DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

AECOM
DELIVERABLES
1 Freeze GF Structure
(exclude kitchen) & HCS
Drawing
Electrical room raised Floor (RFI no. 058.S dated 07 Oct 19);
Support system type unknown;

GF GL M/20-22 Vertical Shaft Structure still pending from


AECOM.
GF GL M-N/1 Vertical Shaft Structure still pending from
AECOM;
GF GL J-K/1 Vertical Shaft Structure still pending from
AECOM;
GF GL CD/6 Vertical Shaft Structure still pending from
AECOM;
Unsupported slab at Stair 04 GL 10/K, RFI no 076.S raised 6
Nov 19.
No annotation for Cantilever slab at GL 20/M-N, RFI 073.S
raised 5 Nov 19.
Dock leveler; BAM issued via email the overlay drawings of 5
Dock leverer.
Toilet; Kitchen toilet to be relocated to lobby area. EI no. 44
and 45 issued. Closed.

Separator Beam on Lifts; Pending design and IFC from


AECOM.

15 Freeze kitchen design


(related
(all level)to structure) Topping slab in GF (rebar detailing)

DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)


AECOM
DELIVERABLES

2 Freeze 1F Structure & HCS


Drawing
Staircase 4 pending resolution between Archi and Structural
on the landing arrangements; Closed.
Staircase no. 23, Staircase at GL 6/C-D, and Staircase no.
25; Closed.
KITCHEN area GL12-16/C-B; On-hold released. Closed.

Still on-hold structural elements at GL D-F/8-11 for the Public


Toilet; Closed.
Public toilet: Plumbing sanitary piping system clashed with
Structural; Archi Consultant to re-layout;

Staircase access clearance clashed with post-tensioned


beam; Closed.
BAM requested opening for cable tray routing on grid 0-
10/11 this will clash with gray racking system; Closed.

Lift pit clashed with post-tension beam at lobby area;


Closed.
Post-tension beams change to Conventional; Received
advance info from AECOM. Closed.
Conveyor shaft (GL 18/M-N);

Missing beams and slabs at multiple location; Closed.

On-hold elements (GL6-8/N/O); Closed.


Toilet to shift south
DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

AECOM
DELIVERABLES

3 Freeze 2F Structure & HCS


Drawing
MEP, ARCHI and Struct (CSD); Under review by BAM and
found clashes and floor penetration; Still pending

On-hold area GL 18-20/C-E; Still Pending

KITCHEN area GL10-16/B-F; Still Pending

Toilet area; Pending

Planned to freeze structural on 31 Dec 2019;

Missing beam on floor openings GL 6-8/A-D; Pending


Missing beams on GL 6-10/D, GL 18-20/B, etc.; Pending

Floor opening for MEP Shaft moved from GL D/6-7 to E-F/6-


7. Additional beam expected. Pending
GL O/10-11 Missing beam provided by AECOM/TTW

GL D/7-8 & 9-10 Missing beam provided by AECOM/TTW


DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

AECOM
DELIVERABLES

4 Freeze Roof Drawing


Super structure: Missing elements found;
Interface detail of Column pedestal with Superstructure
frame missing;
Supporting frame for Siphonics, MEP Ducts, Smoke exhaust,
etc;
BAM requested to AECOM to issue IFC drawings for the
support and platform of ventilation fan installed in Roof Top

Missing support detail and interface detail of steel column


onto pedestals.
Column discrepancy
DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

AECOM
DELIVERABLES

5 Freeze B2 Plant Room


Drawing
Pending approval of STP 1 and STP 2 MAR and Shop Drawings.
BAM: STP Tank arrived by this Month.
Pending approval of Sump Pump MAR

Pending approval of Clean and Raw Filtration System MAR


6 Freeze B1 Plant Room
Drawing
AECOM to resolve the issue of fire tank volume capacity, Floth
highlighted this will create problem in securing the SLF permit due to the
reduction of water tank capacity from 600m3 to 550m3

Pending approval of cable tray and busduct routing (transformer Area)

