PROGRAMME OF WORKS FOR PROPOSED RENOVATION OF COMMUNITY CENTER AT KNUST-KUMASI

ID Task Name Duration Start Finish Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 PROPOSED RENOVATION OF COMMUNITY CENTER AT 269 days Sat 9/21/19 Thu 8/20/20
KNUST-KUMASI
2 DEMOLITION AND ALTERATION WORKS
3 Community centre and Community library works 51.56 days Sat 9/21/19 Sat 11/23/19
4 Removal and installation of floor tiles and hacking off surface 4 days Sat 9/21/19 Thu 9/26/19
5 Removal and installation of wall tiles and hacking off surface 4 days Thu 9/26/19 Tue 10/1/19
6 Surface preparation 3 days Tue 10/1/19 Fri 10/4/19
7 Removal and installation of defective door and windows 4 days Fri 10/4/19 Thu 10/10/19
8 Removal and installation of louvre carriers 3 days Thu 10/10/19 Mon 10/14/19
9 Removal and installation of rotten timber T & G ceiling strips 4 days Mon 10/14/19 Fri 10/18/19
10 Removal and installation of defective cover battens 3 days Fri 10/18/19 Tue 10/22/19
11 Removal and installation of defective mosquito proof aluminium gauze 3 days Tue 10/22/19 Fri 10/25/19
netting
12 Removal and installation of Water closets 2 days Fri 10/25/19 Tue 10/29/19
13 Removal and installation of wash hand basins 2 days Tue 10/29/19 Thu 10/31/19
14 Removal and installation of timber framed windows 4 days Thu 10/31/19 Tue 11/5/19
15 Removal and installation of timber framed doors with fanlights 4 days Tue 11/5/19 Sat 11/9/19
16 Removal and installation of defective doors 3 days Mon 11/11/19 Wed 11/13/19
17 Removal and installation of defective doors with side windows 4 days Thu 11/14/19 Tue 11/19/19
18 Demolition of defective u-drain and disposal off-site 4 days Tue 11/19/19 Sat 11/23/19
19 NEW WORKS
20 Community centre and Community children library works
21 Concrete works 32.75 days Sat 11/23/19 Thu 1/2/20
22 Site preparations 3 days Sat 11/23/19 Wed 11/27/19
23 Column formworks 3 days Fri 11/29/19 Tue 12/3/19
24 Column reinforcement works 3 days Tue 12/3/19 Fri 12/6/19
25 Casting of rc. columns 4 days Fri 12/6/19 Wed 12/11/19
26 Beam formworks 3 days Wed 12/11/19 Mon 12/16/19
27 Beams reinforcement works 2 days Mon 12/16/19 Wed 12/18/19
28 Casting of rc. beams 4 days Wed 12/18/19 Mon 12/23/19
29 Slabs formworks 2 days Mon 12/23/19 Wed 12/25/19
30 Slabs reinforcement works 3 days Wed 12/25/19 Sat 12/28/19
31 Casting of rc. Slabs 4 days Sat 12/28/19 Thu 1/2/20
32 Blockworks 6.63 days Fri 1/3/20 Fri 1/10/20
33 Laying and curing of 150mm blocks at indenticated areas in drawing. 6.63 days Fri 1/3/20 Fri 1/10/20
34 Carpentry works 10.25 days Fri 1/10/20 Wed 1/22/20
35 Fixing of ridge boards 3 days Fri 1/10/20 Tue 1/14/20
36 Fixing of rafters 2 days Tue 1/14/20 Wed 1/15/20
37 Fixing of purlins 3 days Tue 1/14/20 Fri 1/17/20
38 Fixing of ceiling joist and hangers 4 days Fri 1/17/20 Wed 1/22/20
39 Roofing works 4 days Thu 1/23/20 Tue 1/28/20
40 Installation of roof coverings with ridge cappings and hip cappings 4 days Thu 1/23/20 Tue 1/28/20
41 Joinery works 8.63 days Wed 1/29/20 Fri 2/7/20
42 Installation of doors,battens and windows and associated ironmongery 9 days Tue 1/28/20 Fri 2/7/20
43 Metal works 4.63 days Sat 2/8/20 Thu 2/13/20
44 Installation of mosquiqto proof netting and loure carriers 4 days Fri 2/7/20 Thu 2/13/20
45 Plumbing installation works 4.63 days Fri 2/14/20 Wed 2/19/20
46 Installation of wc suit,wash hand basin,roll holder,mounted dispenser and 5 days Wed 2/12/20 Wed 2/19/20
wall mounted mirrors
47 Electrical Installation works 10.25 days Thu 2/20/20 Tue 3/3/20
