Documente Academic
Documente Profesional
Documente Cultură
Gestão da Produção
2019/2020
4. Methods Engineering
4.2 Work Measurement &
Standardized Work
Course included in
Work Measurement
• Methods and Time study is the one element in scientific management beyond
all others making possible the transfer of skill from management to men…
Frederick W. Taylor
Work Measurement
• Time definitions
– Cycle time or Throughput rate
• Time beween two consecutive products (end of the line)
– (Cycle time)-1 = Production rate (units produced per unit of time)
ppecas@tecnico.ulisboa.pt
3
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Times computing
N
– Measured time: t medido t i
• N number of registries
• ti individual registry
t medido FA
– Normal time:
t te
• FA Performance rating normal
• ε equipment efficiency
• te systematic production related elements
ppecas@tecnico.ulisboa.pt
4
Production Management
Methods Engineering Gestão da Produção
– Work sampling
• for non-cyclic operations
Z f (1 f )
2
• for too short operations N 2
p
ppecas@tecnico.ulisboa.pt
Tom Best 5
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Measurement techniques
– Pre-determined Time systems
https://www.ies.ncsu.edu/
Patricia White
ppecas@tecnico.ulisboa.pt
6
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Stop-Watch application example
– Consider an operation composed by 3 elements:
• Element 1 - Part loading (manual)
• Element 2 - Part machining (autonomous)
• Element 3 - Part unloading (manual)
– First step: Estimate the average time of each element
• Element 1 – around 15 min Cycle time
Run times
• Element 2 – around 20 min (min)
0,1 200
• Element 3 – around 8 min 0,25 100
0,5 60
0,75 40
Following a practical method (table), 1,0 30
10 measures are preliminarily recommended 2,0 20
5,0 15
10,0 10
20,0 8
40,0 5
> 40,0 3
ppecas@tecnico.ulisboa.pt
7
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Stop-Watch application example
– Second step: Preliminary analysis
• Results from the 10 measurements and its analysis:
Total 49,5 50,7 46,3 45,5 43,9 44,2 45,7 49,2 49,7 44,2 47,0 2,6 5,5%
ppecas@tecnico.ulisboa.pt
8
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Stop-Watch application example
– Third step: Main results analysis
• Measurement realization during 4 weeks. Each week divided in 10 parts
(5 days; morning/afternoon). In each half-a-day, 4 measurements were
made: 4*2*5days*4weeks= 160 measurements (more than 124).
• The final results were: (El1=17,1; El2=20; El3=8,1)
ppecas@tecnico.ulisboa.pt
9
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Stop-Watch application example
– Fifth step: Identify additional non-systematic elements
• It’s required to change the tool every 20 parts due to its wear; it takes 10
minutes;
• It’s required to perform quality control every 5 parts; it takes 5 minutes;
• The machine efficiency is 81,6%.
t medido FA
t normal te
– Sixth step: Compute Normal Time – tn
• tm*Fa (17,1*110%+20,0+8,1*110%)=47,7 min
• te = 10 min/20parts+5min/5parts = 0,5+1=1,5 min
• 47 ,7
tn 1,5 58,5 1,5 60 ,0 min
0,816
ppecas@tecnico.ulisboa.pt
10
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Stop-Watch application example
– Seventh step: Define the allowances
• 10% of Total Time for unpredictable factors
• 2 coffee-breaks of 15 min
• An average delay of 6 min on each start-up (2 times/day)
• So:
– Total Time = 8 horas = 480 min/day
– Non-productive Time = 0,1*480+2*15+2*6 = 90 min = 1,5 h/day
– Productive Time = 480-90 = 390 min = 6,5 h/day
• Total Time Allowance (margem do tempo Total)
– mtt = NPTime/TT = 1,5/8 = 18,75%
• Productive Time Allowance (margem do Tempo Produtivo)
– mtt = NPTime/PT = 1,5/6,5 = 23,08%
ppecas@tecnico.ulisboa.pt
11
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Stop-Watch application example
– Eighth step: Determine Standard time (tempo padrão)
• The Daily Production Rate is: PT/tn = 390/60 = 6,5 units/day (Average)
tn 60
t padrão 73,84 min
1 m TT 1 0,1875
ppecas@tecnico.ulisboa.pt
12
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Work sampling
Tom Best
ppecas@tecnico.ulisboa.pt
13
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Work Sampling application example
– Consider for example a laser cutting work station
– First step: Identify the tasks to observe and estimate its frequency
• A – Laser on cutting operation 60%
• B – Operator loading the laser cutting table 10%
• C – Operator unloading cut parts 5%
• D – Operator tuning the laser cutting parameters 10%
• E – Laser waiting (operator out from the workstation) 15%
– Second step: Calculate the number of observations
• For the most important task, determine the required observations to achieve the defined level of
statistical significance:
– f = 0,60
– 95% probability (z=2) Z2 f (1 f ) 22 0,6(1 0,6)
N 9600 obs.