Pending issuance of generator exhaust louver opening (genset approved


shop drawings)
Pending Approval of Fire Pump Plant system

MV and Transformer layout shop drawings to be submitted for approval

Chiller Plant Shop Drawing to be submitted


7 Freeze GF Plant Room
Drawing
Pending approval of MSB-1 and MSB-2 MAR
MSB room detail layout (SD) to be submitted after approval of MSB MAR

PLN room approval from AECOM and PLN


8 Freeze RF Plant Room
Drawing
to submit Cooling Tower SD
to submit AHU SD
pending design support / platform of smoke fans and ventilation fans in
the roof
9 Freeze B2 MEP Drawing
Pending approval of STP 1 and STP 2 Shop Drawings.
Pending approval of BMS Shop Drawings

re-arrangement of ducting layout in B2 to be submitted for approval


following EI29 requirement
Detail shop drawings on individual Sump Pump Pit to be submitted for
approval
Emergency Exit Door SD to be submitted following the MOM last 09 Dec
2019

DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

AECOM
DELIVERABLES

10 Freeze B1 MEP Drawing


AECOM Issued EI # 29 design change in B2, B1 & GF parking ventilation
fan static pressure, this will affect the equipment selection, Procurement
and Site Installation

re-arrangement of ducting layout in B1 to be submitted for approval


following EI29 requirement and busduct routing clashes

Pending Approval of BMS MAR

Pending approval of BMS SD

to revise SD following the changes of toilet location in GF

Pending Plumbing Sewage system SD approval


Pending Approval of Power and Cable Tray Layout
Emergency Exit Door SD to be submitted following the MOM last 09 Dec
2019

Pending approval of HVAC Piping SD


Voice and Data SD to be submitted for approval

11 Freeze GF MEP Drawing


Siamese piping connection in basement 1 not specified. Awaiting
AECOM/Floth new IFC drawings and RFI responded instructed BAM to
prepare SD for AECOM/Floth to review. BAM requested to issue EI

Cable ladder/tray specified in the IFC drawings is not sufficient to


accommodate all the cable installed on this cable ladder/tray. BAM SD
and AECOM to review and to issue EI accordingly.

Power supply (feeder cable, feeder protection and panelboard) for the
Dock Leveler, STP and Conveyor is not specified in electrical IFC
drawings.

Operating pressure of the fire pump and the sequence of operation


AECOM/Floth to confirm.
BAM issue SD for PLN room and feeder cable routing – AECOM to secure
approval from PLN
BAM requested to AECOM to issue STP Grease Trap details on GTP1 –
5m3 and GTP2 – 1m3 capacity
Plumbing shop drawing to be revise following the relocation of toilet and
garbage room area
Emergency Exit Door SD to be submitted following the MOM last 09 Dec
2019
BMS Shop Drawing to be submitted for approval
Fire Sprinkler Shop Drawing to be submitted for approval
HVAC Piping SD to be submitted for approval
Pending Approval of Cable Tray and Power Layout
Hot and Cold Water supply SD to be submitted for approval
Seware SD to be submitted for approval
EVAC SD to be submitted for approval
Security System SD to be submitted for approval
Voice and Data SD to be submitted for approval

12 Freeze 1F MEP Drawing

13 Freeze 2F MEP Drawing

14 Freeze RF MEP Drawing

DESIGN FREEZE DATES - MONITORING

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

EMPLOYER
DELIVERABLES

16 Genset arrival date


17 Transportation system
arrival date
CHANGE
REQUESTS
Loading Dock
(19/11/19)

18 Design Freeze: Change #1 - Pending E.I for Architectural revised drawing


Move the E.E. door to the
other side of the office
and combine sliding door
and EE.

19 Design (MEP) Freeze: Pending E.I for Architectural revised drawing


Change #2 - Relocate
charging area (same as GF
MEP Drawing freeze)

20 Design (structure) Freeze: Pending E.I for Architectural revised drawing


Change #4 - remove the
walls to ease the
unloading and change the
angle of loading dock

21 Change #5 - tba (Platform Pending E.I for Architectural revised drawing


on 1st floor behind the
rapid door)

SN Design Freeze ENGINEERING ISSUES (05-Dec-19)

OTHERS
22 As Built Basement 2 Escalator pits; - Not enough space issue with KONE
requirements . Aecom pending advised on RFI.
Travellator pit; - Not enough space issue with KONE
requirements. Aecom pending advised on RFI.
23 Basement 1 issues EI no. 26 received; DUCTING drawings: Found many
clashes, conflicts with Archi clearance on driveways and
discrepancy on IFC of MEP. BAM proposed to use it’s S.D.,
AECOM to consider approved the S.D. and disregards
partially the EI for MEP to. MEP Freeze still pending. Still
waiting information from TTW for the vertical shaft (3
location). Received and closed.

