Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Change Log
2 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Table of Contents
1.0 INTRODUCTION ....................................................................................................8
1.1 Development .......................................................................................................................... 8
1.2 Glossary ................................................................................................................................. 9
1.3 Definitions ............................................................................................................................ 11
1.4 Manual Approval .................................................................................................................. 11
1.5 Manual Revisions ................................................................................................................. 11
2.0 DESIGN BASIS ....................................................................................................12
2.1 Location ............................................................................................................................... 12
2.1.1 Future Wells ..................................................................................................................... 12
2.1.2 Gas Lift ............................................................................................................................. 13
2.1.3 Gas Injection .................................................................................................................... 13
2.1.4 Water Injection ................................................................................................................. 13
2.1.5 System Design Temperatures and Pressures .................................................................. 13
2.1.6 Design Life ....................................................................................................................... 13
2.2 Environment ......................................................................................................................... 14
2.3 Reservoir Summary.............................................................................................................. 15
2.3.1 PVT Properties ................................................................................................................. 15
2.3.2 Water Chemistry............................................................................................................... 16
3.0 SUBSEA SYSTEM ...............................................................................................17
3.1 Well Completions ................................................................................................................. 18
3.2 Surface Controlled Subsurface Safety Valves (SCSSVs) ..................................................... 18
3.3 SMART Selective Capabilities .............................................................................................. 18
3.4 Subsea Trees ....................................................................................................................... 19
3.5 Pipeline End Terminations (PLETs) ...................................................................................... 20
3.6 Flowlines / Risers ................................................................................................................. 21
3.6.1 Flowlines .......................................................................................................................... 21
3.6.2 Risers ............................................................................................................................... 21
3.7 Control System..................................................................................................................... 22
3.7.1 Umbilical Termination Assembly (UTA) ............................................................................ 26
3.7.2 Subsea Distribution Unit (SDU) ........................................................................................ 26
3.7.3 Communication Distribution Unit (CDU) ........................................................................... 26
3.8 Umbilical System .................................................................................................................. 27
3.9 Subsea Chokes .................................................................................................................... 28
3.10 Chemical Injection Systems ................................................................................................. 29
3.10.1 Methanol Injection System ............................................................................................... 29
3.10.2 Low Dosage Hydrate Inhibitor (LDHI) Injection System .................................................... 29
3 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Table of Figures
Figure 2-1 Project Vicinity Map ............................................................................................................ 12
Figure 3-1 Gunflint Field Layout ........................................................................................................... 17
Figure 3-2 PIP Cross Section............................................................................................................... 21
Figure 3-3 Gunflint Master Flo Cv Chart............................................................................................... 28
Figure 4-1 Gulfstar 1 Coordinate System and Heading ........................................................................ 30
Figure 7-1 Dedicated Production Well Routing .................................................................................... 58
Figure 7-2 Commingled Production Well Routing................................................................................. 59
Figure 7-3 Chemical injection locations (subsea tree) .......................................................................... 66
Figure 7-4 MeOH Injection System Schematic ..................................................................................... 66
Figure 7-5 LDHI Injection System Schematic ....................................................................................... 67
Figure 7-6 CI/SI and AI Injection System Schematic ............................................................................ 67
6 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Table of Tables
Table 2-1 Well Coordinates and Depths .............................................................................................. 14
Table 2-2 Typical GOM Water Temperatures ...................................................................................... 14
Table 2-3 PVT Properties .................................................................................................................... 15
Table 2-4 Water Chemistry .................................................................................................................. 16
Table 3-1 Umbilical Data...................................................................................................................... 27
Table 4-1 Coordinates of Gulfstar 1 Spar ............................................................................................. 30
Table 5-1 Methanol Requirement for Gunflint Well Jumper, Trees and Dead Leg Treatment ............... 34
Table 5-2 Estimated times for bottoms-up based on avg. liquid production rates ................................. 35
Table 5-3 Achievable MeOH rates – _____ psi pump discharge pressure .......................................... 42
Table 5-4 Methanol deliverability for _____ psi fixed pump pressure .................................................. 42
Table 5-5 Automatic Shutdown Scenarios ........................................................................................... 44
Table 5-6 Shutdown Timer Table ......................................................................................................... 45
Table 7-1 Internal Fluid, Pressure and Temperature Data ................................................................... 63
Table 7-2 Chemical Injection Locations ............................................................................................... 65
Table 7-3 Summary of MeOH injection rates (Pdis = ____ psia) (HOLD #) ........................................... 68
Table 7-4 Requirements for chemical injection rate ............................................................................. 68
Table 9-1 Valve Testing Criteria ........................................................................................................ 109
Table 11-1 Numbering Block Assigned for Gunflint ............................................................................ 127
Table 11-2 Subsea Equipment........................................................................................................... 128
Table 11-3 Riser Base In-Line Sled ................................................................................................... 128
Table 11-4 Topsides Signals.............................................................................................................. 129
Table 11-5 Well MC 948#2 QAY-2200 ............................................................................................... 130
Table 11-6 MC 948#4 QAY-24000 ..................................................................................................... 132
Table 11-7 Well #2 Interlocks............................................................................................................. 134
Table 11-8 Well #4 Interlocks............................................................................................................. 136
Table 11-9 Well ILS and Well PLET Interlocks ................................................................................... 138
Table 11-10 P35 High Control Nozzle (SDF 130801) ......................................................................... 139
7 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
1.0 INTRODUCTION
1.1 Development
The Gunflint Field is located in Mississippi Canyon Block 948, in approximately 6,100’ water depth.
The Gunflint reservoir is in a Middle/Lower Miocene formation and is expected to produce high GOR
oil, with shut-in tubing pressure of approximately 12,620-psia. Evaluation of the initial appraisal wells
indicated two likely development options: subsea tieback to an existing host, or subsea production to
a new-build local host. The tieback option was eventually selected. The Tieback is envisioned as a
dual flowline loop allowing for round-trip pigging and dead-oil circulation. Hydrocarbons from wells
MC 948#4 and MC 948#2 will be routed through two 8” flowlines to Williams’ Gulfstar 1 Spar (MC
724).
8 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
1.2 Glossary
Abbreviation Term
AISI American Iron and Steel Institute
API American Petroleum Institute
ASME American Society of Mechanical Engineers
BSEE Bureau of Safety and Environmental Enforcement
CDU Communication Distribution Unit
CFR Code of Federal Regulations
CI Chemical Injection
cP centipoise
CRA Corrosion Resistant Alloy
F/L Flowline
FOPR Flow Oil Production Rate
FGPR Flow Gas Production Rate
FWHP Flowing Well Head Pressure
FWPR Flow Water Production Rate
GOR gas/oil ratio
ILS In-line sled
in. inch
LAST Lowest Anticipated Service Temperature
NTL Notice to Lessees
mm millimeter
MD Measured Depth
MPFM Multi-Phase Flow Meter
NACE National Association of Corrosion Engineers
MSCF thousand standard cubic foot
OD Outside Diameter
OHTC Overall Heat Transfer Coefficient
Pcf pounds per cubic feet
PIP Pipe-In-Pipe
PLET pipeline end termination
PP polypropylene
PRE Pitting Resistance Equivalent
psi pounds per square inch
PWHT Post-Weld Heat Treat
RP recommended practice
Scf standard cubic feet
SCR Steel Catenary Riser
SF Safety Factor
SITP Shut-In Tubing Pressure
Stb stock tank barrel
SMYS Specified Minimum Yield Strength
SS Stainless Steel
9 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Abbreviation Term
SCSSV Surface Controlled Sub-Surface Safety Valve
STB/D Stock Tank Barrel per Day
TOR Top Of Riser
TTR Top Tensioned Risers
TVD True Vertical Depth
WD Water Depth
VIT Vacuum Insulated Tubing
WT Wall Thickness
10 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
1.3 Definitions
Term Definition
Action to Secure Action performed to prevent hydrate formation in the subsea system by dry oiling the
flowlines or by treating with methanol (bullheading into wellbore or injection into flowline
jumper)
Arrival Temperature Flowing temperature of the fluids at the boarding facility
Bubble Point The temperature and pressure at which the first bubble of gas forms from the crude oil or
condensate
Chilly Choke The term used to describe excessive cooling when starting up a well into a pipeline under
low pressure. For a period of time, the piping downstream of the choke may dip below the
design temperature of the metal until the well warms up.
