backup calculation

Item / description Qty. Rate Amount Remarks


PCC (1:3:6)
Labour
For pouring
Male coolie 0.75 155 116.25
Female coolie 0.75 110 82.5
198.75

Mason for finishing 0.05 225 11.25

Carpenter for shuttering ( 2sqm per cum.) 0.2 180 36 One carpenter can do 10 sqm. Per day
Helper for shuttering 0.2 110 22 One helper can do 10 sqm. Per day
Add for deshuttering @ 25% 14.5
72.5 Assuming 75mm thk. For 2x2 size ftg. 2.2 sqm ply
Con = 2.15*2.15*.075 = 0.35 shutt. =
Material cost of shuttering 2.15*4*.075 = .65 0.0192 battem

Area of shuttering = 2 sqm. Per cum of concrete, for each For wooden runner
Sqm. Cost = 23.5 / .65 = 36.15 add 4 rs. For nails & oil (2.15x4*3.28*4*4/144)*225 = (705) / 30 =
etc. 23.5 rs. Per 0.65 sqm.
80 2.6m ballies
4”x3”Wooden runner at 225/- per cft. =
(4*3/144)*8*5*225/- 939.1392
78.2616
RCC M20 for footings 152.4528
Assuming Size of 1.5x1.5x.4
Labour
For pouring 1.6
Male coolie 0.67 155 103.85 Conc. = 1.5*1.5*.4 = 0.9cum
Female coolie 0.67 110 73.7 shutt = 1.5 * 4 *.4 = 2.4
177.55 shutt / cum = 2.4/0.9 =2.67 1.34
0.9
One mason can do finishing of 9 cum. ( 10
Mason for finishing 0.11 225 24.75 ftgs. )

Carpenter for shuttering (approx = 3.0 sqm) 0.3 180 54 One carpenter can do 10 sqm. Per day
Helper for shuttering 0.3 110 33 One helper can do 10 sqm. Per day 0.375
Add for deshuttering @ 25% 21.75 0.3
108.75
Material cost of shuttering

1000 rs. For plywood + 750 rs. For


wooden runner = (1000+750)/2.88 = 608
Area of shuttering = 3 sqm. Per cum of concrete, for each
rs. Per Sqm. With 20 uses cost per sqm =
Sqm. Cost = 45.4/-
608/20 = 30.4, Add 5/- for supports & 10/-.
For nails & oil etc. Total = 30.4+5+10 =45.4
136.2

4”x3”Wooden runner at 225/- per cft. =


(4*3/144)*8*5*225/-

RCC M20 for Columns superstrucure


Assuming col. Of 600x230
Labour
For pouring
Male coolie 1.1 225 247.5
Female coolie 1.1 165 181.5
429

Mason for finishing 0.11 350 38.5

Carpenter for shuttering (10 sqm. Shutt / cum) 1.25 250 312.5 One carpenter can do 8 sqm. Per day
Helper for shuttering 1.25 175 218.75 One helper can do 8 sqm. Per day 1.5625
Add for deshuttering @ 25% 132.8125
664.0625
Material cost of shuttering 4.98
1000 rs. (for plywood) + 900 rs. (for wooden runner)
Area of shuttering = 10 sqm. Per cum of concrete, for each Sqm. Cost
= (1000+900)/2.88 = 659 rs. Per Sqm. + Rs.4 for
= 93.9 + 10/- for wirenails & shuttering oil
1040 supports + 24Rs. For chavis
4”x3”Wooden runner at 225/- per cft. =
(4*3/144)*8*6*225/-
(65.9+4+24)
0.0833333333
RCC M20 for Columns below plinth 900
assuming column size of 600*230
Labour
For pouring
Male coolie 0.9 225 202.5
Female coolie 0.9 165 148.5
351

Page 1
backup calculation

One mason can do finishing of 12 cum. (4


Mason for finishing 0.11 250 27.5 ftgs. )

Carpenter for shuttering (10sqm / cum. Of conc.) 1 250 250 One carpenter can do 10 sqm. Per day
Helper for shuttering 1 175 175 One helper can do 10 sqm. Per day
Add for deshuttering @ 25% 106.25
531.25
Material cost of shuttering

1000 rs. (for plywood) + 900 rs. (for wooden runner)


Area of shuttering = 10 sqm. Per cum of concrete, for = (1000+900)/2.88 = 659 rs. Per Sqm. Assuming
each Sqm. Cost = 71.9 + 10/- for wirenails & shuttering oil 15 uses rate per use = 43.9/- add Rs.4 for supports
+ 24Rs. for chavis. Total = 43.9+4+24 = 71.9/-
820 6713.599

4”x3”Wooden runner at 225/- per cft. =


(4*3/144)*8*4*225/- 671.3599
44.75732667

RCC M20 for beams


Labour
For pouring
Male coolie 1.1 155 170.5
Female coolie 1.1 110 121
291.5

Mason for finishing 0.1 225 22.5 One mason can do finishing of 10 cum.

Carpenter for shuttering (10sqm percum.) 1.67 180 300.6 One carpenter can do 6 sqm. Per day

Helper for shuttering 1.67 110 183.7 One helper can do 6 sqm. Per day

Add for deshuttering @ 25% 121.075 2.0875


605.375
Material cost of shuttering

1000 rs. (for plywood) + 1200 rs. (for wooden


Area of shuttering = 10.5 sqm. Per cum of concrete, for runner) = (1000+1200)/2.88 = 763 rs. Per Sqm.
each Sqm. Cost =97.3, add 10/- for shuttering oil & nails, With 12 repetetion rate per sqm = 63.58, add Rs.5
total = 84.5+10 =94.5 for supports + 16 Rs. For chavis Total = 63.5+5+16 =
84.5
992.25

4”x3”Wooden runner at 225/- per cft. =


(4*3/144)*8*8*225/- =1200/-

4*4 chavis of 4 feet in length (4 nos). with 25uses,


cost = ((4*4*4*4/144)*225) /25
RCC M20 for Plinth & tie beams 63.5833333333
Labour 84.5
For pouring
Male coolie 1.1 180 198
Female coolie 1.1 110 121
319

Mason for finishing 0.07 225 15.75 One mason can do finishing of 15 cum.

Carpenter for shuttering ( 10sqm per cum.) 1.25 180 225 One carpenter can do 8 sqm. Per day
Helper for shuttering 1.25 110 137.5 One helper can do 8 sqm. Per day
Add for deshuttering @ 25% 90.625
453.125
Material cost of shuttering

1000 rs. (for plywood) + 1200 rs. (for wooden


Area of shuttering = 10 sqm. Per cum of concrete, for
runner) = (1000+900)/2.88 = 659rs. Per Sqm. With
each Sqm. Cost =65, add 10/- for shuttering oil & nails,
15 repetetion rate per sqm = 43.9, add Rs.5 for
total = 65+10 =75
supports + 16 Rs. For chavis Total = 44+5+16 = 65
750

4”x3”Wooden runner at 225/- per cft. =


(4*3/144)*8*6*225/- =1200/-

RCC M20 for lintel beams


Labour
For pouring
Male coolie 1.5 155 232.5
Female coolie 1.5 110 165
397.5

Mason for finishing 0.07 225 15.75 One mason can do finishing of 15 cum.
1.75
Carpenter for shuttering ( 12sqm per cum.) 2 180 360 One carpenter can do 6 sqm. Per day
Helper for shuttering 2 110 220 One helper can do 6 sqm. Per day
Add for deshuttering @ 25% 145
725
Material cost of shuttering

1000 rs. For plywood + 900 rs. For


Area of shuttering = 12sqm. Per cum of concrete, for each
wooden runner = (1000+900)/2.88 = 659
Sqm. Cost = 731 / 10 =73, add 10/- for shuttering oil &
rs. Per Sqm. + 2x(120/10) for 2 no. for
nails
supports Total = (659+72)
996

4”x3”Wooden runner at 225/- per cft. =


(4*3/144)*8*6*225/-
731
RCC M20 for grid beams
Labour
For pouring

Page 2
backup calculation

Male coolie 1.5 155 232.5


Female coolie 1.5 110 165
397.5
0.0666666667
Mason for finishing 0.07 225 15.75 One mason can do finishing of 15 cum.
1.75
Carpenter for shuttering ( 12qm per cum.) 2 180 360 One carpenter can do 6 sqm. Per day
Helper for shuttering 2 110 220 One helper can do 6 sqm. Per day
Add for deshuttering @ 25% 145
725
Material cost of shuttering

1000 rs. For plywood + 1200 rs. For


wooden runner = (1000+1200)/2.88 = 764
Area of shuttering = 12sqm. Per cum of concrete, for each
rs. Assuming 12uses rate Per Sqm. = 63.6,
Sqm. Cost = 102 , add 10/- for shuttering oil & nails
Add 8/- for supports + 30rs for chavis Total
= (63.6+8+30)
1344

4”x3”Wooden runner at 225/- per cft. =


(4*3/144)*8*8*225/- & Chavis 4' long 6 nos
with 20 uses (4*4*4/144*225*6/20)

RCC M20 for lift walls


Labour
For pouring
Male coolie 1.1 155 170.5
Female coolie 1.1 110 121
291.5

Mason for finishing 0.0666666667 225 15 One mason can do finishing of 15 cum.
1.6
Carpenter for shuttering ( 8sqm per cum.) 1.6 180 288 One carpenter can do 5 sqm. Per day
Helper for shuttering 1.6 110 176 One helper can do 5 sqm. Per day 2.00
Add for deshuttering @ 25% 116
580
Material cost of shuttering

1000 rs. For plywood + 900 rs. For


wooden runner = (1000+900)/2.88 = 659
Area of shuttering = 8sqm. Per cum of concrete, for each
rs. Assuming 12 uses rate Per Sqm. =
Sqm. Cost = 87, add 10/-for shuttering oil & nails
54.91, Add 8/- for supports + 24rs for
chavis Total = (55+8+24)
776
4”x3”Wooden runner at 225/- per cft. =
(4*3/144)*8*6*225/-

RCC M20 for slab


Labour
For pouring
Male coolie 1 155 155
Female coolie 1 110 110
265

Mason for finishing 0.1 150 15 One mason can do finishing of 10cum.
1.75
Carpenter for shuttering ( 7sqm per cum.) 1 130 130 One carpenter can do 7 sqm. Per day
Helper for shuttering 1 100 100 One helper can do 7 sqm. Per day 1.25
Add for deshuttering @ 35% 80.5
310.5
Material cost of shuttering

Hire charges for plate = 20/- per month, we


have two uses per month, i.e rate per sqm
Area of shuttering = 7sqm. Per cum of concrete, for each
= 20, add for wooden runners 4”x4” @ 3no.
Sqm. Cost = 87.5 , add 10/- for shuttering oil & nails
per sqm.(37.5/-), add for ballies at
2.5*120/10(30) = 20+37.5+30 = 87.5/-
682.5

RCC M20 for parapet fins drop walls upto 125mm thk.
Labour
For pouring
Male coolie 1.5 155 232.5
Female coolie 1.5 110 165
397.5

Mason for finishing 0.05 150 7.5 One mason can do finishing of 20cum.
1.75
Carpenter for shuttering ( 16sqm per cum.) 2 130 260 One carpenter can do 8 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 8 sqm. Per day
Add for deshuttering @ 25% 115
575
Material cost of shuttering
1000 rs. For plywood + 900 rs. For
wooden runner = (1000+900)/2.88 = 659
Area of shuttering = 16sqm. Per cum of concrete, for each
rs. With 12 uses rate per Sqm. =54.91 Add
Sqm. Cost = 85 , add 10/- for shuttering oil & nails
6/- for supports + 24rs for chavis Total =
1520 (55+6+24) = 85

RCC M20 forStaircases regular(with waist slab upto 175mm)


Labour
For pouring
Male coolie 1.25 155 193.75
Female coolie 1.25 110 137.5
331.25

Mason for finishing 0.25 150 37.5 One mason can do finishing of 4cum.

Carpenter for shuttering ( 8sqm per cum.) 2 130 260 One carpenter can do 4 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 4 sqm. Per day
Add for deshuttering @ 35% 161
621
Material cost of shuttering
1000 rs. For plywood + 1200 rs. For
wooden runner = (1000+1200)/2.88 = 764
Area of shuttering = 8sqm. Per cum of concrete, for each
rs. Per Sqm. + 8x(120/10) for 8 no. for
Sqm. Cost = 89 , add 11/- for shuttering oil & nails
supports + 32rs for chavis Total =
800 (764+96+32)
892
763.8888888889

RCC M20 for folded Staircases (with thickness upto 150mm)


Labour
For pouring
Male coolie 1.5 155 232.5
Female coolie 1.5 110 165
397.5

Mason for finishing 0.25 150 37.5 One mason can do finishing of 4cum.

Carpenter for shuttering (12sqm per cum.) 3 130 390 One carpenter can do 4 sqm. Per day
Helper for shuttering 3 100 300 One helper can do 4 sqm. Per day
Add for deshuttering @ 35% 241.5
931.5
Material cost of shuttering
1000 rs. For plywood + 1200 rs. For
wooden runner = (1000+1200)/2.88 = 764
Area of shuttering = 12sqm. Per cum of concrete, for each
rs. Per Sqm. + 8x(120/10) for 8 no. for
Sqm. Cost = 91 , add 11/- for shuttering oil & nails
supports + 48rs for chavis Total =
1224 (764+96+48)
908

Reinforcement steel cutting, bending & fixing


Labour for 1Mt. Of steel

For ave. 125 kg. Of steel we require one


pair of F/H
Fitter 8 185 1480
Helper 8 160 1280
Foremen 0.2 225 45
Add for straightning & transportation @ 25% 701.25
3506.25

Providing & fixing PVC sleeve of 40mm dia.


Material cost of sleeves

Labour 0.4347826087
One carpenter can do 10 sleeves of
Carpenter 0.43 180 77.4 230mm length i.e total = 2.3m
77.4 13.75

Providing & fixing UCR masonary in plinth

1.25 times rubble required than the actual


0.2355712603
Labour 4.245
mason 0.46 225 103.5 0.1766784452
One mason pair to do 150cft.
Unskilled labour (2 nos) 1.2 110 132 (I.e.4.245cum) of UCR
235.5

Providing & fixing UCR masonary for Compound wall


etc.

Page 3
backup calculation

1.25 times rubble required than the actual

Labour
mason 0.46 225 103.5 87.7192982456
One mason pair to do 150cft. (I.e.4.245
Unskilled labour ( 2 nos per mason) 1.2 110 132 cum) of UCR
Add for corner stones & 87
add for corner stones preparation ,
assuming 3.0m length & 1.5m height,
corner stones required 30nos @ 5/- for
(.38*3*1.5 = 1.71 cum. I.e 150/1.71 = 87rs.
322.5 Per cum.

Providing & laying 350mm thk. Below plinth


500 nos. bricks required for one cum of
194.34628975 BBM.
2.3206
Labour 1.2195121951
mason 0.56 225 126 3.5375
One mason pair to do 125ft. (I.e.3.53 cum)
Unskilled labour ( 2 nos per mason) 1 110 110 of BBM
236

Page 4
backup calculation

Providing & laying 350mm thk. In superstructure


500 nos. bricks required for one cum of
BBM.

Labour
mason 0.35 225 78.75
One mason pair to do 200cft. (I.e.5.66
Unskilled labour ( 2 nos per mason) 0.7 110 77 cum) of BBM
155.75
Unskilled labour 2 nos. for 1 hour for 10
Scaffolding / sand screening etc. 0.57 80 45.6 sqm area ( 3.5cum.)

Providing & laying 230mm thk. Below plinth


500 nos. bricks required for one cum of
BBM.

Labour
mason 0.108 225 24.3
One mason pair to do 150cft. (I.e.4.25 cum
Unskilled labour ( 2 nos per mason) 0.216 110 23.76 = 18.5 sqm.) of BBM
48.06

Providing & fixing 230thk. BBM in superstructure


500 nos. of bricks per cum. Of masonary

Labour
mason 0.162 225 36.45
One mason pair to do 150cft. (I.e.4.25 cum
Unskilled labour ( 2 nos per mason) 0.216 110 23.76 = 18.5 sqm.) of BBM
60.21

Unskilled labour 2 nos. for 1 hour for 3


sqm area
Scaffolding etc. 0.083 80 6.64
For 1sqm. I.e .23 x .2 = 0.046 cum of sand
Sand screening 0.0552 53 2.9 required. (150 per brass)
9.6

Providing & fixing 115 thk.BBM in superstructure


500 nos. of bricks per cum. Of masonary

Labour
mason 0.17 225 38.25
One mason pair & 3 male coolie to do
Unskilled labour (2 nos) 0.2 110 22 12sqm.. Of BBM
60.25
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area

For 1sqm. I.e .1 x .2 = 0.02 cum of sand


Sand screening 0.02 53 1.1 required. (150 per brass)
7.7

Providing & fixing 150 thk.BBM in superstructure


48nos. Of bricks of 230*150*75 are
required for 1sqm.

Labour
mason 0.2 225 45
One mason pair & 3 male coolie to do
Unskilled labour (2 nos) 0.2 110 22 10sqm.. Of BBM 0.03
67
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area

For 1sqm. I.e .15 x .2 = 0.03 cum of sand


Sand screening 0.03 53 1.6 required. (rate 150/- per brass)
8.2

Providing & laying coursed rubble masonary

1.25 times rubble required than the actual

Labour
mason 0.46 225 103.5

One mason pair to do 150cft. (I.e.4.52


cum) of rubble masonary
Unskilled labour ( 2 nos per mason) 0.7 110 77
Add for corner stones 87

One mason can do 150 cft. Of face dressing


add for face dressing of stones 0.24 175.00 41.22

For corner stones preparation , assuming


3.0m length & 1.5m height, corner stones
required 30nos @ 5/- for (.38*3*1.5 = 1.71
cum. I.e 150/1.71 = 87rs. Per cum.
308.72
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e .35 x .2 = 0.07 cum of sand
Sand screening 0.07 53 3.7 required. (150 per brass)
10.4
29.7 Rate per cum.

Providing & fixing 150 thk.hollow block


24nos. Of blocks of 150*150*300 are
required for 1sqm.

Labour
mason 0.11 225 24.75

Page 5
backup calculation

One mason pair & 2 male coolie to do


Unskilled labour (2 nos) 0.11 110 12.1 18sqm.. Of BBM (2 brass) 18.58736059
36.85
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
Sand screening 0.03 53 1.6 required. (150 per brass) 0.193
8.2

Providing & fixing 200 thk.hollow block


13nos. Of blocks of 200*200*400 are
required for 1sqm.

Labour
mason 0.11 225 24.75
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.11 110 12.1 18sqm.. Of BBM
36.85
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e .2 x .2 = 0.04 cum of sand
Sand screening 0.04 53 2.1 required. (150 per brass)
8.8

Providing & fixing 100 thk.Siporex block


24nos. Of blocks of 150*150*300 are
required for 1sqm.

Labour
mason 0.11 225 24.75
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.11 110 12.1 18sqm.. Of BBM (2 brass)
36.85
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e .1 x .2 = 0.02 cum of sand
Sand screening 0.02 53 1.1 required. (150 per brass)
7.7

Providing & fixing 150 thk.Siporex block


24nos. Of blocks of 150*150*300 are
required for 1sqm.

Labour
mason 0.122 225 27.45
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.122 110 13.42 18sqm.. Of BBM (150 sft. = 16.4 Sqm.)
40.87
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e .15 x .2 = 0.03 cum of sand
Sand screening 0.03 53 1.6 required. (150 per brass)
8.2

Providing & fixing 200 thk.Siporex block


13nos. Of blocks of 200*200*400 are
required for 1sqm.

Page 6
backup calculation

Labour
mason 0.122 225 27.45
One mason pair & 2 male coolie to do
Unskilled labour (2 nos) 0.122 110 13.42 18sqm.. Of BBM (150 sft. = 16.4 Sqm.)
40.87
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e .2 x .2 = 0.04 cum of sand
Sand screening 0.04 53 2.1 required. (150 per brass)
8.8 18.75

Providing & laying 12mmthk. Internal neeru plaster

Labour
mason 0.1 225 22.5
Unskilled labour (2 nos) 0.2 110 22 One mason can do 10 sqm. Of plaster
44.5
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area

For 1sqm. I.e 1 x .012 = 0.012 cum of sand


required. (150 per brass I.e. 53 / cum)
Sand screening 0.012 53 0.6
7.3

Providing & laying 25mmthk. Double coat plaster


19mm of Ist coat in 1:5 & 6mm 2nd coat of
1:4

Labour
mason 0.13 225 29.25
One mason can do 7to 8 sqm. Of plaster &
Unskilled labour (2 nos) 0.27 110 29.7 unskilled labour @2 per mason
58.95

Unskilled labour 2 nos. for 1 hour for 3


sqm area
Scaffolding etc. 0.083 80 6.640

For 1sqm. I.e 1 x .025 = 0.025 cum of sand


required. (150 per brass)
Sand screening 0.025 53 1.325
7.97

Page 7
backup calculation

Providing & laying waterproof plaster for toiletsun/sides & Tanks

19mm of Ist coat in 1:4 & 6mm Final coat


of cement

Labour
mason 0.2 225 45
One mason can do 5 sqm. Of plaster &
Unskilled labour (2 nos) 0.27 110 29.7 unskilled labour @2 per mason

Unskilled labour at 2 nos can clean upto


Unskilled labour (2 nos) 0.2 110 22 10sqm. Area for receiving plaster
96.7
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e 1 x .025 = 0.025 cum of sand
Sand screening 0.025 53 1.3 required. (150 per brass)
8.0

Providing & laying sunk pointing to brickwork

Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of pointing &
Unskilled labour (2 nos) 0.1 110 11 unskilled labour @1 per mason
Unskilled labour at 1 nos can clean upto
Unskilled labour (2 nos) 0.05 110 5.5 20sqm. Area for receiving poitnting
39
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of
Sand screening 0.008 53 0.4 sand required. (150 per brass)
7.1

Providing & laying sunk pointing to Stone masonary

Labour
mason 0.1 225 22.5
One mason can do 7.5 sqm. Of pointing &
Unskilled labour (2 nos) 0.13 110 14.3 unskilled labour @1 per mason

Unskilled labour at 1 nos can clean upto


Unskilled labour (2 nos) 0.05 110 5.5 20sqm. Area for receiving poitnting
42.3
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of
Sand screening 0.008 53 0.4 sand required. (150 per brass)
7.1

Providing & laying 20mmthk. single coat plaster


20mm one coat in 1:5

Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of plaster &
Unskilled labour (2 nos) 0.27 110 29.7 unskilled labour @2 per mason
52.2
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e (1 x .02) = 0.02 cum of sand
Sand screening 0.02 53 1.1 required. (150 per brass)
7.7

Providing & laying 12mmthk.backcoat to dado works

Labour
mason 0.07 225 15.75
Unskilled labour (2 nos) 0.2 110 22 One mason can do 15 sqm. Of plaster
37.75
Unskilled labour 2 nos. for 1 hour for 3
Scaffolding etc. 0.083 80 6.64 sqm area
For 1sqm. I.e (1 x .012) = 0.012 cum of
Sand screening 0.012 53 0.6 sand required. (150 per brass)
7.3

Providing & laying POP over walls & ceiling


20mm one coat in 1:5

Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of plaster &
Unskilled labour (2 nos) 0.1 110 11 unskilled labour @1 per mason
33.5
Unskilled labour 1 nos. for 0.5 hour for
Scaffolding / sand screening etc. 0.1 80 8 4.35 sqm area ( 1 / .23 = 4.35 sqm.)

Providing & laying 230thk. Soling


20mm one coat in 1:5

Labour
mason 0.1 225 22.5
One mason can do 10 sqm. Of plaster &
Unskilled labour (2 nos) 0.1 110 11 unskilled labour @1 per mason
33.5
Unskilled labour 1 nos. for 0.5 hour for
Scaffolding / sand screening etc. 0.1 80 8 4.35 sqm area ( 1 / .23 = 4.35 sqm.)

RCC M20 for sloping slab


Labour
For pouring
Assuming that one pair of labour to 0.8
Male coolie 1.25 155 193.75 cum of slab concreting
Female coolie 1.25 110 137.5 1.25
331.25

Page 8
backup calculation

Two masons can do finishing of 150 sqm.


Mason for finishing 0.13 150 19.5 Of slab

Carpenter for shuttering ( 8sqm per cum.) 1.33 130 172.9 One carpenter can do 6 sqm. Per day
Helper for shuttering 1.33 100 133 One helper can do 6 sqm. Per day
Add for deshuttering @ 35% 107.065
412.965
Material cost of shuttering
Hire charges for plate = 20/- per month, we
have two uses per month, i.e rate per sqm
Area of shuttering = 7sqm. Per cum of concrete, for each
= 20, add for wooden runners 4”x4” @ 3no.
Sqm. Cost = 87.5 , add 10/- for shuttering oil & nails
per sqm.(37.5/-), add for ballies at
682.5 2.5*120/10(30) = 20+37.5+30 = 87.5/-

RCC M20 for Cantilever slabs upto 2.0m span


Labour
For pouring
Assuming that one pair of labour to 1 cum
Male coolie 1 155 155 of slab concreting
Female coolie 1 110 110 1.25
265

Two masons can do finishing of 200 sqm.


Mason for finishing 0.07 150 10.5 Of slab of 150mm thk.

Carpenter for shuttering ( 7 sqm per cum.) 1.17 130 152.1 One carpenter can do 6 sqm. Per day
Helper for shuttering 1.17 100 117 One helper can do 6 sqm. Per day
Add for deshuttering @ 35% 94.185
363.285
Material cost of shuttering
Hire charges for plate = 20/- per month, we
have two uses per month, i.e rate per sqm
Area of shuttering = 7 sqm. Per cum of concrete, for each = 20, add for wooden runners 4”x4” @ 3no.
Sqm. Cost = 117.5 , add 10/- for shuttering oil & nails per sqm.(37.5/-), add for ballies at
(2.5*120)*2/10 i.e. Rs.(60) = 20+37.5+60 =
892.5 117.5/-
117.5

RCC M20 forCopings & sills 20


Labour 66.6666666667
For pouring Size of coping = 0.15 x .10
Assuming that one pair of labour to 50 Rmt
Male coolie 1.33 155 206.15 of Coping
Female coolie 1.33 110 146.3 1.3333333333
352.45

one masons can do finishing of 100 Rmt.


Mason for finishing 0.44 150 66 Of coping

Carpenter for shuttering (20sqm per cum.) 2 130 260 One carpenter can do 10 sqm. Per day
Helper for shuttering 2 100 200 One helper can do 10 sqm. Per day
Add for deshuttering @ 35% 161
621
Material cost of shuttering
Area of shuttering =13 sqm. Per cum of concrete, for each 1000 rs. For plywood + 1200 rs. For
Sqm. Cost = 764 / 15 = 50.93 , add 10/- for shuttering oil & wooden runner = (1000+1200)/2.88 = 764
nails 1220 rs. Per Sqm.
50.9333333333

IPS 50mm thk.


Labour
For pouring
Assuming that one pair of labour to 10 sqm
of IPS (4 panels of 2.5 sqm I.e.
Male coolie 0.1 155 15.5 =1.58x1.58)
Female coolie 0.1 110 11
26.5

one masons can do finishing of above 4


Mason for finishing 0.1 150 15 panels of 10 sqm.
Mason helper 0.1 80 8
23
One carpenter can do shuttering of about
Carpenter for shuttering ( 7 sqm per cum.) 0.034 130 4.42 6.0sqm per day
One carpenter can do shuttering of about
Helper for shuttering 0.034 100 3.4 6.0sqm per day
Add for deshuttering @ 35% 2.737 area = 4x1.58x3x.05 = .948 sqm.