Retaining wall design at GL A; Received and closed.


SA-MD-032 Revised Column C49 & C68 Rebar: B1 to GF
column casted, as-built.

24 Ground Floor BAM have to freeze Ground Floor Structural outline by 28


Architectural Issues Oct. 2019. Still pending, new target 08 Nov 2019. Final
target on 18 Nov 19. New final target date on 27 Nov. 2019.
Freeze date has passed the agreed date.
Louver opening on Façade still pending – Awaiting
AECOM/Anggara to issue new Façade Drawings; BAM
submit Façade cutting plan drawings 26.11.19. Pending
review and approval by AECOM and pending information on
generator opening requirement.
Rev. IFC Architecture Door & Window Schedule due to
revised of intake or exhaust MEP GF: Intake or Exhaust MEP
GF closed.
Door schedule to be updated to capture the latest size of
LOUVRES.
Dock shelter walls and roofing.

25 Level 1 Architectural
Issues
Louver Exhaust Duct clash with window glass Grid D-6; Still
pending
Toilet Exhaust Louver grid 8-O requires opening in the
Façade; Still pending
Un-coordinated smoke duct opening on level 1 grid F-7 and
level 2 grid D-6; Still pending
RFI No. Closed Date Impact to Freeze dates

58.S
AECOM/APD had first kick-off
Open meeting with PLN yesterday 16.12.19

070.S & Yes, new reinforced concrete shaft


071.S 28-Nov-19 wall added.
070.S & Yes, new reinforced concrete shaft
071.S 28-Nov-19 wall added.
070.S & Yes, new reinforced concrete shaft
071.S 28-Nov-19 wall added.
070.S & Yes, new reinforced concrete shaft
071.S 28-Nov-19 wall added.
076.S
10-Dec-19 No impact, post installation allowed.

073.S
10-Dec-19 No impact, post installation allowed.

Open. 20 Dec 19 No. Data to transfer to BAM target


date 20 Dec 19.
No. Beam and HCS maintained.
12-Dec-19 Raised floor solution under
Architectural.

Open. 20 Dec 19 No, if Steel frame with post-


installation method.

Open. 20 Dec 19 Impact to Topping slab progress. Still


pending.

RFI No. Closed Date Impact to Freeze dates


10-Dec-19 Yes. Beam has shifted to resolved.

10-Dec-19 Yes. Added new beam.

Yes. Beam and column design closed-


11 Dec 19.
OPEN Slab reinforcement detail still
Pending. To be issued 17 Dec 19

10-Dec-19 Yes. Cast-in-situ replaces the HCS.

Yes.
Archi and Structural are aligned. MEP-
CLOSED Floth to follow suite and issue SA to
17-DEC-19 BAM on all services (e.g. plumbing,
ducting, etc)

Yes, change beam from Post-tension


10-Dec-19 to conventional

Yes. New beam added to support the


10-Dec-19 opening represented on Architectural
following provision required byMEP.

Yes, change beam from Post-tension


10-Dec-19 to conventional.

10-Dec-19 Yes.

Yes. Still pending.


CLOSED AECOM advised that opening shall
17-DEC-19 follow ARCHITECTURAL,.

Yes.
CLOSED BEAM to use the same as available on
17-DEC-19 revised IFC. BAM to submit S.D.

10-Dec-19 No. Beam and HCS maintained.