– Error percentage (p=1%) p 2
0,01 2
ppecas@tecnico.ulisboa.pt
14
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Work Sampling application example
– Third step: Determine the observation interval and study duration
• The observation interval should be small and, if possible, lower than the lowest task duration. In this
case, 15 seconds of interval.
• 9600*15s = 40 hours of study (40h of production observed – Attention!)
• The observations interval must be randomized (not constant).
– Fourth step: Results analysis
• During the 40 hours of production it were produced 156 parts
Obs. Perc.
A– Laser on cutting operation 6240 65,0%
B - Operator loading the laser cutting table 1050 10,9%
C – Operator unloading cut parts 310 3,2%
D – Operator tuning the laser cutting parameters 800 8,3%
E – Laser waiting (operator out from the workstation 1200 12,5%
Total 9600
ppecas@tecnico.ulisboa.pt
15
Production Management
Methods Engineering Gestão da Produção
Work Measurement
• Work Sampling application example
– Fifth step: Determine tasks unitary time
• Average time of laser cutting per part:
– Time spent in laser cutting: 40h*65% = 26 h
– Number of parts performed: 156 parts
– Average time per part: 26*60/156 = 10,0 min/part
Readings
• E. Henriques, P. Peças, Gestão da Produção I, Capítulo: Estudo dos
Tempos, 2003.
• Chase, Aquilano, Jacobs, Chapter 11, Production and Operations
Management, McGraw-Hill, 1998.
ppecas@tecnico.ulisboa.pt
17
Production Management
Methods Engineering Gestão da Produção
ppecas@tecnico.ulisboa.pt
19
Production Management
Methods Engineering Gestão da Produção
ppecas@tecnico.ulisboa.pt
20
Production Management
Methods Engineering Gestão da Produção
Standardized Work
• Standardized Work Instructions (SWI’s) are specific instructions that allow
processes to be completed in a
– consistent,
– timely, and
– repeatable manner.
ppecas@tecnico.ulisboa.pt
21
Production Management
Methods Engineering Gestão da Produção
Standardized Work
• Consists of three elements:
– Takt time, which is the rate at which products
must be made in a process to meet customer
demand.
– The precise work sequence in which an operator
performs tasks within takt time.
– The standard inventory, including units in
machines, required to keep the process
http://procnc.com
operating smoothly.
• 3 Document of SW
– Production capacity sheet
– Standardized combination table
– Standardized work chart
ppecas@tecnico.ulisboa.pt
22
Production Management
Methods Engineering Gestão da Produção
Standardized Work
https://i.ytimg.com
ppecas@tecnico.ulisboa.pt
23
Production Management
Methods Engineering Gestão da Produção
Standardized Work
https://i.ytimg.com
ppecas@tecnico.ulisboa.pt https://www.kaufmanglobal.com 24
Production Management
Methods Engineering Gestão da Produção
Standardized work
• Five Neglected Aspects of Standardized work
3. Don't try to impose standardized work without also providing a structured improvement
process, a clearly defined, unambiguous means of making improvements (kaizen).
https://www.lean.org/shook
ppecas@tecnico.ulisboa.pt
25
Production Management
Methods Engineering Gestão da Produção
Standardized work
• Five Neglected Aspects of Standardized work
ppecas@tecnico.ulisboa.pt
26