10.557 Shutt per sqm of IPS = 1.264/10 = 0.0948


Material cost of shuttering
Wooden runners of 4"x3" of 2.0m long cost
Area of shuttering = 0.1sqm. Per sqm of IPS Cost of shutt
= (4x3/144)*1.58*3.28*12*225 = 467/-,
=23.35 x.1 = 2.35, add 1/- for shuttering oil & nails
4 with 20uses = 23.35

IPS 50mm thk.


Labour
For pouring
Assuming that one pair of labour to 10 sqm
of IPS (4 panels of 2.5 sqm I.e.
Male coolie 0.1 155 15.5 =1.58x1.58)
Female coolie 0.1 110 11
26.5

one masons can do finishing of above 4


Mason for finishing 0.1 150 15 panels of 10 sqm.
Mason helper 0.1 80 8
23
For Kitchen Otta ;
Assuming the size of Kitchen otta = 3.0m x 0.75m x 0.810m Ht. 812.8
Material cost
Kaddappa
Base 2.46 220.00 541.2
vertical support 1.215 220.00 267.3
Granite 3.675
top 2.34 1695.00 3973.72
Facia in length & Ht. 0.376 1695.00 637.32
Granite shelf (1.5x.75) 1.125 1695.00 1906.88
3.85
4.0425
4.2299125

Box type waterproofing


Labour
For laying shahabad over mortar bed of 40mm
Assuming that one pair of labour to 10 sqm
of IPS (4 panels of 2.5 sqm I.e.
Male coolie 0.1 155 15.5 =1.58x1.58)
Mason 0.1 225 22.5
38

one masons can do finishing of above 4


Mason for finishing 0.1 150 15 panels of 10 sqm.
Mason helper 0.1 80 8
23

Page 9
Standard rate of Labour considered for rate analysis
Revised on Date : 14-08-06
Sr.No. Description Unit Rate Remarks
1 Unskilled coolie (Male) per day 150.00
2 Unskilled coolie (Female) per day 110.00
3 Beldar mazdoor per day 110.00
4 Breaker Operator per day 210.00
5 Helper for Breaker operator per day 150.00
6 Rent for Pneumatic Breaker Needle (8 hr.) per day 1000.00
Machinaries on Hire basis
7 Mixer Per cum 12.00 Rate is derived from average
8 Lift Per cum 12.00 out put of machine (cft) per
9 Vibrator Per cum 6.00 day
Mixing & pouring for
10 P.C.C. Per cum 198.75
11 footing M15 grade Per cum 177.55

12 footing M20 grade Per cum 177.55


13 Columns M15 grade Per cum 429.00
14 Beams M15 grade Per cum 291.50
15 Slabs M15 grade Per cum 150.00
16 Columns M20 grade Per cum 429.00
17 Beams M20 grade Per cum 291.50
18 Slabs M20 grade Per cum 265.00
19 Staircase Per cum 190.00
20 Pardi works Per cum 225.00
Levelling & finishing for
21 P.C.C. Per cum 11.25
22 footing Per cum 24.75
23 Columns Per cum 0.00
24 Beams Per cum 22.50
25 Slabs Per cum 15.00
26 Staircase Per cum 17.50
27 Pardi works Per cum 7.50
Only Labour rate for Shuttering works
28 P.C.C. Per cum 72.50
29 Footing Per cum 108.75
30 Columns Per cum 664.06
31 Beams Per cum 605.38
32 Slabs Per cum 310.50
33 Staircase Per cum 621.00
34 Pardi works (15cm thk.) Per cum 575.00
Masonry & Plaster works
35 U.C.R. masonry works in plinth Per cum 235.50
36 U.C.R. masonry for c.wall pillars etc. Per cum 322.50
36 BBM 350thk. below plinth Per cum 236.00
37 23cm B.B.Masonry works Per sqm 75.00
37 15cm Tokla Brick Masonry works Per sqm 55.00
38 10cm B.B.Masonry works Per sqm 45.00
38 15cm C.C.Block Masonry works Per sqm 36.85
39 External plastering single coat Per sqm 45.00
39 External plastering double coat Per sqm 58.95
40 External plastering (Scaffolding Charges) Per sqm 6.64
40 Internal plastering Per sqm 44.50
41 Internal platering (Scaffolding Charges) Per sqm 4.00
Tile Fixing / Polisher
42 Mosaic Tile fixing Per sqm 32.00
Revised on Date : 14-08-06
Sr.No. Description Unit Rate Remarks
43 Mosaic Tile Skirting fixing Per rmt 10.00
43 Ceramic Tile fixing Per sqm 75.00
44 Marble Flooring Per sqm 100.00
44 Ceramic /Glazed dado Tile fixing Per sqm 90.00
45 Mosaic Tile polishing (3 coats) Per sqm 20.00
45 Mosaic Tile Skirting polishing Per rmt 9.00
46 Marble floor Polishing (regular) Per Sqm 129.00
46 Marble skirting polishing Per Sqm 148.35
47 Marble skirting fixing Per Sqm. 110.00
47 Kota floor fixing & polishing Per Sqm. 100.00
48 Kota skirting fixing & polishing Per Sqm. 110.00
48 Tandoor floor fixing & polishing Per Sqm. 86.00
49 Tandoor skirting fixing & polishing Per Sqm. 94.60
49 Rough shahabad Per Sqm. 65.00
50 Polished shahabad Per Sqm. 80.00
50 Vitrified tiles flooring Per Sqm. 80.00
51 Vitrified tiles Dado Per Sqm. 96.00
51 Granite floor fixing Per Sqm. 172.00
52 Granite skirting fixing Per Sqm. 215.00
52 Kota Steps fixing Per Sqm. 130.00
53 Marble Steps fixing Per Sqm. 167.70
53 Granite Steps fixing Per Sqm. 223.60
54 Tandoor steps Per Sqm. 111.80
54 Kota sill & jams fixing Per Sqm. 132.00
55 Marble sill & jams fixing Per Sqm. 132.00
55 Granite sill & jams fixing Per Sqm. 258.00
56 Tandoor sill & jams Per Sqm. 113.52
Water proofing Works for
57 Box type Per sqm 325.00
58 Toilets / Bathroom (for 200mm sunk) Per sqm 170.00
59 Terrace (roof) Per sqm 125.00
60 Chemical waterproofing Per sqm 130.00
Shuttering material charges
61 for P.C.C. works Per cum 80.00
62 for footing Per cum 136.20
63 for columns Per cum 1040.00
64 for beams Per cum 992.25
65 for slabs Per cum 682.50
66 for Staircase Per cum 800.00
67 for pardi Per cum 1520.00
68 Reinforcement Works Per MT 2000.00
69 KOTAH STONE Per Sqm 100.00
70 Polishing of kotah stone Per Sqm 60.00
Door frame charges
71 Frame making
72 Powder coating (at 15/- per sft) Per Sqm 161.40
73 Enamel painting including red oxide Per sqm. 35.00
74 AC sheets fixing Per sqm. 35.00
75 MS precoated sheets fixing Per sqm. 72.80
76 FRP sheets Per sqm. 72.80
77 Alluminium sheets fixing Per sqm. 72.80
78
79
80
81
Revised on Date : 14-08-06
Sr.No. Description Unit Rate Remarks
Click on the button for entering into "ITEM LIST FOR SELECTION" Item List
RATE AS OF JAN 2011

225
160
160
300
225
1400

18
18
9

300
275

275
425
425
225
425
425
400
275
350

17
33
0
30
22
25
10

110
165
680
910
465
925
850

350 655
475 797
350
110
85
65

80
110
50
60
5

70
RATE AS OF JAN 2011

30
100
135
105
45
15
150
175
110
135
135
100
105
85
100
105
105
225
275
160
190
275
135
160
160
300
135
Assumptions
Tools and plants fixed charges 3%
Eleciticity Charges 0.50%
Water Charges 0.50%
Profit ( Overheads + Profit ) 15%

Summary of Rateanalysis (MKS system)

Default date : 01.03.06


Revision Date : 09.12.06
Item. Rate in
Description Unit
No. Rs.
1 Excavation in soil and soft murum upto 1.5m depth per cum 165.83
2 Excavation in Hard Murum & boulders per cum 213.21
3 Excavation in Soft Rock per cum 356.77
4 Excavation in Hard Rock by chiselling per cum 914.43
5 Soling 230 thk below floor per Sqm 343.98
6 Filling with selected murum obtained from excavat per Cum 127.93
7 Filling with outside murum per Cum 312.71
8 Fillind with sand per Cum 2635.28
9 Antitrmite treatment per Sqm 42.85
10 Carting away surplus xcavated work per Cum 112.61
11 Excavation in hard rock by blasting per cum 691.16
12 P.C.C. (1 :2:4 ) per cum 3439.22
13 P.C.C.(1: 5: 10 ) per cum 2480.67
14 P.C.C. (1 : 4: 8 ) per cum 2690.00
15 P.C.C.(1 :4: 8 ) Plum Concrete per cum 2267.04
16 C.C. M20 for Footing, raft per cum 3393.30
17 C.C. M20 for column below plinth per cum 5405.58
18 C.C. M20 for superstructure Columns per cum 5303.67
19 C.C. M20 for floor Beams per cum 4975.05
20 C.C. M20 for slab per cum 3933.78
21 C.C. M20 for Staircase per cum 4741.52
22 RCC M20 for Pardi, fins per cum 6065.23
23 C.C.M20 for plith Beam per cum 4840.31
24 C.C.M20 for lintels & Chajja per cum 5178.34
25 C.C.M20 for Grid Beam per cum 6343.71
26 C.C.M20 for RCC walls per cum 5372.71
27 M20 for folded Steps upto 150mm thk. per cum 6471.93
28 M20 for sloping slabs per cum 5116.52
29 M20 for cantilever slabs upto 2.0m span per cum 4682.67
30 M20 for Copings & sills per cum 6079.80
31 P/F PVC sleeves 40mm dia. in concrete Rmt. 160.88
32 Welding of bars to existing reinforcement Rmt. 49.76
33 Providing shalitex board expansion joint per sqm 1099.18
34 Ac trafford 6mm thk.sheets per Sqm. 262.79
35 Ac 6mm thk.ridges per Rmt. 163.15
36 Ac trafford 6mm thk.sheets cladding per Sqm. 210.23
37 Ac gutter per Rmt. 176.15
38 MS precoated sheets per Sqm. 530.85
39 MS precoated ridges per Rmt. 306.19
40 MS precoated .55mm thk.sheets cladding per Sqm. 513.94
41 MS precoated gutter per Rmt. 390.33
42 Alluminium sheets per Sqm. 663.62
Default date : 01.03.06
43 Alluminium ridges per Rmt. 374.26
44 Alluminium sheets cladding per Sqm. 676.40
45 Alluminium gutter per Rmt. 497.21
46 FRP sheets per Sqm. 674.18
47 FRP ridges per Rmt. 263.96
48 FRP sheets cladding per Sqm. 686.59
49 FRP gutter per Rmt. 413.90
50 Polycarbonate sheets per Sqm. 1949.83
51 UCR In plinth per cum 1984.99
52 Uncoursed rubble masonry in superstructure per cum 2122.45
53 Brick masonary 35cm thk. Below plinth per cum 2440.13
54 Brick work 35cm thk. In superstructure per cum 2543.86
55 Plinth Masonry 23cm thk per cum 2085.80
56 BBM 23cm thk in superstructure per cum 2162.18
57 P/F 15cm thk. Brick Wall (C.M. 1:4) per sqm 508.67
58 P/F 10cm thk. Brick Wall (C.M. 1:4) per sqm 357.99
59 Coursed rubble masonary per cum 2054.01
60 150mm thk. C.C. Solid block masonry per sqm 453.05
61 200mm thk. C.C. Solid block masonry per sqm 630.23
62 100mm thk. Siporex block masonry per sqm 1844.08
63 150mm thk. Siporex block masonry per sqm 152.04
64 200mm thk. Siporex block masonry per sqm 154.04
65 Ext. Plaster single coat mortor ratio (1:5) per sqm 148.64
66 External Plastering Double coat per sqm 169.76
67 Internal Neeru Plaster CM (1:4)-12mm thk. per sqm 123.49
68 Internal Neeru Plaster CM (1:4) - 20mm thk. per sqm 137.83
69 Waterproof plaster per sqm 290.49
70 Pointing to brick masonary per sqm 69.56
71 Pointing to Stone masonary per sqm 97.50
72 P/A POP plaster to walls per sqm 0.00
73 Back coat for dado work 1:4) per sqm 104.64
74 Grey Mosaic Tile Flooring of 25cm x 25cm per sqm 335.92
75 Grey Mosaic Tile Flooring of 30x30 per sqm 448.10
76 White Mosaic Tile Flooring of 25x25 per sqm 458.88
77 White Mosaic Tile Flooring of 30 x 30 per sqm 615.82
78 Grey Mosaic Tile Skirting of 125 mm ht. per rmt 69.71
79 Grey Mosaic Tile Skirting of 150 mm ht. per rmt 80.90
80 White Mosaic Tile Skirting of 125 mm ht. per rmt 81.97
81 White Mosaic Tile Skirting of 150 mm ht. per rmt 100.62
82 P/L IPS 50mm thk. per sqm 188.70
83 Ceramic Tile Flooring per sqm 680.38
84 Marble Flooring per sqm 1460.65
85 Marble Skirting per Rmt. 151.98
86 Kota Flooring per sqm 601.43
87 Kota Skirting per Rmt. 67.00
88 Tandoor Flooring per sqm 585.44
89 Tandoor Skirting per Rmt 62.87
90 Granite Flooring per sqm 2433.50
91 Granite Skirting per Rmt. 268.38
92 Rough Shahabad flooring per sqm 288.19
93 Polished Shahabad flooring per sqm 353.22
94 Ceramic tiles flooring per sqm 656.48
95 Ceramic tiles Dado per sqm 709.81
96 Ceramic tiles Skirting per Rmt 69.40
97 Vitrified tiles flooring per sqm 1172.95
98 Vitrified tiles Dado per sqm 1265.76
99 Vitrified tiles Skirting per Rmt. 1222.29
Default date : 01.03.06
100 Designer tiles flooring per sqm 709.71
101 Paving blocks flooring (regular) per sqm 399.42
102 Paving blocks heavy duty (M40 & above) per sqm 578.39
103 Chequered tiles flooring per sqm 310.33
104 Marble for steps per Rmt 162.19
105 Kota for sill & Jams per sqm 634.62
106 Marble for Sills & jams per sqm 1376.63
107 Granite for sills & Jams per sqm 2663.11
108 Tandoor for sills & jams per sqm 604.12
109 Granite Kitchen otta Rmt. 5012.81
110 Marble Kitchen otta Rmt. 3395.80
111 Kadappa Kitchen otta Rmt. 1807.80
112 Box type W/P to RCC raft, walls per sqm 475.66
113 Brickbat water proofing for toilets per Cum 2652.48
114 Brickbat water proofing for terrace per sqm 348.14
115 White wash per sqm 4.71
116 Dry distemper per sqm 19.39
117 Oil bound distemper per sqm 42.65
118 Synthetic enamel paint per sqm 46.26
119 Lustre paint per sqm 66.92
120 Cement paint per sqm 36.19
121 Sandtex paint per sqm 70.77
122 Antifungal paint per sqm 91.34
123 Plastic emulsion paint per sqm 71.68
124 Chemical w/p for terrace, toilets per sqm 327.32
125 Providing & fixing TW frame (4"x 2.5") Rmt. 468.65
126 P/F Granite frame (170x20) Rmt. 933.83
127 P/F Marble frame (170x20) Rmt. 578.85
128 P/F flush shutter 35mm Sqmt. 1097.63
129 P/F flush shutter 35mm (internal door) Sqmt. 1138.66
130 P/F flush shutter 35mm (internal door) Sqmt. 1284.05
131 P/F Laminate of appr. shade & colour Sqmt. 432.01
132 P/F MS powder coated fittings Door. 135.56
133 P/F Alluminium fittings Door. 268.17
134 P/F stainless steel fittings Door. 268.17
135 P/F Brass fittings Door. 268.17
136 P/F Night latch Door. 70.73
137 P/F Automatic door closer Door. 70.73
138 P/F eye piece Door. 35.36
139 P/F MS powder coated grills & railing Sqm. 1019.35
140 P/F MS grills & railing with enamel paint Sqm. 798.45
141 P/F MS Z section windows Sqm. 1274.64
142 Reinforcement works MT 55484.06
143 Structural steel works per Sqm. 43578.09
144 12mm dia. Fan hook per No. 31.75
145 Chainlink fencing per Sqm. 259.20
Standard rate of materials considered for rate analysis

Sr.
List of Materials Per Unit Rate (inRs.) Remarks
No.
1 Cement Per Bag 255.00 53 grade O.P.Cement
2 Reinforcement steel CTD Per MT 38000.00
3 Binding wire Per Kg 40.00 18 gauge binding wire
4 Sand Per cum 1060.00
5 Metal (18 to 20)mm Per cum 500.00
6 Metal (12mm) Per cum 340.00
7 Metal (25mm) Per cum 575.00
8 Bricks (230mm) Per No 2.25
9 Bricks (150mm) Per No 5.50
10 Bricks (100mm) Per No 3.30
11 Concrete Blocks (20x20x40)cm Per No 34.00
12 Concrete Blocks (15x15x30)cm
(M15 grade @ 2200/-) Per No 16.00
13 Siporex blocks (10x10x20) cm Per No
14 Siporex blocks (15x15x30) cm Per No
15 Siporex blocks (20x20x40) cm Per No
16 Brick Bats Per cum 250.00
17 Rubble Per cum 500.00
18 Murum Per cum 120.00
19 Neeru Per Bag 50.00 each bag of 25kg.
20 Lime Per Bag 55.00 each bag of 30kg.
21 White cement Per Kg. 12.00
22 M.M. Tile (White) 25cm X 25cm Per sqm 244.00
23 M.M. Tile (White) 25cm X 12cm Per rmt 30.00
24 M.M. Tile (White) 30cm X 30cm Per sqm 350.00
25 M.M. Tile (White) 30cm X 15cm Per rmt 45.00
26 M.M. Tile (Grey) 25cm X 25cm Per sqm 150.00
27 M.M. Tile (Grey) 25cm X 12cm Per rmt 23.00
28 M.M. Tile (Grey) 30cm X 30cm Per sqm 220.00
29 M.M. Tile (Grey) 30cm X 15cm Per rmt 32.00
30 Marble Per sqm 860.00
31 Tandoor Per sqm 291.00
32 Granite Per sqm 1695.00
33 Rough Shahabad Per sqm 75.00
34 Polished Shahabad Per sqm 110.00
35 Ceramic tiles(30cm X 30cm)colour Per sqm 380.00
36 Glazed Tiles (15cm X 15cm) White Per sqm 400.00
37 Vitrified rough tiles Per sqm 800.00
38 Vitrified polished tiles Per sqm 800.00
39 Designer tiles(25mm) Per sqm 430.40
40 Paver blocks (regular) 60mm Per sqm 242.10
41 Paver blocks (heavy duty) Per sqm 386.00
42 Chequered tiles Per sqm 102.00
43 Kota steps Per sqm 377.68
44 Marble steps Per sqm 1032.00
45 Granite steps Per sqm 2118.75
46 Tandoor steps Per sqm 378.30
47 Kaddappa one side polish (40mm) Per sqm 220.00
48 Shahabad stone 25mm Per sqm 82.50
49 Broken glazed tiles Per Kg. 10.00
50 Water proofing Compound Per Kg. 40.00
51 Shalitex board 25mm Per sqm 800
52 Kotah stone cut to size Sqm 290.52
53 Sub frame Per Kg.
54 Main frame Per Kg.
55 Shutter members Per Kg.

Page 19 of 230
Sr.
List of Materials Per Unit Rate (inRs.) Remarks
No.
56 a) Beadings Per Kg.
57 b) Glass Per sqm
58 c) Gasket,wool piles Per m.
59 d) Concealed lock Per No
60 PVC Pipe 51.75
61 Chlordane 20% emulsion Ltr. 66.15
62 Blasting powder kg. 78.75
63 Safety fuse Rmt 4.725
64 Detonating fuse Rmt 6.5
65 Detonator No 8
66 Teak wood frame 4"x2.5" Cft. 1200
67 MS Holdfast No. 10
68 Coal tar Kg. 25
69 Flush shutter 35mm (90/- per sft.) Sqm. 968
70 Brass hinges 75mm No 20
71 Brass hinges 100mm No 26
72 Brass hinges 125mm No 35
73 Brass screws25mm No 1.5
74 Brass screws25mm No. 2
75 Laminate 1mm sqm. 310
76 Fevicol Kg. 250
77 MS tubular Kg. 32
78 Nails Kg. 30
79 MS Z sections (1.5 kg @ 30) Rmt. 45
80 10mm sq. bars (.785 x 30) Rmt. 23.55
81 4mm float glass Sqm. 325
82 Lime Kg. 1.5
83 Ultramarine blue Kg. 114.98
84 Glue Kg. 48.825
85 Sodium chloride Kg. 10
86 Distemper Kg. 67
87 Whitning kg. 20
88 Primer Lts 60.9
89 Putty Kg. 40.95
90 Oil bound distemper Kg. 90.00
91 Synthetic enamel Ltr. 141.75
92 Luster paint Ltr. 218.75
93 Cement paint Kg. 49.35
94 Sandtex paint Kg. 86.3625
95 Antifungal paint kg. 123.375
96 Plastic emulsion ltr. 205.15
97 AC trafford 6mm thk. Sqm. 149.1
98 Bitminous washers 3mm Kg. 32
99 GI flat washers 2mm Kg. 47.25
### GI - 6mm J hooks No. 6.3
### AC -ridges pair Rmt. 94.5
### AC Gutter Rmt. 105
### MS precoated sheets Sqm. 319
### MS precoated -ridges (0.6m width ) Rmt. 181.5
### MS precoated Gutter Rmt. 216.15
### Alluminium sheets Sqm. 415.8
### Alluminium -ridges (0.6m width ) Rmt. 236.5
### Alluminium Gutter Rmt. 302.5
### Structural steel Mt. 30500
110 FRP Sqm. 423.5
111 FRP -ridges (0.6m width ) Rmt. 154
112 FRP gutter Rmt. 209
113 Chain link sqm. 156
114 Polycarbonate sheets sqm. 1400
Page 20 of 230
Sr.
List of Materials Per Unit Rate (inRs.) Remarks
No.
115
116
Click on the button for Labour rates Labour Rate

Page 21 of 230
1058.43
14.17193
9.636915
16.29772

Page 22 of 230
4.71 150.72

1.71 153.9

136.8

156

Page 23 of 230
WELCOME TO ITEM SELECTION SHEET

Sr. Computer Selection


ITEMS
No. code button
0 Blank format _1
1 Earth work Earth work in ordinary soil E1
2 Earth work Earth work in Shadu E2
3 Earth work Earth work in Murum E3
4 Earth work Earth work in Soft Rock E4
5 Earth work Earth work in Hard Rock E5
6 Concreting P.C.C. (1:3:6) C1
7 Concreting P.C.C. (1:4:8) C2
8 Concreting C.C. M15 for footing C3
9 Concreting C.C. M20 for footing C4
10 Concreting C.C. M15 for columns C5
11 Concreting C.C. M20 for columns C6
12 Concreting C.C. M15 for Beams C7
13 Concreting C.C. M20 for Beams C8
14 Concreting C.C. M15 for Slabs C9
15 Concreting C.C. M20 for Slabs C10
16 Masonry U.C.R. Masonry 15" thk. B1
17 Masonry B.B.Masonry 9" thk. B2
18 Masonry B.B.Masonry 6" thk. B3
19 Masonry B.B.Masonry 4" thk. B4
20 Masonry C.C. Block masonry 6" thk. B5
21 Plastering External Plastering Single coat P1
22 Plastering External Plastering Double coat P2
23 Plastering Internal Plastering with C.M.1:4 P3
24 Plastering Internal Plastering with C.M.1:5 P4
25 Flooring Mosaic Tile flooring F1
26 Flooring Mosaic Tile Skirting F2
27 Flooring Ceramic Tile flooring F3
28 Flooring Marble Flooring F4
29 Dado Ceramic /Glazed tile Dado D1
30 W/P Brickbat waterproofing for Toilet W/P1
31 W/P Brickbat waterproofing for Terrace W/P2
32 W/P Glazed china mosaic w/p for terrace W/P3
33 Re Reinforcement works R1
34 Summary of rate analysis SR
Sr.No.
List of Materials Per Unit Rate (inRs.) Remarks

1 Cement Per Bag 245.00


2 Reinforcement steel CTD Per MT 38000.00
3 Binding wire Per Kg 38.00
4 Sand Per cum 1060.00
5 Metal (18 to 20)mm Per cum 550.00
6 Metal (12mm) Per cum 600.00
7 Metal (25mm) Per cum 500.00
8 Bricks (230mm) Per No
9 Bricks (150mm) Per No 4.50
10 Bricks (100mm) Per No 3.00
11 Concrete Blocks (20x20x40)cm Per No
12 Concrete Blocks (15x15x30)cm (M15
grade @ 2200/-) Per No
13 Siporex blocks (10x10x20) cm Per No
14 Siporex blocks (15x15x30) cm Per No
15 Siporex blocks (20x20x40) cm Per No
16 Brick Bats Per cum
17 Rubble Per cum
18 Murum Per cum
19 Neeru Per Bag
20 Lime Per Bag
21 White cement Per Kg.
22 M.M. Tile (White) 25cm X 25cm Per sqm
23 M.M. Tile (White) 25cm X 12cm Per rmt
24 M.M. Tile (White) 30cm X 30cm Per sqm
25 M.M. Tile (White) 30cm X 15cm Per rmt
26 M.M. Tile (Grey) 25cm X 25cm Per sqm
27 M.M. Tile (Grey) 25cm X 12cm Per rmt
28 M.M. Tile (Grey) 30cm X 30cm Per sqm
29 M.M. Tile (Grey) 30cm X 15cm Per rmt
30 Marble Per sqm
31 Tandoor Per sqm
32 Granite Per sqm
33 Rough Shahabad Per sqm
34 Polished Shahabad Per sqm
35 Ceramic tiles(30cm X 30cm)colour Per sqm
36 Glazed Tiles (15cm X 15cm) White Per sqm
37 Vitrified rough tiles Per sqm
38 Vitrified polished tiles Per sqm
39 Designer tiles(25mm) Per sqm
40 Paver blocks (regular) 60mm Per sqm
41 Paver blocks (heavy duty) Per sqm
42 Chequered tiles Per sqm
43 Kota steps Per sqm
44 Marble steps Per sqm
45 Granite steps Per sqm
46 Tandoor steps Per sqm
Sr.No.
List of Materials Per Unit Rate (inRs.) Remarks

