PROGRAMME OF WORKS FOR PROPOSED RENOVATION OF COMMUNITY CENTER AT KNUST-KUMASI

ID Task Name Duration Rounded duration Start Finish p '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20
8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 3
1 PROPOSED RENOVATION OF COMMUNITY CENTER AT 269 days 269days Sat 9/21/19 Thu 8/20/20
KNUST-KUMASI
2 DEMOLITION AND ALTERATION WORKS 51.56 days 52days Sat 9/21/19 Sat 11/23/19
3 Community centre and Community library works 51.56 days 52days Sat 9/21/19 Sat 11/23/19
4 Removal and installation of floor tiles and hacking off surface 4 days 4days Sat 9/21/19 Thu 9/26/19
5 Removal and installation of wall tiles and hacking off surface 4 days 4days Thu 9/26/19 Tue 10/1/19
6 Surface preparation 3 days 3days Tue 10/1/19 Fri 10/4/19
7 Removal and installation of defective door and windows 4 days 4days Fri 10/4/19 Thu 10/10/19
8 Removal and installation of louvre carriers 3 days 3days Thu 10/10/19 Mon 10/14/19
9 Removal and installation of rotten timber T & G ceiling strips 4 days 4days Mon 10/14/19 Fri 10/18/19
10 Removal and installation of defective cover battens 3 days 3days Fri 10/18/19 Tue 10/22/19
11 Removal and installation of defective mosquito proof aluminium gauze 3 days 3days Tue 10/22/19 Fri 10/25/19
netting
12 Removal and installation of Water closets 2 days 2days Fri 10/25/19 Tue 10/29/19
13 Removal and installation of wash hand basins 2 days 2days Tue 10/29/19 Thu 10/31/19
14 Removal and installation of timber framed windows 4 days 4days Thu 10/31/19 Tue 11/5/19
15 Removal and installation of timber framed doors with fanlights 4 days 4days Tue 11/5/19 Sat 11/9/19
16 Removal and installation of defective doors 3 days 3days Mon 11/11/19 Wed 11/13/19
17 Removal and installation of defective doors with side windows 4 days 4days Thu 11/14/19 Tue 11/19/19
18 Demolition of defective u-drain and disposal off-site 4 days 4days Tue 11/19/19 Sat 11/23/19
19 NEW WORKS 1 day 1days Sat 9/21/19 Mon 9/23/19
20 Community centre and Community children library works 32.75 days 33days Sat 11/23/19 Thu 1/2/20
21 Concrete works 32.75 days 33days Sat 11/23/19 Thu 1/2/20
22 Site preparations 3 days 3days Sat 11/23/19 Wed 11/27/19
23 Column formworks 3 days 3days Fri 11/29/19 Tue 12/3/19
24 Column reinforcement works 3 days 3days Tue 12/3/19 Fri 12/6/19
25 Casting of rc. columns 4 days 4days Fri 12/6/19 Wed 12/11/19
26 Beam formworks 3 days 3days Wed 12/11/19 Mon 12/16/19
27 Beams reinforcement works 2 days 2days Mon 12/16/19 Wed 12/18/19
28 Casting of rc. beams 4 days 4days Wed 12/18/19 Mon 12/23/19
29 Slabs formworks 2 days 2days Mon 12/23/19 Wed 12/25/19
30 Slabs reinforcement works 3 days 3days Wed 12/25/19 Sat 12/28/19
31 Casting of rc. Slabs 4 days 4days Sat 12/28/19 Thu 1/2/20
32 Blockworks 6.63 days 7days Fri 1/3/20 Fri 1/10/20
33 Laying and curing of 150mm blocks at indenticated areas in drawing. 6.63 days 7days Fri 1/3/20 Fri 1/10/20
34 Carpentry works 10.25 days 10days Fri 1/10/20 Wed 1/22/20
35 Fixing of ridge boards 3 days 3days Fri 1/10/20 Tue 1/14/20
36 Fixing of rafters 2 days 2days Tue 1/14/20 Wed 1/15/20
37 Fixing of purlins 3 days 3days Tue 1/14/20 Fri 1/17/20
38 Fixing of ceiling joist and hangers 4 days 4days Fri 1/17/20 Wed 1/22/20
39 Roofing works 4 days 4days Thu 1/23/20 Tue 1/28/20
40 Installation of roof coverings with ridge cappings and hip cappings 4 days 4days Thu 1/23/20 Tue 1/28/20
41 Joinery works 8.63 days 9days Wed 1/29/20 Fri 2/7/20
42 Installation of doors,battens and windows and associated ironmongery 9 days 9days Tue 1/28/20 Fri 2/7/20
43 Metal works 4.63 days 5days Sat 2/8/20 Thu 2/13/20
44 Installation of mosquiqto proof netting and loure carriers 4 days 4days Fri 2/7/20 Thu 2/13/20
45 Plumbing installation works 4.63 days 5days Fri 2/14/20 Wed 2/19/20
46 Installation of wc suit,wash hand basin,roll holder,mounted dispenser and 5 days 5days Wed 2/12/20 Wed 2/19/20
wall mounted mirrors
47 Electrical Installation works 10.25 days 10days Thu 2/20/20 Tue 3/3/20
48 Conduiting and Installation of distribution gears 3 days 3days Wed 2/19/20 Sat 2/22/20
49 Wiring of points,and running of wires in conduits 4 days 4days Sat 2/22/20 Thu 2/27/20

