SITE WEEKLY REPORT

JANUARY 2019 - WEEK 4

PESTECH
No.26 Jalan Utarid U5/14 Seksyen U5, 40150 Shah Alam Selan

SIBIYU 132/33KV SUBSTATION PROJECT


(Contract No: PLS 150129)

SITE WEEKLY REPORT (JULY 19 WEEK No. 25)

DATE REPORT : 22 JULY 2019 - 28 JULY 2019

Prepared By, Verified By,

(MOHAMMAD HADOUMI SALDAN) (JULIUS JONG)


PROJECT CUM QAQC Engineer PROJECT CUM CONSTRUCTION
(CIVIL) MANAGER
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

Section A : Site Progress & Next Week Planning

TOTAL
ITEM DESCRIPTION OF WORK WORKDONE
(%)
1.0 Preliminaries and General
1 Hoarding and Security 60%
2.0 Site Clearing and Earthwork
2.2 Earthwork

1 Zone 2 60%

2 Mackintosh Probe Test 89%


3.0 Building Work
3.1 132kV Buiding
1 Excavation 39%
2 Pile Cutting 25%
3 Lean Concrete 39%
4 Concrete work: Pile Cap 0%
5 Concrete work: Stump/Column 0%
6 Concrete work: Ground beam 0%
7 Concrete work: Ground Slab 0%
8 Backfilling 0%
3.2 33kV Buiding
1 Excavation 100%
2 Lean Concrete 100%
3 Rebar & Formwork 100%
4 Concrete work: Pad Footing 75%
5 Concrete work: Stump/Column 0%
6 Concrete work: Ground beam 0%
7 Concrete work: Ground Slab 0%
8 Backfilling 0%
3.3 Guard House
1 Excavation 0%
2 Lean Concrete 0%
3 Rebar & Formwork 0%
4 Concrete work: Pad Footing 0%
5 Concrete work: Stump/Column 0%
6 Concrete work: Ground beam 0%
7 Concrete work: Ground Slab 0%
8 Backfilling 0%
4.0 Transformer Plinth & Oil Interceptor
4.1 132kV Transformer Plinth
1 Piling Works 0%
2 Excavation 0%
3 Lean Concrete 0%
4 Rebar & Formwork 0%
5 Concreting Work 0%
6 Backfilling 0%
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

4.2 132kV Oil Interceptor


1 Piling Works 0%
2 Excavation 0%
3 Lean Concrete 0%
4 Rebar & Formwork 0%
5 Concreting Work 0%
6 Backfilling 0%
4.3 33kV Transformer Plinth
1 Piling Works 0%
2 Excavation 0%
3 Lean Concrete 0%
4 Rebar & Formwork 0%
5 Concreting Work 0%
6 Backfilling 0%
4.4 33kV Oil Interceptor
1 Piling Works 0%
2 Excavation 0%
3 Lean Concrete 0%
4 Rebar & Formwork 0%
5 Concreting Work 0%
6 Backfilling 0%
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

Work Done for Reporting Week :


1. Piling work at 132kV transformer plinth (11nos).
2. Cutting 44 nos piles at 132kV control building.
3. Excavation of pile cap at 132kV Control Building (7nos)
4. Casting lean concrete for 14 nos pile cap.

Work Not Done for Reporting Week:


1. To carry out additional Mackintosh Probe at 132kV gantry.
2. To carry out Mackintosh Probe at Guard House.
3. To start piling work at 132kV transformer plinth.
4. To cast concrete for pad footing at 33kV building (4nos).

Work Plan for The Coming Week :


1. To start piling work at 132kV oil interceptor.
2. To cast concrete for pad footing at 33kV building (4nos).
3. To cast concrete for pile cap at 132kV building (14nos).
4. To excavate 20 nos pile cap at 132 kV building.
5. To cut 66nos piles at 132 kV building.
6. To cast stump at 33kV building (12nos).
7. To backfill 12 pad footing untill pile cap top level.

Issues
1. More manpower needed for pile cutting work.
2. The delay of IFC drawing for site team slow down construction progress.
3. More water pump required pump out water from excavation area.
4. To provide temporary access drain along platform area.
5. Raining during night time delay construction work due to dewatering.
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

PESTECH
tarid U5/14 Seksyen U5, 40150 Shah Alam Selangoh DE

U 132/33KV SUBSTATION PROJECT


(Contract No: PLS 150129)

WEEKLY REPORT (JULY 19 WEEK No. 25)

TE REPORT : 22 JULY 2019 - 28 JULY 2019

(JULIUS JONG)
PROJECT CUM CONSTRUCTION
MANAGER
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

REMARKS

Preliminaries and General


Stage 1 completed. Ongoing Stage 2.
Site Clearing and Earthwork

Has put in the punch list.


Cut: 15900m3/26500m3 Bal: 10600m3
32/36 nos completed
4 test at guardhouse pending
Building Work

Balance: 41 Pile Cap


Balance: 176 Piles
Balance: 41 Pile Cap

Completed
Completed
Completed
Balance: 4 Pad Footing

Transformer Plinth & Oil Interceptor

Balance: 39 Points
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

slow down construction progress.