47 Kaddappa one side polish (40mm) Per sqm


48 Shahabad stone 25mm Per sqm
49 Broken glazed tiles Per Kg.
50 Water proofing Compound Per Kg.
51 Shalitex board 25mm Per sqm
52 Kotah stone cut to size Sqm
53 Sub frame Per Kg.
54 Main frame Per Kg.
55 Shutter members Per Kg.
56 Beadings Per Kg.
57 b) Glass Per sqm
58 c) Gasket,wool piles Per m.
59 d) Concealed lock Per No
60 PVC Pipe
61 Chlordane 20% emulsion Ltr.
62 Blasting powder kg.
63 Safety fuse Rmt
64 Detonating fuse Rmt
65 Detonator No
66 Teak wood frame 4"x2.5" Cft.
67 MS Holdfast No.
68 Coal tar Kg.
69 Flush shutter 35mm (90/- per sft.) Sqm.
70 Brass hinges 75mm No
71 Brass hinges 100mm No
72 Brass hinges 125mm No
73 Brass screws25mm No
74 Brass screws25mm No.
75 Laminate 1mm sqm.
76 Fevicol Kg.
77 MS tubular Kg.
78 Nails Kg.
79 MS Z sections (1.5 kg @ 30) Rmt.
80 10mm sq. bars (.785 x 30) Rmt.
81 4mm float glass Sqm.
82 Lime Kg.
83 Ultramarine blue Kg.
84 Glue Kg.
85 Sodium chloride Kg.
86 Distemper Kg.
87 Whitning kg.
88 Primer Lts
89 Putty Kg.
90 Oil bound distemper Kg.
91 Synthetic enamel Ltr.
92 Luster paint Ltr.
93 Cement paint Kg.
94 Sandtex paint Kg.
95 Antifungal paint kg.
96 Plastic emulsion ltr.
97 AC trafford 6mm thk. Sqm.
98 Bitminous washers 3mm Kg.
Sr.No.
List of Materials Per Unit Rate (inRs.) Remarks

99 GI flat washers 2mm Kg.


100 GI - 6mm J hooks No.
101 AC -ridges pair Rmt.
102 AC Gutter Rmt.
103 MS precoated sheets Sqm.
104 MS precoated -ridges (0.6m width ) Rmt.
105 MS precoated Gutter Rmt.
106 Alluminium sheets Sqm.
107 Alluminium -ridges (0.6m width ) Rmt.
108 Alluminium Gutter Rmt.
109 Structural steel Mt.
110 FRP Sqm.
111 FRP -ridges (0.6m width ) Rmt.
112 FRP gutter Rmt.
113 Chain link sqm.
114 Polycarbonate sheets sqm.
115

116
Click on the button for Labour rates Labour Rate
STANDARD ITEMS OF BOQ
CODE NO BRIEF DESCRIPTION OF ITEMS UNIT Rate

SECTION I -Work Below Plinth

SNJ/EX/ 1 Excavation in soil and soft murum upto 1.5m depth Cum 165.83
SNJ/EX/I 2 Excavation in soil and soft murum from 1.51 m to 3.0m depth Cum 182.41
SNJ/EX/I 3 Excavation in hard murum and boulders upto 1.5 m depth Cum 213.21
SNJ/EX/I 4 Excavation in hard murum and boulders from 1.51 to 3.0 m depth Cum 234.53
SNJ/EX/I 5 Excavation in soft rock upto 1.5 m depth Cum 356.77
SNJ/EX/I 6 Excavation in soft rock from 1.51 to 3.0 m depth Cum 392.45
SNJ/EX/I 7 Excavation in soft rock from 3.1 m to 6.0 m depth Cum 431.69
SNJ/EX/I 8 Excavation in hard rock upto 1.5m depth ( by chiselling) Cum 914.43
SNJ/EX/I 9 Excavation in hard rock from 1.51m to 3m depth ( by chiselling) Cum 1005.88
SNJ/EX/I 10 Excavation in hard rock from 3.1m to 6.0m( by Chiselling) Cum 1106.47
SNJ/EX/I 11 Excavation in hard rock by blasting Cum 691.16
SNJ/EX/I 12 Filling in plinth with selected murum obtained from excavation Cum 127.93
SNJ/EX/I 13 Filling in plinth with murum brought from outside ( labour+material) Cum 312.71
SNJ/EX/I 14 Filling in plinth sand Cum 2635.28
SNJ/EX/I 15 230 mm thick dry rubble soling in plinth Sqm 343.98
SNJ/EX/I 16 Providing preconstructional antitermite treatment to plinth Sqm 42.85
SNJ/EX/I 17 Carting away unwanted excavated material outside the premises Cum 112.61

SECTION II-PCC Work

SNJ/PCC/II 1 Providing and laying PCC 1:5:10 beddintg Cum 2480.67


SNJ/PCC/II 2 Providing and laying PCC 1:4:8 bedding Cum 2690.00
SNJ/PCC/II 3 Providing and laying PCC 1:3:6 bedding Cum 3439.22
SNJ/PCC/II 4 Providing and laying PCC 1:2:4 bedding Cum
SNJ/PCC/II 5 Providing and laying PCC 1:1.5:3 bedding Cum
SNJ/PCC/II 6 Providing and laying 1:4:8 plum concrete Cum 2267.04

SECTION III-RCC Work

SNJ/RCC/III 1 Providing and casting RCC M20 for footings, foundations, combined Cum
footings, eccentric footings, raft, pedastals,pile caps
3393.30
SNJ/RCC/III 2 Providing and casting RCC M20 for columns ( of any size and shpe)upto Cum
plinth and in basement 5405.58
SNJ/RCC/III 3 Providing and casting RCC M20 for columns ( fo any size and shape) in Cum
superstructure at all levels 5303.67
SNJ/RCC/III 4 Providing and casting RCC M20 for plinth beams Cum 4840.31
SNJ/RCC/III 5 Providing and casting RCC M20 for beams ( of any shape and size) at Cum
all levels 4975.05
SNJ/RCC/III 6 Providing and casting RCC M20 for beams in grid system Cum 6343.71
SNJ/RCC/III 7 Providing and casting RCC M20 for lintels Cum 5178.34
SNJ/RCC/III 8 Providing and casting RCC M20 for piles
SNJ/RCC/III 9 Providing and casting RCC M20 for standard slab(thk upto 200 mm) Cum
3933.78
SNJ/RCC/III 10 Providing and casting RCC M20 slab for loft Cum 5178.34
SNJ/RCC/III 11 Providing and casting RCC M20 for cantilever slab upto 2.0 m span Cum
4682.67
SNJ/RCC/III 12 Providing and casting RCC M20 for sloping slab Cum 5116.52
SNJ/RCC/III 13 Providing and casting RCC M20 for pyramidal slab Cum
SNJ/RCC/III 14 Providing and casting RCC M20 for hordi slab Cum
SNJ/RCC/III 15 Providing and casting RCC M20 for folded slab upto thickness of Cum
150mm 6471.93
SNJ/RCC/III 16 Providing and casting RCC M20 for chajjas at any level , of projection Cum
upto 0.75m 5178.34
SNJ/RCC/III 17 Providing and casting RCC M20 for pardies, parapets, fins, upstands of Cum
thickness upto 100 mm 6065.23
SNJ/RCC/III 18 Providing and casting RCC M20 for staircase steps and waist slab with Cum
riser upto 170 mm and tread upto 300 mm and waist slab thickness upto
200 mm.at all levels. 4741.52
SNJ/RCC/III 19 Providing and constructing RCC M20 for coping at all levels Cum 6079.80
SNJ/RCC/III 20 Providing and constructing RCC M20 for sills at all levels Cum 6079.80
SNJ/RCC/III 21 Providing and constructing RCC walls in M20 Cum 5372.71
SNJ/RCC/III 22 Providing and constructing RCC M20 floor Cum
SNJ/RCC/III 23 Extra for addition or deduction in thickness of the structural members as
mentioned above , excluding form work
SNJ/RCC/III 24 Less for providing concrete of grade M15 in lieu of M20 Cum 331.88
SNJ/RCC/III 25 Extra for providing concrete of grade M25 in lieu of M20 Cum
SNJ/RCC/III 26 Extra for providing concrete of grade M30 in lieu of M20 Cum
SNJ/RCC/III 27 Extra for providing concrete of grade M35 in lieu of M20 Cum
SNJ/RCC/III 28 Extra for providing concrete of grade M40 in lieu of M20 Cum
SNJ/RCC/III 29 Providing, cutting, bending, laying reinfocement of mild steel, tor steel of MT
various diameters including binding wire 55484.06
SNJ/RCC/III 30 Welding of bars to existing reinforcement RM 49.76
SNJ/RCC/III 31 Expansion joint for columns RM 1099.18
SNJ/RCC/III 32 Expansion joint for beams RM 1099.18
SNJ/RCC/III 33 Expansion joint for slab RM 1099.18
SNJ/RCC/III 34 Providing post tensioning of beams and slab Sqm
SNJ/RCC/III 35 Providing anticorrosive treatment to reinforcement MT

SECTION IV-Stone /Brick masonry/Block/Siporex Masonry

SNJ/MAS/IV 1 Providing and constructing 350 mm or above brick masorny below plinth Cum
(C:M 1:6) 2440.13
SNJ/MAS/IV 2 Providing and constructing UCR masonry in C: M 1:6 below plinth for Cum
foundation 1984.99
SNJ/MAS/IV 3 Providing and constructing UCR masonry in C:M 1:6 for compound wall, Cum
steps, pillars in superstructure etc 2122.45
SNJ/MAS/IV 4 Providing and constructing 350 mm thick BB masonry in superstructure Cum
for steps, walls, pillars (C:M 1:4) 2543.86
SNJ/MAS/IV 5 Providing and constructing 230 mm thick BB masonry for walls below Sqm
plinth (C:M1:6) 2085.80
SNJ/MAS/IV 6 Providing and constructing 230 mm thick BB masorny for wall in Sqm
superstructure at all levels(C:M1:6) 2162.18
SNJ/MAS/IV 7 Providing and constructing 115 mm thick BB masorny in super structure Sqm
at all levels (C:M 1:4) 357.99
SNJ/MAS/IV 8 Providing and constructing 150 mm thick BB masorny in super structure Sqm
at all levels (C:M 1:4) 508.67
SNJ/MAS/IV 9 Providing and constructing coursed rubble masonry Cum 2054.01
SNJ/MAS/IV 10 Providing and constructing 'Khandki' masonry Cum
SNJ/MAS/IV 11 Providing and constructing 150 mm thk concrete block masonry Sqm 453.05
SNJ/MAS/IV 12 Providing and constructing 200 mm thk concrete block masonry Sqm 630.23
SNJ/MAS/IV 13 Providing and constructing siporex block masonry 100 mm thick Sqm 1844.08
SNJ/MAS/IV 14 Providing and constructing siporex block masonry 150 mm thick Sqm 152.04
SNJ/MAS/IV 15 Providing and constructing siporex block masonry 200 mm thick Sqm 154.04

SECTION V- PLASTERING AND POINTING

SNJ/PLAST/V 1 Providing and applying 12 mm thick internal cement plaster C:M 1:4 Sqm
123.49
SNJ/PLAST/V 2 Providing and applying 20 mm thick sandface cement plaster C:M 1:5 in Sqm
one coat 148.64
SNJ/PLAST/V 3 Providing and applying 12mm back coat plaster behind dado C:M 1:4 Sqm
104.64
SNJ/PLAST/V 4 Providing and applying 20 mm thick sand faced cement plaster in two Sqm
coats first coat with 1:5 & second with 1:4 169.76
SNJ/PLAST/V 5 Provding and applying 25 mm thick plaster to toilet sunks and sides, Sqm
internally to water tanks with waterproofing compound 290.49
SNJ/PLAST/V 6 Providing and applying 20 mm thick rough cast plaster Sqm
SNJ/PLAST/V 7 Providing and applying pebble dash plaster Sqm
SNJ/PLAST/V 8 Providing and applying special finish RENOVO or other such plasters Sqm

SNJ/PLAST/V 9 Providing and making flush groove pointing to brick/block masonry Sqm 69.56
SNJ/PLAST/V 10 Providing and making flush groove pointing to stone masonry Sqm 99.54
SNJ/PLAST/V 11 Providing and making sunk pointing to stone masonry Sqm 97.50

SECTION VI-FLOORING WORK

SNJ/FLOOR/VI 1 Providing and laying IPS floor 50 mm thick with ghotai Sqm 188.70
SNJ/FLOOR/VI 2 Providing and laying marble mosaic tile flooring 25cmx25cm size - grey Sqm
cement based 335.92
SNJ/FLOOR/VI 3 Providing and laying marble mosaic tile flooring 30cmx30cm size - grey Sqm
cement based 448.10
SNJ/FLOOR/VI 4 Providing and laying marble mosaic tile flooring 25cmx25cm size - white Sqm
cement based 458.88
SNJ/FLOOR/VI 5 Providing and laying marble mosaic tile flooring 30cmx30cm size - white Sqm
cement based 615.82
SNJ/FLOOR/VI 6 Providing and laying marble stone flooring Sqm 1460.65
SNJ/FLOOR/VI 7 Providing and laying Kotah stone flooring Sqm 601.43
SNJ/FLOOR/VI 8 Providing and laying granite stone flooring Sqm 2433.50
SNJ/FLOOR/VI 9 Providing and laying tandur stone flooring Sqm 585.44
SNJ/FLOOR/VI 10 Providing and laying polished shahabad flooring Sqm 353.22
SNJ/FLOOR/VI 11 Providing and laying rough shahabad flooring Sqm 288.19
SNJ/FLOOR/VI 12 Providing and laying Jaisalmer stone flooring Sqm
SNJ/FLOOR/VI 13 Providing and laying ceramic tile flooring Sqm 656.48
SNJ/FLOOR/VI 14 Providing and laying vitrified tile flooring Sqm 1172.95
SNJ/FLOOR/VI 15 Providing and laying rough vitrified tile flooring Sqm 1172.95
SNJ/FLOOR/VI 16 Providing and laying designer tiles - interlocking type Sqm 709.71
SNJ/FLOOR/VI 17 Provding and laying interlocking paving blocks Sqm 399.42
SNJ/FLOOR/VI 18 Provding and laying chequered tiles Sqm 310.33
SNJ/FLOOR/VI 19 Providing and laying marble mosaic tile skirting 125mm size - grey Sqm
cement based 557.66
SNJ/FLOOR/VI 20 Providing and laying marble mosaic tile skirting 150 mm size - grey Sqm
cement based 539.34
SNJ/FLOOR/VI 21 Providing and laying marble mosaic tile skirting 125mm size - white Sqm
cement based 655.74
SNJ/FLOOR/VI 22 Providing and laying marble mosaic tile skirting 150 mm size - white Sqm
cement based 670.82
SNJ/FLOOR/VI 23 Providing and laying marble stone skirting Sqm 151.98
SNJ/FLOOR/VI 24 Providing and laying Kotah stone skirting Sqm 67.00
SNJ/FLOOR/VI 25 Providing and laying granite stone skirting Sqm 268.38
SNJ/FLOOR/VI 26 Providing and laying tandur stone skirting Sqm 62.87
SNJ/FLOOR/VI 27 Providing and laying polished shahabad skirting Sqm
SNJ/FLOOR/VI 28 Providing and laying rough shahabad skirting Sqm
SNJ/FLOOR/VI 29 Providing and laying Jaisalmer stone skirting Sqm
SNJ/FLOOR/VI 30 Providing and laying ceramic tile skirting Sqm 69.40
SNJ/FLOOR/VI 31 Providing and laying vitrified tile skirting Sqm 1222.29
SNJ/FLOOR/VI 32 Providing and laying rough vitrified tile skirting Sqm 1222.29
SNJ/FLOOR/VI 33 Providing and laying ceramic tile dado Sqm 709.81
SNJ/FLOOR/VI 34 Providing and laying marble stone dado Sqm
SNJ/FLOOR/VI 35 Providing and laying Kotah stone dado Sqm
SNJ/FLOOR/VI 36 Providing and laying granite stone dado Sqm
SNJ/FLOOR/VI 37 Providing and laying tandur stone dado Sqm
SNJ/FLOOR/VI 38 Providing and laying marble stone for treads and risers Sqm 162.19
SNJ/FLOOR/VI 39 Providing and laying Kotah stone for treads and risers Sqm 898.68
SNJ/FLOOR/VI 40 Providing and laying granite stone for treads and risers Sqm 302.91
SNJ/FLOOR/VI 41 Providing and laying tandur stone for treadsand risers Sqm 72.46
SNJ/FLOOR/VI 42 Providing and laying Jaisalmer stone for treads and risers Sqm
SNJ/FLOOR/VI 43 Providing marble for window sills and jambs Sqm 1376.63
SNJ/FLOOR/VI 44 Provding kotah stone for window sills and jambs Sqm 634.62
SNJ/FLOOR/VI 45 Providing granite stone for window sills and jambs Sqm 2663.11
SNJ/FLOOR/VI 46 Providing tandur stone for window sills and jambs Sqm 604.12
SNJ/FLOOR/VI 47 Providing, making and erecting in position kitchen platform with following RM
specifications. Width of platform 2'3" and height 32" top 5012.81
a. Kadappa slab 40 mm thick as base to granite stone slab.
b. Granite stone slab 20 mm thick with polishing,
c. Making hole for single bowl stainless steel sink with edge polishing
to cut surface of stones
d. One shelf of granite below platform
e. 2 no of vertical supports of kadappa stone with both side polish and
edge polish
f. 4" height granite fascia with edge polish

As per item no 56 above but with marble stone top slab RM 3395.80

As per item no 56 above but with polished kadappa top slab 50 mm RM


thick. 1807.80
SNJ/FLOOR/VI 50 Providing and laying vitrified tile dado Sqm 1265.76
SNJ/FLOOR/VI 51 Provding and laying interlocking paving blocks (heavy duty) Sqm 578.39
SECTION V :DOORS & WINDOWS

1 Providing and fixing in position door frames in correct line, level and
plumb of Teak Wood of size 4" x2.5" including applying coal tar to the
surface coming in contact with masorny including 6 no of MS hold fasts
fixed in concrete bedblocks in masonry ( 6"x6" size), MS rod at bottom RM 468.65
to keep the frame in position etc complete with all labour and material. -
door size 750mm x 2100 mm

2 As per item no 1 above but for door size 900 x 2100 mm RM

3 As per item no 1 above but for door size1000 x 2100 mm RM

4 As per item no 1 above but for door size1200 x 2100 mm RM

5 As per item no 1 above but for door size1500 x 2100 mm RM

6 As per item no 01 but with granite door frame of size 170 mm x 20 mm


and extra patti for rebate formation for 35 mm thick shutter. Door size RM 933.83
750 x 2100 mm

7 As per item no 6 above but for door size 900 x 2100 mm RM

8 As per item no 6 above but for door size1000 x 2100 mm RM

9 As per item no 6 above but for door size1200 x 2100 mm RM

10 As per item no 6 above but for door size1500 x 2100 mm RM

11 As per item no 01 but with marble door frame of size 170 mm x 20 mm


and extra patti for rebate formation for 35 mm thick shutter. Door size RM 578.85
750 x 2100 mm

12 As per item no11 above but for door size 900 x 2100 mm RM

13 As per item no 11 above but for door size1000 x 2100 mm RM

14 As per item no 11 above but for door size1200 x 2100 mm RM

15 As per item no11 above but for door size1500 x 2100 mm RM

16 Providing and fixing in position flush block board door shutters 35 mm


thick including 25 mm lipping patti, both faces finished with commercial
teak ply, including fixing with 4 no of hinges, required screws etc Sq.M 1097.63
complete. - single shutter - size of door - 750 x 2100 mm
17 As per item no 16 above but for door size of 900 x 2100 mm Sq.M 1138.66

18 As per item no 16 above but for door size of 1000 x 2100 mm Sq.M 1284.05

19 As per item no 16 above but for double shutter door of size 1200 x 2100
Sq.M

20 As per item no 16 above but for double shutter door of size 1500 x 2100
Sq.M

21 Providing and fixing laminate of approved colour and shade to doors


Sq.M 432.01
including all labour and material

22 Providing and fixing following MS powder coated fittings and fixtures for
doors
a. Aldrop 250 mm size No
b. Tadipatti No
c. Tower bolts No
d. PVC gattu No
e. Door stopper No
f. D type handles No

23 Providing and fixing following Aluminium fittings and fixtures for doors

a. Aldrop 250 mm size No


b. Tadipatti No
c. Tower bolts No
d. PVC gattu No
e. Door stopper No
f. D type handles No

24 Providing and fixing following stainless steel fittings and fixtures of D-


line or equivalent make for doors
a. Aldrop 250 mm size No
b. Tadipatti No
c. Tower bolts No
d. PVC gattu No
e. Door stopper No
f. D type handles No

25 Providing and fixing following brass fittings and fixtures of D-line or


equivalent make for doors
a. Aldrop 250 mm size No
b. Tadipatti No
c. Tower bolts No
d. PVC gattu No
e. Door stopper No
f. D type handles No

26 Providing and fixing night latch of approved brand to door with all
No
hardware and accessories required
27 Providing and fixing in position automatic door closure of approved
No
make including all labour and material complete.

28 Providing and fixing peep hole / eye piece of approved make to doors
including all labour and material complete

29 Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws, 4 mm
thick clear float glass etc complete with all labour and material.- 2 track
sliding window

30 As per item no 29 above but with aluminium colour anodised sections


-do-

31 Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws,4 mm
thick clear float glass etc complete with all labour and material.- 3 track
sliding window with mosquito net

32 As per item no 31 above but with colour anodised aluminium sections


-do-

33 Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws, 6 mm
thick clear float glass etc complete with all labour and material.- 4 track
sliding window, with mosquito net

34 As per item no 33 above but with colour anodised aluminium sections


-do-

35 Providing, making and erection in correct line, level and plumb


aluminium sliding window with powder coated sections as per detail
design and drawing including all accessories such as locking
arrangement, rollers, wool pile in tracks, EPDM gaskets, screws,6 mm
thick clear float glass etc complete with all labour and material.- 5 track
sliding window, with mosquito net

36 As per item no 35 above but with colour anodised aluminium sections


-do-

37 Providing and fixing in position aluminium openable windows with


powder coated sections, with all accessories such as hinges, peg stays,
4 mm thick clear float glass, beading, EPDM gaskets, etc complete with
all labour and material
38 As per item no 37 above but with colour anodised sections -do-

39 Providing and fixing in position aluminium louvered windows with


powder coated sections as per detail design and drawing with all
accessories and 4 mm thick frosted glass for louvers etc complete.

40 Providing and fixing in position aluminium louvered windows with colour


anodised sections as per detail design and drawing with all accessories
and 4 mm thick frosted glass for louvers etc complete.

41 Providing and erecting in position fixed glazing with aluminium powder


coated sections as per detail design and drawing, including all
accessories such as polysulphide sealants, stainless steel clips, 12 mm
thick glass, all required scaffolding other labour and material complete
the item in all respects.

42 As per item no 31 above but with colour anodised aluminium sections

43 Providing, fabricating and fixing in position for grills & railings in Powder
coated MS tubular sections of all shapes and size, with weight upto
15 kg / sqm, as per detail design and drawing, all labour and material 1019.35
complete.

44 Providing, fabricating and fixing in position for grills & railings in MS


tubular sections with enamel paint of all shapes and size, with weight 798.45
upto 15 kg / sqm, as per detail design and drawing, all labour and
material complete.
45 Providing and fixing in position MS glazed windows with Z section, 4 mm
thick clear float glass, 10 mm MS square bars at 120 mm c/c, reqired
springs, putty and two coats of oilpaint etc complete. 1274.64

46 Providing and fixing in position Sintex door shutters to already fixed


granite frame for toilet doors with all accessories complete.

SECTION VIII - WATERPROOFING WORKS

SNJ/WP/VIII 1 Waterproofing of terrace with brick bat coba upto 115 mm thk Sqm 348.14
SNJ/WP/VIII 2 Waterproofing of toilet sunks with brick bat coba filling Cum 2652.48
SNJ/WP/VIII 3 Box type waterproofing for basement walls and wherever required Sqm 475.66
SNJ/WP/VIII 4 Chemical waterproofing to terrace and toilet sunks Sqm 348.14

SECTION IX - PAINTING

SNJ/PAINT/IX 1 White wash Sqm 4.71


SNJ/PAINT/IX 2 Dry distemper Sqm 19.39
SNJ/PAINT/IX 3 Oil bound distemper Sqm 42.65
SNJ/PAINT/IX 4 Synthetic enamel (oil paint) Sqm 46.26
SNJ/PAINT/IX 5 Plastic emulsion Sqm 71.68
SNJ/PAINT/IX 6 Lustre paint Sqm 66.92
SNJ/PAINT/IX 7 Cement paint Sqm 36.19
SNJ/PAINT/IX 8 Sandtex paint Sqm 70.77
SNJ/PAINT/IX 9 Anti fungal paint such as ACE Sqm 91.34
SNJ/PAINT/IX 10 Aluminium paint to structural steel Sqm

SECTION X - ROOFING WORK

SNJ/ROOF/X 1 AC sheet roofing Sqm


SNJ/ROOF/X 2 AC ridges RM
SNJ/ROOF/X 3 AC sheet cladding Sqm
SNJ/ROOF/X 4 AC flashig Sqm
SNJ/ROOF/X 5 AC gutters Sqm
SNJ/ROOF/X 6 Precoated sheet roofing Sqm
SNJ/ROOF/X 7 Precoated ridges RM
SNJ/ROOF/X 8 Precoated sheet cladding Sqm
SNJ/ROOF/X 9 Precoated sheet flashing Sqm
SNJ/ROOF/X 10 Precoated sheet gutters Sqm
SNJ/ROOF/X 11 Aluminium sheet roofing Sqm
SNJ/ROOF/X 12 Aluminium ridges RM
SNJ/ROOF/X 13 Aluminium sheet cladding Sqm
SNJ/ROOF/X 14 Aluminium flashings Sqm
SNJ/ROOF/X 15 Aluminium gutters Sqm
SNJ/ROOF/X 16 FRP sheet roof Sqm
SNJ/ROOF/X 17 FRP ridges RM
SNJ/ROOF/X 18 FRP sheet cladding Sqm
SNJ/ROOF/X 19 FRP sheet flashing Sqm
SNJ/ROOF/X 20 FRP gutters Sqm
SNJ/ROOF/X 21 Mangalor tiles with frame work Sqm
SNJ/ROOF/X 22 Pan tile roofing on exsting slab Sqm
SNJ/ROOF/X 23 FRP domes Sqm
SNJ/ROOF/X 24 Polycarbonate sheet domes/ roof covering Sqm

SECTION XI - MISCELLANEOUS WORKS 1.73


136.42
SNJ/MISC/XI 1 Structural steel fabrication and erection wherever required for trusses, MT
stanchions, and such other industrial activities. 330.40
SNJ/MISC/XI 2 Box type fan hooks No
SNJ/MISC/XI 3 Anchor fasteners No
SNJ/MISC/XI 4 Fabrication and erection of steel required for railings of balconies, Kg
staircases, terraces etc with painting
SNJ/MISC/XI 5 ACP sheet cladding Sqm
SNJ/MISC/XI 6 Chain link fencing 4' height Sqm
SNJ/MISC/XI 7 Chain link fencing 8' height Sqm
SNJ/MISC/XI 8 Barbed wire fencing Sqm
d

Site: 0 Location : Pune


Computer Code No. : W1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/WP/VIII/3 Unit : per sqm

Description : Box type W/P to RCC raft, walls

Providing box type waterproofing treatment to RCC raft, wall, footings, columns, beams in
basement by fixing rough shahabad stone slabs of about 25 mm thickness in C:M. 1:3 with
waterproofing layer in between shahabad stone and slab bottom/ wall surfaces well pointed with
cement plaster mixed with waterproofing compound carefully well pressed and cured. The said
treatment shall be carried out at the hands of approved waterproofing agency.