48 Conduiting and Installation of distribution gears 3 days Wed 2/19/20 Sat 2/22/20
49 Wiring of points,and running of wires in conduits 4 days Sat 2/22/20 Thu 2/27/20
50 Installation of fixtures(Accessories) 4 days Thu 2/27/20 Tue 3/3/20
51 Finishings 18.88 days Wed 3/4/20 Thu 3/26/20
52 Backing to receive wall tiles 2 days Wed 3/4/20 Thu 3/5/20
53 Bedding to receive floor tiles 2 days Fri 3/6/20 Mon 3/9/20
54 Laying of floor tiles and skirtings 4 days Tue 3/10/20 Fri 3/13/20
55 Laying of wall tiles 4 days Sat 3/14/20 Thu 3/19/20
56 Fixing of plasterboard ceiling to members 5 days Fri 3/20/20 Thu 3/26/20
57 Glazing works 11.25 days Fri 3/27/20 Thu 4/9/20
58 Installation of glazed windows 3 days Fri 3/27/20 Tue 3/31/20
59 Installation of double swing doors with funlights 4 days Wed 4/1/20 Mon 4/6/20
60 Installation of sliding door 3 days Tue 4/7/20 Thu 4/9/20
61 Painting and decoration works 17.88 days Fri 4/10/20 Fri 5/1/20
62 Preparing surface 2 days Fri 4/10/20 Mon 4/13/20
63 Application of first coat emulsion paint to external surfaces of wall and 3 days Tue 4/14/20 Thu 4/16/20
sides and soffit of ceiling
64 Application of second and third coat emulsion paint to external surfaces 5 days Fri 4/17/20 Thu 4/23/20
and sides and soffit of ceiling
65 Application of first coat emulsion paint to internal surfaces of wall 3 days Fri 4/24/20 Tue 4/28/20
66 Application of oil paint on general wood surfaces and generaal surfaces of 3 days Wed 4/29/20 Fri 5/1/20
metal
67 EXTERNAL WORKS
68 Drainage works 29.13 days Sat 5/2/20 Mon 6/8/20
69 Site preparation for U-drains and Roads 3 days Sat 5/2/20 Wed 5/6/20
70 Excavation for trenches 3 days Thu 5/7/20 Mon 5/11/20
71 Formworks to receive concrete 4 days Tue 5/12/20 Fri 5/15/20
72 Casting of Plain concrete 7 days Sat 5/16/20 Mon 5/25/20
73 Backfilling and compaction works 5 days Tue 5/26/20 Mon 6/1/20
74 Positioning of Precast concrete cover slabs 2 days Tue 6/2/20 Wed 6/3/20
75 Apron works 3 days Thu 6/4/20 Mon 6/8/20
76 Road works 20.88 days Tue 6/9/20 Fri 7/3/20
77 Preparing sub-grade for to receive upper layers 2 days Tue 6/9/20 Wed 6/10/20
78 Laying of sub-base material 2 days Thu 6/11/20 Fri 6/12/20
79 Laying of base material 2 days Sat 6/13/20 Tue 6/16/20
80 Spraying of binder on base material 2 days Wed 6/17/20 Thu 6/18/20
81 Application of primer seals 2 days Fri 6/19/20 Mon 6/22/20
82 Side kerb works 3 days Tue 6/23/20 Thu 6/25/20
83 Laying of Precast paving bricks 6 days Fri 6/26/20 Fri 7/3/20
84 Lanscaping works 11.25 days Sat 7/4/20 Fri 7/17/20
85 Removal of turf and leveling works 3 days Sat 7/4/20 Wed 7/8/20
86 Application of Loamy soils 3 days Thu 7/9/20 Mon 7/13/20
87 Planting of grass and watering to required optimum 4 days Tue 7/14/20 Fri 7/17/20
88 Septic tank works 27.13 days Sat 7/18/20 Thu 8/20/20
89 Excavation of septic tank pit 1 day Sat 7/18/20 Mon 7/20/20
90 Blinding works for septic tank 1 day Tue 7/21/20 Tue 7/21/20
91 Laying of septic tank walls 2 days Wed 7/22/20 Thu 7/23/20
92 Formwork for septic tank slab 2 days Fri 7/24/20 Mon 7/27/20
93 Reinforcement works for septic tank slab 3 days Tue 7/28/20 Thu 7/30/20
94 Casting of rc septic tank slab 2 days Fri 7/31/20 Mon 8/3/20
95 Internal screeding and rendering works 3 days Tue 8/4/20 Thu 8/6/20
96 Backfilling and removal of surplus material from site 2 days Fri 8/7/20 Mon 8/10/20
97 General site cleaning 4 days Tue 8/11/20 Fri 8/14/20
98 Testing and comissioning 3 days Sat 8/15/20 Wed 8/19/20
99 Handover 1 day Thu 8/20/20 Thu 8/20/20