Cloud Point The temperature at which a liquid (as petroleum oil) begins to cloud (as from separation of
wax on cooling).
Cooldown Time The minimum preservation temperature for a shutdown before the appearance of hydrates.
Expressed in the number of hours before the hydrate mitigation operations needs to be
completed (e.g., dead oiling, blowdown).
Hydrate Dissociation The pressure at a corresponding temperature of the hydrate curve, below which hydrates
Pressure (HDP) will not form.
Hydrate Dissociation The temperature at a corresponding pressure on the hydrate curve, above which hydrates
Temperature (HDT) will not form.
Inhibited Production Live production fluids which have been treated with methanol or LDHI (low dosage hydrate
inhibitor) so that any produced or condensed water in the flowline, tree, or wellbore will not
form hydrates at ambient conditions and system pressures.
No-Touch Time The period of time following a shut-in, in which the equipment is allowed to cool without the
need for operator intervention. Note that within the no-touch time, the equipment may be
restarted without requiring any hydrate mitigation operations (e.g., methanol injection,
blowdown).
Pour Point With continued cooling, this is the temperature at which the liquid petroleum turns to gel.
11 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
2.1 Location
Reference [6]
The Gunflint Field is located in Mississippi Canyon Block 948, in approximately 6,100’ water depth.
The Gunflint reservoir is in a Middle/Lower Miocene formation and is expected to produce high GOR
oil, with shut-in tubing pressure of approximately 12,620-psia. Evaluation of the initial appraisal wells
indicated two likely development options: subsea tieback to an existing host, or subsea production to
a new-build local host. The tieback option was eventually selected. The Tieback is envisioned as a
dual flowline loop allowing for round-trip pigging and dead-oil circulation. Hydrocarbons from wells
MC 948#4 and MC 948#2 will be routed through two 8” flowlines to Williams’ Gulfstar 1 Spar (MC
725).
Noble Energy is the operator of the Gunflint Field. Partners in the Field development include
Ecopetrol, Marathon and Samson.
12 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
13 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
2.2 Environment
The well water depths, coordinates, MD and TVD are listed in Table 2-1:
Water
Easting Northing MD TVD
Landmark Depth
(ft) (ft) (ft) (ft) (ft)
MC 948#2
6,081.66 1,075,686.0 10,170,574.0 24,330 24,330
OCS-G 28030
Proposed
MC 948#4 6,087.95 1,075,556.73 10,170,358.56 - -
OCS-G 28030
MC 992#1
6,065.69 1,073,894.1 10,171,639.7 26,675 26,675
OCS-G 24133
MC 948#1
OCS-G 28030 6,077.16 1,075,833.8 10,170,644.2 - -
(see Note 2)
Note 1 Wells are assumed to be fully vertical for flow assurance work
Note 2 Exploration well is not intended to be completed, but to be considered for clashing and field
architecture
14 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
15 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Property Units Sample 2.08 Sample 2.09 Sample 2.10 Sample 2.11
Carbonate (mg/l) - - - -
Magnesium (mg/l) 93 81 68 54
16 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
17 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• Control for the ICV comes directly from the wellhead using hydraulic control lines.
18 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Feature Requirement
Tree Type FMC - Horizontal Subsea Tree
Tree Size 5” Production X 2” Annulus
Maximum Rated Working Pressure 15,000 psi
Maximum Rated Water Depth 10,000 feet
Temperature Rating U: (0°F to 250°F)
Product Specification Level PSL-3
Performance Requirement Level PR2
Material Class - Production FF
Material Class - Annulus EE
NACE Compliant No
API 17D Monogram Yes
Field Design Life 20 years
Control System Operating Pressure 5,000 psi
Tree Insulation Production flowpath insulated outboard of PMV
Guide Funnel Configurations BOP to Tree - Funnel down on BOP
Tree to Wellhead - Funnel down on Tree
SCM & Choke - Funnel up
Wellhead Interface TBA
Tree Isolation Sleeve Interface TBA
Tree Mandrel Profile 18-3/4” H-4 with VX/VT Gasket prep
Extended length to accept HDH4 connector
Tree Drift Diameter TBA
Chemical Injection 3x Downhole
3x Tree
Downhole Penetrations TBA
Controls Electro-hydraulic MUX, ProServe
Tree-mounted Instruments TBD
Annulus Service Port 2” nominal Unitech UH-550 connector
2”-15K FSC actuated isolation valve
LTPC w/ 17H hot stab port & ¼-turn isolation valve
Parking receptacle for UH-550
Crossover Arrangement Dual FSC XOV’s
AWV positioned between XOVA and XOVP
Additional Information 3x DH HP / Intelligent Well
1x DHPT penetrator assembly
2x SCSSV HP Lines (rated to 15,000 psig at mudline)
19 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• 6” Header valves on well end PLETs are dual-acting “Fail As-Is” gate valves
• MC 948 #2 will be a non-clad PLET at both the Well and the Flowline.
20 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
3.6.1 Flowlines
• 8” nominal X-65
3.6.2 Risers
• 8” nominal X-65
• Wet-insulated (5LPP)
21 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Reference [6]
22 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
23 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
24 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
25 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
26 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• Monitors and controls subsea trees and distributes flow assurance chemicals.
• The Main Umbilical tubes are terminated at Gulfstar 1, in a bulkhead plate and connected to the
umbilical hang-off.
• The electrical quad cables and fiber optic cables are terminated in a terminal box supplied as part
of the subsea equipment.
• ROV-installed flying leads connect this SUTA to the Subsea Distribution Unit (SDU) and
Communication Distribution Unit (CDU).
• The flying leads connect from the SDU and CDU to the well MC 948#2 and MC 948#4.
27 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• The actuator is ‘fail-as-is’, i.e. it is not to be moved by changes in LP supply pressure without an
electronic actuation signal to the SCM.
• The choke has both electronic and visual position indications. The electronic position indicator is
linear variable differential transformer (LVDT) with digital output.
• The chart for the Gunflint Master Flo choke is shown in Figure 3-6.
28 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• Downhole injection (3): Continuous asphaltene inhibitor and corrosion/scale inhibitor (pre-
mixed cocktail) are planned deep (through CID2 and CID3), with continuous LDHI injected
above the SCSSV (through CID1)
• Subsea tree injection (3): Two methanol injection points (CIT1, between PMV/PWV, and
CIT2, upstream of FIV) are provided. Paraffin inhibitor injection is provided via CIT3 as needed.