0.38
Sr.No. Particulars Quantity Unit Rate per Amount 0.0152
1 Materials : 1.2768
a) Cement 0.80 Bags 255.00 204.00
b) Sand 0.04 Cum 1060.00 42.40
c) Shahabad stone with 5% wastage 1.05 Sqm. 82.50 86.63 117.435
d) Waterproofing compound 0.60 Kg. 40.00 24.00

2 Labours :
Masons for laying tiles & finishing 0.15 No. 150.00 22.50
Unskilled labour 0.30 No. 80.00 24.00

3 Centering & Shuttering


Nil

4 Others
0.00 0.00 0.00
TOTAL (A)
403.53
5 Tools & Plants Charges 2.00% on total (A) 8.07
6 Water charges 0.50% on total (A) 2.02
7 Electricity Charges 0.00% on total (A) 0.00
TOTAL (B)
413.61
8 Over head & Profit 15.00% on total (B) 62.04

TOTAL 475.66

Say Rs. 476 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : W2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/WP/VIII/2 Unit : per Cum

Description : Brickbat water proofing for toilets

Providing & laying brick bat coba of required thickness in C:M. 1:4 over the specified area including
rubbing and cleaning the base formwork if necessary giving proper slope compacting and curing
etc. complete, (in sunk portion of toilets) including providing and fixing 1" dia GI water escape
pipe etc. complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming the thickness of 200mm
1 Materials :
a) Cement 0.63 Bags 255.00 160.65
b) Sand 0.07 Cum 650.00 45.50
c) Brickbats 0.16 Cum 250.00 40.00
d) Waterproofing compound 0.63 Kg. 40.00 25.20
e) 1" dia. GI pipe 0.30 Rmt. 89.00 26.70
2 Labours :
Laying of brickbats & finishing
Mason 0.50 No. 200.00 100.00
Helper 0.50 No. 80.00 40.00

3 Others
Lift 1.00 Cum 12.00 12.00

TOTAL (A) 450.05


4 Tools & Plants Charges 2.00% on total (A) 9.00
5 Water charges 0.50% on total (A) 2.25
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 461.30


7 Over head & Profit 15.00% on total (B) 69.20

Costing for 0.2 cum TOTAL 530.50

Say Rs. 2,652 /- Per per Cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/WP/VIII/1 Unit : per sqm

Description : Brickbat water proofing for terrace

Providing and laying cement bonded waterproofing treatment using brick bats fixed in concrete
1:2:4 in required slope and finishing top with neat cement punning, marking lines at 300 mm c/c
including providing and mixing waterproofing compound ( work to be carried out at the hands of
approved nominated sub contractors) including curing, testing against watertightness

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming 1 sqm. Of area with 115 thk. Coba
1
a) Cement 0.40 Bags 255.00 102.77
b) Sand 0.03 Cum 1060.00 31.80
c) Metal 0.03 Cum 340.00 10.20
d) Brickbats 0.08 Cum 250.00 20.00
e) Waterproofing compound 0.43 Kg. 40.00 17.20

2 Labours :
Laying of brickbats & finishing
Mason 0.40 No. 200.00 80.00
Helper 0.40 No. 80.00 32.00

3 Others
Lift 0.12 Cum 12.00 1.38

TOTAL (A) 295.35


4 Tools & Plants Charges 2.00% on total (A) 5.91
5 Water charges 0.50% on total (A) 1.48
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 302.73


7 Over head & Profit 15.00% on total (B) 45.41

TOTAL 348.14
Say Rs. 348 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : W4 Default Date : Dec 30, 99
Revision on Date : 14-08-06
Item No. : 35 Unit : per sqm

Description : Chemical w/p for terrace, toilets

Providing and applying approved waterproofing chemical as per manufacturer's specifications to


terrace slab, toilet bottoms and sides, balconies etc wherever required with all labour and material

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
Rate given by water proofing agency 1.00 Sqm 275.00 275.00

2 Labours :

3 Centering & Shuttering


Nil

4 Others

TOTAL (A) 275.00


5 Tools & Plants Charges 2.00% on total (A) 5.50
6 Water charges 0.50% on total (A) 1.38
7 Electricity Charges 1.00% on total (A) 2.75

TOTAL (B) 284.63


8 Over head & Profit 15.00% on total (B) 42.69

TOTAL 327.32

Say Rs. 327 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/1 Unit : per sqm

Description : White wash

Providing and applying white wash to walls and ceilings , to concrete / brick /block/ stone surfaces
including preparing the surface by cleaning, including scaffolding of required type, all labour and
material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming 10sqm of area
1 Materials :
a) Slaked Lime 2.80 Kg. 1.50 4.20
b) Ultramarine blue 7.00 Gram 0.11 0.80
c) Glue 8.00 Gram 0.05 0.39
d) Sodium chloride 365.00 Gram 0.01 3.65
2 Labours :
For 10 sqm. Area , labour required =
(0.085+0.035) for first coat &
(0.07+.035)*2 for two coat
Lime washer 0.23 No. 100.00 22.50
Helper 0.11 No. 80.00 8.40

3 Others

TOTAL (A) 39.95


4 Tools & Plants Charges 2.00% on total (A) 0.80
5 Water charges 0.50% on total (A) 0.20
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 40.94


7 Over head & Profit 15.00% on total (B) 6.14

For 10 sqm costing = 63/- TOTAL 47.09

Say Rs. 5 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0 refer page 109 & 75


Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/2 Unit : per sqm

Description : Dry distemper

Providing and applying dry distemper of approved make, colour and shade to walls and ceilings ,
to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, including
scaffolding of required type, all labour and material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming 10sqm of area
1 Materials :
a) Dry distemper 1.35 Kg. 67.00 90.45
b) Glue 80.00 Gram 0.05 3.91
d) Putty 0.20 Kg. 40.95 8.19

2 Labours :
For 10 sqm. Area , labour required =
(0.22+0.05) for first coat & (0.145+.04) for
second coat
Painter 0.37 No. 150.00 54.75
Helper 0.09 No. 80.00 7.20

3 Others

TOTAL (A) 164.50


4 Tools & Plants Charges 2.00% on total (A) 3.29
5 Water charges 0.50% on total (A) 0.82
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 168.61


7 Over head & Profit 15.00% on total (B) 25.29

For 10 sqm costing = 290/- TOTAL 193.90

Say Rs. 19 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/3 Unit : per sqm

Description : Oil bound distemper

Providing and applying oil bound distemper of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning,
filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and
material complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) OBD 1.50 Kg. 90.00 135.00 107.64
b) Primer 0.85 lts. 60.90 51.77
c) Glue 80.00 Gram 0.05 3.91
d) Whitning 1.00 Kg. 20.00 20.00
e) Putty 0.20 Kg. 40.95 8.19

2 Labours :
For 10 sqm. Area , labour required =
(0.275+0.06) for first coat & (0.22+.05) for
second coat
Painter 0.50 No. 250.00 123.75
Helper 0.11 No. 175.00 19.25

3 Others

TOTAL (A) 361.86


4 Tools & Plants Charges 2.00% on total (A) 7.24
5 Water charges 0.50% on total (A) 1.81
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 370.91


7 Over head & Profit 15.00% on total (B) 55.64

For 10 sqm costing = 371.5/- TOTAL 426.54

Say Rs. 43 /- Per per sqm 3.96269

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/4 Unit : per sqm

Description : Synthetic enamel paint

Providing and applying synthetic enamel paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning,
filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and
material complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) Synthetic enamel 1.50 Kg. 141.75 212.63
b) Primer 0.85 lts. 60.90 51.77
c) Glue 80.00 Gram 0.05 3.91
d) Whitning 1.00 Kg. 20.00 20.00
e) Putty 0.20 Kg. 40.95 8.19

2 Labours :
For 10 sqm. Area , labour required =
(0.295+0.09) for first coat & (0.265+.06)
for second coat
Painter 0.56 No. 150.00 84.00
Helper 0.15 No. 80.00 12.00

3 Others

TOTAL (A) 392.49


4 Tools & Plants Charges 2.00% on total (A) 7.85
5 Water charges 0.50% on total (A) 1.96
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 402.30


7 Over head & Profit 15.00% on total (B) 60.34

For 10 sqm costing = 482.95/- TOTAL 462.64

Say Rs. 46 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/6 Unit : per sqm

Description : Lustre paint

Providing and applying lustre paint of approved make,colour and shade to walls and ceilings , to
concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the
cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material
complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) Luster paint 1.50 Ltr. 218.75 328.13
b) Primer 0.85 lts. 60.90 51.77
c) Glue 80.00 Gram 0.05 3.91
d) Whitning 1.00 Kg. 20.00 20.00
e) Putty 0.30 Kg. 40.95 12.29

2 Labours :
For 10 sqm. Area , labour required =
(0.4+0.15) for first coat & (0.375+.12) for
second coat
Painter 0.85 No. 150.00 127.88
Helper 0.30 No. 80.00 23.76

3 Others

TOTAL (A) 567.72


4 Tools & Plants Charges 2.00% on total (A) 11.35
5 Water charges 0.50% on total (A) 2.84
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 581.91


7 Over head & Profit 15.00% on total (B) 87.29

For 10 sqm costing = 623.93/- TOTAL 669.20

Say Rs. 67 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/7 Unit : per sqm

Description : Cement paint

Providing and applying cement paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning,
filling the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour
and material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming 10sqm of area
1 Materials :
a) Cement paint 4.00 Kg. 49.35 197.40
b) Putty 0.15 Kg. 40.95 6.14

2 Labours :
For 10 sqm. Area , labour required =
(0.25+0.15) for first coat & (0.2+.1) for
second coat
Painter 0.45 No. 150.00 67.50
Helper 0.25 No. 80.00 20.00
Unskilled 0.20 No. 80.00 16.00

3 Others

TOTAL (A) 307.04


4 Tools & Plants Charges 2.00% on total (A) 6.14
5 Water charges 0.50% on total (A) 1.54
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 314.72


7 Over head & Profit 15.00% on total (B) 47.21

For 10 sqm costing = 377.82/- TOTAL 361.93

Say Rs. 36 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/8 Unit : per sqm

Description : Sandtex paint

Providing and applying sandtex paint of approved make,colour and shade to walls and wherever
required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning,
filling the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour
and material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming 10sqm of area
1 Materials :
a) Sandtex paint 4.50 Kg. 86.36 388.63
b) Cement paint 1.50 Kg. 49.35 74.03
c) Putty 0.20 Kg. 40.95 8.19

2 Labours :
For 10 sqm. Area , labour required =
(0.3+0.1) for first coat & (0.25+.1) for
second coat
Painter 0.65 No. 150.00 97.50
Helper 0.20 No. 80.00 16.00
Unskilled 0.20 No. 80.00 16.00

3 Others
TOTAL (A) 600.35
4 Tools & Plants Charges 2.00% on total (A) 12.01
5 Water charges 0.50% on total (A) 3.00
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 615.35


7 Over head & Profit 15.00% on total (B) 92.30

For 10 sqm costing = 761.5/- TOTAL 707.66

Say Rs. 71 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/9 Unit : per sqm

Description : Antifungal paint

Providing and applying anti fungal paint of approved make,colour and shade to walls to concrete /
brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty
filling, rubbing , curing etc including scaffolding of required type, all labour and material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming 10sqm of area
1 Materials :
a) Antifungal paint 4.50 Kg. 123.38 555.19
b) Cement paint 1.50 Kg. 49.35 74.03
c) Putty 0.20 Kg. 40.95 8.19

2 Labours :
For 10 sqm. Area , labour required =
(0.3+0.1) for first coat & (0.25+.1) for
second coat
Painter 0.65 No. 150.00 97.50
Helper 0.30 No. 80.00 24.00
Unskilled 0.20 No. 80.00 16.00 17.7

3 Others

TOTAL (A) 774.90


4 Tools & Plants Charges 2.00% on total (A) 15.50
5 Water charges 0.50% on total (A) 3.87
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 794.28


7 Over head & Profit 15.00% on total (B) 119.14

For 10 sqm costing = 953.22/- TOTAL 913.42

Say Rs. 91 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : W3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PAINT/IX/5 Unit : per sqm

Description : Plastic emulsion paint

Providing and applying plastic emulsion paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning,
filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and
material complete.
Providing and applying plastic emulsion paint of approved make,colour and shade to walls and
ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning,
filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and
material complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming 10sqm of area
1 Materials :
a) Plastic emulsion paint 1.75 Kg. 205.15 359.01
b) Primer 0.85 lts. 60.90 51.77
c) Glue 80.00 Gram 0.05 3.91
d) Whitning 1.25 Kg. 20.00 25.00
e) Putty 0.40 Kg. 40.95 16.38

2 Labours :
For 10 sqm. Area , labour required =
(0.425+0.25) for first coat & (0.375+.15)
for second coat
Painter 0.80 No. 150.00 120.00
Helper 0.40 No. 80.00 32.00

3 Others

TOTAL (A) 608.06


4 Tools & Plants Charges 2.00% on total (A) 12.16
5 Water charges 0.50% on total (A) 3.04
6 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 623.27


7 Over head & Profit 15.00% on total (B) 93.49

For 10 sqm costing = 553.7/- TOTAL 716.75

Say Rs. 72 /- Per per sqm 6.68896

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/1 Unit : per Sqm.

Description : Ac trafford 6mm thk.sheets

Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

16.5 4.2
1.21275 72.765
Sr.No. Particulars Quantity Unit Rate per Amount (sheets in row + 1) x no. of purlins
Assuming area of 15 x 4 = 60 sqm. 64 hooks
1 Materials :
a) AC trafford sheets 72.77 Sqm. 149.10 10849.26
(adding 100mm for side laps &
200mm for end lap & 5% for
wastage) 1100 1100

b) Bitumen washers 3mm thk.


0.30 Kg. 32.00 9.60 1014 950
c) J hooks & nuts 64.00 Nos. 6.30 403.20 0.921818182 0.8636364
d) GI flat washer 2mm thk. 0.30 Kg. 47.25 14.18

2 Labours :
For fixing the sheets 60.00 Sqm. 35.00 2100.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 13376.24


4 Tools & Plants Charges 2.00% on total (A) 267.52
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 66.88

TOTAL (B) 13710.64


7 Over head & Profit 15.00% on total (B) 2056.60

Costing for 60 sqm. area TOTAL 15767.24

Say Rs. 263 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/2 Unit : per Rmt.

Description : Ac 6mm thk.ridges

Providing and fixing in positional AC ridges as required including all fixing accessories complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) AC ridges 1.05 Rmt. 94.50 99.23
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 25.00 25.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 138.41


4 Tools & Plants Charges 2.00% on total (A) 2.77
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 0.69

TOTAL (B) 141.87


7 Over head & Profit 15.00% on total (B) 21.28

TOTAL 163.15

Say Rs. 163 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/3 Unit : per Sqm.

Description : Ac trafford 6mm thk.sheets cladding

Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
Cladding, flashing etc.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 4 = 60 sqm.
1 Materials :
a) AC trafford sheets 69.30 Sqm. 149.10 10332.63
(adding 100mm for side laps &
5% for wastage)

b) Bitumen washers 3mm thk.


0.30 Kg. 32.00 9.60
c) J hooks & nuts 48.00 Nos. 6.30 302.40
d) GI flat washer 2mm thk. 0.30 Kg. 47.25 14.18

2 Labours :
For fixing the sheets 1.00 Sqm. 42.00 42.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 10700.81


TOTAL (A) 10700.81
4 Tools & Plants Charges 2.00% on total (A) 214.02
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 53.50

TOTAL (B) 10968.33


7 Over head & Profit 15.00% on total (B) 1645.25

Costing for 60 sqm. area TOTAL 12613.57

Say Rs. 210 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/4 Unit : per Rmt.

Description : Ac gutter

Providing and fixing in required slope AC gutter including fixing with MS flat brackets at 600 mm c/c
of required size, filling the joints with polysulphide sealants etc with all labour and material and
testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) AC Gutter 1.05 Rmt. 105.00 110.25
(adding 5% for wastage)

b) Bitumen washers 3mm thk.


0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 25.00 25.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 149.44


4 Tools & Plants Charges 2.00% on total (A) 2.99
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 0.75

TOTAL (B) 153.17


7 Over head & Profit 15.00% on total (B) 22.98

TOTAL 176.15

Say Rs. 176 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06 sheet width = 1.07m, length = 3.2
Item No. : FDAPL/ROOF/X/5 Unit : per Sqm. 15*2*1.07*2.9*1.05
97.7445
Description : MS precoated sheets (sheets in row + 1) x no. of purlins
area of sheets = 15*2*2.9*1.07 = 93.09
93.09
Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any Purlin spacing = 1.2m
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc (sheets in row + 1) x no. of purlins
complete with all labour and material. 80 hooks

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 5.6 = 84 sqm.
1 Materials :
a) MS precoated sheets
0.55mm 97.74 Sqm. 319.00 31180.50
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage)

b) Bitumen washers 3mm thk.


0.38 Kg. 32.00 12.00
c) J hooks & nuts 80.00 Nos. 6.30 504.00
d) GI flat washer 2mm thk. 0.38 Kg. 47.25 17.72

2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 37829.41


4 Tools & Plants Charges 2.00% on total (A) 756.59
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 189.15

TOTAL (B) 38775.15


7 Over head & Profit 15.00% on total (B) 5816.27

Costing for 84 sqm. area TOTAL 44591.42

Say Rs. 531 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/2 Unit : per Rmt.

Description : MS precoated ridges

Providing and fixing in position MS precoated ridges as required including all fixing accessories
complete
Sr.No. Particulars Quantity Unit Rate per Amount
1 Materials :
a) MS precoated ridges 1.05 Rmt. 181.50 190.58
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 55.00 55.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 259.76


4 Tools & Plants Charges 2.00% on total (A) 5.20
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 1.30

TOTAL (B) 266.25


7 Over head & Profit 15.00% on total (B) 39.94

TOTAL 306.19

Say Rs. 306 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/3 Unit : per Sqm.

Description : MS precoated .55mm thk.sheets cladding

Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any
other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc
complete with all labour and material. For Cladding

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 2 = 30 sqm. sheets required = 15*1.07*2*1.05
1 Materials : 33.705
a) MS precoated sheets
0.55mm 33.71 Sqm. 319.00 10751.90
(adding 70mm for side laps &
5% for wastage)

b) Bitumen washers 3mm thk.


0.23 Kg. 32.00 7.20
c) J hooks & nuts 48.00 Nos. 6.30 302.40
d) GI flat washer 2mm thk. 0.23 Kg. 47.25 10.63

2 Labours :
For fixing the sheets 32.00 Sqm. 90.00 2880.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 13952.13


TOTAL (A) 13952.13
4 Tools & Plants Charges 2.00% on total (A) 279.04
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 69.76

TOTAL (B) 14300.93


7 Over head & Profit 15.00% on total (B) 2145.14

Costing for 32 sqm. area TOTAL 16446.07

Say Rs. 514 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/4 Unit : per Rmt.

Description : MS precoated gutter

Providing and fixing in required slope precoated sheet gutter including fixing with MS flat brackets at
600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and
material and testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) MS precoated Gutter 1.05 Rmt. 216.15 226.96
(adding 5% for wastage)

b) Bitumen washers 3mm thk.


0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 90.00 90.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 331.14


4 Tools & Plants Charges 2.00% on total (A) 6.62
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 1.66

TOTAL (B) 339.42


7 Over head & Profit 15.00% on total (B) 50.91

TOTAL 390.33

Say Rs. 390 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/5 Unit : per Sqm.

Description : Alluminium sheets

Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

Sr.No. Particulars Quantity Unit Rate per Amount 150.72


Assuming area of 15 x 5.6 = 84 sqm. 4.71
1 Materials : 1.536
a) MS precoated sheets
0.55mm 97.74 Sqm. 415.80 40642.16 122.88
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage)

b) Bitumen washers 3mm thk.


0.38 Kg. 32.00 12.00
c) J hooks & nuts 80.00 Nos. 6.30 504.00
d) GI flat washer 2mm thk. 0.38 Kg. 47.25 17.72

2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 47291.08


5 Tools & Plants Charges 2.00% on total (A) 945.82
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 236.46

TOTAL (B) 48473.36


8 Over head & Profit 15.00% on total (B) 7271.00

Costing for 84 sqm. area TOTAL 55744.36

Say Rs. 664 /- Per per Sqm.

Prepared by :
Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/10 Unit : per Rmt.

Description : Alluminium ridges

Providing and fixing in position aluminium ridges as required including all fixing accessories
complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) MS precoated ridges 1.05 Rmt. 236.50 248.33
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 55.00 55.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 317.51


5 Tools & Plants Charges 2.00% on total (A) 6.35
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.59

TOTAL (B) 325.45


8 Over head & Profit 15.00% on total (B) 48.82

TOTAL 374.26

Say Rs. 374 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/11 Unit : per Sqm.

Description : Alluminium sheets cladding

Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required
levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
cladding

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 2 = 30 sqm.
1 Materials :
a) MS precoated sheets
0.55mm 33.71 Sqm. 415.80 14014.54
(adding 70mm for side laps &
5% for wastage)

b) Bitumen washers 3mm thk.


0.23 Kg. 32.00 7.20
c) J hooks & nuts 48.00 Nos. 6.30 302.40
d) GI flat washer 2mm thk. 0.23 Kg. 47.25 10.63

2 Labours :
For fixing the sheets 32.00 Sqm. 90.00 2880.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 17214.77


5 Tools & Plants Charges 2.00% on total (A) 344.30
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 86.07

TOTAL (B) 17645.14


8 Over head & Profit 15.00% on total (B) 2646.77

Costing for 30 sqm. area TOTAL 20291.91

Say Rs. 676 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/12 Unit : per Rmt.

Description : Alluminium gutter

Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600
mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material
and testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) MS precoated Gutter 1.05 Rmt. 302.50 317.63
(adding 5% for wastage)

b) Bitumen washers 3mm thk.


0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 90.00 90.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 421.81


5 Tools & Plants Charges 2.00% on total (A) 8.44
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 2.11

TOTAL (B) 432.36


8 Over head & Profit 15.00% on total (B) 64.85

TOTAL 497.21

Say Rs. 497 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/13 Unit : per Sqm.

Description : FRP sheets

Providing and fixing in position FRP sheet of 1.5 mm thick of Finoram or any other approved make at
all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and
material.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 5.6 = 84 sqm.
1 Materials :
a) FRP sheets 1.5mm 97.74 Sqm. 423.50 41394.80 7.7 15.4
(adding 70mm for side laps &
200mm for end lap & 5% for
wastage) 347908.2 160650

b) Bitumen washers 3mm thk.


0.38 Kg. 32.00 12.00 3080 757
c) J hooks & nuts 80.00 Nos. 6.30 504.00 73920 97.648613
d) GI flat washer 2mm thk. 0.38 Kg. 47.25 17.72 2587777
2601726.8
538200
6075612
2 Labours : 30378.06
For fixing the sheets 84.00 Sqm. 72.80 6115.20 15.4
1972.601299
9863.006494

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 48043.71


5 Tools & Plants Charges 2.00% on total (A) 960.87
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 240.22

TOTAL (B) 49244.81


8 Over head & Profit 15.00% on total (B) 7386.72

Costing for 84 sqm. area TOTAL 56631.53

Say Rs. 674 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/14 Unit : per Rmt.

Description : FRP ridges

Providing and fixing in position FRP ridges as required including all fixing accessories complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) MS precoated ridges 1.05 Rmt. 154.00 161.70
(adding 5% for wastage)
b) Bitumen washers 3mm thk.
0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95

2 Labours :
For fixing the sheets 1.00 Rmt 48.05 48.05

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 223.93


5 Tools & Plants Charges 2.00% on total (A) 4.48
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.12

TOTAL (B) 229.53


8 Over head & Profit 15.00% on total (B) 34.43

TOTAL 263.96

Say Rs. 264 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/15 Unit : per Sqm.
Description : FRP sheets cladding

Providing and fixing in position FRP sheet roofing with 1.5 mm thick sheets at all required levels
including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For
cladding

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 2 = 30 sqm.
1 Materials :
a) MS precoated sheets
0.55mm 33.71 Sqm. 423.50 14274.07
(adding 70mm for side laps &
5% for wastage)

b) Bitumen washers 3mm thk.


0.23 Kg. 32.00 7.20
c) J hooks & nuts 48.00 Nos. 6.30 302.40
d) GI flat washer 2mm thk. 0.23 Kg. 47.25 10.63

2 Labours :
For fixing the sheets 32.00 Sqm. 90.00 2880.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 17474.30


5 Tools & Plants Charges 2.00% on total (A) 349.49
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 87.37

TOTAL (B) 17911.16


8 Over head & Profit 15.00% on total (B) 2686.67

Costing for 30 sqm. area TOTAL 20597.83

Say Rs. 687 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/16 Unit : per Rmt.
Description : FRP gutter

Providing and fixing in required slope FRP gutter including fixing with MS flat brackets at 600 mm c/c
of required size, filling the joints with polysulphide sealants etc with all labour and material and
testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) MS precoated Gutter 1.05 Rmt. 209.00 219.45
(adding 5% for wastage)

b) Bitumen washers 3mm thk.


0.02 Kg. 32.00 0.64
c) J hooks & nuts 2.00 Nos. 6.30 12.60
d) GI flat washer 2mm thk. 0.02 Kg. 47.25 0.95
e) Polysulphide sealant 0.03 Kg. 500.00 12.50

2 Labours :
For fixing the sheets 1.00 Rmt 105.00 105.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 351.14


5 Tools & Plants Charges 2.00% on total (A) 7.02
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.76

TOTAL (B) 359.91


8 Over head & Profit 15.00% on total (B) 53.99

TOTAL 413.90

Say Rs. 414 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/ROOF/X/13 Unit : per Sqm.

Description : Polycarbonate sheets

Providing and fixing in position polycarbonate sheet roof as per detail design and drawing with
minimum thickness of sheet as 2 mm of Lexan or any other approved make including making the
joints waterproof with all labour and material and accessories to complete the work.
Providing and fixing in position polycarbonate sheet roof as per detail design and drawing with
minimum thickness of sheet as 2 mm of Lexan or any other approved make including making the
joints waterproof with all labour and material and accessories to complete the work.

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 5.6 = 84 sqm.
1 Materials :

a) Polycabonate sheets 2mm


88.20 Sqm. 1500.00 132300.00
add 5% for wastage
b) Bitumen washers 3mm thk.
0.38 Kg. 32.00 12.00
c) J hooks & nuts 80.00 Nos. 6.30 504.00
d) GI flat washer 2mm thk. 0.38 Kg. 47.25 17.72

2 Labours :
For fixing the sheets 84.00 Sqm. 72.80 6115.20

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 138948.92


5 Tools & Plants Charges 2.00% on total (A) 2778.98
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 694.74

TOTAL (B) 142422.64


8 Over head & Profit 15.00% on total (B) 21363.40

Costing for 84 sqm. area TOTAL 163786.04

Say Rs. 1,950 /- Per per Sqm.


