Client :
Owner :
Bidder :
Notes :
TABLE OF CONTENT
1. COMPANY PROFILE ............................................................................................................................................. 3
2. SITE IDENTIFICATION........................................................................................................................................... 3
3. SCOPE OF WORK .................................................................................................. Error! Bookmark not defined.
4. OBJECTIVE, TARGET, AND PROGRAM ................................................................................................................. 5
4.1. Objective ..................................................................................................................................................... 5
4.2. Target .......................................................................................................................................................... 5
4.3. Program....................................................................................................................................................... 5
5. Project Organizational Structure......................................................................................................................... 6
5.1 Organizational Structure ............................................................................................................................. 6
5.2 Role And Responsibility ............................................................................................................................... 7
6. PPE Requirement ................................................................................................................................................ 6
6.1 Mandatory PPE............................................................................................................................................ 6
6.2 Depend on the type of working being performed ..................................................................................... 7
6.2 For initial issue of PPE ................................................................................................................................. 7
7. HSE MANAGEMENT SYSTEM .............................................................................................................................. 8
7.1 HSE and HIRADC Problem Identification ................................................................................................... 10
7.2 Safety Induction ........................................................................................................................................ 10
7.3 Tool Box Meeting ...................................................................................................................................... 10
7.4 Safety Checklist ......................................................................................................................................... 11
7.5 Sub-contractor Regulation ........................................................................................................................ 11
7.6 Inspection & Patrol ................................................................................................................................... 11
7.7 Reporting & analyzing ............................................................................................................................... 12
7.8 HSE Schedule ............................................................................................................................................. 13
7. HSE Control ....................................................................................................................................................... 14
7.1. Personal Protective Equipment (PPE) ......................................................................................................... 9
7.2. Protecting Equipment ............................................................................................................................... 10
7.3. HSE Facility ................................................................................................................................................ 14
7.4. HSE Activity ............................................................................................................................................... 14
7.5. Garbage and Waste Handling ................................................................................................................... 15
7.6. Green Construction ................................................................................................................................... 15
7.7. Measurement of Environmental Parameters ........................................................................................... 16
7.8. Method Statement.................................................................................................................................... 16
7.9. Job Safety Analysis ....................................................................................... Error! Bookmark not defined.
8. EMERGENCY RESPONSE .................................................................................................................................... 17
8.1. FIRST AID ...................................................................................................... Error! Bookmark not defined.
8.2. FIRE FIGHTER ................................................................................................ Error! Bookmark not defined.
8.3. SECURITY ...................................................................................................... Error! Bookmark not defined.
8.4. Man Power Identity Data ............................................................................. Error! Bookmark not defined.
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 3 of 24
1. COMPANY PROFILE
PT Selaras Daya Utama, also known as SEDAYU, is Indonesia’s leading Renewable Energy Engineering
Procurement Construction (EPC) company, especially in Solar Power Systems – providing world-class engineering,
procurement, installation and support services to the private and public sectors. As one of the pioneers in Indonesia’s
Renewable Energy sector since 2009, SEDAYU has developed Solar Power Systems throughout Indonesia for Indonesia
State Electricity company, i.e. PT Perusahaan Listrik Negara (PLN), Ministry of Energy and Mineral Resources, i.e.
ESDM, Ministry of Transportation, Bank Indonesia and many others.
Working together with the world’s leading technology providers in Renewable Energy, including the world’s
largest integrated solar module manufacturing company – REC Solar (Norway), Sharp Solar (Japan), Panasonic (Japan)
and the world’s leader in Solar Inverter technology – ABB (Switzerland), SMA (Germany), Fronius (Austria), SUNGROW
and HUAWEI (China), SEDAYU always delivers the latest and the best technology according to the internationally
accepted best-practice implementation.
2. SITE IDENTIFICATION
The 1229KWp solar photovoltaic power system will be installed on the existing rooftop of HNK Indonesia –
Sampang Agung.
Marking for PV module and bracket in the Scaffolding, Measuring Tape, Yarn, Marker
rooftop
4.2. Target
The WHSE Target that need to be achieved in this project are:
1) Quality Target
Every working activity applies the Standard Operation Procedure to achieve expectable result that is stated
in the agreement.
2) Safety Target
The safety target is Zero Accident, which mean zero lost time injury.
3) Health Target
The health target is Zero Occupational Disease.
4) Environment Target
The environment target is Zero Pollution, which mean PT Selaras Daya Utama is committed to avoid
polluting the environment during the Solar Photovoltaic Power System installation in HNK Indonesia.