3.10.1 Methanol Injection System
Hydrate inhibition with methanol is selected for protecting isolated parts of the subsea production
system (tree and well jumper). Methanol will be required for batch treatment during the following
operations:
• In special cases (for example during hydrate remediation or treatment of dead legs)
3.10.2 Low Dosage Hydrate Inhibitor (LDHI) Injection System
• LDHI is planned for downhole continuous injection above the SCSSV for continuous hydrate
mitigation.
3.10.3 Corrosion/Scale Inhibitor Injection System
• Corrosion/Scale is injected continuously downhole.
• Corrosion inhibitor is injected to control the interior corrosion of the metal surface from the well
to the riser.
• Scale inhibitor (if required, based on water production and chemistry) is injected to prevent
deposition of inorganic scales (calcium carbonates, barium sulfate etc.) within the well and/or
the subsea production system.
3.10.4 Asphaltene Inhibitor Injection System
• Asphaltene inhibitor downhole is continuously injected close to the reservoir perforation zone
(just above the production packer).
3.10.5 Paraffin Inhibitor
• Continuous injection of paraffin inhibitor is not planned, however as a contingency and if
needed; paraffin inhibitor can be injected downstream of the FIV through CIT3.
29 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Water Tieback
Location Easting Northing
Host Depth Distance
(ft) (block) (ft) (ft) (ft)
30 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
31 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
4.3.1 Pigging
Flowlines, Flowline jumpers, risers, and ILS/PLETs are designed for operational pigging. Pigging will
not be required for the well jumpers.
All flowlines are designed to accommodate maintenance and inspection pigging. Flowline sections in
the pigging route will preclude sudden inside diameter (ID) changes. When a change in diameter is
required, a taper of 1:6 or shallower will be provided on the diameter. Thus, at least six length units in
the axial pipe direction will be provided for one length unit of diameter change.
4.3.2 Blowdown
Flow Assurance analysis shows, post blowdown pressures at the deepest point in subsea flowline will
range between 250-400 psi. For the corresponding seabed temperatures of 40 °F, the fluid remains in
hydrate forming zone.
Blowdown cannot be used as an effective hydrate mitigation strategy due to the resulting pressure at
the wellhead location (deepest points in the system) not being outside of the hydrate formation
temperature. However, blowdown can be carried out to buy out additional time (34 hours to 50 hours)
in case hot oil circulation is not possible.
32 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
33 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• 4 to 8 hours:
o Displace jumper (2 x jumper volume) with methanol
o Displace tree with 3-5 bbl of methanol
Table 5-1 Methanol Requirement for Gunflint Well Jumper, Trees and Dead Leg Treatment
Notes:
1. Methanol volume required for two jumper flushing; one jumper volume = 4 bbl
2. Time includes 5 min. allocated for valve switching and alignment
3. Volume for light treatment of tree piping (up to ~100 ft of tubing).
34 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Table 5-2 Estimated times for bottoms-up based on avg. liquid production rates
35 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Proceed to
Dead Oiling
No
OPEN AMV.
Yes AP >?
Note:
Proceed to Refer to section 6.1 or 6.2 for
Annulus Management No actual step-by-step procedure.
Proceed to Flowline
Back Pressure
No
36 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Open PCV.
Close PCV.
37 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Initial Conditions:
- The tree has been shutdown for < 4 hours
- Flowline is receiving production from other well
- Both wells will be flowing into the same flowine
Note:
Based on WC, is
LDHI limitations will be exceeded
Yes MeOH injection at
by watercut restraints during Late
Tree desired?
Life conditions.
OPEN AMV.
Yes AP >?
Proceed to
Annulus Management No
Proceed to Flowline
Back Pressure
No
Note:
Refer to section 6.3 for actual
Ensure pressure across BSDV is equalized and OPEN. step-by-step procedure.
38 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Open PCV.
Close PCV.
39 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
START
Initial Conditions:
- Wells are shut-in
- BSDVs are closed
- Methanol system is available
SD > 4
No
hours?
Proceed to
Warm Restart
Yes
SD 8-10
No
hours?
Proceed to
applicable Restart
Yes
Note:
Bullhead methanol down to SCSSV (xxx bbl),
Refer to section10.1 for actual
in well 948 #2 (VIT completion) – if SCSSV closed
step-by-step procedure.
Hurricane SD
or /
No
SD expected to be
extended (a week)?
Proceed to
applicable Restart
Yes
40 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Depressurize flowlines
Is dead oiling
No
available?
Yes
41 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Table 5-3 Achievable MeOH rates – _____ psi pump discharge pressure
HOLD
Table 5-4 Methanol deliverability for _____ psi fixed pump pressure
42 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
43 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5.5.1 Valve
When timer is expired, MCS initiates a valve closure command to the corresponding valve listed in
this column.
5.5.2 Timer
Timers are used for different alarm scenarios to initiate valve closure. If the shutdown signal is
cleared prior to completion of the shutdown sequence, the sequence is to terminate until the
Underwater Safety Valve 1 (USV1) and Alternate Isolation Valve (AIV) are in the close position. Then,
Timers are reset. This method ensures the well is shut-in and in a safe state before restart for
production.
HMI Valve Open command on subsea valves are inhibited while a shutdown signal is active.
5.5.3 Activate
Timer expiration without using the timer reset.
44 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
46 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
47 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
7. Equalize pressure across CIT2 and open. Required topside pressure is DPT minus 2312
psi.
8. Open PWV. When UPT pressure equals DPT, open PWV.
If PMV and SCSSV are open, skip to step 12.
9. Check UPT/DPT/FPT readings.
11. Equalize pressure across PMV and open. When UPT/DPT equals last recorded SITP,
PMV is equalized.
Flow Well
13. Close PCV.
14. Start available LDHI Injection pump, Inject LDHI according to watercut vs. flowrate
equalize pressure across CID1 and open. table in Section 5.
15. Start available AI Injection pump, equalize Inject AI according to chart provided in Section
pressure across CID3 and open. 5.
48 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
18. Start available PI Injection pump, equalize Inject PI according to chart provided in Section
pressure across CIT3 and open. 5.
19. Start available CI/SI Injection pump, Inject CI/SI according to chart provided in
equalize pressure across CID3 and open. Section 5.
20. Adjust chemical injection rates as Refer to Injection Rates in Section 5.
required.
49 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
50 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
51 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
52 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
7. Equalize pressure across CIT2 and open. Required topside pressure is DPT minus 2312
psi.
8. Open PWV. When UPT pressure equals DPT, open PWV.
If PMV and SCSSV are open, skip to step 13.
9. Check UPT/DPT/FPT readings.
11. Equalize pressure across PMV and open. When UPT/DPT equals last recorded SITP,
PMV is equalized.
Flow Well
13. Close PCV.
14. Start available LDHI Injection pump, Inject LDHI according to watercut vs. flowrate
equalize pressure across CID1 and open. table in Section 5.
15. Start available AI Injection pump, equalize Inject AI according to chart provided in Section
pressure across CID3 and open. 5.
16. Open FIV.
18. Start available PI Injection pump, equalize Inject PI according to chart provided in Section
pressure across CIT3 and open. 5.
53 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
54 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
55 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
56 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
7.1.1 Philosophy
In the early life of production, both the wells MC 948#4 and MC 948#2 will be flowing through a
dedicated flowline and riser as shown in Figure 7-1. The production through MC 948#4 and MC
948#2 will reduce drastically during mid and late life of the field. Fluids from both the wells will be
commingled in late life of field as shown in Figure 7-2 to minimize the likelihood of slugging and to
reduce wax formation risk (Ref [5]).
