Documente Academic
Documente Profesional
Documente Cultură
widening to four lane divided highway from Km 120+000 to Km 228+000 of NH-11 (Jaipur – Mahua
Section).
CHAPTER 11
QUALITY CONTROL & QUALITY ASSURANCE
11.0 Methodology of Construction:-
11.1 General:-
The construction work was executed, in general, in accordance with the drawings,
technical specifications and instructions issued by the Engineer. Standard cross section
used during execution of the work is given Appendix 5.2.1, 5.2.2 & 5.2.3. Methodology
followed for execution of individual items of work, technical specification requirements
and actual achievements are summarized below.
Wherever necessary, temporary road diversions near work sites were constructed to
ensure the unhindered and safe movement of existing traffic. Suitable junctions were
provided for smooth movement of Traffic at all exit and re-entry points of diversions with
the existing road.
The execution of the project was carried out in such a way that always 2-lane is
available for safe movement of traffic. Concessionaire has submitted the diversion plan
for the concurrence of IC and based on the concurrence Concessionaire has executed
the Road Diversions.
Setting out of road and structures was done in accordance with the reference points of
the existing road and structures, temporary bench marks (TBMs), road cross-sections
and longitudinal profiles as provided in the DPR. The TBMs were established at a
regular interval generally within 200m. In addition, the Contractor had fixed pegs for
controlling the line at an interval of 10-20m as required.
Material investigations of various borrow areas along the road were carried out to
identify suitable sources of materials for embankment, sub grade and shoulder
construction. Specified mandatory tests were carried out to determine suitability of the
borrow material and only the sources meeting specification requirement were selected
and approved. Details of the approved borrow areas are given in Appendix 11.4.1
All roadwork activities for the entire pavement construction were carried out in
accordance with the approved specifications. Original ground in excavation was tested
for in-situ density for a depth of 300mm below the sub- grade level and if the same was
Materials approved for construction of the embankment / sub grade were transported to
site of work by dump trucks, spread by combination of dozers and motor grader and
finally compacted by vibratory roller at appropriate moisture content in order to obtain
required degree of compaction.
Results Obtained
Test Conducted Specification Limits
(Average)
Existing Ground Not Specified
Liquid Limit (%) 23.50 Not specified
Plasticity Index l(%) 7.20 Not specified
Free Swell Index (%) Not specified
Maximum Dry Density (gm/cc) 1.91 Not specified
Optimum Moisture Content (%) 10.80 Not specified
California Bearing Ratio (%) 12.90 Not specified
Field Density of Compacted layer (%) 95.80 >95
Borrow Material (Embankment/ Sub-
grade)
Sand Content (%) 34.00 <50
Liquid Limit (%) 23.50 < 45
Plasticity Index (%) 7.20 < 25
Free Swell Index 19.96 >1.52
Maximum Dry Density (gm/cc) 2.050 >1.75
Optimum Moisture Content (%) 8.50 Not specified
California Bearing Ratio (%) 14.11 >10
Field Density of compacted layer (%) 98.76 >97
Construction of 500mm thick sub grade was required at full road width at new construction
stretches
Sub grade material from approved borrow source was transported to site. The fill material
was spread in layers compacted thoroughly to achieve a density of 97% of Modified
Specification
Tests Conducted Obtained Value
Requirements
Liquid Limit (%) 21.43 <25
Plasticity Index (%) 4.04 <06
Maximum Dry Density (gm/cc) 2.296 --
Optimum Moisture Content (%) 6.05 --
Water Absorption (%) 1.15 <2
California Bearing Ratio (%) 65.05 > 30
10% Fine Value (KN) 195 > 50
Rolling operations were continued till the density achieved was 98% of the MDD
determined as per IS: 2720 (part 8). Any areas of segregation or otherwise defective were
made good and re-compacted.
