Documente Academic
Documente Profesional
Documente Cultură
This paper was prepared for presentation at the SPE Asia Pacific Oil & Gas Conference held in Melbourne, Australia, 7-10 November 1994.
This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the
authors. Contents of the paper, as presented, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the
authors. The material, as presented, does not necessarily reflect any position of the Society of Petroleum Engineers, its officers, or members. Papers
presented at SPE meetings are subject to publication review by Editorial Committees of the Society of Petroleum Engineers. Permission to copy is
restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledgment of where
and by whom the paper is presented. Write Libranian, SPE P.O. Box 833836, Richardson, TX 75083-3836 USA. Telex 163245 SPEUT.
Deoilers where first accepted in the oil and The PACS design offers the operational
gas industry 10 years ago, and dewaterers 5 advantages of parallel vessels in a much
years ago. They both consisted of single smaller deck space. Where typical current
hydrocyclones or "liners" in a pressure vessel. vessel on-line turndown ratios are in the range
To treat the required capacity a number of of 3:1 to 7:1 the PACS design provides an
individual vessels were piped together to order of magnitude higher with turndown ratios
provide a total system. These systems were typically in the 15:1 to 50:1 range, which easily
large and bulky. The size and weight meets all requirements.
advantages over conventional equipment
almost disappeared at large flowrates. PROCESS DESIGN
Furthermore the large number of connecting
flanges increased the hazards associated Process engineers tend to focus on oil and/or
with potential leaks. gas issues to maximize total production. Only
by equally addressing water and/or solids
The next development was the arrangement issues and appropriately handling these "by-
of a number of hydrocyclones in a pressure products" will maximum crude and gas
vessel. These vessels can contain from 2 or production be ensured.
- The stability or toughness depends on
Solids handling problems are caused by temperature, Ph, salinity, viscosity,
suspended solids, dissolved solids or a density of the bulk phase, volume
combination of both. These solids may fraction, size of the dispersed droplets,
originate either from the reservoir as sand, and the age of the emulsion.
clay and silt, or they may be corrosion
products or scale. Solids can cause erosion Other oil field conditions affect the emulsion
of valves, piping and other process and provide additional problems for adequate
equipment. They can build up in process separation. These conditions include the
vessels creating ideal conditions for bacterial presence of scale, waxes, asphaltenes, and
growth, which in turn may lead to serious free and dissolved gases.
corrosion problems.
In dewatering applications a particularly tough
Residual hydrocarbon content in water is also duty is the separation of an equal (50/50)
an important parameter to control in order to mixture of oil and water. It is not always clear
ensure compliance with environmental which phase is continuous, or at what mixture
regulations and optimize oil production. For the transition from continuous to dispersed
high water cut production the processing of phase occurs. When a transition does take
water becomes a major part of the operation. place (which may occur within the
hydrocyclone) large increases in viscosity can
Engineers designing or specifying water occur resulting in poor separation.
treatment facilities should have a fundamental
knowledge of water chemistry before trying to The challenge of adequately treating an
solve a water treatment problem. These emulsion becomes quite complex and the
fundamentals about the nature of water solution will be based largely on empirical
emulsions include: data. While the discussion here has centred
on treatment by hydrocyclones, thermal,
- Emulsions are defined as electrical and chemical treatments are also
heterogeneous systems consisting of important when used in conjunction with
at least one immiscible liquid hydrocyclones as a total process solution.
dispersed in another in the form of
small droplets. These systems are PROCESS SELECTION
either thermodynamically unstable
(easy) or they can be persistent when Details on hydrocyclone process design
stabilized by surface active features have been adequately covered in
components and solids (tough). other papers. A knowledge of the importance
- Water dispersed in oil is often referred of differential pressures, reject ratios,
to as regular emulsion or oil external pressure constants, turndown ratios, and
emulsion. Oil dispersed in water is a fundamentals of control are all important
reverse emulsion or water external concepts. Individual vendors will provide
emulsion. Multiple emulsions are also these details as applicable to their equipment.
possible such as an oil external Provided below is a more global view of
emulsion in a water emulsion. process solution possibilities.
- Surface active or emulsifying agents
(chemicals) can be introduced, or Stand-Alone Desander
occur naturally, with great variety in the
crude oil or gas reservoir system. The For removing solids and associated problems
tough emulsion results from a from a production system, desanders can be
reduction in interfacial tension, and/or utilized either upstream or downstream of a
a stability provided from electrostatic production separator.
repulsion barriers between the
immiscible liquids.
