Connecting the electrical wiring in the new extension to the existing factory supply
SEQUENCE OF OPERATIONS:
New conduits to be cut to length and threaded using hand held dies and fixed as per drawings.
Cables to be passed through conduits leaving tails at socket locations
All second fix works to be carried out before connection to existing circuits
Incoming supply to be isolated before fuse box is exposed
Incoming supply to be locked off to prevent accidental reconnection
New circuits to be connected and tested as per 17th Ed standards
Plant/Tools needed
PPE required
Delete and/or add as
appropriate:
M
Lock out equipment, pipe threading tools, battery powered driver/drills for
fixing conduits, hacksaw for cutting conduit
Materials to be used
Operatives required
Specific Training
needed – give
Steel conduit, cables
17th Ed electricians P
Trade training up to 17th Ed
L
details
Machinery Yes. Lock off procedures to be in place before any live circuits are exposed
Shutdown and
Lock-Off
E
Procedures
A
appropriate:
Means of Access to Na
M
Height
Delete and/or add as
appropriate:
Fall Prevention Na
Measures
COSHH Assessment Na
P
Carried Out
Traffic Management Na
in Place
L
First Aid Cover – See works office
give details
Overhead Power Na
Cables – are
E
goalposts in place
Dust Control
Vibration Control Na
A
Site Contact Details See works office
including
Emergency
Numbers Etc
M
P
L
E
© Simply-docs – HS.MS.23 Worked Example Method Statement – Electrical Installation
S
ISSUED TO:
A
M
P
L
E
© Simply-docs – HS.MS.23 Worked Example Method Statement – Electrical Installation