This work consisted of providing sub grade selected material for shoulders to a width of
2.0 meter on either side of the carriageway. The selected soil from borrow areas of sub-
grade material was used for shoulder construction also. Soaked CBR (4 days) at 97% of
MDD for materials passing 19.00mm sieve was 13.31%, which was more than the
required minimum of 10%. The materials were brought to site by dump trucks from borrow
areas and dumped and spread by motor graders or dozers, water sprinkled and mixed and
brought to before being compacted. Oversize material and if any more than 75mm thick
and vegetative material were got handpicked during construction process. Vibratory and
steel wheeled tandem rollers were used for compaction. The rolling operations were
continued till the compaction achieved not less than 97%.
11.8.1 Description:-
WMM material consisted of graded crushed aggregates of different nominal sizes blended
and mixed with water in wet mix plant, laid and rolled to a dense mass on prepared sub
base layer. The thickness of an individual layer was not less than 75mm and not more
than 150mm.
Results Specification
Test - Conducted
Obtained Requirements
Aggregate Impact Value (%) (Average)
21.19 30 % Max
Combined Flakiness & Elongation Index 26.91 30% Max
(%)
Maximum Dry Density (gm/cc) 2.235 ---
Optimum Moisture Content (%) 6.50 ---
Los Angles Abrasion Value(%) 21.19 40% Max
Water Absorption, Average (%) 0.515 2 Max
Plasticity Index of particles passing from
Zero 6 Max
425 micron (%)
Results Specification
Test - Conducted
Obtained Requirements
Aggregate Impact Value (%) (Average)
27.78 30 % Max
Combined Flakiness & Elongation Index 27.89 30% Max
(%)
Completion Report Independent Consultant ICT Pvt. Ltd.
Chapter – 11 (11-5)
Improvement, Operation, Maintenance, Rehabilitation and Strengthening of existing 2 Lane Road and
widening to four lane divided highway from Km 120+000 to Km 228+000 of NH-11 (Jaipur – Mahua
Section).
Results Specification
Test - Conducted
Obtained Requirements
Maximum Dry Density (gm/cc) (Average)
2.434 ---
Optimum Moisture Content (%) 6.30 ---
Water Absorption, Average (%) 1.46 2 Max
Plasticity Index of particles passing from
4.48 6 Max
425 micron (%)
Results Specification
Test - Conducted
Obtained Requirements
Aggregate Impact Value (%) (Average)
20.34 30 % Max
Combined Flakiness & Elongation Index 24.95 30% Max
(%)
Maximum Dry Density (gm/cc) 2.312 ---
Optimum Moisture Content (%) 6.00 ---
Water Absorption, Average (%) 0.26 2 Max
Plasticity Index of particles passing from
NP 6 Max
425 micron (%)
11.8.3 Gradation:-
The aggregates used in WMM confirm to the Grading requirements set forth in MORT&H
specifications. The average gradation of some samples obtained in the field is given
below.
Table 11.8.3.2: Gradation of WMM Aggregates of the Material obtained from Plant
at Km 204/00 GHF:-
A Job Mix Design of WMM was prepared using trial and error method by blending the
materials of different nominal size aggregates in a proportion to get a well-graded mix from
course to fine. The design mix proportion of All in Aggregate Type-I, All in aggregate Type-
II, 10mm and dust was 53%, 32%, 09% and 06% respectively and Dust 13%.
Table 11.8.3.3: Gradation of WMM Aggregates of the Material obtained from Plant
at Km 204/00 TDM:
The wet mix macadam mix was prepared as per the Job Mix Design in the wet mix plant.
The moisture content was checked and controlled in such a way that it was well with in the
permissible limits during construction operations i.e during laying and compaction.
Immediately after mixing in the plant the mix was brought to the construction site by dump
trucks and spread on the prepared sub base using Mechanical Paver/Motor grader to the
required line, and thickness.
For portions, where mechanical Paver could not be used, laying by Grader was done as
approved by the IC. The surface of the aggregate was then carefully checked and all high
or low spots remedied by removing or adding aggregates as required. Care was taken to
minimize segregation during laying.