If there is incentive to locate a desander separate in the desander section and
upstream of a separator, the desander must settle by gravity through the connection
be sized to account for the fluid flow and the pipe into the accumulator tank.
gas volume under the actual process - solids removal; isolate accumulator
conditions. The more conventional location tank from the desander by closing
for a desander is downstream of the valve, vent off pressure through fill-up
production separator on the water outlet leg line and open both drain lines.
where the majority of the sand will - accumulator flushing; after initial
accumulate. The water outlet line must be in draining fill up with water and drain.
the bottom center position to minimize sand - recommission accumulator tank; close
build up in the separator. drain valves and open isolating valves.
The operation of hydrocyclones in series with The use of dewaterers is dependent on their
degassers occurred as far back as 1983 correct installation location. A dewaterer must
during field trials at Esso's Kingfish B be installed as far "upstream" as possible in
platform, and subsequent testing on Snapper the process system, where the greatest level
and Barracouta platforms. Even during initial of pressure and temperature can be best
testing the significant overall efficiency utilized. Useful separation is expected at oil
increases were apparent. viscosity's of less than 10 cSt.
- The integration of desanding at the well Desanding hydrocyclones have already been
head location. used in a limited number of wellhead
- The integration of separator and applications. For example, for the removal of
dehydration duties within one vessel. proppant from wellstreams, without an
- The integration of water treatment upstream degassing facility. In these cases
processes within the one vessel. the desander has been successful in
removing particles greater than 400 microns
These systems can be further integrated in size. However, it has been accepted that
within a combined package. the efficient removal of much finer particles, in
the region of 30-50 microns, is possible if the
The most exciting of the integrated packaging effects of free gas in the influent to the
ideas is the use of desanders at the wellhead. desander can be understood and controlled.
Several wellhead desanding studies are The benefits provided by successfully
underway worldwide involving the cooperative developing wellhead desanders for finer
efforts of universities, process system and particle removal are self-evident. Removal of
technology companies, and over ten produced sand before it enters the separation
international oil companies. The goals of these train will:
studies are to determine the operating
- Substantially reduce or completely mini units allow. These savings are possible
avoid the need for sand-jetting primary because the mini deoilers have been designed
separators. to treat nearly the same amount of water as
- Substantially reduce the fall-off in the small deoilers (150 to 250 BWPD for the
process performance caused by sand mini versus 200 to 300 BWPD for the small),
build-up and reduced separator while occupying only 25% of the cross
residence time. This will result in less sectional area that the small deoiler occupies.
water carry-over in oil streams and
improved produced water quality. CONCLUSIONS
- Substantially reduce erosion and
corrosion problems throughout the Desanders have been in use in the oil and gas
separation system. industry for over 25 years, albeit in a relatively
minor role. The introduction, and large
acceptance of deoiler hydrocyclones in the
early 1980's for produced water treatment
Mini Deoiling Hydrocyclones was a revolutionary achievement for process
equipment selection in a conservative
Most of the initial deoiling development work industry. Ten years on a large amount of
throughout the 1980's on liquid-liquid learning and information has resulted in the
hydrocyclones focused on the optimization of deoiler being a well proven technology. The
physical geometries. Although significant, that surge in deoiler acceptance has resulted in
research has now reached a point of the revisiting of the desander for more
diminishing returns. All current commercial demanding applications. Furthermore the
hydrocyclones, of similar size, achieve future potential of the dewaterer adds a new
comparable performance. dimension to the ongoing objective of size and
weight reduction of oil and gas process
To realize significant performance increases facilities.
"mini" deoiling hydrocyclones have been
developed. These "mini" 25mm deoilers will As the complexity of the separation task
typically separate 98% of particles equal to or increases, due to increasing environmental
coarser than 10 micron at a minimum inlet standards, so does the requirement of real
pressure of 20 psig. At an available inlet commitment to development work.
pressure of 80 psig, capacities range from Furthermore a whole new approach is needed
150 to 250 BWPD. in the conceptual design of these systems. It
is conceivable that a number of future
For the majority of oil field applications the production systems, especially minimum
deoiler is required to discharge oil in water facility offshore structures, will include solely
levels of less than 30 to 40 mg/l. A number of hydrocyclone based process equipment. The
more stringent requirements are emerging9 in savings in size and weight and obviously cost
some countries that include discharge of these systems will result in a second
requirements of less than 15 to 25 mg/l. hydrocyclone lead revolution.
These lower specification requirements are
normally achieved by combining
hydrocyclones in series with additional
separation equipment. However, the new
25mm hydrocyclones can often meet the
stricter requirements without additional
separation equipment.
FWKO
TABLE 1
FIGURE 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7