4.3. Program
PT Selaras Daya Utama, in every activity, are committed to ensure all involved workers in this project (directly or
indirectly) are in secure, healthy and safe condition. To fulfil that commitment, we make HSE Program which is
consist of:
1) HSE Regulation
Occupational Health and Safety regulation
Environmental regulation
Drugs and Alcoholic regulation
Safety riding and driving regulation
2) Planning
Setting up Health and safety sign
3) Performance Monitoring
Toolbox meeting
Safety Patrol
HSE committee meeting
Reporting
STOP Card
4) Inspection
Environmental inspection
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 6 of 24
First Aid, Fire Management Inspection
Security inspection
Safety tools and equipment
Project Manager
Ronny Sihaloho
Quality Manager
Vicky Vikranaya
Site Manager
Oit Rustana
Site
HSE Manager Project Support
Engineer
Nindy Febriani Yoga Bagus
Ilham Lubis
Installation
Team
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 7 of 24
5.2 Role And Responsibility
1) Project Manager
a. Give managerial support and provide proper HSE facility conform to the Standard during the project
duration.
b. Responsible or involved to:
Approve HSE problem Identification, HIRADC & HSE Program
Control any aspect related to occupational health and safety
HSE inspection activity
Resource control
Information distribution regarding to HSE
Assemble emergency response team
Make report to head quarter
HSE audit and Appraisal
2) HSE Manager
a. Ensure the existence of QHSE procedure on-site
b. Responsible and involved to:
Preparation of HSE problem Identification, HIRADC & HSE Program
Preparation of legal and regulation requirement
Preparation of HSE plan according to site condition
Supply of First Aid facility
Control any aspect related to occupational health and safety
Supervise Sub-contractor implementation to HSE Procedure
Ensure the HSE standard are met
Coordinate the HSE inspection
Resource control
Hazardous material control and handling, ensure the label are properly and appropriately
attached
Information distribution regarding to HSE
External communication in term of HSE activity reporting to the corresponding agency
Evaluate the conformity to the local government regulation.
Involve in audit and appraisal of HSE activity, include the feedback action
Measure the health and environmental parameter
Prepare monthly report to the head quarter
3) HSE Coordinator
a. Supervise the technical implementation of QHSE according to the procedure and standard.
b. Responsible and involved to:
Control any aspect related to occupational health and safety
Ensure the HSE standard are met
HSE work permit inspection
Conduct HSE Patrol
Resource control
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 8 of 24
Conduct HSE Induction to all workers on-site
HSE talk/tool box meeting
Involve in audit and appraisal of HSE activity
4) Site Manager
a. Together with his/her staff support and actively involved in the QHSE Procedure & standard
implementation on-site
b. Responsible and involved to:
Preparation of HSE problem Identification, HIRADC & HSE Program
Preparation of HSE plan according to site condition
Control any aspect related to occupational health and safety
Conduct HSE Inspection
Prepare HSE Work Permit
Conduct HSE Coordination meeting
Resource control
Hazardous material control and handling
Waste control after work activity
Supervise the implementation of HIRADC & HSE Program
Install HSE sign on-site
6. PPE REQUIREMENT
Personal Protective Equipment that is require to be worn while working in the Workplace, except
inside offices or outside workplace are:
Safety shoes will be replaced at least after on year used, safety glasses will be replaced every six
months. However if protective equipment is unserviceable it shall be replaced.
Management will issue the required PPE to each new employee at no cost. Stock keeper is
responsible for maintaining adequate stocks of PPE at all times.
Stock keeper shall liaise with HSE Coordinator and users on the suability of proposed or new PPE.
Subcontractor Management should comply with the requirements.
SAFETY EQUIPMENT
NO LOCATION
Fire Lighting Safety Safety Safety Scaffolding,
Extinguisher Equipment Barricade Sign, Lifeline ladder
Warning
1 Rooftop √ √ √ √ √
2 Inverter Room √ √
3 LVMDP Room √ √
4 Mobilization Area √ √ √
5 Lifting Area √ √ √ √
HSE Talk, general briefing to all corresponding unit in one working area.
Tool Box Meeting, 10-15 minutes’ team briefing to corresponding unit in one working area or working
discipline, JSA and HIRADC Talk for worker correspond to each task
Aside of giving the guidance, HSE talk and Tool Box meeting is a forum for worker to give feedback and
consult related to HSE case.
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 11 of 24
6.4 Safety Checklist
Safety checklist consist of:
1) Visual check of equipment
2) PPE Check
Full Body Harness: Sternal & Dorsal D-ring (front & rear), Positioning D-ring (right and left side), Back
Padding, Lanyard Positioning
Full Arrester Lanyard: Shock absorber with 2 ropes and big snap-hook in both end
Work Positioning Lanyard with little snap-hook in one end
3) Safety Helmet, Safety Shoes, Safety Gloves, Safety Glasses
4) Tools Check
5) Task and responsibility distribution
6) Safety Kit:
To be installed
For documentation
7) Personnel medical check-up who work on-site:
Visual check by Team Leader
In specific, the chosen subcontractor shall ask approval to the PT Selaras Daya Utama Project Team
about their working plan, and during the installation they shall follow the agreed regulation in the project. PT
Selaras Daya Utama will make sure that the subcontractors are certificated and comply with the WHSE
Requirements.