11.8.6 Compaction:-
Immediately after spreading the mix, the surface was compacted to the required grade
and Cross fall / Camber uniformly with 10 MT capacity rollers (Vibromax). Speed of the
roller is restricted to 5 Km / hour.
Rolling was commenced from the outer edges and progressed towards the center in order
to get the required Camber and Cross fall.
Rolling operations were carried out till field density achieved was minimum 98% of
laboratory density (MDD). Failure portion was rectified immediately by giving additional
passes of roller or replacing the material is required.
After completion of all operations, the finished layer of WMM was protected by placing
boulders and taking other measures to prohibit traffic movement on the surface.
Sl.
Type of Test Average Result Specification Limit
No.
1 Residence of 600 micron IS Sieve (%) 0.02 0.05 max
2 Viscosity by Say bolt Furd Viscosity 140~500
NA
at 600C, (centistokes) (at 60o C)
3 Coagulation of Emulsion at Low
NA Nil
temperature
4 Storage stability after 24 hours (%) NA 1 Max
5 Particle charge NA Positive
6 Miscibility with water NA Nil
7 Test on Residue
a) Residue by evaporation 82 65 min
b) Penetration NA 60-210
c) Ductility (at 2o C/cm/min) NA 75 min
d) Solubility in tricloroethilene (%) NA 97.50 min
The surface of the non-bituminous base course built with WMM (Wet Mix Macadam)
proposed to be paved was thoroughly cleaned by using brushes and compressed air.
Within 12 hours of the cleaning operation the surface was given a prime coat. Average
viscosity of emulsion when checked at site was found 271 centi-stroke.
Rate of spread was regularly checked in the field by placing iron tray on the surface and
carrying out weighing operations. The sample average value of application was 1.34
kg/m2 and was within the specification requirement of 1.2 to 1.5 kg/m2.
At the locations where the prime coat got contaminated anywhere in any way by dust,
traffic or other means before laying a bituminous treatment or mix on the primed surface
was rectified by applying an additional coat of prime
To prevent prime coat from damages due to the movement of vehicle, only ½ side of the
road was primed at a time and boulders were placed on the top of the primed surface until
bituminous layer covers it.
11.10 Tack Coat:-
11.10.1 Binder:-
Bituminous emulsion of the same grade and quality as used for prime coat was used for
tack coat also. The average rate of spray (sample average) of emulsion was 0.25 kg/M2
and was within the specification limits of 0.20 to 0.30 kg/M2.
The surface on which the tack coat was to be applied was thoroughly cleaned using
brooms, wire brushes and finally by using compressed air and made free from dust, dirt
and any extraneous material.
Dense Bituminous macadam (DBM) was hot mixed, hot laid, plant mixture of well-graded
dried aggregates and bitumen which when compacted, formed a dense material.
This work of laying of bituminous macadam consisted of construction of a single course of
compacted crushed aggregates premixed with a bituminous binder laid immediately after
mixing, on a previously prepared base to the requirements of specifications and on
conformity with the lines, grades and cross sections as shown in the drawings.
11.11.1 Bitumen:-
Bitumen used for the purpose was of 60/70 grade as per IS: 73 and in accordance with
MORT& H specifications clause 504.2.1.
Requirement
Sl. Observed result at
Description as per MOST
No. laboratory
table
1. Aggregate Impact Value Max 27% 20.52%
2. Flakiness & Elongation Max 30% 28.22%
3. Water Absorption (37.5 mm) Max. 2 % 0.428%
4. Water Absorption (19 mm) Max. 2% 0.580%
5. Water Absorption (13.2 mm) Max. 2% 0.653%
6. Water Absorption (5.5 mm) (Stone Dust) Max. 2% 1.094%
7. Bulk Specific Gravity 37.5 mm 2.62
8. Bulk Specific Gravity 19 mm 2.61
9. Bulk Specific Gravity 13.2 mm 2.603
10. Bulk Specific Gravity 5.5 mm (Stone Dust) 2.590
11. Apparent Specific Gravity 37.5 mm 2.65
12. Apparent Specific Gravity 19 mm 2.65
13. Apparent Specific Gravity 13.2 mm 2.648
14. Apparent Specific Gravity 5.5 mm 2.666
Requirement Observed
Sl.