Rate analysis

Site: 0 Location : Pune


Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm

Description : Grey Mosaic Tile Flooring of 25cm x 25cm

Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 25 cm x 25 cm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.16 Bags 255.00 40.80
b) Sand 0.03 Cum 1060.00 31.80
c) Mosaic tile ( as approved) 1.05 Sqm 150.00 157.50
d) White/ coloured cement 0.01 Bags 150.00 1.50

2 Labours :
a) for fixing & joint grouting 1.00 Sqm 32.00 32.00
b) for polishing (including 3 coats) 1.00 Sqm 20.00 20.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 283.60


5 Tools & Plants Charges 2.00% on total (A) 5.67
6 Water charges 0.50% on total (A) 1.42
7 Electricity Charges 0.50% on total (A) 1.42

TOTAL (B) 292.11


8 Over head & Profit 15.00% on total (B) 43.82

TOTAL 335.92

Say Rs. 336 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm
Description : Grey Mosaic Tile Flooring of 30x30

Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins
with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid,
waxing etc. complete. Size of tile 30 cm x 30cm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.16 Bags 255.00 40.80
b) Sand 0.05 Cum 1060.00 53.00
c) Mosaic tile ( as approved) 1.05 Sqm 220.00 231.00
d) White/ coloured cement 0.01 Bags 150.00 1.50

2 Labours :
a) For fixing & joint grouting 1.00 Sqm 32.00 32.00

b) for polishing (including 3 coats)


1.00 Sqm 20.00 20.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 378.30


5 Tools & Plants Charges 2.00% on total (A) 7.57
6 Water charges 0.50% on total (A) 1.89
7 Electricity Charges 0.50% on total (A) 1.89

TOTAL (B) 389.65


8 Over head & Profit 15.00% on total (B) 58.45

TOTAL 448.10

Say Rs. 448 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm

Description : White Mosaic Tile Flooring of 25x25


Providing & laying mosaic tile flooring of 20 to 25 mm thk. & size 25x25cm of White colour in required
positions & set in a bed of 1:6 cement mortor including neat cement float, filling the joint with
appropriate coloured cement slurry, curing, polishing etc. complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.16 Bags 255.00 40.80
b) Sand 0.03 Cum 1060.00 31.80
c) Mosaic tile ( as approved) 1.05 Sqm 244.00 256.20
d) White/ coloured cement 0.55 Kg 12.00 6.60

2 Labours :
a) For fixing & joint grouting 1.00 Sqm 32.00 32.00

b) for polishing (including 3 coats)


1.00 Sqm 20.00 20.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 387.40


5 Tools & Plants Charges 2.00% on total (A) 7.75
6 Water charges 0.50% on total (A) 1.94
7 Electricity Charges 0.50% on total (A) 1.94

TOTAL (B) 399.02


8 Over head & Profit 15.00% on total (B) 59.85

TOTAL 458.88

Say Rs. 459 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/2 Unit : per sqm

Description : White Mosaic Tile Flooring of 30 x 30

Providing,laying and fixing marble mosaic tiles in white cement on C.M. 1:6 bed including filling the
joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute
acid, waxing etc. complete. Size of tile 30 cm x 30 cm
Sr.No. Particulars Quantity Unit Rate per Amount
1 Materials :
a) Cement 0.16 Bags 255.00 40.80
b) Sand 0.05 Cum 1060.00 53.00
c) Mosaic tile ( as approved) 1.05 Sqm 350.00 367.50
d) White/ coloured cement 0.55 Kg 12.00 6.60

2 Labours :
a) For fixing & joint grouting 1.00 Sqm 32.00 32.00

b) for polishing (including 3 coats)


1.00 Sqm 20.00 20.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 519.90


5 Tools & Plants Charges 2.00% on total (A) 10.40
6 Water charges 0.50% on total (A) 2.60
7 Electricity Charges 0.50% on total (A) 2.60

TOTAL (B) 535.50


8 Over head & Profit 15.00% on total (B) 80.32

TOTAL 615.82

Say Rs. 616 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/22 Unit : per rmt

Description : Grey Mosaic Tile Skirting of 125 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing filling the joints with cement slurry, polishing, cleaning complete - gray
mosaic tile skirting 125 mm high

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.02 Bags 255.00 5.10
b) Sand 0.01 Cum. 1060.00 10.60
c) Mosaic tile skirting(as
approved) 1.05 rmt 23.00 24.15

2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00

b) for polishing (including 3 coats)


1.00 rmt 9.00 9.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 58.85


5 Tools & Plants Charges 2.00% on total (A) 1.18
6 Water charges 0.50% on total (A) 0.29
7 Electricity Charges 0.50% on total (A) 0.29

TOTAL (B) 60.62


8 Over head & Profit 15.00% on total (B) 9.09

TOTAL 69.71

Say Rs. 70 /- Per per rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/23 Unit : per rmt

Description : Grey Mosaic Tile Skirting of 150 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, polishing, cleaning, curing etc complete - gray mosaic tile skirting 150 mm
high

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.02 Bags 255.00 5.10
b) Mosaic tile skirting(as
approved) 0.01 Cum 1060.00 10.60
c) Mosaic tile skirting(as
approved) 1.05 rmt 32.00 33.60

2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00

b) for polishing (including 3 coats)


1.00 rmt 9.00 9.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 68.30


5 Tools & Plants Charges 2.00% on total (A) 1.37
6 Water charges 0.50% on total (A) 0.34
7 Electricity Charges 0.50% on total (A) 0.34

TOTAL (B) 70.35


8 Over head & Profit 15.00% on total (B) 10.55

TOTAL 80.90

Say Rs. 81 /- Per per rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/24 Unit : per rmt

Description : White Mosaic Tile Skirting of 125 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry,polishing, cleaning curing etc complete -
white mosaic tile skirting 125 mm high

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.02 Bags 255.00 5.10
b) Sand 0.01 cum. 1060.00 10.60
b) Mosaic tile skirting(as
approved) 1.05 rmt 30.00 31.50
c) White/ coloured cement 0.25 Kg 12.00 3.00

2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00

b) for polishing (including 3 coats)


1.00 rmt 9.00 9.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 69.20


5 Tools & Plants Charges 2.00% on total (A) 1.38
6 Water charges 0.50% on total (A) 0.35
7 Electricity Charges 0.50% on total (A) 0.35

TOTAL (B) 71.28


8 Over head & Profit 15.00% on total (B) 10.69

TOTAL 81.97

Say Rs. 82 /- Per per rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/25 Unit : per rmt

Description : White Mosaic Tile Skirting of 150 mm ht.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing,filling the joints with cement slurry, cleaning complete - white mosaic tile
skirting 150 mm high

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.02 Bags 255.00 5.10
b) Sand 0.01 Cum 1060.00 10.60
c) Mosaic tile skirting(as
approved) 1.05 rmt 45.00 47.25
d) White/ coloured cement 0.25 Kg 12.00 3.00

2 Labours :
a) For fixing & joint grouting 1.00 rmt 10.00 10.00

b) for polishing (including 3 coats)


1.00 rmt 9.00 9.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 84.95


5 Tools & Plants Charges 2.00% on total (A) 1.70
6 Water charges 0.50% on total (A) 0.42
7 Electricity Charges 0.50% on total (A) 0.42

TOTAL (B) 87.50


8 Over head & Profit 15.00% on total (B) 13.12

TOTAL 100.62

Say Rs. 101 /- Per per rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/1 Unit : per sqm

Description : P/L IPS 50mm thk.

Provding and laying in position IPS flooring 50mm thick in proportion of 1:2:4 laid in proper line and
level including finishing the top surface with cement punning, curing, cleaning etc complete with all
labour and material.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.02 Cum 1060.00 23.85
c) Metal 12mm 0.05 Cum 340.00 15.30

2 Labours :
a) for pouring 1.00 Sqm 26.50 26.50
b) for finishing 1.00 Sqm 23.00 23.00
c) for shuttering 1.00 Sqm 10.56 10.56
3 Centering & Shuttering 1.00 Sqm 4.00 4.00
Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 159.31


5 Tools & Plants Charges 2.00% on total (A) 3.19
6 Water charges 0.50% on total (A) 0.80
7 Electricity Charges 0.50% on total (A) 0.80

TOTAL (B) 164.09


8 Over head & Profit 15.00% on total (B) 24.61

TOTAL 188.70

Say Rs. 189 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : F3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 29 Unit : per sqm

Description : Ceramic Tile Flooring

Providing and laying ceramic tiles of approved quality of approved colour, size & thickness for flooring
in required position laid on a bed 30mm thk.in 1:6 cement mortor including cement float filling joints
with white/colour cement slurry cleaning curing etc. complete as shown in detailed drawing or as
directed by architect incharge.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.16 Bags 255.00 40.80
b) Sand 0.05 Cum 1060.00 53.00
c) Ceramic tile (as approved) 1.05 Sqm 380.00 399.00
d) white cement 0.55 Kg 12.00 6.60

2 Labours :
for flooring including fixing, 1.00 Sqm 75.00 75.00
cleaning & curing etc. complete 0.00 0.00 0.00

3 Centering & Shuttering


Providing good Specified
material/
material / erection & dismantling
4 Others
0.00 0.00 0.00

TOTAL (A) 574.40


5 Tools & Plants Charges 2.00% on total (A) 11.49
6 Water charges 0.50% on total (A) 2.87
7 Electricity Charges 0.50% on total (A) 2.87

TOTAL (B) 591.63


8 Over head & Profit 15.00% on total (B) 88.74

TOTAL 680.38

Say Rs. 680 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/6 Unit : per sqm

Description : Marble Flooring

Providing, laying and fixing in position marble slabs for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40

c) Marble (including 5% wastage)


1.05 Sqm 860.00 903.00
d) White cement 0.22 Kg 12.00 2.64

2 Labours :
a) for fixing & joint grouting 1.00 Sqm 100.00 100.00
b) for polishing 1.00 Sqm 129.00 129.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1233.14


TOTAL (A) 1233.14
5 Tools & Plants Charges 2.00% on total (A) 24.66
6 Water charges 0.50% on total (A) 6.17
7 Electricity Charges 0.50% on total (A) 6.17

TOTAL (B) 1270.13


8 Over head & Profit 15.00% on total (B) 190.52

TOTAL 1460.65

Say Rs. 1,461 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/35 Unit : per Rmt.

Description : Marble Skirting

Providing and fixing in position dado of tiles / stone as per requirement, including fixing with C:M 1:4
backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete -marble stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Marble (including 10%
wastage) 1.10 Sqm 860.00 946.00
c) White cement 1.00 Kg 12.00 12.00
d) Sand 0.01 Cum 1060.00 10.60

2 Labours :
a) for fixing & joint grouting 1.00 Sqm 110.00 110.00
b) for polishing 1.00 Sqm 148.35 148.35

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1283.05


5 Tools & Plants Charges 2.00% on total (A) 25.66
6 Water charges 0.50% on total (A) 6.42
7 Electricity Charges 0.50% on total (A) 6.42

TOTAL (B) 1321.54


8 Over head & Profit 15.00% on total (B) 198.23

Costing per Sqm. TOTAL 1519.77

Say Rs. 152 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/7 Unit : per sqm

Description : Kota Flooring

Providing, laying and fixing in required position machine cut machine polished Kotah stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40
c) Kota (including 5% wastage) 1.05 Sqm 290.52 305.05
d) White cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing & polishing 1.00 Sqm 100.00 100.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 507.75


5 Tools & Plants Charges 2.00% on total (A) 10.15
6 Water charges 0.50% on total (A) 2.54
7 Electricity Charges 0.50% on total (A) 2.54

TOTAL (B) 522.98


8 Over head & Profit 15.00% on total (B) 78.45

TOTAL 601.43

Say Rs. 601 /- Per per sqm


Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/27 Unit : per Rmt.

Description : Kota Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, polishing, cleaning , curing etc complete
- kotah stone 100 mm height

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.34 Bags 255.00 86.70
b) Kota (including 15% wastage) 1.15 Sqm 290.52 334.10
c) White / coloured cement 1.10 Kg 12.00 13.20
d) Sand 0.01 Cum 1060.00 10.60

2 Labours :
a) for fixing & polishing 1.00 Sqm 121.00 121.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 565.60


5 Tools & Plants Charges 2.00% on total (A) 11.31
6 Water charges 0.50% on total (A) 2.83
7 Electricity Charges 0.50% on total (A) 2.83

TOTAL (B) 582.57


8 Over head & Profit 15.00% on total (B) 87.38

Costing per sqm TOTAL 669.95

Say Rs. 67 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/9 Unit : per sqm

Description : Tandoor Flooring

Providing, laying and fixing in required position machine cut machine polished Tandur stone flooring of
required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including
cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40
c) Tandoor (including 5%
wastage) 1.05 Sqm 291.00 305.55
d) White cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing & polishing 1.00 Sqm 86.00 86.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 494.25


5 Tools & Plants Charges 2.00% on total (A) 9.89
6 Water charges 0.50% on total (A) 2.47
7 Electricity Charges 0.50% on total (A) 2.47

TOTAL (B) 509.08


8 Over head & Profit 15.00% on total (B) 76.36

TOTAL 585.44

Say Rs. 585 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/29 Unit : per Rmt
Description : Tandoor Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning , curing etc complete - tandur
stone 100 mm height

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.34 Bags 255.00 86.70
b) Tandoor (including 15%
wastage) 1.15 Sqm 291.00 334.65
c) White / coloured cement 0.35 Kg 12.00 4.20
d) Sand 0.01 Cum 1060.00 10.60

2 Labours :
a) for fixing & polishing 1.00 Sqm 94.60 94.60

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 530.75


5 Tools & Plants Charges 2.00% on total (A) 10.62
6 Water charges 0.50% on total (A) 2.65
7 Electricity Charges 0.50% on total (A) 2.65

TOTAL (B) 546.67


8 Over head & Profit 15.00% on total (B) 82.00

Costing for each Sqm TOTAL 628.67

Say Rs. 63 /- Per per Rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/8 Unit : per sqm

Description : Granite Flooring

Providing, laying and fixing in position granite stone for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete
Providing, laying and fixing in position granite stone for flooring in plain or diamond pattern or as
required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing,
polishing, cleaning etc. complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40
c) Granite (including 5%
wastage) 1.05 Sqm 1695.00 1779.75
d) White / coloured cement 0.35 Kg 12.00 4.20

2 Labours :
a) For fixing 1.00 Sqm 172.00 172.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2054.45


5 Tools & Plants Charges 2.00% on total (A) 41.09
6 Water charges 0.50% on total (A) 10.27
7 Electricity Charges 0.50% on total (A) 10.27

TOTAL (B) 2116.08


8 Over head & Profit 15.00% on total (B) 317.41

TOTAL 2433.50

Say Rs. 2,433 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/28 Unit : per Rmt.

Description : Granite Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with white cement, cleaning, curing etc complete - granite
stone / tile 100 mm height

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.34 Bags 255.00 86.70
b) Granite (including 15%
wastage) 1.15 Sqm 1695.00 1949.25
c) White cement 0.35 Kg 12.00 4.20
d) Sand 0.01 Cum 1060.00 10.60

2 Labours :
a) for fixing & polishing 1.00 Sqm 215.00 215.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2265.75


5 Tools & Plants Charges 2.00% on total (A) 45.32
6 Water charges 0.50% on total (A) 11.33
7 Electricity Charges 0.50% on total (A) 11.33

TOTAL (B) 2333.72


8 Over head & Profit 15.00% on total (B) 350.06

Costing for each Ssqm TOTAL 2683.78

Say Rs. 268 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/11 Unit : per sqm

Description : Rough Shahabad flooring

Providing, laying and fixing in required position machine cut rough shahabad stone flooring of required
size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement
float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40
c) Rough shahabad (including
5% wastage) 1.05 Sqm 75.00 78.75
d) White / coloured cement 0.35 Kg 3.00 1.05
2 Labours :
a) For fixing 1.00 Sqm 65.00 65.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 243.30


5 Tools & Plants Charges 2.00% on total (A) 4.87
6 Water charges 0.50% on total (A) 1.22
7 Electricity Charges 0.50% on total (A) 1.22

TOTAL (B) 250.60


8 Over head & Profit 15.00% on total (B) 37.59

TOTAL 288.19

Say Rs. 288 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/10 Unit : per sqm

Description : Polished Shahabad flooring

Providing, laying and fixing in required position machine cut machine polished shahabad stone
flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4
including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40
c) Polished shahabad (including
5% wastege) 1.05 Sqm 110.00 115.50
d) White / coloured cement 0.35 Kg 12.00 4.20

2 Labours :
a) For fixing 1.00 Sqm 80.00 80.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 298.20


5 Tools & Plants Charges 2.00% on total (A) 5.96
6 Water charges 0.50% on total (A) 1.49
7 Electricity Charges 0.50% on total (A) 1.49

TOTAL (B) 307.15


8 Over head & Profit 15.00% on total (B) 46.07

TOTAL 353.22

Say Rs. 353 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/13 Unit : per sqm

Description : Ceramic tiles flooring

Providing and fixing in position ceramic tile of various sizes such as 200 x 200 mm, 300 x 300 mm, 200
x 300 etc of approved make, color and shade on C:M 1:6 bedding including filling the joints with neat
cement slurry of matching colour, including cutting the tiles to required size, curing, cleaning etc
complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.03 Cum 650.00 21.13
c) Ceramic tiles(including 5%
wastage) 1.05 Sqm 380.00 399.00
d) White / coloured cement 0.25 Kg 12.00 3.00

2 Labours :
a) For fixing 1.00 Sqm 75.00 75.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00
TOTAL (A) 554.23
5 Tools & Plants Charges 2.00% on total (A) 11.08
6 Water charges 0.50% on total (A) 2.77
7 Electricity Charges 0.50% on total (A) 2.77

TOTAL (B) 570.85


8 Over head & Profit 15.00% on total (B) 85.63

TOTAL 656.48

Say Rs. 656 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/13 Unit : per sqm

Description : Ceramic tiles Dado

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete
- ceramic tiles of approved make and type and given height.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.03 Cum 650.00 16.25
c) Ceramic tiles(including 10%
wastage) 1.10 Sqm 380.00 418.00
d) White / coloured cement 0.30 Kg 12.00 3.60

2 Labours :
a) For fixing 1.00 Sqm 90.00 90.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 599.25


5 Tools & Plants Charges 2.00% on total (A) 11.99
6 Water charges 0.50% on total (A) 3.00
7 Electricity Charges 0.50% on total (A) 3.00

TOTAL (B) 617.23


8 Over head & Profit 15.00% on total (B) 92.58

TOTAL 709.81

Say Rs. 710 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/33 Unit : per Rmt

Description : Ceramic tiles Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete
- ceramic tiles of approved make and type and colour 100 mm height

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.02 Cum 1060.00 15.90
c) Ceramic tiles(including 10%
wastege) 1.07 Sqm 380.00 406.60
d) White / coloured cement 1.00 Kg 12.00 12.00

2 Labours :
a) For fixing 1.00 Sqm 80.00 80.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 585.90


5 Tools & Plants Charges 2.00% on total (A) 11.72
6 Water charges 0.50% on total (A) 2.93
7 Electricity Charges 0.50% on total (A) 2.93

TOTAL (B) 603.48


8 Over head & Profit 15.00% on total (B) 90.52

Costing per Sqm. TOTAL 694.00

Say Rs. 69 /- Per per Rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/14 Unit : per sqm

Description : Vitrified tiles flooring

Providing and fixing in position vitrified tile flooring of approved make,size and shade on bed of cement
mortar 1:6 in required line and level, filling the joints with white cement, cleaning etc complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.20 Bags 255.00 51.00
b) Sand 0.03 Cum 650.00 16.25
c) Vetrified tiles(including 5%
wastage) 1.05 Sqm 800.00 840.00
d) White / coloured cement 0.25 Kg 12.00 3.00

2 Labours :
a) For fixing 1.00 Sqm 80.00 80.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 990.25


5 Tools & Plants Charges 2.00% on total (A) 19.81
6 Water charges 0.50% on total (A) 4.95
7 Electricity Charges 0.50% on total (A) 4.95

TOTAL (B) 1019.96


8 Over head & Profit 15.00% on total (B) 152.99

TOTAL 1172.95
Say Rs. 1,173 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 30 Unit : per sqm

Description : Vitrified tiles Dado

Providing and fixing in position vitrified tile flooring of approved make,size and shade in required line
and level, filling the joints with white cement, cleaning etc complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.02 Cum 1060.00 21.20
c) Vetrified tiles(including 10%
wastage) 1.10 Sqm 800.00 880.00
d) White / coloured cement 0.30 Kg 0.00 0.00

2 Labours :
a) For fixing 1.00 Sqm 96.00 96.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1068.60


5 Tools & Plants Charges 2.00% on total (A) 21.37
6 Water charges 0.50% on total (A) 5.34
7 Electricity Charges 0.50% on total (A) 5.34

TOTAL (B) 1100.66


8 Over head & Profit 15.00% on total (B) 165.10

TOTAL 1265.76

Say Rs. 1,266 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 30 Unit : per Rmt.

Description : Vitrified tiles Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including
fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete
-polished vitrified tile 100 mm height

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.02 Cum 1060.00 15.90
c) Vetrified tiles(including 10%
wastage) 1.07 Sqm 800.00 856.00
d) White / coloured cement 0.30 Kg 12.00 3.60

2 Labours :
a) For fixing 1.00 Sqm 85.00 85.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1031.90


5 Tools & Plants Charges 2.00% on total (A) 20.64
6 Water charges 0.50% on total (A) 5.16
7 Electricity Charges 0.50% on total (A) 5.16

TOTAL (B) 1062.86


8 Over head & Profit 15.00% on total (B) 159.43

Costing per sqm TOTAL 1222.29

Say Rs. 1,222 /- Per per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/16 Unit : per sqm

Description : Designer tiles flooring

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade,
over bed of 1:6 mortar in proper line and level including finishing, compaction, filling joints cleaning etc
complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.18 Bags 255.00 45.90
b) Sand 0.04 Cum 1060.00 41.34
c) Designer tiles(including 5%
wastage) 1.05 Sqm 430.40 451.92

2 Labours :
a) For fixing 1.00 Sqm 60.00 60.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 599.16


5 Tools & Plants Charges 2.00% on total (A) 11.98
6 Water charges 0.50% on total (A) 3.00
7 Electricity Charges 0.50% on total (A) 3.00

TOTAL (B) 617.13


8 Over head & Profit 15.00% on total (B) 92.57

TOTAL 709.71

Say Rs. 710 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/17 Unit : per sqm

Description : Paving blocks flooring (regular)


Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on
bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating
etc complete. ( of strength M20 - 65 mm thick)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :

a) Sand 0.05 Cum 1060.00 53.00


b) Paver blocks (including 5%
wastege) 1.05 Sqm 242.10 254.21

2 Labours :
a) For fixing 1.00 Sqm 30.00 30.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 337.21


5 Tools & Plants Charges 2.00% on total (A) 6.74
6 Water charges 0.50% on total (A) 1.69
7 Electricity Charges 0.50% on total (A) 1.69

TOTAL (B) 347.32


8 Over head & Profit 15.00% on total (B) 52.10

TOTAL 399.42

Say Rs. 399 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/18 Unit : per sqm

Description : Paving blocks heavy duty (M40 & above)

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on
bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating
etc complete. ( of strength M40 - 65 mm thick)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Sand 0.05 Cum 1060.00 53.00
b) Paver blocks (including 5%
wastage) 1.05 Sqm 386.00 405.30

2 Labours :
a) For fixing 1.00 Sqm 30.00 30.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 488.30


5 Tools & Plants Charges 2.00% on total (A) 9.77
6 Water charges 0.50% on total (A) 2.44
7 Electricity Charges 0.50% on total (A) 2.44

TOTAL (B) 502.95


8 Over head & Profit 15.00% on total (B) 75.44

TOTAL 578.39

Say Rs. 578 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/19 Unit : per sqm

Description : Chequered tiles flooring

Providing and laying chequered tiles in required position in proper line and level, on bed of C:M 1:6
including filling the joints with neat cement slurry, cleaning, curing etc complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.21 Bags 255.00 53.55
b) Sand 0.04 Cum 1060.00 41.34
c) Chequered tiles(including 5%
wastage) 1.05 Sqm 102.00 107.10
2 Labours :
a) For fixing 1.00 Sqm 60.00 60.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 261.99


5 Tools & Plants Charges 2.00% on total (A) 5.24
6 Water charges 0.50% on total (A) 1.31
7 Electricity Charges 0.50% on total (A) 1.31

TOTAL (B) 269.85


8 Over head & Profit 15.00% on total (B) 40.48

TOTAL 310.33

Say Rs. 310 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/42 Unit : per sqm

Description : Kota for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing etc
complete -kotah stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.04 Cum 620.00 24.80
c) Kota steps (including 5%
wastege) 1.05 Sqm 250.00 262.50

2 Labours :
a) for fixing & polishing 1.00 Sqm 400.00 400.00
3 Centering & Shuttering
Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 758.70


5 Tools & Plants Charges 2.00% on total (A) 15.17
6 Water charges 0.50% on total (A) 3.79
7 Electricity Charges 0.50% on total (A) 3.79

TOTAL (B) 781.46


8 Over head & Profit 15.00% on total (B) 117.22

TOTAL 898.68

Say Rs. 899 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/40 Unit : per Rmt

Description : Marble for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing etc
complete -marble stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.04 Cum 1060.00 42.40
c) Marble steps (including 5%
wastage) 1.05 Sqm 1032.00 1083.60
d) White cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing & polishing 1.00 Sqm 167.70 167.70

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00
TOTAL (A) 1369.30
5 Tools & Plants Charges 2.00% on total (A) 27.39
6 Water charges 0.50% on total (A) 6.85
7 Electricity Charges 0.50% on total (A) 6.85

TOTAL (B) 1410.38


8 Over head & Profit 15.00% on total (B) 211.56

Costing per sqm TOTAL 1621.94

Say Rs. 162 /- Per per Rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/41 Unit : per Rmt

Description : Granite for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.04 Cum 640.00 25.60
c) Granite steps (including 5%
wastage) 1.05 Sqm 2118.75 2224.69
d) White cement 1.00 Kg 12.00 12.00

2 Labours :
a) for fixing & polishing 1.00 Sqm 223.60 223.60

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2557.29


5 Tools & Plants Charges 2.00% on total (A) 51.15
6 Water charges 0.50% on total (A) 12.79
7 Electricity Charges 0.50% on total (A) 12.79

TOTAL (B) 2634.01


TOTAL (B) 2634.01
8 Over head & Profit 15.00% on total (B) 395.10

Costing per sqm. TOTAL 3029.11

Say Rs. 303 /- Per per Rmt

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/43 Unit : per sqm

Description : Tandoor for steps

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M
1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing, curing etc
complete -tandur stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.04 Cum 1060.00 42.40
c) Tandoor steps (including 5%
wastage) 1.05 Sqm 378.30 397.22
d) White cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing & polishing 1.00 Sqm 111.80 111.80

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 611.72


5 Tools & Plants Charges 2.00% on total (A) 12.23
6 Water charges 0.50% on total (A) 3.06
7 Electricity Charges 0.50% on total (A) 3.06

TOTAL (B) 630.07


8 Over head & Profit 15.00% on total (B) 94.51

costing per sqm. TOTAL 724.58

Say Rs. 72 /- Per per sqm


Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/50 Unit : per sqm

Description : Kota for sill & Jams


Providing and fixing in position window sills and jambs of stone as per requirement, including fixing
with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing
nosing etc complete -kotah stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.20 Bags 255.00 51.00
b) Sand 0.02 Cum 1060.00 21.20
c) Kota sill (including 10%
wastege) 1.10 Sqm 290.52 319.57
d) White cement 1.00 Kg 12.00 12.00

2 Labours :
a) for fixing & polishing 1.00 Sqm 132.00 132.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 535.77


5 Tools & Plants Charges 2.00% on total (A) 10.72
6 Water charges 0.50% on total (A) 2.68
7 Electricity Charges 0.50% on total (A) 2.68

TOTAL (B) 551.85


8 Over head & Profit 15.00% on total (B) 82.78

TOTAL 634.62

Say Rs. 635 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/48 Unit : per sqm

Description : Marble for Sills & jams


Providing and fixing in position window sills and jambs of stone as per requirement, including fixing
with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing, edge polishing,
nosing,curing etc complete -marble stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.20 Bags 255.00 51.00
b) Sand 0.02 Cum 1060.00 21.20
c) Marble sill (including 10%
wastage) 1.10 Sqm 860.00 946.00
d) White cement 1.00 Kg 12.00 12.00

2 Labours :
a) for fixing & polishing 1.00 Sqm 132.00 132.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1162.20


5 Tools & Plants Charges 2.00% on total (A) 23.24
6 Water charges 0.50% on total (A) 5.81
7 Electricity Charges 0.50% on total (A) 5.81

TOTAL (B) 1197.07


8 Over head & Profit 15.00% on total (B) 179.56

TOTAL 1376.63

Say Rs. 1,377 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/49 Unit : per sqm

Description : Granite for sills & Jams


Providing and fixing in position window sills and jambs stone as per requirement, including fixing with
C:M 1:4bedding, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc
complete -granite stone of approved colour

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.28 Bags 255.00 71.40
b) Sand 0.04 Cum 1060.00 42.40
c) Granite sill (including 10%
wastage) 1.10 Sqm 1695.00 1864.50
d) White cement 1.00 Kg 12.00 12.00

2 Labours :
a) for fixing & polishing 1.00 Sqm 258.00 258.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2248.30


5 Tools & Plants Charges 2.00% on total (A) 44.97
6 Water charges 0.50% on total (A) 11.24
7 Electricity Charges 0.50% on total (A) 11.24

TOTAL (B) 2315.75


8 Over head & Profit 15.00% on total (B) 347.36

TOTAL 2663.11

Say Rs. 2,663 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/51 Unit : per sqm

Description : Tandoor for sills & jams


Providing and fixing in position window sills and jambs of stone as per requirement, including fixing
with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing,
curing etc complete -tandur stone

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.20 Bags 255.00 51.00
b) Sand 0.02 Cum 1060.00 21.20
c) Tandoor sill (including 10%
wastege) 1.10 Sqm 291.00 320.10
d) White cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing & polishing 1.00 Sqm 113.52 113.52

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 510.02


5 Tools & Plants Charges 2.00% on total (A) 10.20
6 Water charges 0.50% on total (A) 2.55
7 Electricity Charges 0.50% on total (A) 2.55

TOTAL (B) 525.32


8 Over head & Profit 15.00% on total (B) 78.80

TOTAL 604.12

Say Rs. 604 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/56 Unit : Rmt.

