Introduction January 2019

D. For more information on summary of quantities requirements in the plans see the
Basis of Estimates Manual, Chapter 8.
E. Review the final Contract Documents to ensure that a clear method of payment is
conveyed for all items of work on the project either by the appropriate pay item or in
the pay item notes.

Modification for Non-Conventional Projects:

Delete SDM I.5.

I.6 PHASE SUBMITTAL REQUIREMENTS


During the design process, submittals will be made at various stages of project
development. The purpose of these phase submittals is to ensure the design meets the
Department's intent for a given project and that the work done matches the scope agreed
upon at the initiation of the contract. For a summary of phase submittals, see FDM 121.

Modification for Non-Conventional Projects:

Delete SDM I.6 and see the RFP for requirements.