Description as per MOST result at
No.
table laboratory
1. Water Absorption (37.5 mm – 19.0 mm) Max. 2 % 0.428 %
2. Water Absorption (19 mm – 13.2 mm) Max. 2 % 0.580 %
3. Water Absorption (13.2 mm – 5.5 mm) Max. 2 % 0.653 %
4. Water Absorption (5.5 mm – 0 mm) Max. 2 % 1.09 %
5. Bulk Specific Gravity (37.5 mm – 19.0 mm) 2.620
6. Bulk Specific Gravity (19 mm – 13.2 mm ) 2.610
7. Bulk specific Gravity (13.2 mm – 5.5 mm) 2.603
8. Bulk specific Gravity (5.5 mm – 0 mm) 2.590
9. Apparent Specific gravity (37.5 mm – 19 mm) 2.650
10. Apparent Specific Gravity (19 mm – 13.2 mm) 2.650
11. Apparent Specific Gravity (13.2 mm – 5.5 mm) 2.648
12. Apparent Specific Gravity (5.5 mm – 0) 2.666
13. Aggregate Impact value Max 27 % 19.62 %
14. Combined flakiness and Elongation Indices Max. 30 % 28.70 %
Requirement
Sl. Observed result
Description as per MOST
No. at laboratory
table
1. Aggregate Impact Value Max. 30 % 18.95 %
2. Combined Flakiness and Elongation Indices Max. 30 % 22.50 %
3. Water Absorption (37.5 – 19.0 mm) Max. 2 % 1.09 %
4. Water Absorption (19 mm – 13.2 mm) Max. 2 % 1.01 %
5. Water Absorption (13.2 mm – 5.5 mm) Max. 2 % 1.16 %
6. Water Absorption (5.5 mm – 0 mm) Max. 2 % 1.36 %
7. Bulk Specific Gravity (37.5 mm – 19.0 mm) 2.812
8. Bulk Specific Gravity (19 mm – 13.2 mm ) 2.773
9. Bulk specific Gravity (13.2 mm – 5.5 mm) 2.766
10. Bulk specific Gravity (5.5 mm – 0 mm) 2.893
11. Apparent Specific gravity (37.5 mm – 19 mm) 2.887
12. Apparent Specific Gravity (19 mm – 13.2 mm) 2.858
13. Apparent Specific Gravity (13.2 mm – 5.5 mm) 2.874
14. Apparent Specific Gravity (5.5 mm – 0) 2.666
Observed
Requirement as
S. No. Description result at
per MOST table
laboratory
1. Water Absorption (37.5 mm – 19.0 mm) Max. 2 % 0.24 %
2. Water Absorption (19 mm – 13.2 mm) Max. 2 % 0.43 %
3. Water Absorption (13.2 mm – 5.5 mm) Max. 2 % 1.03 %
4. Water Absorption (5.5 mm – 0 mm) Max. 2 % 1.28 %
5. Bulk Specific Gravity (37.5 mm – 19.0 mm) 2.802
6. Bulk Specific Gravity (19 mm – 13.2 mm ) 2.784
7. Bulk specific Gravity (13.2 mm – 5.5 mm) 2.755
8. Bulk specific Gravity (5.5 mm – 0 mm) 2.732
9. Apparent Specific gravity (37.5 mm – 19 mm) 2.820
10. Apparent Specific Gravity (19 mm – 13.2 mm) 2.818
11. Apparent Specific Gravity (13.2 mm – 5.5 mm) 2.830
12. Apparent Specific Gravity (5.5 mm – 0) 2.832
13. Aggregate Impact value Max 27 % 14.45 %
14. Combined flakiness and Elongation Indices Max. 30 % 21.74 %
Table 11.11.3.1: Gradation of DBM Aggregates (Grading-1) Adopted in Job Mix Design
at Km. 147.000 GHF Plant
1. 37.5 mm 30 %
2. 19 mm 16 %
3. 13.2 mm 17 %
4. 5.5 mm (Stone Dust) 37 %
5. Bitumen Content (60/70) 4.30 % By wt of total Mix (Minimum 4.0 % As per
(OBC) MORT&H)
6. Stability (Kgs) 31 > 20.25 KN (As per MORT&H)
7. Design Lab Density 2.348 gm/cc
8. Flow (mm) 5.2 mm (3 mm – 6 mm) as per MORT&H
9. Total air voids in the Mix 4.6 % (3% - 6%) As per MORT&H
10. Voids in Mineral Aggregates 13.72 % (Min 11.5%) As per MORT&H
(VMA)
11. Voids Filled with Bitumen 67% (65% - 75 %) As per MORT&H
(VFB)
0.5% dosages by wt of Bitumen, anti- stripping agent (DERBO-101) from M/s
Dharmsons Enterprises was added to bitumen in DBM Mix
Table 11.11.3.2: Gradation of DBM Aggregates (Grading-2) Adopted in Job Mix Design at Km.