Description : Granite Kitchen otta


Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top
Sr.No. Particulars Quantity Unit Rate per Amount
Considering the size of 3.0m x.75m
1 Materials :
a) Cement 2.55 Bags 255.00 650.25
b) Sand 0.03 Cum 1060.00 31.80
c) Granite (including 10%
wastage) 3.71 Sqm 1695.00 6293.54

d) Kaddappa (with 10% wastage)


3.82 Sqm 220.00 840.40
e) White / colour cement 0.35 Kg 12.00 4.20
2 Labours :

a) for fixing of Kadappa & granite


2.25 Sqm 1506.00 3388.50
(considering labour rate @ 105/-
per rft length I.e = 105/- per 0.75
sft. Rate per sqm =
(105/.75)*10.76 = Rs. 1506
b) For moulding & edge polishing 4.42 Rmt. 246.00 1087.32
c) For Cutout making for sink
fixing 1.00 No. 400.00 400.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 12696.01


5 Tools & Plants Charges 2.00% on total (A) 253.92
6 Water charges 0.50% on total (A) 63.48
7 Electricity Charges 0.50% on total (A) 63.48

TOTAL (B) 13076.89


8 Over head & Profit 15.00% on total (B) 1961.53

Total costing for 3 Rmt. TOTAL 15038.42

Say Rs. 5,013 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/57 Unit : Rmt.

Description : Marble Kitchen otta


Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top- Marble stone

Sr.No. Particulars Quantity Unit Rate per Amount


Considering the size of 3.0m x.75m
1 Materials :
a) Cement 2.55 Bags 255.00 650.25
b) Sand 0.03 Cum 1060.00 31.80
c) Marble (including 10%
wastage) 3.71 Sqm 860.00 3193.18

d) Kaddappa (with 10% wastage)


3.82 Sqm 220.00 840.40
e) White / colour cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing of Kadappa & Marble
2.25 Sqm 1147.00 2580.75
(considering labour rate @ 80/-
per rft length I.e = 80/- per 0.75
sft. Rate per sqm =
(80/.75)*10.76 = Rs. 1147
b) For edge polishing 4.57 Rmt. 196.80 900.00
c) For Cutout making for sink
fixing 1.00 No. 400.00 400.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 8600.58


4 Tools & Plants Charges 2.00% on total (A) 172.01
5 Water charges 0.50% on total (A) 43.00
6 Electricity Charges 0.50% on total (A) 43.00

TOTAL (B) 8858.60


7 Over head & Profit 15.00% on total (B) 1328.79
Total costing for 3 Rmt. TOTAL 10187.39

Say Rs. 3,396 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/58 Unit : Rmt.

Description : Kadappa Kitchen otta


Providing, making and erecting in position kitchen platform with following specifications. Width of
platform 2'3" and height 30" top- Kadappa stone
Sr.No. Particulars Quantity Unit Rate per Amount
Considering the size of 3.0m x.75m
1 Materials :
a) Cement 2.55 Bags 255.00 650.25
b) Sand 0.03 Cum 1060.00 31.80
c) Top & shelf kadappa (including
10% wastage) 3.80 Sqm 258.00 980.40
d) Kaddappa Verticals & Facia
(with 10% wastage) 1.60 Sqm 220.00 352.00
e) White / colour cement 0.35 Kg 12.00 4.20

2 Labours :
a) for fixing of Kadappa 2.25 Sqm 860.00 1935.00
(considering labour rate @ 60/-
per rft length I.e = 60/- per 0.75
sft. Rate per sqm =
(60/.75)*10.76 = Rs. 717
b) For moulding & edge polishing 4.57 Rmt. 82.00 375.00
c) For Cutout making for sink
fixing 1.00 No. 250.00 250.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 4578.65


4 Tools & Plants Charges 2.00% on total (A) 91.57
5 Water charges 0.50% on total (A) 22.89
6 Electricity Charges 0.50% on total (A) 22.89

TOTAL (B) 4716.01


7 Over head & Profit 15.00% on total (B) 707.40

Total costing for 3 Rmt. TOTAL 5423.41

Say Rs. 1,808 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : F4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/FLOOR/VI/43 Unit : per sqm

Description : Designer tiles for steps

Providing and fixing in position treads and risers of designer tiles as per requirement, including fixing
with C:M 1:4 backing, filling the joints with cement slurry, cleaning, etc complete -

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 240.00 52.80
b) Sand 0.04 Cum 620.00 24.80
c) Designer Tiles (including 5%
wastage) 1.05 Sqm 780.00 819.00
d) White cement 0.35 Kg 30.00 10.50

2 Labours :
a) for fixing & polishing 1.00 Sqm 300.00 300.00

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1207.10


5 Tools & Plants Charges -3.00% on total (A) -36.21
6 Water charges -0.50% on total (A) -6.04
7 Electricity Charges -0.50% on total (A) -6.04

TOTAL (B) 1158.82


8 Over head & Profit 15.00% on total (B) 173.82

costing per sqm. TOTAL 1332.64

Say Rs. 1,333 /- Per per sqm


Rs 320/- per step
Prepared by :

Name : _________________________________ Sign: ________________


1
0.2 mason
0.5 labour
0.01
0.344
0.86
137.6
0.2
0.5
0.2 40
0.35 28
68
0.2 40
0.5 40
0.2 40
0.4 32
0.25 50
0.45 36
90
0.15 30
0.3 24
`
0.4 80
0.8 64
144
158.4
65.20
0.9 180
0.45 36
Rate analysis

Site: 0 Location : Pune


Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/2 Unit : per cum

Description : UCR In plinth

Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation steps, platforms etc.below plinth
including curing , weepholes if required, including specials such as corners, quions, headers, through stones etc.
dewatering if required, racking out joints 10 mm deep etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Rubble 1.25 cum 500.00 625.00
b) Cement 1.57 Bags 240.00 376.80
c) Sand 0.40 cum 1060.00 424.00

2 Labours :
for U.C.R. masonry works 1.00 cum 250.00 250.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1675.80


5 Tools & Plants Charges 2.00% on total (A) 33.52
6 Water charges 0.50% on total (A) 8.38
7 Electricity Charges 0.50% on total (A) 8.38

TOTAL (B) 1726.07


8 Over head & Profit 15.00% on total (B) 258.91

TOTAL 1984.99

Say Rs. 1,985 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/3 Unit : per cum

Description : Uncoursed rubble masonry in superstructure

Providing & constructing UCR masonry II sort in cement mortar 1:6 for compound wall, steps, pillars ,
platforms etc. and wherever required including scaffolding, curing , weepholes if required, including
specials such as corners, quions, headers through stones etc. dewatering if required, racking out joints 10
mm deep etc. complete.
Sr.No. Particulars Quantity Unit Rate per Amount
1 Materials :
a) Rubble 1.25 cum 500.00 625.00
b) Cement 1.57 Bags 255.00 400.35
c) Sand 0.40 cum 1060.00 424.00

2 Labours :
for U.C.R. masonry works 1.00 cum 322.50 322.50

3 Centering & Shuttering


Nil

4 Others
Scaffolding 1.00 Cum 20.00 20.00

TOTAL (A) 1791.85


5 Tools & Plants Charges 2.00% on total (A) 35.84
6 Water charges 0.50% on total (A) 8.96
7 Electricity Charges 0.50% on total (A) 8.96

TOTAL (B) 1845.61


8 Over head & Profit 15.00% on total (B) 276.84

TOTAL 2122.45
Say Rs. 2,122 /- Per per cum

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/1 Unit : per cum

Description : Brick masonary 35cm thk. Below plinth

Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in plinth for
steps, or any where as required including racking out joints 1.5 cm deep including scaffolding, curing etc.
complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Bricks 500.00 Nos. 2.25 1125.00
b) Cement 1.70 Bags 255.00 433.50
c) Sand 0.26 cum 1060.00 275.60

2 Labours :
for brick masonry works 1.00 cum 236.00 236.00

3 Centering & Shuttering


Nil

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2070.10


5 Tools & Plants Charges 2.00% on total (A) 41.40
6 Water charges 0.50% on total (A) 10.35
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 2121.85


8 Over head & Profit 15.00% on total (B) 318.28

TOTAL 2440.13
Say Rs. 2,440 /- Per per cum

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/4 Unit : per cum

Description : Brick work 35cm thk. In superstructure

Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in
superstructure at all levels wherever required including raking out joints 1.5 cm deep including scaffolding,
curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Bricks 500.00 Nos. 2.25 1125.00
b) Cement 1.70 Bags 255.00 433.50
c) Sand 0.30 cum 1060.00 318.00

2 Labours :
for brick masonry works 1.00 cum 236.00 236.00

3 Centering & Shuttering


Nil

4 Others
Add for scaffolding & sand screening
etc. 1.00 cum 45.60 45.60

TOTAL (A) 2158.10


5 Tools & Plants Charges 2.00% on total (A) 43.16
6 Water charges 0.50% on total (A) 10.79
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 2212.05


8 Over head & Profit 15.00% on total (B) 331.81

TOTAL 2543.86

Say Rs. 2,544 /- Per per cum

Rate analysis

Site: 0 Location : Pune


Computer Code No. : B2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/5 Unit : per cum

Description : Plinth Masonry 23cm thk

Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls,etc below plinth wherever required
including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Bricks 500.00 No 3.00 1500.00
b) Cement 0.90 Bags 210.00 189.00
c) Sand 0.05 cum 850.00 42.50

2 Labours :
for Brick masonry works 1.00 sqm 38.00 38.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1769.50


5 Tools & Plants Charges 2.00% on total (A) 35.39
6 Water charges 0.50% on total (A) 8.85
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 1813.74


8 Over head & Profit 15.00% on total (B) 272.06

TOTAL 2085.80

Say Rs. 2,086 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/6 Unit : per cum

Description : BBM 23cm thk in superstructure

Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls in superstructure at all levers
wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Bricks 500.00 No 3.00 1500.00
b) Cement 0.90 Bags 255.00 229.50
c) Sand 0.05 cum 1060.00 53.00

2 Labours :
for Brick masonry works 1.00 sqm 42.00 42.00

3 Others
Scaffolding / sand screening etc. 1.00 sqm. 9.80 9.80
TOTAL (A) 1834.30
5 Tools & Plants Charges 2.00% on total (A) 36.69
6 Water charges 0.50% on total (A) 9.17
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 1880.16


8 Over head & Profit 15.00% on total (B) 282.02

TOTAL 2162.18

Say Rs. 2,162 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : B3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/8 Unit : per sqm

Description : P/F 15cm thk. Brick Wall (C.M. 1:4)

Providing & constructing 6" thk, brick masonry using 'Thoklas' bricks in C.M. 1:4, at all levels wherever
required including raking out joints, scaffolding, curing etc,. All complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Thokla Bricks (15cm thk.) 48.00 No 5.50 264.00
b) Cement 0.26 Bags 255.00 66.30
c) Sand 0.04 Cum 650.00 26.00

2 Labours :
for Brick masonry works 1.00 Sqm 67.00 67.00

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 8.23 8.23

TOTAL (A) 431.53


5 Tools & Plants Charges 2.00% on total (A) 8.63
6 Water charges 0.50% on total (A) 2.16
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 442.32


8 Over head & Profit 15.00% on total (B) 66.35

TOTAL 508.67

Say Rs. 509 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : B4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/7 Unit : per sqm

Description : P/F 10cm thk. Brick Wall (C.M. 1:4)

Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick 1:2:4
p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking out
joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete mullion
with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete and
reinforcement will be paid in items of Columns and reinforcement respectively)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Bricks 58.00 No 3.30 191.40
b) Cement 0.17 Bags 255.00 43.35
c) Sand 0.03 Cum 650.00 16.25

2 Labours :
for Brick masonry works 1.00 Sqm 45.00 45.00

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 Sqm. 7.70 7.70

TOTAL (A) 303.70


5 Tools & Plants Charges 2.00% on total (A) 6.07
6 Water charges 0.50% on total (A) 1.52
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 311.29


8 Over head & Profit 15.00% on total (B) 46.69

TOTAL 357.99

Say Rs. 358 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/9 Unit : per cum

Description : Coursed rubble masonary

Providing & constructing coursed rubble masonry II sort in cement mortar 1:6 for foundation steps,
platforms etc.at all required levels including curing, scaffolding if required, weepholes if required, including
specials such as corners, quions, headers through stones etc. dewatering if required, raking out joints 10
mm deep etc. complete.
specials such as corners, quions, headers through stones etc. dewatering if required, raking out joints 10
mm deep etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Rubble 1.25 cum 500.00 625.00
b) Cement 1.75 Bags 255.00 446.25
c) Sand 0.31 cum 1060.00 332.84

2 Labours :
For coursed rubble masonary 1.00 cum 308.72 308.72

3 Centering & Shuttering


Nil

4 Others
Scaffolding & sand screening 1.00 Cum. 29.71 29.71

TOTAL (A) 1742.53


5 Tools & Plants Charges 2.00% on total (A) 34.85
6 Water charges 0.50% on total (A) 8.71
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 1786.09


8 Over head & Profit 15.00% on total (B) 267.91

TOTAL 2054.01

Say Rs. 2,054 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: Location :
Computer Code No. : B5 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/11 Unit : per sqm

Description : 150mm thk. C.C. Solid block masonry


Providing & constructing 150 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Concrete blocks 18.00 No 16.00 288.00
b) Cement 0.15 Bags 255.00 37.49
c) Sand 0.04 Cum 1060.00 42.40

2 Labours :
for C.C.block masonry works 1.00 Sqm 8.23 8.23

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 Job 8.23 8.23

TOTAL (A) 384.35


5 Tools & Plants Charges 2.00% on total (A) 7.69
6 Water charges 0.50% on total (A) 1.92
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 393.95


8 Over head & Profit 15.00% on total (B) 59.09

TOTAL 453.05

Say Rs. 453 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : B5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MAS/IV/12 Unit : per sqm

Description : 200mm thk. C.C. Solid block masonry

Providing & constructing 200 mm thick solid concrete block masonry in C.M. 1:4 including cutting if
required, curing, scafflolding, raking out joints etc. complete..

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Concrete blocks 12.00 No 34.00 408.00
b) Cement 0.11 Bags 255.00 28.05
c) Sand 0.05 Cum 1060.00 53.00

2 Labours :
for C.C.block masonry works 1.00 Sqm 36.85 36.85

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 Job 8.76 8.76
0.00 0.00 0.00

TOTAL (A) 534.66


5 Tools & Plants Charges 2.00% on total (A) 10.69
6 Water charges 0.50% on total (A) 2.67
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 548.03


8 Over head & Profit 15.00% on total (B) 82.20

TOTAL 630.23

Say Rs. 630 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: Location :
Computer Code No. : B5 Default Date :
Revised on Date : 14-08-06
Item No. : 22 / Unit : per sqm

Description : 100mm thk. Siporex block masonry

Providing 100mm thk siporex blocks of size 0.1 x 0.1 x 0.2 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a)Siporex blocks 24.00 No 60.00 1440.00
b) Cement 0.15 Bags 255.00 37.49
c) Sand 0.04 Cum 1060.00 42.40

2 Labours :
for 100mm Siporex block masonry
works 1.00 Sqm 36.85 36.85

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 Sqm 7.70 7.70

TOTAL (A) 1564.44


5 Tools & Plants Charges 2.00% on total (A) 31.29
6 Water charges 0.50% on total (A) 7.82
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 1603.55


8 Over head & Profit 15.00% on total (B) 240.53

TOTAL 1844.08

Say Rs. 1,844 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: #REF! Location : #REF!


Computer Code No. : B5 Default Date : #REF!
Revised on Date : 14-08-06
Item No. : 22 / Unit : per sqm

Description : 150mm thk. Siporex block masonry

Providing 150mm thk siporex blocks of size 0.15 x 0.15 x 0.3 with c.m. 1:6,in super structure including
striking joints, taking out joints and scaffolding, curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a)Siporex blocks 24.00 No 0.00 0.00
b) Cement 0.15 Bags 255.00 37.49
c) Sand 0.04 Cum 1060.00 42.40
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2 Labours :
for 100mm Siporex block masonry
works 1.00 Sqm 40.87 40.87

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 Sqm 8.23 8.23

TOTAL (A) 128.99


5 Tools & Plants Charges 2.00% on total (A) 2.58
6 Water charges 0.50% on total (A) 0.64
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 132.21


8 Over head & Profit 15.00% on total (B) 19.83
TOTAL 152.04

Say Rs. 152 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 22 / III 7 Unit : per sqm

Description : 200mm thk. Siporex block masonry

Providing 200mm thk Siporex blocks of size 0.2x0.2x0.4 with c.m. 1:6,in super structure including striking
joints, taking out joints and scaffolding, curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a)Siporex blocks 13.00 No 0.00 0.00
b) Cement 0.11 Bags 255.00 28.05
c) Sand 0.05 Cum 1060.00 53.00

2 Labours :
for 100mm Siporex block masonry
works 1.00 Sqm 40.87 40.87

3 Centering & Shuttering


Nil

4 Others
Scaffolding / sand screening etc. 1.00 Sqm 8.76 8.76
TOTAL (A) 130.68
5 Tools & Plants Charges 2.00% on total (A) 2.61
6 Water charges 0.50% on total (A) 0.65
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 133.95


8 Over head & Profit 15.00% on total (B) 20.09

TOTAL 154.04

Say Rs. 154 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________


2.631579
#REF!
0.304
1.7024
0.304
0.0608
1.7024
0.391552

0.04864 0.051072
Rate analysis

Site: 0 Location : Pune


Computer Code No. : C1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PCC/II/3 Unit : per cum

Description : P.C.C. (1 :2:4 )

Providing & laying PCC 1:2:4 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.00 Bags 255.00 1530.00
b) Sand 0.47 cum 1060.00 498.20
c) Metal (1.5") 0.48 cum 575.00 276.00
d) Metal ( 3/4)" 0.48 cum 500.00 240.00

2 Labours :
a)Mixing & Pouring 1.00 cum 198.75 198.75
b)Levelling & finishing 1.00 cum 11.25 11.25
c) Shuttering 1.00 cum 72.50 72.50

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 80.00 80.00
Errection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 25.00 25.00

TOTAL (A) 2931.70


5 Tools & Plants Charges 2.00% on total (A) 58.63
6 Water charges 0.50% on total (A) 0.29
7 Electricity Charges 0.50% on total (A) 0.00

TOTAL (B) 2990.63


8 Over head & Profit 15.00% on total (B) 448.59

TOTAL 3439.22

Say Rs. 3,439 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : C1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PCC/II/1 Unit : per cum

Description : P.C.C. (1 : 5 : 10 )

Providing & laying PCC 1:5:10 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 2.74 Bags 255.00 698.70
b) Sand 0.49 cum 1060.00 519.40
c) Metal (1.5") 0.48 cum 575.00 276.00
d) Metal ( 3/4)" 0.48 cum 500.00 240.00

2 Labours :
a)Mixing & Pouring 1.00 cum 198.75 198.75
b)Levelling & finishing 1.00 cum 11.25 11.25
c) Shuttering 1.00 cum 72.50 72.50

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 80.00 80.00
Errection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 2114.60


5 Tools & Plants Charges 2.00% on total (A) 42.29
6 Water charges 0.50% on total (A) 0.21
7 Electricity Charges 0.50% on total (A) 0.00

TOTAL (B) 2157.10


8 Over head & Profit 15.00% on total (B) 323.57

TOTAL 2480.67
Say Rs. 2,481 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : C2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PCC/II/2 Unit : per cum

Description : P.C.C. (1 : 4: 8 )

Providing & laying PCC 1:4:8 using metal 40 mm & 20 mm size in equal parts including, spreading,
levelling, ramming, curing,formwork etc. all complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 3.20 Bags 255.00 816.00
b) Sand 0.48 cum 1100.00 528.00
c) Metal (1") 0.48 cum 0.00 0.00
d) Metal ( 3/4)" 0.48 cum 550.00 264.00

2 Labours :
for
a)Mixing & Pouring 1.00 cum 198.75 198.75
b)Levelling & finishing 1.00 cum 11.25 11.25
c) Shuttering 1.00 cum 72.50 72.50
282.50

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 80.00 80.00
erection & dismantling
4
Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 2271.00


5 Tools & Plants Charges 2.00% on total (A) 45.42
6 Water charges 0.50% on total (A) 11.36
7 Electricity Charges 0.50% on total (A) 11.36

TOTAL (B) 2339.13


8 Over head & Profit 15.00% on total (B) 350.87

TOTAL 2690.00

Say Rs. 2,690 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PCC/II/6 Unit : per cum

Description : Plum concrete with P.C.C. (1 : 4: 8 )

Providing and laying plum concrete of 1:4:8 mix using stone of size not more than 230 mm in size and
proportion of plum to concrete @ 35:65 including curing, formwork if required, etc complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 2.21 Bags 255.00 563.55
b) Sand 0.31 cum 1060.00 330.72
c) Metal (1.5") 0.31 cum 575.00 179.40
d) Metal ( 1)" 0.31 cum 500.00 156.00
e) Rubble 0.46 cum 500.00 227.50

2 Labours :
for
a)Mixing & Pouring 1.00 cum 275.00 275.00
b)Levelling & finishing 1.00 cum 11.25 11.25
c) Shuttering 1.00 cum 72.50 72.50

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 80.00 80.00
erection & dismantling
4
Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 1913.92


5 Tools & Plants Charges 2.00% on total (A) 38.28
6 Water charges 0.50% on total (A) 9.57
7 Electricity Charges 0.50% on total (A) 9.57

TOTAL (B) 1971.34


8 Over head & Profit 15.00% on total (B) 295.70

TOTAL 2267.04

Say Rs. 2,267 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : C4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/1 Unit : per cum

Description : C.C. M20 for Footing, raft

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.40 Bags 255.00 1632.00
b) Sand 0.45 cum 850.00 382.50
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (concreting) 1.00 cum 177.55 177.55
b)Levelling & finishing 1.00 cum 24.75 24.75
c) Shuttering 1.00 cum 108.75 108.75

3 Centering & Shuttering


Providing good Specified material 1.00 cum 136.20 136.20
for erection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 2864.75


5 Tools & Plants Charges 2.00% on total (A) 57.30
6 Water charges 0.50% on total (A) 14.32
7 Electricity Charges 0.50% on total (A) 14.32

TOTAL (B) 2950.69


8 Over head & Profit 15.00% on total (B) 442.60

TOTAL 3393.30

Say Rs. 3,393 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: Location :
Computer Code No. : C6 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/2 Unit : per cum

Description : C.C. M20 for Columns below plinth

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Columns upto plinth

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 255.00 1981.35
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 351.00 351.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 531.25 531.25

3 Centering & Shuttering


Providing good Specified material/
1.00 cum 820.00 820.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 4563.60


5 Tools & Plants Charges 2.00% on total (A) 91.27
6 Water charges 0.50% on total (A) 22.82
7 Electricity Charges 0.50% on total (A) 22.82

TOTAL (B) 4700.51


8 Over head & Profit 15.00% on total (B) 705.08

TOTAL 5405.58

Say Rs. 5,406 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : C6 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/3 Unit : per cum

Description : C.C. M20 for superstructure Columns

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Columns at all levels

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.80 Bags 255.00 1734.00
b) Sand 0.45 cum 650.00 292.50
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 0.00 0.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 429.00 429.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 664.06 664.06

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 1040.00 1040.00
erection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 4477.56


5 Tools & Plants Charges 2.00% on total (A) 89.55
6 Water charges 0.50% on total (A) 22.39
7 Electricity Charges 0.50% on total (A) 22.39

TOTAL (B) 4611.89


8 Over head & Profit 15.00% on total (B) 691.78

TOTAL 5303.67

Say Rs. 5,304 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/5 Unit : per cum
Description : C.C. M20 for floor Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Floor beams

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.20 Bags 255.00 1581.00
b) Sand 0.45 cum 650.00 292.50
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 291.50 291.50
b) Levelling & finishing 1.00 cum 22.50 22.50
c) Shuttering 1.00 cum 605.38 605.38

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 992.25 992.25
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 4200.13


5 Tools & Plants Charges 2.00% on total (A) 84.00
6 Water charges 0.50% on total (A) 21.00
7 Electricity Charges 0.50% on total (A) 21.00

TOTAL (B) 4326.13


8 Over head & Profit 15.00% on total (B) 648.92

TOTAL 4975.05

Say Rs. 4,975 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : Pune


Computer Code No. : C10 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/9 Unit : per cum

Description : C.C. M20 for slab

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Floor slabs

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.20 Bags 255.00 1581.00
b) Sand 0.45 cum 640.00 288.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 0.00 0.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 265.00 265.00
b)Levelling & finishing 1.00 cum 15.00 15.00
c) Shuttering 1.00 cum 310.50 310.50

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 682.50 682.50
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 3472.00


5 Tools & Plants Charges 2.00% on total (A) 69.44
6 Water charges 0.50% on total (A) 17.36
7 Electricity Charges 0.50% on total (A) 17.36