Site Delayed Activities *Dates highlighted in Yellow means Forecast as per

Baseline Actual / Forecast


No. Activities
Start Finish Start

3 132kV Substructure Works(Ground Floor) 13/May/19 21/Aug/19 16/Jul/19

4 33kV Pad Footing 4/Jun/19 27/Jul/19 28/Jun/19

5 33kV Substructure Works (Ground Floor) 27/Jul/19 30/Aug/19 28/Jul/19

6 Piling Works for 132kV Transformer Yard & Oil 19/Aug/19 6/Sep/19 23/Jul/19
Interceptor
Yellow means Forecast as per the Catch up plan by Civil Subcontractors

Actual / Forecast
Remarks
Finish

1. Pile cutting: 14/234 piles. Balance 220piles.


2. Excavation for pile cap: 19/67 pile cap. Balance: 48 pile caps.
2/Oct/19 3. Lean concrete: 12/67 pile cap. Balance: 45 pile caps.
4. Plan to cast 12 nos pile caps on 26/7/2019.

1. Lean concrete completed


2. Excavation completed.
5/Aug/19 4. Plan to cast pad footing on 31/7/2019
5. Stump pending ground beam layout plan IFC drawing.

28/Aug/19 Pending pad footing to complete.

1. Setting Out complete.


2. Piling Works for 132kV Transformer Plinth (50 points) might start on
23/7/19.
10/Aug/19 3. Next Piling works will be at 132 Oil Interceptor (12 points), Cable
Trench.
4. Pile arrive at site: 50nos pile.
SITE PROGRESS PHOTOS

1) Cube test at Kemena Industries (7 days)

2) Concrete trial mix at Paragon Concrete.


3) Excavation work for pile cap and pile cutting.

4) Lean concrete casting for pile cap.


5) Formwork installation for pile cap at 132 kV building.

6) Backfilling work at 33kV pad footing.


7) Rock Excavation at Zone 2.
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4

RAINFALL RECORD for JULY 2019


RAINFALL OCCURRENCE
Day Date Period (hours)
8 9 10 11 12 13 14 15 16 17
MON 22/7/2019
TUE 23/7/2019
WED 24/7/2019
THU 25/7/2019
FRI 26/7/2019
SAT 27/7/2019
SUN 28/7/2019

CLOSE
SUNNY
RAINY
SITE WEEKLY REPORT
JANUARY 2019 WEEK 4

PESTECH SDN BHD


Description : SITE MANPOWER RECORD SUNDAY
Project : SIBIYU 132/33 KV SUBSTATION PROJECT PUBLIC HOLIDAY
Contract Ref No. : PLS 150129
22/07/2019 - 28/07/2019
No. Description 22 23 24 25 26 27 28
M T W T F S S
1 PROJECT CUM CONSTRUCTION
MANAGER 1 1 1

2 PROJECT CUM QAQC ENGINEER 2 2 2 2 2


3 SAFETY OFFICER 1 1 1 1 1 1 1
4 SAFETY SUPERVISOR 1 1 1 1 1
5 SURVEYOR 1 1 1 1 1
6 QAQC ASSISTANT 1 1 1 1 1 1
7 SITE SUPERVISOR 1 1 1 1 1 1 1
8 MECHANIC 1 1 1 1 1
9 OPERATOR 2 6 6 6 6 6 2
10 DRIVER 1 1 1 1 1 1 1
11 FOREMAN 1 1 1 1
12 BAR BENDER 4 4 4 4
13 CONCRETOR 4 4 4 4
12 GENERAL WORKER 8 11 3 4 3 5 1
13 SEB REPRESENTATIVE 1 1 1 1 1
14 SITE MANAGER 1 1 1
15 PLANNER 2
16 SITE CLERK 1 1 1 1 1
17 WELDER 1 1 1 1 1
18 QUANTITY SURVEYOR
19 CONSULTANT (INSPIRA)
20 SECURITY GUARD 3 3 3 3 3 3
21 DESIGN ENGINEER
22 CLERK OF WORK (INSPIRA) 1 1 1 1 1
23 3RD PARTY TESTER
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
13 36 36 36 25 37 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
SITE WEEKLY REPORT
JANUARY 2019 - WEEK 4
Appendix J : Vehicle, Machineries and Tools Record
Project : SIBIYU 132/33 KV SUBSTATION PROJECT
Contract Ref No. : PLS150129

22/07/2019 - 28/07/2019
No. Description 22 23 24 25 26 27 28
Remarks
M T W T F S S
1 Excavator#1 1 1 1 1 1 1 1
2 Excavator#2 1 1 1 1 1 1 1
4 Excavator #3 (c/w breaker) 1 1 1 1 1 1 1
5 Excavator #4 (c/w breaker) 1 1 1 1 1 1 1
6 Excavator #5 (c/w breaker) 1 1 1 1 1 1 1
8 Excavator (Small) 1 1 1 1 1 1 1
9 10t Roller 1 1 1 1 1 1 1 PH/Sunday
10 1t Roller 1 1 1 1 1 1 1 Idle/Breakdown
11 Plate Compactor 1 1 1 1 1 1 1
12 Dump truck #1 1 1 1 1 1 1 1
13 Dump truck #2 1 1 1 1 1 1 1
15 Total Station 1 1 1 1 1 1 1
16 Dumping Level 1 1 1 1 1 1 1
17 Prism 1 1 1 1 1 1 1
18 Generator #1 1 1 1 1 1 1 1
19 Generator #2 1 1 1 1 1 1 1
21 Steer Loader (Bobcat) 1 1 1 1 1 1 1
22 Piling Rig #1 1 1 1 1 1 1 1
25 Lorry Crane 1 1 1 1 1 1 1
26
27
28
29
30
31
32
33
34
35
36
Sub-Total 19 19 19 19 19 19 19 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 133