147.000 SPECO Plant
1. 37.5 mm – 19 mm Size Aggregate 15 %
2. 19 mm – 13.2 mm Size Aggregate 20 %
3. 13.2 mm – 5.5 mm Size Aggregate 19 %
4. 5.5 mm 0 mm Size Aggregate 46 %
5. Bitumen Content (60/70) (OBC) 4.67 % By wt of total Mix (Minimum 4.5 % As
per MORT&H)
As per Anu Lab Test Report Anti Stripping Agent (DERBO-101) from M/s
Dharmsons Enterprises, 0.8% dosage by weight of Bitumen was added to the 60/70
penetration grade bitumen at DBM mix production stage at the HM plant.
Table 11.11.3.3: Gradation of DBM Aggregates (Grading-1) Adopted in Job Mix Design at
Km. 204.000 TDM Plant
1. 37.5 mm – 19 mm 28 %
2. 19 mm – 13.2 mm 10 %
3. 13.2 mm – 5.5 mm 25 %
4. 5.5 mm 0.00 mm 37 %
5. Bitumen Content (60/70) 4.25 % By wt of total Mix (Minimum 4.0 % As per
(OBC) MORT&H)
6. Stability (Kgs) 32.51 KN at 600C (Min 20.25 KN)
7. Design (gm/cc) 2.535 gm/cc
8. Flow (mm) 4.50 mm (3 – 6) As per MORT&H
9. Total air voids in the Mix% 4.20 % (3% - 6%) As per MORTH
10. Voids in Mineral Aggregates 12.51 % (11.5%) As per MORT&H
(VMA)%
11. Voids Filled with Bitumen 70.25 % (65 – 75) As per MORT&H
(VFB)%
Table 11.11.3.4: Gradation of DBM Aggregates (Grading-2) Adopted in Job Mix Design
at Km. 204.000 LINNHOFF Plant (TDM)
1. 37.5 mm – 19 mm Size 25 %
Aggregate
2. 19 mm – 13.2 mm Size 17 %
Aggregate
3. 13.2 mm – 5.5 mm Size 14 %
Aggregate
4. 5.5 mm 0 mm Size Aggregate 42% + Filler (Dust) – 2 %
5. Bitumen Content (60/70) (OBC) 4.60 % By wt of total Mix (Minimum 4.5 % As per
MORT&H)
As per the Anu Lab Agra and CEG test house Jaipur, 0.7% dosages by wt of
Bitumen, anti- stripping agent (DERBO-101) from M/S Dharmsons Enterprises
was added to bitumen in DBM Mix
Blending of clean and dry aggregates of different nominal size was done as per design
proportions. Necessary adjustment was done to get the desired result of the mixed
gradation. Aggregates were heated in the dryer of the hot mix plant to the specified
temperature, generally 150 o C to 160 o C. Temperature of bitumen when mixed with the
aggregates was maintained between 1500 C and 1650 C.