17-Dec-19 Closed. Beam can proceed
diary notes from 10Dec19 BIM M

RFI No. Closed Date Impact to Freeze dates

AECOM/TTW to resolve and issue


OPEN new IFC of Structural and Archi on 23
Dec 19

AECOM/TTW to resolve and issue


OPEN new IFC of Structural and Archi on 23
Dec 19
AECOM/TTW to issue new IFC of
OPEN Structural and Archi on 24 Dec 19
AECOM/TTW to issue new IFC of
OPEN Structural and Archi on 24 Dec 19
AECOM/TTW to issue new IFC of
OPEN Structural and Archi on 26 Dec 19
MEP ok to shift opening, Angara to
OPEN agree and TTW to support with
structural sizing 23 Dec 19
OPEN Some missing beams 23 Dec 19.

AECOM/TTW to issue new IFC of


OPEN Structural and Archi on 23 Dec 19
17 Dec 19
Closed
17 Dec 19
Closed
RFI No. Closed Date Impact to Freeze dates

OPEN

OPEN

OPEN

OPEN

OPEN

OPEN
RFI No. Closed Date Impact to Freeze dates

Closed. Closed on 12 Dec. 19


15-Dec-19
Open Floth closed. AECOM to issue
approved MAR today, 17 Dec 19.
15-Dec-19

Closed. 15-Dec-19 Closed on 12 Dec. 19

Pending solution from AECOM,


550m3 not problem. RFI reply 18 Dec
6-Jan-20 19

Closed SD approval received 12 Dec 2019


12-Dec-19
Closed drawing received 12 dec 2019
12-Dec-19
Denki submitted SD to bam 20 Dec.
6-Jan-20 BAM to aecom-23-Dec
Denki submitted SD to bam 20 Dec.
6-Jan-20 BAM to aecom-23-Dec
Denki submitted SD to bam 20 Dec.
6-Jan-20 BAM to aecom-23-Dec
15-Jan-20

15-Jan-20

15-Jan-20

1-Apr-20
1-Apr-20

1-Apr-20

Closed SD approval received 12 Dec 2019


BAM issued SD on 07 Dec 19. Pending BMS chiller points, PT Bukaka (need
AECOM approval. Denki issued PO to assistance from APD to push to submit).
BMS specialist. 20 Dec. 19. Bill of lading, lifting method
OPEN plan, BAM did not received anything.
(20 Dec 19) Equipment installatino method pending.

OPEN BAM to submit S.D. to AECOM on 20 Mark to provide this list to AECOM and
Dec 19. Consultants today via email!!!!!

OPEN BAM/Denki will submit S.D. on 20


Dec 2019
Current progress: Nego MOM send by Problem:
AECOM, Denki issue PO to PT Number of points from Tender is more
OPEN Handal-PENDING. 3 addl CCTV, 3(6) from IFC. Floth have to revise the IFC to
(20-Dec-19 addl Emergency door (APD Free 3 follow Tender drawings. 20 Dec 19 to
revised IFC) emergency door agreement from PT issue revised IFC by AECOM/FLOTH
Handal)

RFI No. Closed Date Impact to Freeze dates


0066.E
0067.E Closed
0068.E 12 Dec 19

Pending approval from AECOM.


12-Dec-19 Target 18 Dec 19

Closed and
Approved
10-Dec-19

Submitted to AECOM 07 Dec 19.


12-Dec-19 Pending approval from AECOM 18
Dec 19

MEP (E.G. Exhause, Supply, etc) based


12-Dec-19 on latest Archi-GF. Soffit services 20
Dec 19.
12-Dec-19 Harsya to Check the status
12-Dec-19 submitted to AECOM 04 Dec 2019
Current progress: Nego MOM send by
AECOM, Denki issue PO to PT
Handal-PENDING. 3 addl CCTV,
OPEN 3(total addtl 6) addl Emergency door
(20-Dec-19 (APD Free 3 emergency door
revised IFC) agreement from PT Handal)

12-Dec-19 DENKI submitted. Closed.


12-Dec-19 DENKI submitted. Closed.

0111.M 10-Jan-20

0094.E 10-Jan-20

0118.E 10-Jan-20

10-Jan-20

10-Jan-20

0122.M 10-Jan-20
10-Jan-20

10-Jan-20

10-Jan-20
10-Jan-20
10-Jan-20
10-Jan-20
10-Jan-20
10-Jan-20
10-Jan-20
10-Jan-20
10-Jan-20

RFI No. Closed Date Impact to Freeze dates


RFI No. Closed Date Impact to Freeze dates
N0.

