Sunteți pe pagina 1din 4

OPA 960RKTB

Packaged Reverse Cycle R410A Installation &


Air Cooled Air Conditioner Maintenance

GENERAL Mounting 5. Check that the air filters have been


This OPA 960RKTB Outdoor Unit must be The unit should be fastened to a firm flat correctly installed if fitted.
installed in accordance with all national and horizontal base using the holes supplied in 6. Check air diffuser dampers are open if
local safety codes. the mounting channels. appropriate.
CONFIGURATIONS When the unit is being installed on a roof
The OPA 960RKTB is supplied in one of it is recommended that the unit is installed START UP PROCEDURE
two standard configurations : on a substantial structure with anti-vibration Use the supplied Commissioning Sheet to
1. Horizontal supply/return air with box mounts or pads. help you complete the following procedure:
mounting channel (RKTBH), or Flexible duct connections are recommended 1. After the four hour delay period has
2. Downward supply/return air with box between the supply and return ducts and expired, switch on the unit. Ensure the
mounting channel (RKTBU). the unit. crankcase heater thermostat has been
reconnected.
Condensate Drain 2. Check the supply voltage between each
Refrigeration System
The condensate drain should be 'U' trapped phase and neutral.
General
outside the unit. The trap should have a 3. Compressors fitted are directional. Check
The OPA 960 has two independent
vertical height of at least 100 mm. The drain for correct rotation. If rotation is incorrect
refrigeration circuits and two compressors
should have a slope of at least 1 in 50 and the compressor will not pump, be noisy,
to provide the flexibility and economy of
must not be piped to a level above the unit and will draw minimal current. To correct
two stage operation, i.e. utilising one or
drain pipe (refer Fig. 3). motor rotation, change the phasing at
two circuits as conditions vary, plus the
the main power terminal. If changing the
advantage of staggered starting.
Electrical Requirements phasing, check the indoor air fan then
Each refrigeration system has been runs in the correct direction also.
Electrical work must be done by a qualified
charged with HFC-410A (R410A) 4. Measure the current draw on each phase
electrician. The outdoor unit must be wired
refrigerant; refer wiring diagram to the compressor motors and measure
directly from a distribution board by means
specification table for amount. Tapping the current draw of each fan motor.
of a circuit breaker or H.R.C. fuse, and a
points are provided to measure discharge Check all readings against the specified
mains isolator provided - preferably close to
and suction operating pressures. values in the wiring diagram.
the unit.
Note: DO NOT USE REWIRABLE FUSES. 5. Fit R410A compatible gauges and
Compressors measure the suction and discharge
The compressors are directional scroll The OPA 960 is provided with a 24V AC pressures of both refrigeration circuits.
type. The compressor lubricant is polyol control circuit for a thermostat, on/off switch 6. Check that the outdoor air fan motors are
ester oil (POE). Note, this oil absorbs and/or time clock. running smoothly.
moisture quickly if exposed to open air. The control transformer 240V primary 7. Test the operation of the reversing valve
On commissioning, the compressors must voltage is used for countries with 230-240V by running the unit in both the heating
be checked for correct rotation (refer Start power supply. For countries with supply and cooling mode.
Up Procedure). A time delay prevents voltages 200-220V, change the primary 8. Check the indoor unit's fan belt tension
simultaneous starting of the compressors. voltage on the transformer to 208V. after 20 mins of operation and adjust if
Standard units are suitable for use with necessary (refer Commissioning Sheet).
ECONOMISER (Option) thermostats with either manual Heat/Cool 9. Check the supply air flow at each outlet.
If the outdoor air temperature or heat selection or automatic changeover subject to 10.Check the tightness of all electrical
content preferably, is below that of the the contact ratings of the thermostats. connections and sign the check label.
return air the fresh air damper opens and 11.Touch up any outdoor unit paintwork
the return air damper closes to provide the A 24 hour power supply to the compressor
damage to prevent corrosion.
first stage of cooling. A spill air facility in crank case heaters is required, otherwise the
the building may be necessary for when warranty is void.
SETTING SUPPLY AIR FLOW
the return air damper is closed. The fresh Consult OPA 960 Technical Data pamphlet
air damper should return to minimum CHECK TESTS
for details of airflow/duct static pressure, if
setting and the return air damper open 1. Leave the on/off switch in the off position
required.
before compressors are allowed to operate and close the mains isolating switch.
to provide further cooling. A low limit A four hour delay period is required to If the indoor air returning to the unit is
thermostat is fitted to prevent compressors allow the crankcase heaters to drive any regularly expected to be above 50%RH,
operating with a mixed air-on coil liquid refrigerant out of the compressor oil. then the coil face velocity should be limited
temperature below 18°C; resets at 20°C. Bypass the crankcase heater thermostat to be 2.5 m/s or less (refer Air Handling
This is by-passed during heating mode. (CCHT) for this period only. graph in Technical Data pamphlet).
2. Check that the shipping blocks beneath High humidity levels can occur in tropical or
INSTALLATION each compressor have been removed subtropical conditions, and/or when heavily
and that each compressor is secure on its moisture laden fresh air is introduced.
Positioning
mounts. Select a fan speed that avoids water carry-
Refer to dimension diagrams for minimum
3. Check that all fan motors are free running. over problems.
clearances. If multiple units are to be
4. Check that the thermostat is correctly In a free blow or low resistance application,
placed side-by-side then allow at least 2 m
wired to the unit and is set at the desired beware of exceeding the fan motor's full
between coil faces.
temperature. load amp limit (refer wiring diagram).
The indoor air fan motor is fitted with MAINTENANCE Yearly
a factory set adjustable pitch pulley. Monthly 1. Check all refrigerant piping for chafing
Instructions for the adjustment of pulleys is 1. Check air filters, if fitted, and vacuum or and vibration.
included on the back page of the supplied wash clean as necessary. 2. Check the operation of electric heaters,
Commissioning Sheet. One revolution of 2. Check condensate drain for free if fitted.
adjustment is equal to approx. 7% change in drainage. 3. Check air supply at all diffusers.
air volume flow rate. 3. Check compressor compartment for oil 4. Check for excessive noise and vibration
stains indicating refrigerant leaks. and correct as necessary.
OUTDOOR UNIT CONTROLLER (OUC) 5. Check for insulation and duct damage
Three Monthly (or every 1200 hrs of operation)
The Outdoor Unit Controller (OUC) and repair as necessary.
Check the indoor unit's fan belt tension and
includes a temperature sensing head 6. Remove lint and dust accumulation from
adjust if necessary.
pressure control which enables the system outdoor coil fins.
to compensate for outdoor ambient Six Monthly 7. Touch up any paintwork damage to
temperatures below 20°C on cooling cycle, 1. Check the tightness of electrical prevent corrosion.
and above 15°C on heating cycle. The OUC connections.
also has features which protect against icing 2. Check the tightness of all fans, motor NOTE
or overheating of coils, rapid cycling of the mountings, pulleys and belt tension. The manufacturer reserves the right to
compressor and loss of refrigerant charge. 3. Check suction and discharge operating make changes in specifications at any time
If the outdoor air fans take some time pressures. without notice or obligation. Certified data is
to begin rotating when the system is 4. Replace indoor air filters (if fitted). available on request.
powered on, or they don't appear to be 5. Check condensate drain for free
rotating appropriately while the compressor drainage. This pamphlet replaces the previous
is running, consult the OUC label on issue no. 3714 dated 02/14.
the electrical box. If necessary, refer Wiring revision I.
to temperzone for further diagnostic
information.