7.1.3 Turndown
Turndown rates are recognized when producing subsea field pairs with operating challenges such as
slugging, lower arrival temperatures, thus, hydrate, and wax issues etc. The gunflint system shows
likelihood of slugging issues when individual well flowrates drop below ~9,000 STBPD. The limiting
flowrate at which the slugging will be predominant is based on the arrival pressure of 650 psig. At
higher arrival pressure, system can be operated for much lower flowrates without slugging tendencies
(Ref [5]).
57 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Host
8” WET
Insulated Riser MC 948#2
8” WET
Insulated Riser
8” WET
Insulated
Jumper
8” WET
Insulated
Jumper
MC 948#4
58 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Host
8” WET
Insulated Riser MC 948#2
8” WET
Insulated Riser
8” WET
Insulated
Jumper
8” WET
Insulated
Jumper
MC 948#4
59 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
3. Pressure up on AWV with methanol through Methanol pump pressure plus hydrostatic
AMON line until (PI-9352C) is equal to last pressure of methanol (2112 psi) should be
recorded pressure minus 2212. equal to pressure plus 100 psi.
4. Open AWV.
7. Bleed annulus pressure to topsides. When When pressure stabilizes, re-route valves to
pressure stabilizes, proceed to next step. inject methanol into AMON line.
Record volume of fluid bled off.
Displace Annulus Fluids Into Production Flow
9. Start methanol pump, and inject methanol Inject three times (minimum) the volume
into the AMON line, through the crossover that was bled off, back into the flowline.
loop (XOVP), and into the production flow, to
displace bled off annulus fluids.
10. Close XOVP and XOVA.
60 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
61 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
62 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Ref [6]
During normal production operations, downhole, subsea and topsides pressure and temperature
information verifies that the system is performing properly. It monitors and alarms for abnormal
conditions, also data monitoring, and interpolation, which reduce hydrate formation risk in the subsea
system.
Pressure and temperature gauges monitor the production flow stream at various subsea locations as
follows:
• Downhole – Gunflint production wells are equipped with permanent downhole pressure and
temperature gauges located just above the perforations. By having downhole gauges, a continual
measurement of downhole pressure and temperature will be made without rig intervention and
interruption of production. The gauges will be used to conduct conventional pressure transient
test, interference and static test. The downhole sensors will also enable a wellbore and network
flowline model to run real time.
• Production Tree - subsea pressure and temperature sensors are located as follows:
o Dual-pressure and dual-temperature gauges, UPT1/UPT2 located between the PMV and
PWV monitors the flowing wellhead temperature and pressure on the tree
o Dual-pressure and dual-temperature gauges, DPT1/DPT2, located downstream of the
production choke valve monitors flowing conditions in the well jumper
o Dual-pressure and dual-temperature gauges APT1/APT2, located between the AMV and
AWV, monitors annulus pressure and temperature
o Dual-pressure and dual-temperature gauges FPT1/FPT2, located downstream of FIV. These
gauges will be used to monitor the pressure and temperature at the PLETs during short term
and extended shutdowns. During system startup, the operator will be able to confirm the
production flowline pressures to establish pressure communication with the subsea system.
In addition to the pressure and temperature sensors on the trees, there is a choke position indicator
(CPI) that is located on each production choke.
At the host platform, the arrival temperature and pressure will be monitored to assure operation
above both the hydrate and wax appearance points.
63 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Four alarm settings can be programmed at the MCS for each subsea sensor; they are:
• High – Low
Pressure alarm(s) will be set and maintained for downhole pressure to monitor drawdown.
Pressure alarm(s) will be set and maintained to monitor for annulus pressure increase or decreases
from the last diagnostic test.
If failure of the Annulus Pressure Transmitter (APT) is encountered, engineering approval is required
for an acceptable duration between annulus pressure checks. These checks should be performed
according to the approved schedule.
The XOVP and XOVA remain closed except when performing these checks.
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
64 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
65 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
The umbilical consists of one ¾ʺ ID tube for methanol injection. Figure 7-4 shows a schematic of
MeOH injection system along with ½ʺ ID steel flying leads.
66 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
67 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Methanol injection rates were calculated against various injection pressures like, shut-in tubing
pressure; maximum expected flowing pressure downstream and upstream of choke and average
flowing pressure downstream of choke. Table 7-3 is a summary of maximum possible methanol
injection rate with pump discharge pressure of HOLD psia. Table 7-4 shows summary of dosage
requirement of LDHI, CI/SI combination, asphaltene injection and PI injection requirements for
operating Gunflint subsea field.
Table 7-3 Summary of MeOH injection rates (Pdis = ____ psia) (HOLD #)
MeOH pump discharge Pressure at injection point Max deliverable MeOH rate
pressure (psia) (psia) (gpm)
3,600
5,540
HOLD
9,370
12,620
68 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
• Step Size
• Pulse Width
• Pulse Period
• Solenoid Duration
• Max difference between Calculated Position and Sensor Position (Default value of 10%)
The operator can specify the position open, in terms of percentage open, to which the choke should
be operated, and the SEM shall operate the choke in either the Open or Close direction until the
require position is reached. The SEM shall determine the number pulses based on the current
position which is indicated by the position sensor, however it is possible from the dialogue window to
de-select sensor mode in which case the SEM shall use the calculated position. It is possible to reset
the calculated position from the dialogue window. During an operation the calculated position is
maintained by the SEM, as a percentage open, based on the number of pulses issued.
The MCS shall not limit the number of Choke operations triggered, the MCS shall check against any
interlocks on the Choke.
69 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
4. Pressure up on PWV with methanol through Methanol pump pressure plus hydrostatic
CIT2 until DPT equals UPT. pressure (2112 psi) should be equal to, or
greater than the UPT plus 100 psi.
5. Open PWV.
4. Pressure up on PMV with methanol through Methanol pump pressure plus hydrostatic
CIT2 until UPT equals SITP. pressure (2112 psi) should be equal to, or
greater than the SITP plus 100 psi.
5. Open PMV.
70 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
2. Pressure up on AWV with methanol through Methanol pump pressure plus hydrostatic
AMON line until (PI-9352C) is equal to last pressure of methanol (2112 psi) should be
recorded pressure minus 2212. equal to pressure plus 100 psi.
3. Open AWV.
71 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
72 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
73 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
74 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
75 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
76 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
77 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
78 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
79 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
80 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5. AAV closes.
6. AMV closes.
7. AWV closes.
8. FIV closes.
81 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
82 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5. AAV closes.
6. AMV closes.
7. AWV closes.
8. FIV closes.
83 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
84 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
8.6 SESD activated from Platform or a TSE at BSDV (SESD / BSDV TSE)
The host facility initiates a SESD/BSDV TSE because of a problem in the subsea system or a TSE
associated with the BSDV.
5. AAV closes.
6. AMV closes.
7. AWV closes.
8. FIV closes.
85 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AFTER – SESD ACTIVATED FROM PLATFORM OR A TSE AT BSDV (SESD / BSDV TSE)
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
86 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
8.7 Subsea ESD activated from Mobile Offshore Drilling Unit (SESD MODU)
The rig or intervention vessel initiates a SESD MODU because of dropped objects.