Open. 20 Dec 19 Impact on Façade cladding

Open. 20 Dec 19 Impact on structural.


iary notes from 10Dec19 BIM Meeting with Aecom/APD/Consultants

Internal Remarks

BAM explain and presented the issue


to AECOM
SD approval received 12 Dec 2019

SUbmitted 09 DEc 2019

approval received 12 Dec 2019

pending solution from AECOM

SD approval received 12 Dec 2019

drawing received 12 dec 2019

DEnki submitted to bam 9 Dec, BAM to chk and submit to AECOM

DEnki to submit on Monday 16 Dec 19

IDC from bam complete, Denki to revise the dwg accordingly


Denki to re-submit 16 Dec 2019
bam to forward to AECOm on 13 Dec 19

Denki submitted to bam 12 Dec 19

AECOM to advise
bam to forward to AECOm on 13 Dec 19

Approved 10 Dec 2019

Submitted to AECOM 07 Dec 19

Denki awaiting the revise drawings

Harsya to Check the status


submitted to AECOM 04 Dec 2019
Nego MOM send by AECOM, Denki issue PO to Handal

Denki to re-submit 13 Dec 2019


Denki to re-submit (missing track from BAM)

Denki to revise the drawings to include the piping of SIamese connection 16 Dec 2019

Submitted to AECOM 04 Dec 19, pending approval from AECOM

Denki to re-submit drawing of STP feeder supply base on RFI responsed. CONveyor still outstanding from AECOM

AECOM to advise

to re-submit to AECOM on 13 Dec 2019

Pending from AECOM


Denki awaiting the revise drawings

Nego MOM send by AECOM, Denki issue PO to Handal

Denki submit 16 Dec 2019


SUBMITTED TO aecom 06 dEC 2019
Denki to re-submit (missing track from BAM)
submitted to AECOM 04 Dec 2019
IDC from BAM
IDC from BAM
IDC from BAM
IDC from BAM
IDC from BAM
nding from AECOM
DESIGN FREEZE DATES - MONITORING
CONSTRAINT
SN Design Freeze DATE Actual Date

AECOM DELIVERABLES
1 Freeze GF Structure (exclude kitchen) & HCS Drawing 19-Nov-19

15 Freeze kitchen design (related to structure) 25-Nov-19


(all level)

DESIGN FREEZE DATES - MONITORING


CONSTRAINT
SN Design Freeze DATE Actual Date

AECOM DELIVERABLES
2 Freeze 1F Structure & HCS Drawing 10-Dec-19
DESIGN FREEZE DATES - MONITORING
CONSTRAINT
SN Design Freeze DATE Actual Date

AECOM DELIVERABLES
3 Freeze 2F Structure & HCS Drawing 31-Dec-19
DESIGN FREEZE DATES - MONITORING
CONSTRAINT
SN Design Freeze DATE Actual Date

AECOM DELIVERABLES

4 Freeze Roof Drawing 11-Dec-19


DESIGN FREEZE DATES - MONITORING
CONSTRAINT
SN Design Freeze DATE Actual Date

AECOM DELIVERABLES
5 Freeze B2 Plant Room Drawing 15-Dec-19 (MEP to input)

6 Freeze B1 Plant Room Drawing 6-Jan-20

7 Freeze GF Plant Room Drawing 15-Jan-20

8 Freeze RF Plant Room Drawing 1-Apr-20

9 Freeze B2 MEP Drawing 30-Nov-19

10 Freeze B1 MEP Drawing 12-Dec-19

11 Freeze GF MEP Drawing 10-Jan-20


12 Freeze 1F MEP Drawing 6-Feb-20

13 Freeze 2F MEP Drawing 21-Feb-20

14 Freeze RF MEP Drawing 6-Mar-20

DESIGN FREEZE DATES - MONITORING


CONSTRAINT
SN Design Freeze DATE Actual Date

EMPLOYER DELIVERABLES
16 Genset arrival date 27-Jan-20
17 Transportation system arrival date 2-Apr-20

CHANGE REQUESTS
Loading Dock (19/11/19)

18 Design Freeze: Change #1 - Move the E.E. door to the 7-Dec-19


other side of the office and combine sliding door and
EE.