The quality aggregates and binder content was checked regularly
Bituminous concrete (BC) consisted of well graded aggregates and Polymer modified
bitumen (PMB-40) with the Modifier ELAVALOY from DuPont, USA ,blended by M/s
Osnar Chemical Pvt Ltd mixed together max 1% dosages with 0.2% of
Catalyst( Phosphoric acid) in the base Bitumen 80/100 in hot mix plant, laid and
compacted to form a close graded premixed surfacing.
Different trial mixes of aggregates of 19mm nominal size and 6 mm (dust) nominal size
aggregates collected from the crusher plant were carried out to obtain desired gradation
as specified in MORT&H Table-500-18(Grading-1). The final gradation adopted in the
design is given in table below.
Design
Sl.No Description
Value (%)
1 Crushed 19-13.2 mm Aggregates 45.00
2 Crushed 13.2-5.5 mm Aggregates 10.00
3 Crushed 5.5-0 mm Aggregates 43.00
4 Filler( Stone Dust) 2.00
Optimum Binder(PMB-40 with polymer Elvaloymax1%
5 dosage with 0.2% of catalyst(Poly- Phosphoric acid) in 5.00
the base bitumen 80/100 by Weight of Total Mix
Different trial mixes of aggregates of 12mm and 6 mm (dust) nominal size aggregates
collected from the crusher plant were carried out to obtain desired gradation as specified
in MORT&H Table-500-18(Grading-2). The final gradation adopted in the design is given
in table below.
Obtained Specification
S. N Type of Test
Result Limits
I Aggregates
1 Aggregate Impact value (%) 17.24 24 Max
2 Specific Gravity of 19mm-13.2mm aggregates 2.709 ---
3 Specific Gravity of 13.2mm-5.5mm aggregates 2.643
4 Specific Gravity of 5.5mm-0mm aggregates 2.620
5 Water Absorption (%) Av of all above 0.766 1 Max
6 Flakiness and Elongation Index (%) 22.16 30 Max
The mix proportion of different nominal size aggregates and binder content obtained
while preparing Job Mix Formula of BC are given in the Table below.
Different trial mixes of aggregates of 12mm and 6 mm (dust) nominal size aggregates
collected from the crusher plant were carried out to obtain desired gradation as specified
in MORT&H Table-500-18(Grading-2). The final gradation adopted in the design is given
in table below.
Specification
S. N Type of Test Obtained Result
Limits
I Aggregates
1 Aggregate Impact value (%) 18.46 24 Max
Specific Gravity of 19mm-13.2mm
2 2.837 ---
aggregates
Specific Gravity of 13.2mm-5.5mm
3 2.611
aggregates
Specific Gravity of 5.5mm-0mm
4 2.651
aggregates
5 Water Absorption (%) Av of all above 0.846 1 Max
6 Flakiness and Elongation Index (%) 23.70 30 Max
7 Polished stone value 62.00 55 Min
PMB-40 (as per Anu Lab Agra test
II
certificate)
1 Penetration at 25 oC 45.67 30-50
o
2 Softening Point ( C) 61.5 60 Min
Elasto-recovery of half thread in
3 76 50 Min
ductilo-meter at 15 oC (%)
The mix proportion of different nominal size aggregates and binder content obtained while
preparing Job Mix Formula of BC are given in the Table below.
The dumped trucks transported the mix. Full care was taken to avoid any segregation
during transit and settling dust on the mix.
Asphalt Paver with sensors of laying capacity of 9m width was used for laying.
Compaction operations were done immediately after laying the mix, following the paver.
It was ensured that the temperature of mix at the time of compaction of the BC layer was
within the range of 900C - 1250C. No compaction was allowed to be carried out at
temperatures below 900C. Entire compaction exercise was carried out longitudinally,
commencing from the outer edges and progressing towards the center. At super
elevated curves, rolling was commenced from the lower edge and progressed towards
higher edge. Compaction was carried out by smooth wheeled rollers of 10 MT.
