019 G2

0 0 0 2 7/19/2019 7/20/2019 G3

0 0 0 1 7/22/2019 7/22/2019 G1

0 0 0.00 3 7/21/2019 7/23/2019 G2

0 0 0.00 2 7/21/2019 7/22/2019 G3


0 0 0.00 2 7/21/2019 7/22/2019 G3

0 0 0.00 2 7/23/2019 7/24/2019 G1

0 0 0.00 2 7/24/2019 7/25/2019 G2

0 0 0.00 4 7/23/2019 7/26/2019 G3

0 0 0.00 2 7/25/2019 7/26/2019 G4

0 0 0.00 4 7/25/2019 7/28/2019 G5

0 0 0.00 2 7/25/2019 7/26/2019 G1

0 0 0.00 2 7/26/2019 7/27/2019 G2

0 0 0.00 4 7/27/2019 7/30/2019 G3

0 0 0.00 2 7/27/2019 7/28/2019 G4

0 0 0.00 2 7/29/2019 7/30/2019 G5

0 0 0.00 5 7/27/2019 7/31/2019 G1

0 0 0.00 1 7/29/2019 7/29/2019 G4

0 0 0.00 2 7/28/2019 7/29/2019 G2

0 0 0.00 4 7/31/2019 8/3/2019 G3


0 0 0.00 4 7/31/2019 8/3/2019 G3

0 0 0.00 3 8/1/2019 8/3/2019 G1

0 0 0 2 7/30/2019 7/31/2019 G2

0 0 0 4 8/1/2019 8/4/2019 G2

0 0 0 2 8/4/2019 8/5/2019 G3

0 0 0 3 8/4/2019 8/7/2019 G4
11 33 100 2 8/5/2019 8/7/2019 G5
0 0 0 1 8/4/2019 8/5/2019 G6
0 0 0 2 8/4/2019 8/6/2019 G1
0 0 0 2 8/5/2019 8/7/2019 G2
0 0 0 1 8/6/2019 8/7/2019 G3
0 0 0 2 8/8/2019 8/10/2019 G4
16 60 4.68
7/23/2019
Status

u/p

u/p

u/p

u/p
u/p
Completed 7/23/2019 7/24/2019 7/25/2019 7/26/2019

Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch
dia Inch dia dia Inch dia dia Inch dia dia Inch dia dia

60 24

18
78 24 0 0 0 0 0 0 0
78 0 0 0 0
24 0 0 0
/26/2019 7/27/2019 7/28/2019 7/29/2019 7/30/2019 7/31/2019

Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch
Inch dia dia Inch dia dia Inch dia dia Inch dia dia Inch dia dia
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
/31/2019 8/1/2019 8/2/2019 8/3/2019 8/4/2019 8/5/2019

Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch
Inch dia dia Inch dia dia Inch dia dia Inch dia dia Inch dia dia

24

12 1 1
0 19 0 1 0 1 0 0 0 32
19 1 1 0 32
0 0 0 0 0
8/5/2019 8/6/2019 8/7/2019 8/8/2019 8/9/2019 8/10/2019

Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch Welding Fitup Inch
Inch dia dia Inch dia dia Inch dia dia Inch dia dia Inch dia dia

30

36
66 0 0 0 0 0 0 0 0 0
0 0 0 0 0
66 0 0 0 0
/10/2019

Welding
Inch dia
0
131 Total fitup completed
0 90 Total welding completed
INSULATION WORK SCHEDULE
Sr. Area UOM Qty Start Finish
1 AQC Casing
2 AQC outlet duct
3 AQC Integral piping
4 AQC BHP piping
5 IBR piping
REFRACTORY WORK SCHEDULE
Sr. Area UOM Qty Start Finish
1 AQC inlet duct
2 AQC hopper