TOTAL (B) 3576.16


8 Over head & Profit 10.00% on total (B) 357.62

TOTAL 3933.78
Say Rs. 3,934 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/19 Unit : per cum

Description : C.C. M20 for Staircase

Providing & casting M 200 for RCC staircase upto 17 cm riser 30 cm tread & 20 cm th waist slab but
excluding parapet as per detailed drawing & design at all levels with all leads & lift or as directed
including formwork, centering, scaffolding, machine mixing, & mixing , laying, levelling, vibrating and
finishing rough and broken surfaces with C.M. 1:2 including curing etc. complete (excluding steel
reinforcement)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.20 Bags 255.00 1581.00
b) Sand 0.60 cum 650.00 390.00
c) Metal ( 3/4)" 0.65 cum 500.00 325.00
d) Metal ( 1/2)" 0.20 cum 340.00 68.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 190.00 190.00
b)Levelling & finishing 1.00 cum 17.50 17.50
c) Shuttering 1.00 cum 621.00 621.00
0.00 0.00 0.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 800.00 800.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 4022.50


5 Tools & Plants Charges 2.00% on total (A) 80.45
6 Water charges 0.50% on total (A) 20.11
7 Electricity Charges 0.50% on total (A) 0.00
TOTAL (B) 4123.06
8 Over head & Profit 15.00% on total (B) 618.46

TOTAL 4741.52

Say Rs. 4,742 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/17 Unit : per cum

Description : RCC M20 for Pardi, fins

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For pardis,parapets and fins

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.80 Bags 255.00 1734.00
b) Sand 0.60 cum 1060.00 636.00
c) Metal ( 3/4)" 0.65 cum 500.00 325.00
d) Metal ( 1/2)" 0.20 cum 340.00 68.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 225.00 225.00
b)Levelling & finishing 1.00 cum 7.50 7.50
c) Shuttering 1.00 cum 575.00 575.00
0.00 0.00 0.00
0.00 0 0.00 0.00
3 Centering & Shuttering 0.00 0.00 0.00
Providing good Specified material/ 1.00 cum 1520.00 1520.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lifts 1.00 cum 12.00 12.00

TOTAL (A) 5120.50


TOTAL (A) 5120.50
5 Tools & Plants Charges 2.00% on total (A) 102.41
6 Water charges 0.50% on total (A) 25.60
7 Electricity Charges 0.50% on total (A) 25.6025

TOTAL (B) 5274.12


8 Over head & Profit 15.00% on total (B) 791.12

TOTAL 6065.23

Say Rs. 6,065 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/4 Unit : per cum

Description : C.C. M20 for Plinth Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Plinth beams

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 250.00 1942.50
b) Sand 0.45 cum 640.00 288.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 0.00 0.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 319.00 319.00
b)Levelling & finishing 1.00 cum 15.75 15.75
c) Shuttering 1.00 cum 453.13 453.13
3 Centering & Shuttering
Providing good Specified material/ 1.00 cum 750.00 750.00
erection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00

TOTAL (A) 4086.38


5 Tools & Plants Charges 2.00% on total (A) 81.73
6 Water charges 0.50% on total (A) 20.43
7 Electricity Charges 0.50% on total (A) 20.43

TOTAL (B) 4208.97


8 Over head & Profit 15.00% on total (B) 631.34

TOTAL 4840.31

Say Rs. 4,840 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : Dec 31, 99
Item No. : FDAPL/RCC/III/7&16 Unit : per cum

Description : C.C. M20 for lintels & chajjas

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For lintels & chajja

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.00 Bags 255.00 1530.00
b) Sand 0.45 cum 650.00 292.50
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 397.50 397.50
b)Levelling & finishing 1.00 cum 15.75 15.75
c) Shuttering 1.00 cum 725.00 725.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 996.00 996.00
erection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 4371.75


5 Tools & Plants Charges 2.00% on total (A) 87.44
6 Water charges 0.50% on total (A) 21.86
7 Electricity Charges 0.50% on total (A) 21.86

TOTAL (B) 4502.90


8 Over head & Profit 15.00% on total (B) 675.44

TOTAL 5178.34

Say Rs. 5,178 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/6 Unit : per cum

Description : C.C. M20 for grid Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Grid beams
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Grid beams

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 255.00 1981.35
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 397.50 397.50
b)Levelling & finishing 1.00 cum 15.75 15.75
c) Shuttering 1.00 cum 725.00 725.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 1344.00 1344.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 5355.60


5 Tools & Plants Charges 2.00% on total (A) 107.11
6 Water charges 0.50% on total (A) 26.78
7 Electricity Charges 0.50% on total (A) 26.78

TOTAL (B) 5516.27


8 Over head & Profit 15.00% on total (B) 827.44

TOTAL 6343.71

Say Rs. 6,344 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/8 Unit : per cum

Description : C.C. M20 for RCC walls

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For lift & Basement walls

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 255.00 1981.35
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 291.50 291.50
b)Levelling & finishing 1.00 cum 15.00 15.00
c) Shuttering 1.00 cum 580.00 580.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 776.00 776.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 4535.85


5 Tools & Plants Charges 2.00% on total (A) 90.72
6 Water charges 0.50% on total (A) 22.68
7 Electricity Charges 0.50% on total (A) 22.68

TOTAL (B) 4671.93


8 Over head & Profit 15.00% on total (B) 700.79

TOTAL 5372.71

Say Rs. 5,373 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/15 Unit : per cum

Description : M20 for folded Steps upto 150mm thk.

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For folded staircase slabs

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 255.00 1981.35
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 397.50 397.50
b)Levelling & finishing 1.00 cum 37.50 37.50
c) Shuttering 1.00 cum 931.50 931.50

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 1224.00 1224.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 5463.85


5 Tools & Plants Charges 2.00% on total (A) 109.28
6 Water charges 0.50% on total (A) 27.32
7 Electricity Charges 0.50% on total (A) 27.32

TOTAL (B) 5627.77


8 Over head & Profit 15.00% on total (B) 844.16

TOTAL 6471.93
Say Rs. 6,472 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/28 Unit : Rmt.

Description : P/F PVC sleeves 40mm dia. in concrete

Providing & fixing in corrent position.line, level 40 mm dia Finolex or equivalent PVC pipe in RCC
members such as columns, beams, slabs, paradi, chajjas etc. including fixing / typing with binding wire
& M.S. rod to secure in position during concrete including all lifts etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) PVC pipe 1.00 Rmt. 51.75 51.75
b) Binding wire 0.20 Kg. 40.00 8.00

2 Labours :
a) Cutting & fixing sleeves 1.00 Rmt. 77.40 77.40
0.00 0.00 0.00

TOTAL (A) 137.15


5 Tools & Plants Charges 2.00% on total (A) 2.74
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 139.89


8 Over head & Profit 15.00% on total (B) 20.98

TOTAL 160.88

Say Rs. 161 /- Per Rmt.


Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/12 Unit : per cum

Description : M20 for sloping slabs

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For sloping slabs

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 255.00 1981.35
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 331.25 331.25
b)Levelling & finishing 1.00 cum 19.50 19.50
c) Shuttering 1.00 cum 412.97 412.97

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 682.50 682.50
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 4319.57


5 Tools & Plants Charges 2.00% on total (A) 86.39
6 Water charges 0.50% on total (A) 21.60
7 Electricity Charges 0.50% on total (A) 21.60

TOTAL (B) 4449.15


8 Over head & Profit 15.00% on total (B) 667.37
TOTAL 5116.52

Say Rs. 5,117 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/11 Unit : per cum

Description : M20 for cantilever slabs upto 2.0m span

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For cantilever slabs

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 6.00 Bags 255.00 1530.00
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 265.00 265.00
b)Levelling & finishing 1.00 cum 10.50 10.50
c) Shuttering 1.00 cum 363.29 363.29

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 892.50 892.50
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 3953.29


5 Tools & Plants Charges 2.00% on total (A) 79.07
6 Water charges 0.50% on total (A) 19.77
7 Electricity Charges 0.50% on total (A) 19.77

TOTAL (B) 4071.88


8 Over head & Profit 15.00% on total (B) 610.78

TOTAL 4682.67

Say Rs. 4,683 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/19 Unit : per cum

Description : M20 for Copings & sills

Providing and laying in situ C.C. M-20 of trap metal for R.C.C.work of Copings & sills as per detailed
drawings and design or as directed including centering formwork, compacting using vibrator, curing
and roughening the surface if special finish is to be provided etc. complete. (excluding reinforcement
& fitter work).

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.77 Bags 255.00 1981.35
b) Sand 0.45 cum 1060.00 477.00
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 340.00 85.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 352.45 352.45
b)Levelling & finishing 1.00 cum 66.00 66.00
c) Shuttering 1.00 cum 621.00 621.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 1220.00 1220.00
Fixing & removing
4 Others
Mixer & Vibrator 1.00 cum 18.00 18.00
Lift 1.00 cum 12.00 12.00

TOTAL (A) 5132.80


5 Tools & Plants Charges 2.00% on total (A) 102.66
6 Water charges 0.50% on total (A) 25.66
7 Electricity Charges 0.50% on total (A) 25.66

TOTAL (B) 5286.78


8 Over head & Profit 15.00% on total (B) 793.02

TOTAL 6079.80

Say Rs. 6,080 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

E/O for providing M25 grade concrete instead of M20 grade


Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference = x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =

E/O for providing M30 grade concrete instead of M20 grade


Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference = x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =

E/O for providing M35 grade concrete instead of M20 grade


Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference = x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =

E/O for providing M40 grade concrete instead of M20 grade


Cement consumption for M20 grade = 7.77 bags
Cement consumption for M25 grade = 7.77 bags
Difference in cement consumption =
Basic rate difference = x 150 =
Total rate difference including OH/profit etc. =
Say Rs. =

Rate analysis

Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/29 Unit : Rmt.

Description : Welding of bars to existing reinforcement

Welding the reinforcement bars to existing steel or as per the requirement including finishing the welding
work neatly, all labour and material etc complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Welding rods 5.00 No. 2.34 11.70
For one Rmt. Of welding
(Assuming that average 6 nos of 16mm
dia. Bars are welded for one end of
beam)
Welding rods used are of 4mm &
ESAB / Advani make

2 Labours :
a)Welder 0.03 No. 150.00 4.50
b)Helper 0.03 No. 100.00 3.00
One welder can do about 30rmt. Of
welding

3 Scaffolding
If required for welding at heights
15.49 Sft. 0.75 11.62
Assuming the area of scaffolding to be
1.2m x1.2m

4 Others
Hire charges of welding machine 0.25 Hr. 31.25 7.81
Assuming the hire charges rate of
250 /-for 8 hrs.

TOTAL (A) 38.63


5 Tools & Plants Charges 2.00% on total (A) 0.77
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 10.00% on total (A) 3.86

TOTAL (B) 43.27


8 Over head & Profit 15.00% on total (B) 6.49

TOTAL 49.76

Say Rs. 50 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C11 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/30 Unit : per sqm

Description : Providing shalitex board expansion joint

Providing & fixing shalitex board expansion joint of 25mm thickness for beams, columns & slab

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Shalitex board 1.00 Sqm. 800.00 800.00
Add for wastage @ 5% 0.05 Sqm. 800.00 40.00

2 Labours :
a)carpenter 0.37 No. 150.00 55.50
b)Helper 0.37 No. 100.00 37.00
One pair of carp/helper can do about 2
columns as given below.
Assuming the size of column to be
450x230 & joint on 450mm face, Ht. Of
col.of about 3m. Area = 3 x 0.45 =
1.35 sqm.
4 Others

TOTAL (A) 932.50


5 Tools & Plants Charges 2.00% on total (A) 18.65
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 4.66

TOTAL (B) 955.81


8 Over head & Profit 15.00% on total (B) 143.37

TOTAL 1099.18

Say Rs. 1,099 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C10 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/9 Unit : per cum

Description : C.C. M20 for precast slab of 50 mm thick slab

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.10 Bags 215.00 21.50
b) Sand 0.03 cum 850.00 25.50
c) Metal ( 3/4)" 0.04 cum 425.00 17.85
d) Metal ( 1/2)" 0.02 cum 450.00 7.88

2 Labours :
a) Mixing & Pouring (Concreting) 0.07 cum 212.00 14.84
b)Levelling & finishing 0.07 cum 66.00 4.62
c) Shuttering 0.07 cum 621.00 43.47

3 Centering & Shuttering


Providing good Specified material/ 0.07 cum 1220.00 85.40
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75

TOTAL (A) 263.56


5 Tools & Plants Charges -3.00% on total (A) -7.91
6 Water charges -0.50% on total (A) -1.32
7 Electricity Charges -0.50% on total (A) -1.32

TOTAL (B) 253.01


8 Over head & Profit 0.00% on total (B) 0.00

TOTAL 253.01

Say Rs. 253 /- Per per cum

Prepared by : OR Rs 15/ sqm

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/8 Unit : per cum

Description : C.C. M50 for RCC walls

Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For lift & Basement walls
mild steel/tor steel reinforcement) .---For lift & Basement walls

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 9.65 Bags 210.00 2026.50
b) Sand 0.85 cum 1060.00 901.00
c) Metal ( 3/4)" 0.70 cum 550.00 385.00
d) Metal ( 1/2)" 0.50 cum 550.00 275.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 185.00 185.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 486.00 486.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 776.00 776.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75

TOTAL (A) 5077.00


5 Tools & Plants Charges -3.00% on total (A) -152.31
6 Water charges -0.50% on total (A) -25.39
7 Electricity Charges -0.50% on total (A) -25.39

TOTAL (B) 4873.92


8 Over head & Profit 15.00% on total (B) 731.09

TOTAL 5605.01

Say Rs. 5,605 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : C8 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/8 Unit : per cum

Description : C.C. M30 for Concrete Road

Providing & laying M 30 (as per design mix) for Road work using machine crushed metal of approved
quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering
formwork, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with
1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 7.50 Bags 210.00 1575.00
b) Sand 0.85 cum 1060.00 901.00
c) Metal ( 3/4)" 0.70 cum 550.00 385.00
d) Metal ( 1/2)" 0.50 cum 550.00 275.00

2 Labours :
a) Mixing & Pouring (Concreting) 1.00 cum 185.00 185.00
b)Levelling & finishing 1.00 cum 0.00 0.00
c) Shuttering 1.00 cum 150.00 150.00

3 Centering & Shuttering


Providing good Specified material/ 1.00 cum 365.00 365.00
Fixing & removing

4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75
Lift 1.00 cum 17.75 17.75

TOTAL (A) 3878.50


5 Tools & Plants Charges -3.00% on total (A) -116.36
6 Water charges -0.50% on total (A) -19.39
7 Electricity Charges -0.50% on total (A) -19.39

TOTAL (B) 3723.36


8 Over head & Profit 15.00% on total (B) 558.50

TOTAL 4281.86

Say Rs. 4,282 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : 0
Computer Code No. : C4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/2 Unit : per cum

Description : C.C. M30 for Footing, raft

Providing & laying M 300 (as per design mix) for RCC work (without plaster) using machine crushed
metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift
including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc,
finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding
mild steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 8.50 Bags 210.00 1785.00
b) Sand 0.45 cum 850.00 382.50
c) Metal ( 3/4)" 0.60 cum 500.00 300.00
d) Metal ( 1/2)" 0.25 cum 550.00 137.50

2 Labours :
a) Mixing & Pouring (concreting) 1.00 cum 107.20 107.20
b)Levelling & finishing 1.00 cum 16.50 16.50
c) Shuttering 1.00 cum 86.25 86.25

3 Centering & Shuttering


Providing good Specified material 1.00 cum 136.20 136.20
for erection & dismantling

4 Others
Mixer & Vibrator 1.00 cum 24.75 24.75

TOTAL (A) 2975.90


5 Tools & Plants Charges 2.00% on total (A) 59.52
6 Water charges 0.50% on total (A) 14.88
7 Electricity Charges 0.50% on total (A) 14.88

TOTAL (B) 3065.18


8 Over head & Profit 15.00% on total (B) 459.78

TOTAL 3524.95
Say Rs. 3,525 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________


0.175732

35.281 3447

1
69.98101

3.17529
76.35838

2.21
0.312
0.624
0.312
0.455
0.276364
7.738182
7.970327
250
31.25
0.576
24.8
36
3.217503 2.284427
57.91506 41.11969
463.3205 328.9575
14362.93
0.309375

24.75 17.775
Assign 0.3 hrs
1165.5
254.25
270
100

160
15
310.5

1023.75

24.75
17.75

3341.50
167.08
30.0025
30.0025

3568.58
535.287

4103.87
1.043239
638
892
30
1560
118
1678 1929.7
2,753
18.75
12.5
WELCOME TO RATE ANALYSIS
Enter the data in yellow cells.

a) Site Name : Location : Pune


b) Default date : Revision on date :
c)

For MKS system click MKS For FPS system click FPS

d) Tools & Plants & fixed Charges : 5.00%


e) Water Charges : 1.00%
f) Electricity Charges : 1.00%
g) PROFIT ( Over heads+ Profit) : 10.00% + 5.00% = 15.00%
(Over head) + ( Profit ) = (TOTAL)

Instructions Uneditable text


Enter Data Clickable links
Rate analysis

Site: 0 Location : Pune


Computer Code No. : Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/1 Unit : per cum

Description : Excavation in soil and soft murum upto 1.5m depth

Excavation upto 1.5 M depth in ordinary soil or soft murum, old foundations etc. in pits, over areas and in
trenches by machinery or otherwise including removing the excavated materials upto a distance of 100
M beyond building premises, stacking as directed dewatering manually or mechanically if required,
shoring, strutting, preparing the bed for foundation and necessary back filling in layers including dry and
wet compaction etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :

2 Labours :
a) Unskilled coolie for excn. 0.56 No 200.00 112.00
b) Labour for backfilling 0.08 No 200.00 16.00
Assuming that one pair
to do excavation of 125 cft.

3 Centering & Shuttering


NIL

4 Others
Shoring 1.00 L/S 10.00 10.00
Dewatering 1.00 L/s 2.00 2.00

TOTAL (A) 140.00


5 Tools & Plants Charges 2.00% on total (A) 2.80
6 Water charges 0.50% on total (A) 0.70
7 Electricity Charges 0.50% on total (A) 0.70

TOTAL (B) 144.20


8 Over head & Profit 15.00% on total (B) 21.63

TOTAL 165.83
Say Rs. 166 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : E3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/3 Unit : per cum

Description : Excavation in Hard Murum & boulders

Excavation upto 1.5 M depth in hard murum & boulders etc. in pits, over areas and in trenches by
machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond
building premises, stacking as directed dewatering manually or mechanically if required, shoring,
strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet
compaction etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :

NIL
2 Labours :
a) Unskilled coolie (Male) 0.70 No 200.00 140.00
( It is assumed that 1 m/c + 1 f/c
can excavate nearly 100cft of mu-
rum in a day with specified lead
and lift)
c) Add for backfilling & compaction 0.08 No 200.00 16.00

3 Centering & Shuttering

NIL

4 Others
Shoring 1.00 L/S 20.00 20.00
Dewatering 1.00 L/s 4.00 4.00
TOTAL (A) 180.00
5 Tools & Plants Charges 2.00% on total (A) 3.60
6 Water charges 0.50% on total (A) 0.90
7 Electricity Charges 0.50% on total (A) 0.90

TOTAL (B) 185.40


8 Over head & Profit 15.00% on total (B) 27.81

TOTAL 213.21

Say Rs. 213 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : Pune
Computer Code No. : E4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/5 Unit : per cum

Description : Excavation in Soft Rock

Excavation upto 1.5 M depth in soft rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
Nil
2 Labours :
a) 1 Breaker Needle with breaker
operator 0.18 Per day 1040.00 187.20
( It is assumed that with a break-
er needle in a day we can excav-
ate nearly 200cft and the same
with lead & lift as specified.)
i.e. For 1 cum. It requires
0.18 days of breaker
b) Unskilled coolie 2 nos. (Male) 0.47 No 200.00 94.00
For 150 cft ( 4.25cum) 2 persons
are required, therefore for one
cum 0.71 person is required
Labour for backfilling 0.08 No 200.00 16.00
3 Centering & Shuttering
NIL

4 Others
Dewatering 1.00 L/s 4.00 4.00

TOTAL (A) 301.20


5 Tools & Plants Charges 2.00% on total (A) 6.02
6 Water charges 0.50% on total (A) 1.51
7 Electricity Charges 0.50% on total (A) 1.51

TOTAL (B) 310.24


8 Over head & Profit 15.00% on total (B) 46.54

TOTAL 356.77

Say Rs. 357 /- Per per cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : Pune
Computer Code No. : E5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/8 Unit : per cum

Description : Excavation in Hard Rock by chiselling


Excavation upto 1.5 M depth in hard rock in pits and trenches by machinery or otherwise including
removing the excavated materials upto a distance of 100 M beyond building premises,stacking as
directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for
foundation and necessary back filling in layers including dry and wet compaction etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials : NIL

2 Labours :
a)1 Breaker Needle with operator 0.54 Per day 1000.00 540.00
( It is assumed that with a break-
er needle in a day we can excav-
-ate nearly 65cft (1.84cum.)
with lead & lift as specified.)
i.e. For 1 cum. It requires
0.54 days of breaker

c) Unskilled coolie (Male) 1.06 No 200.00 212.00


For 100 cft ( 2.83cum) 3 persons
are required, therefore for one
cum1.06 person for 1cum.
d) Backfilling 0.08 No 200.00 16.00

3 Centering & Shuttering


NIL

4 Others
Dewatering 1.00 L/s 4.00 4.00

TOTAL (A) 772.00


5 Tools & Plants Charges 2.00% on total (A) 15.44
6 Water charges 0.50% on total (A) 3.86
7 Electricity Charges 0.50% on total (A) 3.86
TOTAL (B) 795.16

8 Over head & Profit 15.00% on total (B) 119.27

TOTAL 914.43
Say Rs. 914 /- Per per cum

Prepared by :
Name : ________________________________ Sign : _______________

Rate analysis

Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/15 Unit : per Sqm

Description : Soling 230thk. Below floor

Providing and laying 230 mm thick dry trap rubble soling in plinth including filling the interstices with
murum and stone chips, watering,compacting, ramming etc complete with all labour and material.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a)Rubble 0.30 Cum 900.00 269.10
b)Murrum 0.02 Cum 120.00 2.40

2 Labours :
a) Unskilled coolie (Male) 0.05 No 200.00 10.80
b) Unskilled coolie (Female) 0.05 No 150.00 8.10
Assuming that one pair
to do 200 sft. (18.59 sqm.)Of soling
area

3 Centering & Shuttering


NIL

4 Others
NIL 0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 290.40


5 Tools & Plants Charges 2.00% on total (A) 5.81
6 Water charges 0.50% on total (A) 1.45
7 Electricity Charges 0.50% on total (A) 1.45

TOTAL (B) 299.11


8 Over head & Profit 15.00% on total (B) 44.87

TOTAL 343.98

Say Rs. 344 /- Per per Sqm


850/cum
Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/12 Unit : per Cum

Description : Filling with selected murrum obtained from excavation

Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)
Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling,
watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for
payment)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
NIL 0.00 0.00 0.00
NIL

2 Labours :
a) Unskilled coolie (Male) 0.35 No 200.00 70.00
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours 0.09 No 200.00 18.00
Net labour required = (2 / 2.83)/8

3 Centering & Shuttering


NIL

4 Others (m/c – compactor)


Hire charges at 10/- per hour 1.00 1 20.00 20.00

TOTAL (A) 108.00


5 Tools & Plants Charges 2.00% on total (A) 2.16
6 Water charges 0.50% on total (A) 0.54
7 Electricity Charges 0.50% on total (A) 0.54

TOTAL (B) 111.24


8 Over head & Profit 15.00% on total (B) 16.69

TOTAL 127.93

Say Rs. 128 /- Per per Cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/13 Unit : per Cum

Description : Filling with outside murrum

Providing & filling in plinth murrum brought from outside including spreading, levelling, watering, and
ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Murrum 1.30 Cum 120.00 156.00

Assuming the difference of loose


volume & compacted volume = 30%

2 Labours :
a) Unskilled coolie (Male) 0.35 No 200.00 70.00
Assuming that one male coolie
to do100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours 0.09 No 200.00 18.00
Net labour required = (2 / 2.83)/8

3 Centering & Shuttering


NIL

4 Others (m/c – compactor)


Hire charges at 10/- per hour 1.00 1 20.00 20.00

TOTAL (A) 264.00


5 Tools & Plants Charges 2.00% on total (A) 5.28
6 Water charges 0.50% on total (A) 1.32
7 Electricity Charges 0.50% on total (A) 1.32

TOTAL (B) 271.92


8 Over head & Profit 15.00% on total (B) 40.79

TOTAL 312.71

Say Rs. 313 /- Per per Cum

Prepared by :
Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 1 Unit : per Cum

Item No. : FDAPL/EX/I/14 Filling with sand

Providing & filling in plinth with approved sand including spreading, levelling, watering, and ramming (in
layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Sand 1.20 Cum 1764.00 2116.80

Assuming the difference of loose


volume & compacted volume = 20%

2 Labours :
a) Unskilled coolie (Male) 0.35 No 200.00 70.00
Assuming that one male coolie
to do 100 cft. (2.83cum.)
b) Unskilled coolie (for watering &
compactor) for 2 hours 0.09 No 200.00 18.00
Net labour required = (2 / 2.83)/8

3 Centering & Shuttering


NIL

4 Others (m/c – compactor)


Hire charges at 10/- per hour 1.00 1 20.00 20.00

TOTAL (A) 2224.80


5 Tools & Plants Charges 2.00% on total (A) 44.50
6 Water charges 0.50% on total (A) 11.12
7 Electricity Charges 0.50% on total (A) 11.12

TOTAL (B) 2291.54


8 Over head & Profit 15.00% on total (B) 343.73
TOTAL 2635.28

Say Rs. 2,635 /- Per per Cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/16 Unit : per Sqm

Description : Antitermite treatment

Providing & applying preconstructional anti termite treatment to bottom and sides of excavated surfaces
by approved agency (MODE of Measurement will be on plinth area basis.)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
Chemical 0.50 Ltr. 66.15 33.08

Assuming the treatment with 10 ltr. Per


sqm. Of area & 0.5 ltr. Of chemical Per
10 ltr of water (i.e 5% concentration)

2 Labours :

a) Unskilled coolie (for spreading) for 1


hours for one footing of 4 sqm. Area
0.03 No 100.00 3.10
Net labour required = (1 / 4)/8

3 Centering & Shuttering


NIL

4 Others (m/c – compactor)


0.00 0.00 0.00

TOTAL (A) 36.18


5 Tools & Plants Charges 2.00% on total (A) 0.72
6 Water charges 0.50% on total (A) 0.18
7 Electricity Charges 0.50% on total (A) 0.18

TOTAL (B) 37.26


8 Over head & Profit 15.00% on total (B) 5.59

TOTAL 42.85

Say Rs. 43 /- Per per Sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : E1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/17 Unit : Cum

Description : Carting away surplus excavated earth

Carting away the unwanted excavated,/ demolished material outside the premises and unloading and
spreading it as and where required as per the rules of local authority including loading, unloading,
carting, spreading etc complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
NIL 0.00

2 Labours :
a) Unskilled coolie 2 nos. do filling of
tractor (100cft) in 15 minutes 0.18 No 200.00 36.00
Net labour required = (0.5 / 2.83)

3 Centering & Shuttering

NIL

4 Others (m/c – tractor)

Tractor hire charges at 40/- per trip 1.00 1 60.00 60.00


TOTAL (A) 96.00
5 Tools & Plants Charges 2.00% on total (A) 1.92
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 97.92


8 Over head & Profit 15.00% on total (B) 14.69

TOTAL 112.61

Say Rs. 113 per Cum

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : 0
Computer Code No. : E5 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/EX/I/11 Unit : per cum

Description : Excavation in Hard Rock by blasting


Excavation in Hard Rock for foundation by blasting including removing the excavated material upto
a distance of 10m with normal lift upto 1.5m and stacking & spreading in such a way as to not
disturd any site activity or as directed. Dewatering Preparing the bed for foundation & necessary
back filling, watering including shoring & Shuttering etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :

Per hole approx. 250 gm. Of blasting


powder & one detonator is required

a) Blasting powder 0.7 Kg. 125 87.50


b) Detonator 2 No 12 24.00
c) Safety fuse 2 rmt 6.5 13
d) Detonating fuse 8 rmt 9 72

2 Labours :

a) Unskilled coolie (Male) 1.06 No 200.00 212.00


For 100 cft ( 2.83cum) 3 persons
are required, therefore for one
cum1.06 person for 1cum.