5. AAV closes.
6. AMV closes.
7. AWV closes.
8. FIV closes.
87 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AFTER – SUBSEA ESD ACTIVATED FROM MOBILE OFFSHORE DRILLING UNIT (SESD MODU)
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
88 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
4. AAV closes.
5. AMV closes.
6. AWV closes.
7. FIV closes.
89 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AFTER – SHUT-IN
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
90 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
4. AAV closes.
5. AMV closes.
6. AWV closes.
7. FIV closes.
91 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AFTER – SHUT-IN
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
92 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
4. AAV closes.
5. AMV closes.
6. AWV closes.
7. FIV closes.
93 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AFTER – SHUT-IN
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
94 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
BEFORE / AFTER SCHEMATICS not shown following procedures 8.11. through 8.25.
95 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
96 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
8.22 LDHI Injection Shutdown (Pump Flow Rate < 120 gal/day)
8.23 Asphaltene Inhibitor Injection Shutdown (Pump Flow Rate < 12 gal/day)
97 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
98 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
2. Place all boarding valves (BSDVs) in Each boarding valve (BSDV) must be
bypass. manned continuously while in bypass.
3. Block and flag the LP and HP umbilical The HPU must be manned continuously
lines at the HPU to safeguard against while the umbilicals are blocked in.
blowdown of the umbilicals.
4. Activate ESD.
Record Information
5. Confirm that signal was received to initiate
closure of the BSDV (boarding valve).
6. Confirm that the ESD timers begin Timers can be set to a shorter duration to
countdown within MCS reduce test time. After the ESD test, timers
must be returned back to their normal
setting as defined in the DWOP.
7. Confirm that closure signals were sent to Refer to appropriate test form in Appendix E
the subsea wells.
8. Record successful initiation of the ESD Refer to appropriate test form in Appendix E
timers.
9. Reset ESD prior to expiration of the HPU
blowdown timers.
10. Remove all wells, and boarding valves out of
bypass.
11. Place umbilicals back in communication with Ensure timers have been reset back to
HPU. original times as defined in the DWOP.
12. End of procedure
99 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Shut-In Well
5. Close all chemical injection valves and The automated sequence closes the
shutdown any unnecessary injection pumps, CITs/CIDs, prior to closing the FIV. The
prior to PCV closure on test well. CITs/CIDs are manually closed as a
precaution in the event the sequence does
not execute as planned.
6. Close PCV on well to be shut-in.
8. Place all the wells except the ‘ESD’ well in The MCS HMI must be monitored
bypass. continuously while the wells are in bypass.
9. Place all boarding valves (BSDVs) except Each boarding valve (BSDV) must be
the ‘ESD’ BDSV in bypass. manned continuously while in bypass.
10. Block and flag the LP and HP umbilical The HPU must be manned continuously
lines at the HPU to safeguard against while the umbilicals are blocked in.
blowdown of the umbilicals.
Activate ESD & Record Valve Closures
11. Activate ESD.
13. Confirm that the ESD timers begin Timers can be set to a shorter duration to
countdown within MCS reduce test time. After the ESD test, timers
must be returned back to their normal
setting as defined in the DWOP.
14. Record closure of the USV when the USV Refer to appropriate test form in Appendix E
timer expires.
15. Record closure of the SCSSV when the Refer to appropriate test form in Appendix E
SCSSV timer expires.
16. Reset ESD prior to expiration of the HPU
blowdown timers.
100 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
101 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
102 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
6. Place non-test well(s) in Test Mode (bypass) HMI must be continuously monitored while
on subsea MCS. wells in test mode.
7. Activate Subsea ESD and confirm closure of Test Well: Confirm CIT1, CIT2, CIT3, CID1,
the following valves on the test flowline and CID2, CID3, XOVP, XOVA, FIV, FIV, AAV,
test well. Record closure time of USV1. PWV, PMV, AWV, AWV, AMV and SCSSV
closure. PCV will stop.
Refer to Gunflint Subsea Cause and Effects
8. Reset Subsea ESD after verifying timer T9 Timer T9 closes the SCSSV valve. It is set
starts to countdown. at 7 minutes.
9. Place devices back in service.
103 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
104 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
105 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
106 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
107 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
108 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Note:
1. Should the designated primary USV fail to test or meet the allowable leakage rate as outlined above,
notify the appropriate BSEE GOMR District Office and designate another certified subsea valve as
the primary USV. Once designated, test the valve for conformance with the conditions specified in the
NTL mentioned above.
109 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5. Record subsea wellhead pressure using UPT/DPT pressure readings are not test-
UPT/DPT gauges. related information.
6. Close topsides choke. Allow pressure to stabilize.
Gulfstar 1 gauge - tag # ______
7. Close pipeline BSDV.
8. Monitor pipeline pressures for leakage for 5 The boarding valve (BSDV) is tested for
minutes. zero leakage.
9. Record test data.
Restart Well
10. If no leak detected, proceed to Warm
System Restart, when ready to resume
production. If leak detected, notify
Supervisor.
110 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
BSDV BSDV
HOST AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
FIV
WELL MC 948 #2
SCSSV
MPFM
GLIV
N-PL1-BV DH
PT
5" BV 5" BV
SOUTH FLOWLINE
S-PL2-HV1 S-PL2-HV2
5" BV
WELL MC 948 #4
111 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
6. Open PCV as needed and bleed off 20% of Open PCV 5 steps at a time.
SITP. Note: Differential across the SCSSV
should be at least 20% of SITP.
7. Close FIV.
Test SCSSV
8. Record pressure and temperature between
SCSSV and FIV using UPT and the DPT.
9. Monitor for pressure build up for 30 minutes. Acceptable leakage rate is 400 cc/min oil, or
Record pressure and temperature at end of 15 scf/min gas.
30 minutes.
10. Enter pressure and temperature into the Send documentation generated by the
Noble Energy Leakage Rate Calculator. The Leakage Rate Calculator to the Noble
calculator will determine whether the SCSSV Production Superintendent.
passes or fails.
Fail: Leave well shut in until further
evaluation.
Pass: Continue to next step.
Restart Well
11. Proceed to applicable Restart, when ready
to resume production.
112 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
113 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
6. Open PCV and bleed down to flowline Open PCV 5 steps at a time.
pressure.
7. Close FIV.
Test SCSSV
8. Record pressure and temperature between
PWV and FIV using DPT.
9. Monitor for pressure build up for 15 minutes. Acceptable leakage rate is 400 cc/min oil, or
Record pressure and temperature at end of 15 scf/min gas.
15 minutes.
10. Enter pressure and temperature into the Send documentation generated by the
Noble Energy Leakage Rate Calculator. The Leakage Rate Calculator to the Noble
calculator will determine whether the USV Production Superintendent.
passes or fails.
Fail: Leave well shut in until further
evaluation.
Pass: Continue to next step.
Restart Well
11. Proceed to applicable Restart, when ready
to resume production.
114 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
115 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
1. Check other well’s flowrates / drawdowns Match pressures using the latest Well
that flow into affected flowline. Information Report
Ramp down as necessary to maintain target
flowing bottomhole pressure in other well(s)
in the flowline.
2. Close all chemical injection valves (on The CITs/CIDs are manually closed prior to
affected well) and shutdown any the PCV. As the PCV is ramped closed,
unnecessary injection pumps, prior to PCV tree and tubing pressure rises, thus
closure. increasing the risk of plugging chemical
injection lines.
3. Close PCV. When closed, proceed to next Ensure PCV is closed by CPA or CPI
step. reading of 0.5% or less.
4. Monitor annulus pressure during shut-in. If pressure exceeds alarm set point,
proceed to Annulus Management.
