Documente Academic
Documente Profesional
Documente Cultură
ITEMIZED BREAKDOWN
DIRECT COST
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL
PART A EARTHWORKS
Structural Concrete for Footing, Footing Tie Beam, Column, Suspended Slab, Girder/Beam 3
900(1)c1 318.40 m 5,512.96 1,755,326.78
(Class A, 4000psi @ 28 days)
901(1)c2 Structural Concrete for Slab on Fill (Class A, 2500psi @ 28 days) 1,020.60 m
3
5,058.01 5,162,204.11
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 216.20 m
2
828.46 179,112.85
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 868.00 m
2
1,197.29 1,039,244.36
ITEMIZED BREAKDOWN
DIRECT COST
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL
1014(1)b1 Prepainted Metal Sheets, Corrugated, Long Span, 0.4 mm thk 11,152.00 m
2
786.21 8,767,864.07
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 216.00 m 734.79 158,715.28
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.4 mm thk) 240.00 m 997.60 239,423.39
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 108.00 m 4,156.26 448,876.44
ITEMIZED BREAKDOWN
DIRECT COST
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL
SUMMARY OF QUANTITIES
BACK-UP CALCULATIONS
PART A EARTHWORKS
803(1)a Structure Excavation
Description L (m) x W (m) x H (m) x pcs = Volume (cu.m.) Remarks
F-1 2.4 m x 2.2 m x 1.55 m x 24 = 196.42 cu.m. Footing 1
F-2 2m x 1.8 m x 1.55 m x 16 = 89.28 cu.m. Footing 2
F-3 1.8 m x 1.5 m x 1.55 m x 42 = 175.77 cu.m. Footing 3
WF-1 47 m x 0.3 m x 0.65 m x 1 = 9.17 cu.m. Wall Footing(CR & Office)
470.64 cu.m. Total Volume
.
804(1)a Embankment from Structure Excavation
Description L (m) x W (m) x H (m) x pcs = Volume (cu.m.) Remarks
F-1 2.4 m X 2.2 m x 1m x 24 = 126.72 cu.m. Footing 1
F-2 2m X 1.8 m x 1m x 16 = 57.6 cu.m. Footing 2
F-3 1.8 m X 1.5 m x 1m x 42 = 113.4 cu.m. Footing 3
WF-1 357 m x 0.3 m 0.4 m x 1 = 42.84 cu.m. Wall Footing(CR & Office)
340.56 cu.m.
x 1.25 Compaction Factor
425.7 cu.m. Total Volume
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
Description L (m) x H (m) = Area (sq.m.) x pcs = Area (sq.m.) Remarks
CHB 310 m x 2.8 m = 868 sq.m. x 1 = 868 sq.m. Perimeter
868 sq.m. Total Area
Item No./Description : A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : mo
Output : 1
A. Labor
126.16
Minor Tools (10% of labor cost)
2
a. 8' x 8' Tarpaulin ft 64.00 20.00 1,280.00
b. Good Lumber (Frames) bd-ft 48.00 47.50 2,280.00
c. Assorted Common Working Nails kg 1.00 70.00 70.00
A. Labor
A. Labor
3
a. Backhoe (0.80m ) 1 1.00 1,537.00 1,537.00
3
b. Dump Truck (12yd ) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 37.05
a. Embankment Materials m
3
1.25 397.00 496.25
(w/ 25% Shrinkage Factor)
Item No./Description : 900(1)c1 Structural Concrete for Footing Tie Beam, Column, Suspended Slab, Girder/Beam
(Class A, 4000psi @ 28 days)
3
Unit of Measurement : m
Output per hour : 3.72
Item No./Description : 900(1)c2 Structural Concrete for Footing and Slab on Fill (Class A, 2500 psi @ 28 days)
3
Unit of Measurement : m
Output per hour : 3.32
Item No./Description : 902(1)a Reinforcing Steel of Reinforced Concrete Structures for One-Storey, Grade 40
Unit of Measurement : kg
Output per hour : 143.438
Item No./Description : 902(1)b Reinforcing Steel of Reinforced Concrete Structures for One-Storey, Grade 60
Unit of Measurement : kg
Output per hour : 143.438
2
Area = 205.01 m
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack, 3.8 m full extension 62 14.00 4.50 3,906.00
c. Adjustable U-head Jack, 0.6m 80 14.00 0.85 952.00
d. Adjustable Base Jack, 0.6m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Round Wing Nut 558 14.00 0.15 1,171.80
B. Equipment
Item No./Description : 1046(2)a1 100mm CHB Non-Load Bearing (including Reinforcing Steel)
2
Unit of Measurement : m
Output per hour : 3.825
B. Equipment
Item No./Description : 1046(2)a2 150mm CHB Non-Load Bearing (including Reinforcing Steel)
2
Unit of Measurement : m
Output per hour : 3.18
B. Equipment
B. Equipment
Installation
a. Construction Foreman 1 16.00 136.93 2,190.88
b. Skilled Laborer 2 16.00 100.61 3,219.52
2 16.00 77.86 2,491.52
B. Equipment
Item No./Description : 1021(1)c Plain Cement Floor Finish with Floor Hardener
2
Unit of Measurement : m
Output per hour : 5.95
B. Equipment
B. Equipment
B. Equipment
Item No./Description : 1003(1)a1 4.5mm Fiber Cement Board on Metal Frame Ceiling
2
Unit of Measurement : m
Output per hour : 1.243
B. Equipment
B. Equipment
B. Equipment
B. Equipment
a. Glazed Tiles m
2
1.050 740.00 777.00
b. Cement bags 0.325 230.00 74.75
c. Sand m
3
0.026 447.00 11.73
d. Tile Grout bags 0.125 250.00 31.25
e. Tile Adhesive (25 kg) bags 0.143 250.00 35.75
f. Consumables (3% of Materials Cost) 27.91
B. Equipment
a. Unglazed Tiles m
2
1.050 850.00 892.50
b. Cement bags 0.325 230.00 74.75
c. Sand m
3
0.026 447.00 11.73
d. Tile Grout bags 0.125 250.00 31.25
e. Tile Adhesive (25 kg) bags 0.125 250.00 31.25
f. Consumable (3% of Materials Cost) 31.24
B. Equipment
a. Cement-based Waterproofing m
2
1.050 350.00 367.50
B. Equipment
B. Equipment
B. Equipment
Item No./Description : 1014(1)b1 Prepainted Metal Sheets ( Corrugated, Long Span,0.4mm thk)
2
Unit of Measurement : m
Output per hour : 2.076
B. Equipment
B. Equipment
B. Equipment
B. Equipment
Fabrication
a. Construction Foreman 1 1.00 136.93 136.93
b. Skilled Laborer 2 1.00 100.61 201.22
2 1.00 77.86 155.72
Erection
a. Skilled Laborer 3 0.49 100.61 147.90
b. Unskilled Laborer 3 0.49 77.86 114.45
B. Equipment
B. Equipment
B. Equipment
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials
A. Labor
B. Equipment
F. Materials