Compaction operation was continued till no movement of BC under the roller was
noticed. During the entire operation of lying, proper care was exercised to keep the
surface clean and avoid any dust settling on to the surface. Spread rate of BC mix was
regularly checked and controlled in order to achieve the compacted thickness of 40 mm
as per design
Pothole filling work was carried out, periodically on un-tackled existing road stretches to
bring the road surface for traffic movement. Bituminous mix was used for potholes of
depth less than 100mm thick. Repair of deeper potholes was carried out using granular
material at bottom and bituminous mix on top as per provisions in the contract.
The existing Bridges and culverts have been extended as to match the new road cross
section. Minor maintenance works included clearing the vent way and water channel on
the upstream and downstream sides including clearing and grubbing and removal of
rubbish materials; rehabilitation of slab bottom and pointing/plastering of damaged
surface; reinstating cushion in pipe culverts; and repairing of protection works etc.
The Concrete Mix design used during execution of the work are tabulated below
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 15
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 20
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 25
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 30
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 35
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 40
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 15
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 20
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 25
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 30
3 Characteristic cube compressive strength @ 28 30 Mpa
Days
4 Current Margin as per IRC:21 12 Mpa
5 Target Mean Strength = 30+12 = 42 Mpa 42 Mpa
6 Nominal Mazimum Size of Aggregate 20 mm
7 Workability in terms of Slump @ placement 70 – 100 mm
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 35
A. DESIGN STIPULATION
1 Type Of Mix Design Mix
2 Grade of Concrete M 40
3 Characteristic cube compressive strength @ 28 40 Mpa
Days
4 Current Margin as per IRC:21 12 Mpa
5 Target Mean Strength = 30+12 = 42 Mpa 52 Mpa
6 Nominal Mazimum Size of Aggregate 20 mm
7 Workability in terms of Slump @ placement 70 – 100 mm
8 Degree of Quality Control V. Good
2) Filter Material
Proportion of aggregate.
20 mm: 30 %
10 mm: 45 %
Dust : 25 %
FILTER MEDIA
Reinforcement steel of grade Fe- 415, manufactured by Tata Iron &Steel Company and
Rastriya Ispat Nigam Limited(RINL) was used for the work. Physical properties as per
independent test conducted at National Test House at Jaipur are tabulated below.
12m
S.N Properties mm 10mm mm
m
1 Weight per meter (kg/m) 0.388 0.612 0.884 2.41
2 Yield Stress (N/ mm2) 528.6 538.5 497.7 504.9
Ultimate Tensile Strength at Break
2 622.9 636.3 617 594.8
(N/ mm2)
3 Elongation at Break (%) 20 26 20 21
0.2% Proof Stress, Ultimate Stress and Elongation at break for all sizes of steel bar were
found permissible limits.
Table 11.15.5.1: Test result of RCC Hume Pipe (Three Edge Bearing Test)
Load to be
Sl Load Applied
Pipe (size, type) / Test applied as per IS
No (KN/m)
458:2003 (kN/m)
mm (NP4)
72.60KN/Rmt or
1 Load to develop 0.25 mm wide crack 175
174.24KN/2.4m
108.90KN/Rmt or
2 Ultimate load at break 265
261.36KN/2.4Rmt
The quality assurance system controls the quality of the material, machine, operators
and supervisors of contractors. The system ensures that the materials to be used in the
work are from approved sources and are in accordance with the specifications. Similarly,
the quality of equipment is assured to be in accordance with the specifications. The
number and quality of personnel – the operators, technicians and supervisory staff of
contractors would require to be adequate, to carry out works properly and efficiently.
The process of workmanship was supervised by PIU with regard to materials, equipment
and personal. Carrying out quality control tests had been in practice a joint effort of
contractor, supervising engineer and technical staff of the TA consultants. In addition to
regular tests, separate (independent) tests were also carried out for technical audit
purpose.