5. Close PMV (USV).
6. Open PCV and bleed down to flowline Open PCV 5 steps at a time.
pressure.
7. Close FIV.
Test SCSSV
116 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
117 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
6. Open PCV as needed and bleed off 20% of Open PCV 5 steps at a time.
SITP. Note: Differential across the SCSSV
should be at least 20% of SITP.
7. Close PCV. Ensure PCV is closed by CPA or CPI
reading of 0.5% reading or less.
8. Close PWV (USV).
9. Open PCV and bleed down to flowline Open PCV 5 steps at a time.
pressure.
10. Close FIV.
118 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
14. Enter pressure and temperature into the Send documentation generated by the
Noble Energy Leakage Rate Calculator. The Leakage Rate Calculator to the Noble
calculator will determine whether the USV Production Superintendent.
passes or fails.
Fail: Leave well shut in until further
evaluation.
Pass: Continue to next step.
Restart Well
15. Proceed to applicable Restart, when ready
to resume production.
119 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
120 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5. Monitor annulus pressure during shut in. If pressure exceeds set point, proceed to
Annulus Management.
6. Collect data required for the build up test. Send data to be analyzed to Noble Energy
reservoir engineer.
7. Close PCV when all build up test data has Ensure PCV is closed by CPA or CPI
been collected. When closed, proceed to reading of 0.5% or less.
next step.
8. Proceed to applicable Restart, when ready
to resume production.
121 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
SIV CID2
AI
CID3
122 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
5. Open FIV.
9. Inject 6 bbl of methanol into well jumper. Inject 2x volume methanol into well jumper.
123 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
124 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
TREATING JUMPER
AMON Line
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
LDHI
CID1
(2" UH-575) CI/SI
CID2
SIV AI
CID3
125 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
126 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
127 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Range 20000-20099
DESCRIPTION TAG
SDU ZZZ-20000
NPL2 ZAY-20001
NPL3 ZAY-20002
SPL2 ZAY-20003
WELL #2 JUMPER ZAY-20004
WELL #4 JUMPER ZAY-20005
FLOWLINE JUMPER ZAY-20006
BULKHEAD PLATE ZZZ-20007
NPL2-BV HV-20008
NPL2-HV1 XV-20009
NPL2-HV2 XV-20010
Range 20400-20499
DESCRIPTION TAG
NPL1 ZAY-20400
NPL1-GLIV XV-20401
SPL1 ZAY-20402
SPL1-GLIV XV-20403
LP SUPPLY (FUTURE) PT-20404
LP RETURN (FUTURE) ZAY-20405
128 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Range 21000-21999
DESCRIPTION TAG
PSD XY-21000
PSHL - NORTH XY-21001
PSHL - SOUTH XY-21002
ESD XY-21003
SESD XY-21004
SESD MODU XY-21005
TEST ESD XY-21006
LP Bleed XY-21007
HP Bleed XY-21008
LOSS OF COMMUNICATION XY-21009
MEOH FLOW RATE FT-21010
LDHI1 FLOW RATE FT-21011
LDHI2 FLOW RATE FT-21012
LDHI3 FLOW RATE FT-21013
CI-SI1 FLOW RATE FT-21014
CI-SI2 FLOW RATE FT-21015
CI-SI3 FLOW RATE FT-21016
AI-PI1 FLOW RATE FT-21017
AI-PI2 FLOW RATE FT-21018
AI-PI3 FLOW RATE FT-21019
MEOH PUMP SD XY-21020
LDHI PUMP SD XY-21021
CI-SI PUMP SD XY-21022
AI PUMP SD XY-21023
129 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
130 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
131 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
LOCAL TAG
Hydraulic Valves 24001-24029 Manual Valves 24030-24039 Sensors 24040-24099
DESCRIPTION TAG DESCRIPTION TAG DESCRIPTION TAG
SCSSV-A SV-24001 SV1 HV-24030 ASD CT-24040 PT-24040 TT-24040
SCSSV-B SV-24002 SV2 HV-24031 APT-1 PT-24041 TT-24041
PMV XV-24003 THI HV-24032 APT-2 PT-24042 TT-24042
132 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
133 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
11.2 Interlocks
Reference [11]
Ref Command
Interlock Level Explanation
No. Tag Function
1. C PMV - C or PWV - C 1 Prevents SCSSV from closing while
well is flowing
SCSSVA
2. O (PMV - C or PWV - C) & 3 Ensures pressure can be equalized
XOVP & XOVA & AWV – C across SCSSV before opening
3. C PMV or PWV - C 1 Same as SCSSVA
4. SCSSVB O (PMV or PWV - C) & 3 Same as SCSSVA
XOVP – C & XOVA – C & AWV – C
5. C PCV < 1% & FIV – C 1 Prevent PMV from closing while well
is flowing
PMV
6. O PWV – C & PCV < 1% & 2 Ensure equalization across PMV
FIV - C & XOVP - C & XOVA - C & AWV - C before opening
7. C PCV < 1% & FIV - C 1 Prevent PWV from closing while
well is flowing
PWV
8. O PCV < 1% & 2 Ensure equalization across PWV
FIV - O & XOVP - O & XOVA - O & AWV - O before opening
9. C PCV < 1% 1
10. O (PMV - C & PWV - C) or 5 Opening up well using FIV should
FIV PMV- O & PWV - O & PCV < 1% & be avoided. It will damage valve
(NPL3-HV1 - O or NPL3-HV2 - O & and could harm completion.
SPL2-HV2 - O & SPL2-HV1 - O)
11. C - -
12. CIT1 O (CIT3 – C) & 2 Ensure correct routing of methanol
(MC 948#4-CIT1 - C) & (MC 948#4-CIT3 - C) injection. Prevent injection into
multiple wells simultaneously.
13. C - -
CIT2
14. O - -
15. C - -
16. CIT3 O (CIT1 - C) & 2 Wells #2 & #4 are on a common
(MC 948#4-CIT1 - C) & (MC 948#4CIT3 - C) MeOH circuit. This interlock helps
prevent commingled flow.
17. C - -
CID1
18. O - -
19. C - -
CID2
20. O - -
21. C - -
CID3
22. O - -
23. C - -
24. XOVP O (AAV - C) & (XOVA - C) 2 Ensures annulus cavity is isolated
from production flow.
134 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Ref Command
Interlock Level Explanation
No. Tag Function
25. C - -
26. O (AAV - C) & (XOVP - C) 2 Ensures annulus cavity is isolated
XOVA
from production flow.
27. C - -
28. AMV O (AWV - C) & (AAV - C) & (XOVP - C) 2 Ensures annulus cavity is isolated
from production flow.
29. C - -
30. AWV O (AAV - C) & (XOVP - C) & (XOVA - C) & 2 Wells MC 948#2 and #4 share a
(MC 948#4-AWV - C) common annulus monitor line.