19 Design (MEP) Freeze: Change #2 - Relocate charging 3-Jan-20


area (same as GF MEP Drawing freeze)
20 Design (structure) Freeze: Change #4 - remove the 7-Dec-19
walls to ease the unloading and change the angle of
loading dock

21 Change #5 - tba (Platform on 1st floor behind the rapid 7-Jan-20


door)

CONSTRAINT
SN Design Freeze DATE Actual Date
OTHERS
22 As Built Basement 2

23 Basement 1 issues

Ground Floor Architectural Issues


ENGINEERING ISSUES (05-Dec-19)

1.

2.

3.

4.

5.

6.

7.
8.

9.

10.

1.

ENGINEERING ISSUES (05-Dec-19)


1.

2.
3.
4.
5.

6.
7.
8.
9.

10.
11.

12.
13.
14.
15.
16.
ENGINEERING ISSUES (05-Dec-19)
1.

2.
3.
4.
5.
6.
7.
ENGINEERING ISSUES (05-Dec-19)

1.
2.
3.
4.
ENGINEERING ISSUES (05-Dec-19)

1.

1.

1.

2.

3.

4.

5.
6.

7.

ENGINEERING ISSUES (05-Dec-19)

ENGINEERING ISSUES (05-Dec-19)


1.

2.

1.

2.
3.

3.

4.

5.
ENGINEERING ISSUES (05-Dec-19)

Electrical room raised Floor (RFI no. 058.S dated 07 Oct 19); Support system type unknown;
Pending details.
GF GL M/20-22 Vertical Shaft Structure still pending from AECOM. Received reply with details.
Closed.
GF GL M-N/1 Vertical Shaft Structure still pending from AECOM; Received reply with sketch
details via SA. Closed.
GF GL J-K/1 Vertical Shaft Structure still pending from AECOM; Received reply with sketch
details via SA. Closed.
GF GL CD/6 Vertical Shaft Structure still pending from AECOM; Received reply with sketch
details via SA. Closed.
Unsupported slab at Stair 04 GL 10/K, RFI no 076.S raised 6 Nov 19. Received info, but details
pending from TTW.
No annotation for Cantilever slab at GL 20/M-N, RFI 073.S raised 5 Nov 19. Pending
Dock leverer; BAM issued via email the overlay drawings of 5 Dock leverer. Still Pending on final
arrangements
Toilet; Kitchen toilet to be relocated to lobby area. Pending final design and IFC from AECOM.

Separator Beam on Lifts; Pending design and IFC from AECOM.

Topping slab in GF (rebar detailing)

ENGINEERING ISSUES (05-Dec-19)


Staircase 4 pending resolution between Archi and Structural on the landing arrangements; Not
received yet, overdue and still pending
Staircase no. 23, Staircase at GL 6/C-D, and Staircase no. 25; On-hold (Pending)
KITCHEN area GL12-16/C-B; Pending
Still on-hold structural elements at GL D-F/8-11 for the Public Toilet; Still pending
Planned to freeze structural on 25 Nov 2019; New target date established 10 Dec 19. Still
pending
Louver Exhaust Duct clash with window glass Grid D-6; Still pending
Toilet Exhaust Louver grid 8-O requires opening in the Façade; Still pending
Un-coordinated smoke duct opening on level 1 grid F-7 and level 2 grid D-6; Still pending
Public toilet: Plumbing sanitary piping system clashed with Structural; Archi Consultant to re-
layout; Still pending.
Staircase access clearance clashed with post-tensioned beam; Pending
BAM requested opening for cable tray routing on grid 0-10/11 this will clash with gray racking
system
Lift pit clashed with post-tension beam at lobby area; Still pending.
Post-tension beams change to Conventional; Received advance info from AECOM.
Conveyor shaft (GL 18/M-N); Still Pending clear opening
Missing beams and slabs at multiple location; Still pending
On-hold elements (GL6-8/N/O); Still pending
ENGINEERING ISSUES (05-Dec-19)
MEP, ARCHI and Struct (CSD); Under review by BAM and found clashes and floor penetration;
Still pending
On-hold area GL 18-20/C-E; Still Pending
KITCHEN area GL10-16/B-F; Still Pending
Toilet area; Pending
Planned to freeze structural on 31 Dec 2019;
Missing beam on floor openings GL 6-8/A-D; Pending
Missing beams on GL 6-10/D, GL 18-20/B, etc.; Pending
ENGINEERING ISSUES (05-Dec-19)