Abstract of the tests and their frequency as per specification requirement, for source
approval of local materials, manufactured materials, and tests to be conducted during
construction along with specification limits is given in Appendices 11.17.1.1, 11.17.1.2 &
11.17.1.3 respectively.
Construction plants and laboratory equipment were required to be calibrated from time to
time. Suggested checklist of calibration of plant and lab equipment is depicted in
Appendix 11.17.1.4.
Job mix designs of different works (bituminous work concrete) also were required to be
prepared as the source or quality of material changed. Suggested checklist of the same
is illustrated in Appendix 11.17.1.5
The quality control activities, in general, were conducted as per the specification
requirements. Obviously the delivery of quality product was the prime responsibility of
the contractor. Nevertheless, the supervising engineers had controlled the quality of
work vide witnessing tests conducted by the contractor’s engineers. The technical staff
of the audit consultants had regularly assisted supervising engineers to conduct quality
control tests. After the deployment of an additional technical staff from August 2006, an
improvement was noticed in quality control of materials and construction work as well.
Some of the tests of manufactured materials like: cement, steel bar, bitumen, etc were
conducted at outside laboratory by third party. Hume-pipe were tested in the at plant site
of the manufacturer.
Similarly, the contractor had conducted Roughness Index Test by Bump Integrator from
km 120+000 to km 229+000. Roughness Index of finished road was varying from 1600
mm/km to 2000 mm/km, which was within the maximum the permissible value of
2000mm/km.
As in case of regular tests, the independent tests also showed that the quality of work
done, in general, was satisfactory.
Sl. Km Docket
No.
Details Km to
from Name
MS-1
1 Quality Control Test Record as per Schedule "J" 120.00 125.00 QC/1
2 Quality Control Test Record as per Schedule "J" 125.00 130.00 QC/2
3 Quality Control Test Record as per Schedule "J" 130.00 135.00 QC/3
4 Quality Control Test Record as per Schedule "J" 135.00 140.00 QC/4
5 Quality Control Test Record as per Schedule "J" 140.00 145.00 QC/5
6 Quality Control Test Record as per Schedule "J" 145.00 150.00 QC/6
7 Quality Control Test Record as per Schedule "J" 150.00 155.00 QC/7
8 Quality Control Test Record as per Schedule "J" 155.00 160.00 QC/8
9 Quality Control Test Record as per Schedule "J" 160.00 165.00 QC/9
10 Quality Control Test Record as per Schedule "J" 165.00 170.00 QC/10
11 Quality Control Test Record as per Schedule "J" 170.00 175.00 QC/11
MS-2
Quality Control Test Record SLABS AND PIPE
12 120.00 174.74 QC/12
CULVERTS MS-1 as per Schedule "J"
Quality Control Test Record
13 120.00 174.74 QC/13
MINOR BRIDGES MS-1 as per Schedule "J"
14 Quality Control Test Record as per Schedule "J" 175.00 180.00 QC/14
15 Quality Control Test Record as per Schedule "J" 180.00 185.00 QC/15
Quality Control Test Record GRADE
16 181.35 182.50 QC/16
SEPERATOR as per Schedule "J"
17 Quality Control Test Record as per Schedule "J" 185.00 190.00 QC/17
18 Quality Control Test Record as per Schedule "J" 190.00 195.00 QC/18
19 Quality Control Test Record as per Schedule "J" 195.00 200.00 QC/19
20 Quality Control Test Record as per Schedule "J" 200.00 205.00 QC/20
21 Quality Control Test Record as per Schedule "J" 205.00 210.00 QC/21
Quality Control Test Record Underpass as per
22 207.70 208.30 QC/22
Schedule "J"
23 Quality Control Test Record as per Schedule "J" 210.00 215.00 QC/23
24 Quality Control Test Record as per Schedule "J" 215.00 220.00 QC/24
Quality Control Test Record Underpass as per
25 219.45 220.08 QC/25
Schedule "J"
26 Quality Control Test Record as per Schedule "J" 220.00 225.00 QC/26
27 Quality Control Test Record as per Schedule "J" 225.00 230.00 QC/27