31. C - -
AAV
32. O AAV is always interlock 2
33. C - -
PCV
34. O - -
135 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Ref Command
Interlock Level Explanation
No. Tag Function
1. C PMV - C or PWV - C 1 Prevents SCSSV from closing while
well is flowing
SCSSVA
2. O (PMV - C or PWV - C) & 3 Ensures pressure can be equalized
XOVP & XOVA & AWV – C across SCSSV before opening
3. C PMV or PWV - C 1 Same as SCSSVA
4. SCSSVB O (PMV or PWV - C) & 3 Same as SCSSVA
XOVP – C & XOVA – C & AWV – C
5. C PCV < 1% & FIV – C 1 Prevent PMV from closing while well
is flowing
PMV
6. O PWV – C & PCV < 1% & 2 Ensure equalization across PMV
FIV - C & XOVP - C & XOVA - C & AWV - C before opening
7. C PCV < 1% & FIV - C 1 Prevent PWV from closing while
well is flowing
PWV
8. O PCV < 1% & 2 Ensure equalization across PWV
FIV - O & XOVP - O & XOVA - O & AWV - O before opening
9. C PCV < 1% 1
10. O (PMV - C & PWV - C) or 5 Opening up well using FIV should
FIV PMV- O & PWV - O & PCV < 1% & be avoided. It will damage valve
(SPL2-HV1 - O & SPL2-HV2 - O & and could harm completion.
NPL3-HV1 - O or NPL3-HV2 - O)
11. C - -
12. CIT1 O (CIT3 – C) & 2 Ensure correct routing of methanol
(MC 948#2-CIT1 - C) & (MC 948#2-CIT3 - C) injection. Prevent injection into
multiple wells simultaneously.
13. C - -
CIT2
14. O - -
15. C - -
16. CIT3 O (CIT1 - C) & 2 Wells #2 & #4 are on a common
(MC 948#2-CIT1 - C) & (MC 948#2-CIT3 - C) MeOH circuit. This interlock helps
prevent commingled flow.
17. C - -
CID1
18. O - -
19. C - -
CID2
20. O - -
21. C - -
CID3
22. O - -
23. C - -
24. XOVP O (AAV - C) & (XOVA - C) 2 Ensures annulus cavity is isolated
from production flow.
25. C - -
26. O (AAV - C) & (XOVP - C) 2 Ensures annulus cavity is isolated
XOVA
from production flow.
136 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Ref Command
Interlock Level Explanation
No. Tag Function
27. C - -
28. AMV O (AWV - C) & (AAV - C) & (XOVP - C) 2 Ensures annulus cavity is isolated
from production flow.
29. C - -
30. AWV O (AAV - C) & (XOVP - C) & (XOVA - C) & 2 Wells MC 948#4 and #2 share a
(MC 948#2-AWV - C) common annulus monitor line.
31. C - -
AAV
32. O AAV is always interlock 2
33. C - -
PCV
34. O - -
137 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Ref Command
Interlock Level Explanation
No. Tag Function
1. C - -
NPL2-HV1
2. O - -
3. C - -
NPL2-HV2
4. O - -
5. C (MC 948#2-FIV - C & NPL3-HV2 - C) or 4
NPL3-HV1 (NPL3-HV2 - O & SPL2-HV2 - O & SPL2-HV1 - O)
6. O - -
7. C (MC 948#4-FIV - C or SPL2-HV1 - O) & 6
NPL3-HV2 (MC 948#2-FIV - C or NPL3-HV1 - O)
8. O - -
9. C (MC 948#4-FIV - C & SPL2-HV2 - C) or 4
SPL2-HV1 (SPL2-HV2 - O & NPL3-HV2 - O & NPL3-HV1 - O)
10. O - -
11. C (MC 948#4-FIV - C or SPL2-HV1 - O) & 6
SPL2-HV2 (MC 948#2-FIV - C or NPL3-HV1 - O)
12. O - -
138 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Bean Size
Mic Percent Stem Travel Percent Signal
Cv
(Steps)* Open (In.) Travel (4 - 20 Ma)
1/64 in. mm
0 0 0.0% 0 0 0.000 0.0% 4.000
1 0 0.0% 0 0 0.017 0.6% 4.100
2 0 0.0% 0 0 0.033 1.2% 4.200
3 0 0.0% 0 0 0.050 1.9% 4.300
4 0 0.0% 0 0 0.067 2.5% 4.400
5 0 0.0% 0 0 0.083 3.1% 4.500
6 0 0.0% 0 0 0.100 3.7% 4.600
7 0 0.0% 0 0 0.117 4.4% 4.700
8 0 0.0% 0 0 0.133 5.0% 4.800
9 0 0.0% 0 0 0.150 5.6% 4.900
10 0 0.0% 0 0 0.167 6.2% 5.000
11 0 0.0% 0 0 0.183 6.9% 5.100
12 0 0.0% 0 0 0.200 7.5% 5.200
13 0 0.0% 0 0 0.217 8.1% 5.300
14 0 0.0% 0 0 0.233 8.7% 5.400
15 0 0.0% 0 0 0.250 9.4% 5.500
16 0 0.0% 0 0 0.267 10.0% 5.600
17 0 0.0% 0 0 0.283 10.6% 5.700
18 0 0.0% 0 0 0.300 11.2% 5.800
19 0 0.0% 0 0 0.317 11.9% 5.900
20 0 0.0% 0 0 0.333 12.5% 6.000
21 0 0.0% 0 0 0.350 13.1% 6.100
22 0 0.0% 0 0 0.367 13.7% 6.200
23 0 0.0% 0 0 0.383 14.4% 6.300
24 0 0.0% 0 0 0.400 15.0% 6.400
25 0 0.0% 0 0 0.417 15.6% 6.500
26 0.0 0.0% 0 0 0.433 16.2% 6.600
27 0.0 0.0% 0 0 0.450 16.9% 6.700
28 0.1 0.0% 0 0 0.467 17.5% 6.800
29 0.1 0.0% 0 0 0.483 18.1% 6.900
30 0.3 0.0% 0 0 0.500 18.7% 7.000
31 0.4 0.1% 3 1 0.517 19.4% 7.100
32 0.5 0.2% 5 2 0.533 20.0% 7.200
33 0.6 0.3% 6 2 0.550 20.6% 7.300
34 0.7 0.5% 7 3 0.567 21.2% 7.400
35 0.8 0.6% 8 3 0.583 21.9% 7.500
139 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Bean Size
Mic Percent Stem Travel Percent Signal
Cv
(Steps)* Open (In.) Travel (4 - 20 Ma)
1/64 in. mm
36 0.9 0.7% 9 4 0.600 22.5% 7.600
37 1.0 0.8% 10 4 0.617 23.1% 7.700
38 1.0 1.0% 11 4 0.633 23.7% 7.800
39 1.2 1.1% 11 5 0.650 24.4% 7.900
40 1.2 1.2% 12 5 0.667 25.0% 8.000
41 1.4 1.4% 13 5 0.683 25.6% 8.100
42 1.5 1.5% 13 5 0.700 26.2% 8.200
43 1.5 1.6% 14 6 0.717 26.9% 8.300
44 1.6 1.7% 14 6 0.733 27.5% 8.400
45 1.8 1.9% 15 6 0.750 28.1% 8.500
46 1.9 2.0% 15 6 0.767 28.7% 8.600
47 1.9 2.1% 16 6 0.783 29.4% 8.700
48 2.0 2.3% 16 7 0.800 30.0% 8.800
49 2.1 2.4% 17 7 0.817 30.6% 8.900
50 2.1 2.5% 17 7 0.833 31.2% 9.000