Super structure: Missing elements found;


Interface detail of Column pedestal with Superstructure frame missing;
Supporting frame for Siphonics, MEP Ducts, Smoke exhaust, etc;
BAM requested to AECOM to issue IFC drawings for the support and platform of ventilation fan
installed in Roof Top
ENGINEERING ISSUES (05-Dec-19)

BMS, ventilation

AECOM Issued EI # 29 design change in B2, B1 & GF parking ventilation fan static pressure,
this will affect the equipment selection, Procurement and Site Installation

Siemese piping connection in basement 1 not specified. Awaiting AECOM/Floth new IFC
drawings and RFI responded instructed BAM to prepare SD for AECOM/Floth to review. BAM
requested to issue EI
Cable ladder/tray specified in the IFC drawings is not sufficient to accommodate all the cable
installed on this cable ladder/tray. BAM to submit SD and AECOM to issue EI accordingly.

Power supply (feeder cable, feeder protection and panelboard) for the Dock Leveler, STP and
Conveyor is not specified in electrical IFC drawings.
Incoming line from telcom and data subscriber is not specified in the ELV drawings, BAM
request to the Engineer the external routing of the incoming line for Telcom and Data is required
urgently because of the ongoing concreting of perimeter wall
Operating pressure of the fire pump and the sequence of operation AECOM/Floth to confirm.
BAM issue SD for PLN room and feeder cable routing – AECOM to secure approval from PLN

BAM requested to AECOM to issue STP Grease Trap details on GTP1 – 5m3 and GTP2 – 1m3
capacity

ENGINEERING ISSUES (05-Dec-19)

Pending E.I for Architectural revised drawing

Pending E.I for Architectural revised drawing

Pending E.I for Architectural revised drawing

Pending E.I for Architectural revised drawing

ENGINEERING ISSUES (05-Dec-19)


Escalator pits; - Not enough space issue with KONE requirements . Aecom pending advised on
RFI.
Travellator pit; - Not enough space issue with KONE requirements. Aecom pending advised on
RFI.

EI no. 26 received; DUCTING drawings: Found many clashes, conflicts with Archi clearance on
driveways and discrepancy on IFC of MEP. BAM proposed to use it’s S.D., AECOM to consider
approved the S.D. and disregards partially the EI for MEP to. MEP Freeze still pending. Still
waiting information from TTW for the vertical shaft (3 location). Received and closed.

Retaining wall design at GL A; Received and closed.


SA-MD-032 Revised Column C49 & C68 Rebar: B1 to GF column casted, as-built.

BAM have to freeze Ground Floor Structural outline by 28 Oct. 2019. Still pending, new target
08 Nov 2019. Final target on 18 Nov 19. New final target date on 27 Nov. 2019. Freeze date has
passed the agreed date.
Louver opening on Façade still pending – Awaiting AECOM/Anggara to issue new Façade
Drawings; BAM submit Façade cutting plan drawings 26.11.19. Pending review and approval by
AECOM and pending information on generator opening requirement.
Rev. IFC Architecture Door & Window Schedule due to revised of intake or exhaust MEP GF:
Intake or Exhaust MEP GF closed.
RFI No. Closed Date Impact to Progress

58.S
No.

28-Nov-19

28-Nov-19

28-Nov-19

28-Nov-19

No (if post-anchor).

073.S No (if post-anchor).

No.

Yes (on beam & HCS GL 8-10).

No.

RFI No. Closed Date Closed Date


RFI No. Closed Date Closed Date
RFI No. Closed Date Closed Date
RFI No. Closed Date Closed Date

Yes.
RFI No. Closed Date Closed Date

RFI No. Closed Date Closed Date


N0.

S-ar putea să vă placă și