DIMENSIONS (mm) OPA 960RKTB


Fig. 1 OPA 960RKTBH – Horizontal Supply & Return Air PROJECTION

2790
500 MIN. CLEARANCE
OPTIONAL
OUTDOOR WEATHER Not to Scale
AIR FLOW HOOD
U V W

RETURN POINT Loads (kg)


AIR
U V W X Y Z
1000 MIN. CLEARANCE

ACCESS
PANEL
206 194 194 231 230 246
1000 MIN.
2150 CLEARANCE Net Weight 1167 kg
FOR FILTER
ACCESS

Note : A 2 m clearance
SUPPLY is required above the
AIR exhaust air fans
Y X
Z
OUTDOOR
AIR FLOW FILTER
ACCESS 130
500 MIN. CLEARANCE 850
240 558 596
60 OPTIONAL
WEATHER
HOOD

1860 479 1200

615
265
100
DRAIN 35
1364 1364 1" BSP 2079
MOUNTING CENTRES FEMALE MOUNTING CENTRES
2900 O/A
DIMENSIONS (mm) OPA 960RKTB
Fig. 2 OPA 960RKTBU – Downward Supply & Return Air
PROJECTION

160
1165
OUTDOOR
AIR FLOW Not to Scale
220

575

545

567

235

OUTDOOR
AIR FLOW 475
415

60

SUPPLY
& RETURN AIR

Fig. 5 Condensate Drain


100 mm VENT PIPE
APPROX. FOR LONG
CONDENSATE
DRAIN RUNS
100 mm
MINIMUM MINIMUM
200 mm SLOPE
APPROX. 20 mm PER m
(1 IN 50)
OPEN
DRAIN
'U' TRAP

NOTE
The manufacturer reserves the right to make
changes in specifications at any time without
notice or obligation. Certified data is available
on request.
05/14 Pamphlet No. 3714 © temperzone limited 2014

S-ar putea să vă placă și