51 2.2 2.6% 18 7 0.850 31.9% 9.100
52 2.2 2.8% 18 7 0.867 32.5% 9.200
53 2.3 2.9% 19 7 0.883 33.1% 9.300
54 2.4 3.0% 19 8 0.900 33.7% 9.400
55 2.5 3.2% 19 8 0.917 34.4% 9.500
56 2.6 3.3% 20 8 0.933 35.0% 9.600
57 2.7 3.4% 20 8 0.950 35.6% 9.700
58 2.8 3.6% 21 8 0.967 36.2% 9.800
59 2.9 3.7% 21 8 0.983 36.9% 9.900
60 3.0 3.8% 21 8 1.000 37.5% 10.000
61 3.1 3.9% 22 9 1.017 38.1% 10.100
62 3.1 4.1% 22 9 1.033 38.7% 10.200
63 3.2 4.2% 22 9 1.050 39.4% 10.300
64 3.4 4.3% 23 9 1.067 40.0% 10.400
65 3.5 4.5% 23 9 1.083 40.6% 10.500
66 3.7 4.6% 23 9 1.100 41.2% 10.600
67 3.8 4.8% 24 9 1.117 41.9% 10.700
68 3.9 5.0% 24 10 1.133 42.5% 10.800
69 4.0 5.2% 25 10 1.150 43.1% 10.900
70 4.1 5.3% 25 10 1.167 43.7% 11.000
71 4.2 5.5% 25 10 1.183 44.4% 11.100
72 4.3 5.6% 26 10 1.200 45.0% 11.200
73 4.4 5.8% 26 10 1.217 45.6% 11.300
74 5 6.0% 27 11 1.233 46.2% 11.400
140 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Bean Size
Mic Percent Stem Travel Percent Signal
Cv
(Steps)* Open (In.) Travel (4 - 20 Ma)
1/64 in. mm
75 5 6.2% 27 11 1.250 46.9% 11.500
76 5 6.3% 27 11 1.267 47.5% 11.600
77 5 6.5% 28 11 1.283 48.1% 11.700
78 5 6.6% 28 11 1.300 48.7% 11.800
79 5 6.8% 28 11 1.317 49.4% 11.900
80 5 6.9% 29 11 1.333 50.0% 12.000
81 5 7.1% 29 12 1.350 50.6% 12.100
82 6 7.3% 29 12 1.367 51.2% 12.200
83 6 7.4% 30 12 1.383 51.9% 12.300
84 6 7.5% 30 12 1.400 52.5% 12.400
85 6 7.7% 30 12 1.417 53.1% 12.500
86 6 8.2% 31 12 1.433 53.7% 12.600
87 7 8.8% 32 13 1.450 54.4% 12.700
88 7 9.6% 34 13 1.467 55.0% 12.800
89 7 10.4% 35 14 1.483 55.6% 12.900
90 8 11.3% 37 15 1.500 56.2% 13.000
91 8 12.3% 38 15 1.517 56.9% 13.100
92 8 13.3% 40 16 1.533 57.5% 13.200
93 8 14.4% 41 16 1.550 58.1% 13.300
94 8 15.6% 43 17 1.567 58.7% 13.400
95 9 16.8% 45 18 1.583 59.4% 13.500
96 9 18.1% 46 18 1.600 60.0% 13.600
97 10 19.4% 48 19 1.617 60.6% 13.700
98 11 20.7% 50 20 1.633 61.2% 13.800
99 11 22.1% 51 20 1.650 61.9% 13.900
100 12 23.5% 53 21 1.667 62.5% 14.000
101 13 24.9% 54 22 1.683 63.1% 14.100
102 13 26.4% 56 22 1.700 63.7% 14.200
103 14 27.9% 57 23 1.717 64.4% 14.300
104 15 29.4% 59 23 1.733 65.0% 14.400
105 16 31.0% 61 24 1.750 65.6% 14.500
106 17 32.5% 62 25 1.767 66.2% 14.600
107 17 34.1% 64 25 1.783 66.9% 14.700
108 18 35.7% 65 26 1.800 67.5% 14.800
109 19 37.4% 67 26 1.817 68.1% 14.900
110 20 39.0% 68 27 1.833 68.7% 15.000
111 21 40.6% 69 28 1.850 69.4% 15.100
112 22 42.3% 71 28 1.867 70.0% 15.200
113 22 44.0% 72 29 1.883 70.6% 15.300
141 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Bean Size
Mic Percent Stem Travel Percent Signal
Cv
(Steps)* Open (In.) Travel (4 - 20 Ma)
1/64 in. mm
114 23 45.6% 74 29 1.900 71.2% 15.400
115 24 47.3% 75 30 1.917 71.9% 15.500
116 25 49.0% 76 30 1.933 72.5% 15.600
117 26 50.7% 78 31 1.950 73.1% 15.700
118 27 52.4% 79 31 1.967 73.7% 15.800
119 28 54.1% 80 32 1.983 74.4% 15.900
120 28 55.8% 81 32 2.000 75.0% 16.000
121 29 57.5% 83 33 2.017 75.6% 16.100
122 30 59.2% 84 33 2.033 76.2% 16.200
123 31 60.9% 85 34 2.050 76.9% 16.300
124 32 62.6% 86 34 2.067 77.5% 16.400
125 33 64.2% 87 35 2.083 78.1% 16.500
126 34 65.9% 88 35 2.100 78.7% 16.600
127 34 67.5% 89 36 2.117 79.4% 16.700
128 35 69.2% 91 36 2.133 80.0% 16.800
129 36 70.8% 92 36 2.150 80.6% 16.900
130 37 72.4% 93 37 2.167 81.2% 17.000
131 38 74.0% 94 37 2.183 81.9% 17.100
132 39 75.6% 95 38 2.200 82.5% 17.200
133 39 77.2% 96 38 2.217 83.1% 17.300
134 40 78.7% 97 38 2.233 83.7% 17.400
135 41 80.2% 97 39 2.250 84.4% 17.500
136 42 81.7% 98 39 2.267 85.0% 17.600
137 42 83.2% 99 39 2.283 85.6% 17.700
138 43 84.6% 100 40 2.300 86.2% 17.800
139 44 86.0% 101 40 2.317 86.9% 17.900
140 44 87.3% 102 40 2.333 87.5% 18.000
141 45 88.7% 102 41 2.350 88.1% 18.100
142 46 90.0% 103 41 2.367 88.7% 18.200
143 46 91.2% 104 41 2.383 89.4% 18.300
144 47 92.4% 105 42 2.400 90.0% 18.400
145 48 93.5% 105 42 2.417 90.6% 18.500
146 48 94.6% 106 42 2.433 91.2% 18.600
147 49 95.6% 106 42 2.450 91.9% 18.700
148 49 96.6% 107 42 2.467 92.5% 18.800
149 49 97.5% 107 43 2.483 93.1% 18.900
150 50 98.3% 108 43 2.500 93.7% 19.000
151 50 98.9% 108 43 2.517 94.4% 19.100
152 50 99.5% 109 43 2.533 95.0% 19.200
142 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
Bean Size
Mic Percent Stem Travel Percent Signal
Cv
(Steps)* Open (In.) Travel (4 - 20 Ma)
1/64 in. mm
153 50 99.9% 109 43 2.550 95.6% 19.300
154 50 100.0% 109 43 2.567 96.2% 19.400
155 51 100.0% 109 43 2.583 96.9% 19.500
156 51 100.0% 109 43 2.600 97.5% 19.600
157 51 100.0% 109 43 2.617 98.1% 19.700
158 51 100.0% 109 43 2.633 98.7% 19.800
159 51 100.0% 109 43 2.650 99.4% 19.900
160 51 100.0% 109 43 2.667 100.0% 20.000
143 of 144
Document Title System Operations Manual
Document Number GUN-SS-GNS-OPS-PRO-0001
Document Revision A
12.0 APPENDIX A
12.1 References
144 of 144