HSE project team shall include the working area. Special intention shall be given to the area that has
been identified as accident-prone and has high pollution potential. HSE team will give direct notification to
stop the activity if hazardous activity were founded.
The inspection and supervision are only performed by personnel that are sufficiently competent,
educated, and trained for the task they are allocated to perform. PT Selaras Daya Utama shall identify and
provide adequate HSE training to all personnel and shall include additional refresher and familiarization
training as appropriate. The training records will be maintained.
Inspection by Management every month
- Execution/working Procedure
- Management system
- Policy
- Skill and quality of the workers
General HSE Construction Equipment and Personal Protective Equipment Inspection
- Lifting Equipment Inspection
- Heavy Equipment Inspection
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 12 of 24
- Welding machine, Transformer, Rectifier Inspection
- Hand Power Tool Inspection
- Compressed Cylinder Gas Inspection
- Air Compressor Inspection
- Portable Fire Extinguisher Inspection
- Personal Protective Equipment Inspection
Environmental Inspection:
- Hazardous waste
- Non-schedule waste
Inspection Schedule:
- Daily
- Management joint safety patrol to be conducted by Contractor by Contractor management and
Subcontractor’s
- Management in coordination with HSE clients. (weekly)
- General Inspection / CHSEMS Audit (monthly) Work In Progress
- Tools, equipment and Safety equipment and Safety equipment included PPE (monthly, weekly, and
daily) and before delivery to project site.
Person In
No Document Name Schedule Report To
Charge
Client & PT. Selaras Daya
1 HSE Monthly Report HSE Monthly
Utama
Welding Client, PT. Selaras Daya
2 Major Accident Superintendent 1 x 24 Hours Utama and Government
/HSE bodies
Welding
Client & PT. Selaras Daya
3 Medical Treatment Superintendent 1 x 24 Hours
Utama
/HSE
Disability Accident,
Fatality Accident and Welding
4 Environmental that Superintendent 1 x 24 Hours Company
need government /HSE
concerned
The garbage and waste in the project location should be separated according to the classification. The
regulation of waste disposal is:
The amount of hazardous and toxic material should be minimized, and only should be used as needed
by the project. Every data of hazardous and toxic material should be recorded in form K3L-15 and should
always be updated.
The use of hazardous and toxic material should be with extra careful, and required the worker to use
protection devices according to the requirement and prerequisite material information of the corresponding
hazardous and toxic material. MSDS should always be available for every hazardous and toxic material.
Team project will manage the location and prepare the storage location for hazardous & toxic
material’s waste. The entry and discharge of hazardous & toxic material’s waste should be recorded. The waste
will be collected by the appointed third party periodically.
PT Selaras Daya Utama will conduct measurement according to the quality standard. If there is
nonconformity from the measurement, then the project team shall conduct corrective action.
Cleanliness and tidiness are some of PT Selaras Daya Utama top priorities. In this project, several officers
will have a duty to clean-up the area during the project period, according to the Cleanliness and Tidiness Standard.
9. METHOD STATEMENT
This is arrangement of method statement in the project
10.EMERGENCY RESPONSE
HSE Manager and team are responsible to plan the Emergency Response simulation. All workers are
responsible to notify the danger signal to the security officer.
Muster point location will be in the open space near the exit door of the project, where all worker could be
evacuated immediately. During the safety induction, all workers will be notified the location of First Aid and
Light Fire Extinguisher.
First Aid should be checked and updated regularly.
Inflammable objects and materials should not be overly stock in the project site to avoid the possibility of huge
wildfire.
Emergency Response follows the following fire reporting procedures to workers :
SELF EXTINGUISH
FIRE / FIRE -WET WASTE
HAPPENED -SAND
-FIRE EXTINGUISER
REPORT TO SECURITY
SELESAI
FIRE FIGHTING
PROCESS
FINISH
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 18 of 24
Work Accident emergency flowchart:
ACCIDENTS
HAPPENED
Effect?
Minor injuries
Died
Luka Berat
Report Safety man, Project
Superintendent, and the person in
Report Safety man, Project charge of the location
Superintendent, and the Report Safety man, Project
person in charge of the location Superintendent, and the person
in charge of the location
Contact the Security
Coordinator
Selesai Paperwork:
-Report to the police
Call Ambulance to be taken to the -Visum
hospital -Delivery orders
Died
Insurance report
FINISH
JOB NO :
DOC NO : HNK-TNG-VOL IB-02
VOLUME IB
REV :
PAGE : 19 of 24
10.1 Emergency Department
TEAM LEADER
OIT RUSTANA