Page 1
PROGRAMME OF WORKS FOR PROPOSED RENOVATION OF COMMUNITY CENTER AT KNUST-KUMASI
ID Task Name Duration Rounded duration Start Finish p '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20
8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 3
50 Installation of fixtures(Accessories) 4 days 4days Thu 2/27/20 Tue 3/3/20
51 Finishings 18.88 days 19days Wed 3/4/20 Thu 3/26/20
52 Backing to receive wall tiles 2 days 2days Wed 3/4/20 Thu 3/5/20
53 Bedding to receive floor tiles 2 days 2days Fri 3/6/20 Mon 3/9/20
54 Laying of floor tiles and skirtings 4 days 4days Tue 3/10/20 Fri 3/13/20
55 Laying of wall tiles 4 days 4days Sat 3/14/20 Thu 3/19/20
56 Fixing of plasterboard ceiling to members 5 days 5days Fri 3/20/20 Thu 3/26/20
57 Glazing works 11.25 days 11days Fri 3/27/20 Thu 4/9/20
58 Installation of glazed windows 3 days 3days Fri 3/27/20 Tue 3/31/20
59 Installation of double swing doors with funlights 4 days 4days Wed 4/1/20 Mon 4/6/20
60 Installation of sliding door 3 days 3days Tue 4/7/20 Thu 4/9/20
61 Painting and decoration works 17.88 days 18days Fri 4/10/20 Fri 5/1/20
62 Preparing surface 2 days 2days Fri 4/10/20 Mon 4/13/20
63 Application of first coat emulsion paint to external surfaces of wall and 3 days 3days Tue 4/14/20 Thu 4/16/20
sides and soffit of ceiling
64 Application of second and third coat emulsion paint to external surfaces 5 days 5days Fri 4/17/20 Thu 4/23/20
and sides and soffit of ceiling
65 Application of first coat emulsion paint to internal surfaces of wall 3 days 3days Fri 4/24/20 Tue 4/28/20
66 Application of oil paint on general wood surfaces and generaal surfaces of 3 days 3days Wed 4/29/20 Fri 5/1/20
metal
67 EXTERNAL WORKS 29.13 days 29days Sat 5/2/20 Mon 6/8/20
68 Drainage works 29.13 days 29days Sat 5/2/20 Mon 6/8/20
69 Site preparation for U-drains and Roads 3 days 3days Sat 5/2/20 Wed 5/6/20
70 Excavation for trenches 3 days 3days Thu 5/7/20 Mon 5/11/20
71 Formworks to receive concrete 4 days 4days Tue 5/12/20 Fri 5/15/20
72 Casting of Plain concrete 7 days 7days Sat 5/16/20 Mon 5/25/20
73 Backfilling and compaction works 5 days 5days Tue 5/26/20 Mon 6/1/20
74 Positioning of Precast concrete cover slabs 2 days 2days Tue 6/2/20 Wed 6/3/20
75 Apron works 3 days 3days Thu 6/4/20 Mon 6/8/20
76 Road works 20.88 days 21days Tue 6/9/20 Fri 7/3/20
77 Preparing sub-grade for to receive upper layers 2 days 2days Tue 6/9/20 Wed 6/10/20
78 Laying of sub-base material 2 days 2days Thu 6/11/20 Fri 6/12/20
79 Laying of base material 2 days 2days Sat 6/13/20 Tue 6/16/20
80 Spraying of binder on base material 2 days 2days Wed 6/17/20 Thu 6/18/20
81 Application of primer seals 2 days 2days Fri 6/19/20 Mon 6/22/20
82 Side kerb works 3 days 3days Tue 6/23/20 Thu 6/25/20
83 Laying of Precast paving bricks 6 days 6days Fri 6/26/20 Fri 7/3/20
84 Lanscaping works 11.25 days 11days Sat 7/4/20 Fri 7/17/20
85 Removal of turf and leveling works 3 days 3days Sat 7/4/20 Wed 7/8/20
86 Application of Loamy soils 3 days 3days Thu 7/9/20 Mon 7/13/20
87 Planting of grass and watering to required optimum 4 days 4days Tue 7/14/20 Fri 7/17/20
88 Septic tank works 27.13 days 27days Sat 7/18/20 Thu 8/20/20
89 Excavation of septic tank pit 1 day 1days Sat 7/18/20 Mon 7/20/20
90 Blinding works for septic tank 1 day 1days Tue 7/21/20 Tue 7/21/20
91 Laying of septic tank walls 2 days 2days Wed 7/22/20 Thu 7/23/20
92 Formwork for septic tank slab 2 days 2days Fri 7/24/20 Mon 7/27/20
93 Reinforcement works for septic tank slab 3 days 3days Tue 7/28/20 Thu 7/30/20
94 Casting of rc septic tank slab 2 days 2days Fri 7/31/20 Mon 8/3/20
95 Internal screeding and rendering works 3 days 3days Tue 8/4/20 Thu 8/6/20
96 Backfilling and removal of surplus material from site 2 days 2days Fri 8/7/20 Mon 8/10/20
97 General site cleaning 4 days 4days Tue 8/11/20 Fri 8/14/20
98 Testing and comissioning 3 days 3days Sat 8/15/20 Wed 8/19/20

Page 2
PROGRAMME OF WORKS FOR PROPOSED RENOVATION OF COMMUNITY CENTER AT KNUST-KUMASI
ID Task Name Duration Rounded duration Start Finish p '19 Oct '19 Nov '19 Dec '19 Jan '20 Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20
8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 3
99 Handover 1 day 1days Thu 8/20/20 Thu 8/20/20

Page 3