3 Centering & Shuttering


NIL

4 Others
Compressor for drilling holes 0.50 120 350.00 175.00

TOTAL (A) 583.50

5 Tools & Plants Charges 2.00% on total (A) 11.67


6 Water charges 0.50% on total (A) 2.92
7 Electricity Charges 0.50% on total (A) 2.92
TOTAL (B) 601.01

8 Over head & Profit 15.00% on total (B) 90.15

TOTAL 691.16
Say Rs. 691 /- Per per cum

Prepared by :
Name : ________________________________ Sign : _______________
Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MISC/XI/2 Unit : per Sqm.

Description : Structural steel works

Providing, fabricating & erecting & fixing, cutting, bending, grinding, welding the structural steel
work consisting of m.s. plates I beams channels, angles, chequered plates, including fabricating as
per shop drawing including erection to required line and level and providing and fixing buts, bolts
and required appropriate washers etc. complete including painting

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 4 = 60 sqm.
1 Materials :
a) Structural steel 1.05 Mt. 30500.00 32025.00
(adding 5% for wastage)
b) Welding rods 155.00 No. 3.50 542.50
c) Oxygen Gas 1.50 Cyli. 250.00 375.00
d) DA 0.50 Cyli. 800.00 400.00
c) Bolts, nuts & washers 1.00 Kg. 47.25 47.25
d) Primer Painting 2.00 lts. 40.00 80.00
d) Enamel Painting 5.00 lts. 110.00 550.00

2 Labours :
For fabrication & errection 1.00 Mt. 2250.00 2250.00
For painting 1.00 Mt. 450.00 450.00

3 Centering & Shuttering


Nil

4 Others
Welding M/C 1.00 Day 250.00 250.00

TOTAL (A) 36969.75


TOTAL (A) 36969.75
5 Tools & Plants Charges 2.00% on total (A) 739.40
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 184.85

TOTAL (B) 37893.99


8 Over head & Profit 15.00% on total (B) 5684.10

TOTAL 43578.09

Say Rs. 43,578 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MISC/XI/3 Unit : per No.

Description : 12mm dia. Fan hook

Providing & fixing and securing in position box type fan hooks of 12 mm diameter MS rods 30 cm
long as directed

Sr.No. Particulars Quantity Unit Rate per Amount


Assuming area of 15 x 4 = 60 sqm.
1 Materials :
a) MS rods 12mm 0.28 Kg. 27.50 7.71
(adding 5% for wastage)
b) Sand 1.00 L/s 2.00 2.00
c) Binding wire 0.05 Kg. 32.00 1.60

2 Labours :
For preparing the hook & fixing in
place
Fitter (0.5 hrs.) 0.06 No. 150.00 9.38
Helper (0.5hrs.) 0.06 No. 100.00 6.25

3 Others
TOTAL (A) 26.93
4 Tools & Plants Charges 2.00% on total (A) 0.54
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 0.13

TOTAL (B) 27.61


7 Over head & Profit 15.00% on total (B) 4.14

TOTAL 31.75

Say Rs. 32 /- Per per No.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : B1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/MISC/XI/5 Unit : per Sqm.

Description : Chainlink fencing

Providing and erecting in position chain link fencing of GI 18 gauge, 50 mm opening size as
required including fixing the angle supports in bed blocks of C:M 1:3:6 at 2.4 m c/c, ms 6 mm dia at
top, U nails for fixing, etc complete with all labour and material. - 1.2 m high fencing ( Structural
steel for angles,flats will be paid separately)

Sr.No. Particulars Quantity Unit Rate per Amount


Consider lengthof 24 x 1.2 = 28.8 sqm.
1 Materials :
a) Chain link 18 guage 30.24 Sqm. 156.00 4717.44
(adding 5% for wastage)
b) U nails 2.00 Kg. 40.00 80.00
c) 6mm dia. Wire 12.40 Kg. 32.00 396.80
d) Concrete 1:3:6 0.40 Cum. 1979.00 783.68

2 Labours :
For excavation 11 Nos. 5 55.00
For poles errecting (0.5 mason & 0.50 No. 150.00 75.00
0.5 helpers) 0.50 No. 100.00 50.00
For fixing chain link 0.50 No. 150.00 75.00
(.5 mason & 1 helpers) 1.00 No. 100.00 100.00

3 Others

TOTAL (A) 6332.92


4 Tools & Plants Charges 2.00% on total (A) 126.66
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 31.66

TOTAL (B) 6491.25


7 Over head & Profit 15.00% on total (B) 973.69

Costing for 28.8 sqm. TOTAL 7464.93

Say Rs. 259 /- Per per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________


300 mm
46.15385 per mt.
0.3 mm
153.8462 total rods
538.4615
28.8

12.4
33
Rate analysis

Site: 0 Location : Pune


Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/1 Unit : Rmt.

Description : Providing & fixing TW frame (4"x 2.5")


Providing and fixing in position door frames in correct line, level and plumb of Teak Wood of size 4"
x2.5" including applying coal tar to the surface coming in contact with masorny including 6 no of MS
hold fasts fixed in concrete bedblocks in masonry ( 6"x 6" size), MS rod at bottom to keep the frame in
position etc complete with all labour and material. - door size 900mm x 2100 mm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.18 Bags 255.00 45.90
b) Sand ( as approved) 0.01 Cum 1060.00 13.78
c) MS Holdfast 6.00 Nos. 10.00 60.00
d) Teak wood (4*2.5/144*17.83)*1.1 =
1.362 1.36 Cft 1200.00 1632.00
e) MS Tie rod 8mm 0.34 Kg. 27.50 9.28
f) Coal tar 0.50 Kg. 25.00 12.50

2 Labours :
Carpenter for frame making 0.68 Nos. 200.00 136.00
Helper for frame making 0.27 Nos. 100.00 27.20
(0.5 carp + 0.2 help are required per
cft of frame making) 0.00
Mason for fixing of frame 0.50 Nos. 150.00 75.00
Unskilled labour 0.20 Nos. 80.00 16.00

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2027.66


4 Tools & Plants Charges 2.00% on total (A) 40.55
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 10.14

TOTAL (B) 2078.35


7 Over head & Profit 15.00% on total (B) 311.75

Total costing for (0.9+2.1*2 = 5.1Rmt.) TOTAL 2390.10


Say Rs. 469 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/1 Unit : Rmt.

Description : P/F Granite frame (170x20)


As per item no 01 but with granite door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.18 Bags 255.00 45.90
b) Sand ( as approved) 0.01 Cum 1060.00 13.78
c) MS Holdfast 6.00 Nos. 10.00 60.00
d) Granite with 10% wastage 1.77 Sqm. 1695.00 2995.07
((0.9+.09*2+2.1*2+.05*2)*.17) +
((.86+2.08*2+.05*2)*(.17-.035)) =
1.606 x 1.1 = 1.77
e) MS Tie rod 8mm 0.34 Kg. 27.50 9.28
f) White / colour cement 0.25 Kg. 12.00 3.00

2 Labours :
Labour rate for cutting, fixing &
moulding of frame 1.77 Sqm. 516.00 913.32

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 4040.34


4 Tools & Plants Charges 2.00% on total (A) 80.81
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 20.20

TOTAL (B) 4141.35


7 Over head & Profit 15.00% on total (B) 621.20

Total costing for (0.9+2.1*2 = 5.1 Rmt.) TOTAL 4762.56

Say Rs. 934 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/3 Unit : Rmt.

Description : P/F Marble frame (170x20)

As per item no 01 but with marble door frame of size 170 mm x 20 mm and extra patti for rebate
formation for 35 mm thick shutter. Door size 900x 2100 mm
Sr.No. Particulars Quantity Unit Rate per Amount
1 Materials :
a) Cement 0.18 Bags 255.00 45.90
b) Sand ( as approved) 0.01 Cum 1060.00 13.78
c) MS Holdfast 6.00 Nos. 10.00 60.00
d) Marble with 10% wastage 1.77 Sqm. 946.00 1671.58
((0.9+.09*2+2.1*2+.05*2)*.17) +
((.86+2.08*2+.05*2)*(.17-.035)) =
1.606 x 1.1 = 1.77
e) MS Tie rod 8mm 0.34 Kg. 27.50 9.28
f) White / colour cement 0.25 Kg. 12.00 3.00

2 Labours :
Labour rate for cutting, fixing &
moulding of frame 1.77 Sqm. 396.00 700.92

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 2504.46


4 Tools & Plants Charges 2.00% on total (A) 50.09
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 12.52

TOTAL (B) 2567.07


7 Over head & Profit 15.00% on total (B) 385.06

Total costing for (0.9+2.1*2 = 5.1 Rmt.) TOTAL 2952.13

Say Rs. 579 /- Per Rmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/4 Unit : Sqmt.

Description : P/F flush shutter 35mm

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws
etc complete. - single shutter - size of door - 750 x 2100 mm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Shutter 35mm thk. 1.36 Sqm. 968.00 1312.61
(2.055 x 0.66 = 1.356
b) Brass Hinges 75mm 4.00 No 20.00 80.00
c) Brass screws 25mm 16.00 No 1.50 24.00

2 Labours :
Carpenter for fixing shutter 0.20 Nos. 200.00 40.00
Helper for fixing shutter 0.10 Nos. 100.00 10.00
(0.2 carp + 0.2 help are required per
cft of frame making)

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1466.61


5 Tools & Plants Charges 2.00% on total (A) 29.33
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 7.33

TOTAL (B) 1503.27


8 Over head & Profit 15.00% on total (B) 225.49

Total costing for (0.75*2.1 = 1.575 sqmt.) TOTAL 1728.76

Say Rs. 1,098 /- Per Sqmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqmt.

Description : P/F flush shutter 35mm (internal door)

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws
etc complete. - single shutter - size of door - 900 x 2100 mm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Shutter 35mm thk. 1.67 Sqm. 968.00 1611.72
(2.055 x 0.81 = 1.356)
b) Brass Hinges 100mm 4.00 No 35.00 140.00
c) Brass screws 25mm 16.00 No 1.50 24.00

Labours :
2 Carpenter for fixing shutter 0.20 Nos. 200.00 40.00
Helper for fixing shutter 0.10 Nos. 100.00 10.00
(0.2 carp + 0.2 help are required per
cft of frame making)

3 Centering & Shuttering


Nil
4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1825.72


5 Tools & Plants Charges 2.00% on total (A) 36.51
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 9.13

TOTAL (B) 1871.36


8 Over head & Profit 15.00% on total (B) 280.70

Total costing for (0.9*2.1 = 1.89 sqmt.) TOTAL 2152.07

Say Rs. 1,139 /- Per Sqmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/5 Unit : Sqmt.

Description : P/F flush shutter 35mm (internal door)

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping
patti, both faces finished with commercial teak ply, including fixing with 8 no of hinges, required screws
etc complete. - double shutter - size of door - 1500 x 2100 mm

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Shutter 35mm thk. 2.89 Sqm. 1016.40 2937.40
(2.055 x 1.41 = 1.356
b) Brass Hinges 125mm 8.00 No 35.00 280.00
c) Brass screws 50mm 32.00 No 2.00 64.00

2 Labours :
Carpenter for fixing shutter 0.50 Nos. 200.00 100.00
Helper for fixing shutter 0.50 Nos. 100.00 50.00

(0.2 carp + 0.2 help are required per


cft of frame making)
3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 3431.40


4 Tools & Plants Charges 2.00% on total (A) 68.63
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 17.16

TOTAL (B) 3517.18


7 Over head & Profit 15.00% on total (B) 527.58

Total costing for (1.5*2.1 = 2.52 sqmt.) TOTAL 4044.76

Say Rs. 1,284 /- Per Sqmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : FDAPL/DW/VII/6 Unit : Sqmt.

Description : P/F Laminate of appr. shade & colour

Providing and fixing laminate of approved colour and shade to doors including all labour and material

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Laminate sheet of 1 mm thk. 1.00 Sqm. 310.00 310.00
b) Fevicol 0.05 Kg. 250.00 12.50
c) Sundry material (plywood pieces &
0.5" nail) 1.00 L/S 10.00 10.00

2 Labours :
Carpenter for fixing & polishing of
laminates 0.07 Nos. 200.00 14.00
Helper 0.20 Nos. 100.00 20.00

(0.2 carp + 0.2 help are required for


fixing the sheet of 4'x8' I.e = 2.88
sqm.) & 0.25 help for polishing

3 Others
Nil 0.00 0.00 0.00

TOTAL (A) 366.50


TOTAL (A) 366.50
4 Tools & Plants Charges 2.00% on total (A) 7.33
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 1.83

TOTAL (B) 375.66


7 Over head & Profit 15.00% on total (B) 56.35

TOTAL 432.01

Say Rs. 432 /- Per Sqmt.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.

Description : P/F MS powder coated fittings

Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop
250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a. Aldrop 300 x 16mm size 1.00 Nos. 0.00 0.00
b. Tadipatti 1.00 Nos. 0.00
c. Tower bolts 1.00 Nos. 0.00
d. PVC gattu 1.00 Nos.
e. Door stopper 1.00 Nos.
f. D type handles 2.00 Nos.
g) Screws 24.00 Nos.

2 Labours :
Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 115.00


5 Tools & Plants Charges 2.00% on total (A) 2.30
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 0.58
TOTAL (B) 117.88
8 Over head & Profit 15.00% on total (B) 17.68

TOTAL 135.56

Say Rs. 136 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.

Description : P/F Alluminium fittings

Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a. Aldrop 300 x 16mm size 1.00 Nos. 112.50 112.50
b. Tadipatti 1.00 Nos. 0.00
c. Tower bolts 1.00 Nos. 0.00
d. PVC gattu 1.00 Nos.
e. Door stopper 1.00 Nos.
f. D type handles 2.00 Nos.
g) Screws 24.00 Nos.

Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

Centering & Shuttering


3 Nil

Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 227.50


5 Tools & Plants Charges 2.00% on total (A) 4.55
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.14

TOTAL (B) 233.19


8 Over head & Profit 15.00% on total (B) 34.98

TOTAL 268.17

Say Rs. 268 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.

Description : P/F stainless steel fittings

Providing and fixing following stainless steel fittings and fixtures for doors, including Aldrop 250mm,
tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a. Aldrop 300 x 16mm size 1.00 Nos. 112.50 112.50
b. Tadipatti 1.00 Nos. 0.00
c. Tower bolts 1.00 Nos. 0.00
d. PVC gattu 1.00 Nos.
e. Door stopper 1.00 Nos.
f. D type handles 2.00 Nos.
g) Screws 24.00 Nos.

Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)
Centering & Shuttering
3 Nil

Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 227.50


5 Tools & Plants Charges 2.00% on total (A) 4.55
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.14

TOTAL (B) 233.19


8 Over head & Profit 15.00% on total (B) 34.98

TOTAL 268.17

Say Rs. 268 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.

Description : P/F Brass fittings

Providing and fixing following Brass fittings and fixtures for doors, including Aldrop 250mm, tadipatti,
towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a. Aldrop 300 x 16mm size 1.00 Nos. 112.50 112.50
b. Tadipatti 1.00 Nos. 0.00
c. Tower bolts 1.00 Nos. 0.00
d. PVC gattu 1.00 Nos.
e. Door stopper 1.00 Nos.
f. D type handles 2.00 Nos.
g) Screws 24.00 Nos.

Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.75 Nos. 100.00 75.00
(0.2 carp + 0.75 help are required for
fixing the fittings for one door)

Centering & Shuttering


3 Nil

Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 227.50


5 Tools & Plants Charges 2.00% on total (A) 4.55
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 1.14

TOTAL (B) 233.19


8 Over head & Profit 15.00% on total (B) 34.98

TOTAL 268.17

Say Rs. 268 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.

Description : P/F Night latch

Providing and fixing night latch of approved brand to door with all hardware and accessories required
Sr.No. Particulars Quantity Unit Rate per Amount
1 Materials :
a) Night Latch 1.00 Nos. 0.00
b) Screws 24.00 Nos.

Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.20 Nos. 100.00 20.00
(0.2 carp + 0.2 help are required for
fixing the latch for one door)

Centering & Shuttering


3 Nil

Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 60.00


5 Tools & Plants Charges 2.00% on total (A) 1.20
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 0.30

TOTAL (B) 61.50


8 Over head & Profit 15.00% on total (B) 9.23

TOTAL 70.73

Say Rs. 71 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.

Description : P/F Automatic door closer

Providing and fixing in position automatic door closure of approved make including all labour and
material complete.
Providing and fixing in position automatic door closure of approved make including all labour and
material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Automatic door closer (godrej or
equivalent) 1.00 Nos. 0.00
b) Screws 24.00 Nos.

Labours :
2 Carpenter for fixing 0.20 Nos. 200.00 40.00
Helper 0.20 Nos. 100.00 20.00
(0.2 carp + 0.2 help are required for
fixing )

Centering & Shuttering


3 Nil

Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 60.00


5 Tools & Plants Charges 2.00% on total (A) 1.20
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 0.30

TOTAL (B) 61.50


8 Over head & Profit 15.00% on total (B) 9.23

TOTAL 70.73

Say Rs. 71 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Door.
Description : P/F eye piece

Providing and fixing peep hole / eye piece of approved make to doors including all labour and material
complete

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Eye piece 1.00 Nos. 0.00
b) Screws 24.00 Nos.

Labours :
2 Carpenter for fixing 0.10 Nos. 200.00 20.00
Helper 0.10 Nos. 100.00 10.00
(0.1 carp + 0.1 help are required for
fixing the latch for one door)

Centering & Shuttering


3 Nil

Others
4 Nil 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 30.00


5 Tools & Plants Charges 2.00% on total (A) 0.60
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 0.15

TOTAL (B) 30.75


8 Over head & Profit 15.00% on total (B) 4.61

TOTAL 35.36

Say Rs. 35 /- Per Door.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqm.

Description : P/F MS powder coated grills & railing


Providing, fabricating and fixing in position for grills & railings in Powder coated MS tubular sections of
all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, all labour and
material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Steel sections 15.00 Kg. 32.00 480.00
b) Nails 0.20 Kg. 32.00 6.40
c) Cement 0.05 Bag 255.00 12.75

2 Labours :
For fabricating & fixing in position 15.00 Kg. 8.00 120.00
Mason for finishing 0.10 No. 200.00 20.00
For powder coating 1.27 Sqm. 161.40 205.62

(Assuming ave. 40x40x1.5mm section


of medium wt. Surface area for 1.884
kg. = 0.16 sqm.)Surface area for 15kg.
= 1.274 sqm.

For paint touch up 1.00 L/s 20.00 20.00

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 864.77


5 Tools & Plants Charges 2.00% on total (A) 17.30
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 4.32

TOTAL (B) 886.39


8 Over head & Profit 15.00% on total (B) 132.96

TOTAL 1019.35

Say Rs. 1,019 /- Per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqm.
Description : P/F MS grills & railing with enamel paint

Providing, fabricating and fixing in position for grills & railings in MS tubular sections of all shapes and
size, with weight upto 15 kg / sqm, as per detail design and drawing, painted with one coat of zinc
chromate & two coats of enamel paint,all labour and material complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Steel sections 15.00 Kg. 32.00 480.00
b) Nails 0.20 Kg. 32.00 6.40
c) Cement 0.05 Bag 255.00 12.75

2 Labours :
For fabricating & fixing in position 15.00 Kg. 8.00 120.00
Mason for finishing 0.10 No. 200.00 20.00
For enamel painting 1.27 Sqm. 30.00 38.22

(Assuming ave. 40x40x1.5mm section


of medium wt. Surface area for 1.884
kg. = 0.16 sqm.)Surface area for 15kg.
= 1.274 sqm.

3 Others
Nil 0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 677.37


4 Tools & Plants Charges 2.00% on total (A) 13.55
5 Water charges 0.00% on total (A) 0.00
6 Electricity Charges 0.50% on total (A) 3.39

TOTAL (B) 694.30


7 Over head & Profit 15.00% on total (B) 104.15

TOTAL 798.45

Say Rs. 798 /- Per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Location : 0
Computer Code No. : D1 Default Date : Dec 30, 99
Revised on Date: 14-08-06
Item No. : 31 Unit : Sqm.
Description : P/F MS Z section windows
Providing and fixing in position MS glazed windows with Z section, 4 mm thick clear float glass, 10 mm
MS square bars at 120 mm c/c, required springs, putty and two coats of oilpaint etc complete.
Sr.No. Particulars Quantity Unit Rate per Amount
Assuming the window size to be = 1.2 x 1.2m
1 Materials :
a) MS Zsections (25mm) 9.60 Rmt. 45.00 432.00
b) 10mm Sq. bars 8.00 Rmt. 23.55 188.40
c) 4mm thk. Float glass (with 5%
wastage) 1.44 Sqm. 325.00 468.00
d) MS holdfast 4.00 Nos 20.00 80.00
e)
f) Nails 0.10 Kg. 32.00 3.20
g) Cement 0.05 Bag 78.75 3.94
h) Fittings (stopper, handle, pin hinges
I.e = 26+10+20) 1.00 L/s 56.00 56.00
I) Putty 0.80 Kg. 20.00 16.00

2 Labours :
For fabricating & fixing in position
(9.6*1.53+8*.785 = 14.2 kg. 20.97 Kg. 10.00 209.68
Mason for finishing 0.10 No. 200.00 20.00
For enamel painting 1.08 Sqm. 30.00 32.40
For fixing glass 0.32 No. 150.00 47.52
(0.22 glazier reqd. for each Sqm.)

4 Others
Nil 0.00 0.00 0.00

TOTAL (A) 1557.14


5 Tools & Plants Charges 2.00% on total (A) 31.14
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 7.79

TOTAL (B) 1596.07


8 Over head & Profit 15.00% on total (B) 239.41

Total costing for 1.2 x 1.2m TOTAL 1835.48

Say Rs. 1,275 /- Per Sqm.

Prepared by :

Name : _________________________________ Sign: ________________


Rate analysis

Site: 0 Location : Pune


Computer Code No. : P1 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 23 Unit : per sqm

Description : Ext. Plaster single coat mortor ratio (1:5)

Providing sand faced plaster externally in cement mortor in all position for a coat of 15 to 20mm thk. in
c.m. 1:5 finishing the surface taking out grains and curing for twenty one days scaffolding etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.16 Bags 215.00 34.40
b) Sand 0.03 Cum 1060.00 31.80

2 Labours :
for Plastering 1.00 Sqm 52.20 52.20

3 Centering & Shuttering


Nil

4 Others
Scaffolding & sand screening
charges 1.00 Sqm 7.70 7.70

TOTAL (A) 126.10


5 Tools & Plants Charges 2.00% on total (A) 2.52
6 Water charges 0.50% on total (A) 0.63
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 129.25


8 Over head & Profit 15.00% on total (B) 19.39

TOTAL 148.64

Say Rs. 149 /- Per per sqm

Prepared by :
Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : P2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PLAST/V/4 Unit : per sqm

Description : External Plastering Double coat

Providing & applying 23 mm av. Th 1:3 c.m. sand faced plaster in 2 coats (base coat of 15
mm th and finishing coat of 8 mm th) to concrete & brick surfaces, risers or otherwise
including mixing plasticizers & waterproofing compound supplied free as directed as
including curing, scaffolding, corners, & edges, bands, splays, grroves, drips, offsets (for
which no extra payment will be made) curing etc. complete.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.22 Bags 255.00 56.10
b) Sand 0.03 Cum 700.00 21.00

2 Labours :
for Plastering 1.00 Sqm 58.95 58.95

3 Centering & Shuttering

Nil

4 Others
Scaffolding & sand screening
charges 1.00 Sqm 7.97 7.97

TOTAL (A) 144.02


5 Tools & Plants Charges 2.00% on total (A) 2.88
6 Water charges 0.50% on total (A) 0.72
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 147.62


8 Over head & Profit 15.00% on total (B) 22.14
TOTAL 169.76

Say Rs. 170 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : P3 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PLAST/V/2 Unit : per sqm

Description : Internal Neeru Plaster CM (1:4)-12mm thk.

Providing & applying av. 12 mm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves,
offsets etc. for which which no extra payment will be made.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.13 Bags 255.00 33.15
b) Sand 0.01 Cum 1060.00 14.84
c) Neeru 0.10 Bags 50.00 5.00

2 Labours :
for Plastering 1.00 Sqm 44.50 44.50

3 Centering & Shuttering

Nil

4 Others
Scaffolding charges 1.00 Sqm 7.28 7.28

TOTAL (A) 104.77


5 Tools & Plants Charges 2.00% on total (A) 2.10
6 Water charges 0.50% on total (A) 0.52
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 107.39


8 Over head & Profit 15.00% on total (B) 16.11

TOTAL 123.49

Say Rs. 123 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : Pune


Computer Code No. : P4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : FDAPL/PLAST/V/1 Unit : per sqm

Description : Internal Neeru Plaster CM (1:4) - 20mm thk.

Providing & applying av. 2 cm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves,
offsets etc. for which which no extra payment will be made.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.17 Bags 255.00 43.35
b) Sand 0.02 Cum 700.00 16.80
c) Neeru 0.10 Bags 50.00 5.00

2 Labours :
for Plastering work 1.00 Sqm 44.50 44.50

3 Centering & Shuttering

4 Others
Scaffolding charges 1.00 Sqm 7.28 7.28

TOTAL (A) 116.93


5 Tools & Plants Charges 2.00% on total (A) 2.34
6 Water charges 0.50% on total (A) 0.58
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 119.85


8 Over head & Profit 15.00% on total (B) 17.98

TOTAL 137.83

Say Rs. 138 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : P2 Default Date :
Revised on Date : 14-08-06
ITEM NO -
FDAPL/PLAST/V/10 Unit : per sqm

Description : Waterproof plaster

Extra for providing chemical admixtures in plastering for waterproofing as per manufacturer's
specifications.( Pidilite / Laticrete / Roffee/ Fosroc or any other approved make)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.34 Bags 255.00 86.70
b) Sand 0.03 Cum 1060.00 31.80
c) Waterproofing compound 0.34 Kg. 40.00 13.60

2 Labours :
for Plastering 1.00 Sqm 106.37 106.37

3 Centering & Shuttering


Nil

4 Others
Sand screening & material
shifting 1.00 Sqm 7.97 7.97
TOTAL (A) 246.44
5 Tools & Plants Charges 2.00% on total (A) 4.93
6 Water charges 0.50% on total (A) 1.23
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 252.60


8 Over head & Profit 15.00% on total (B) 37.89

TOTAL 290.49

Say Rs. 290 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : P2 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item no - FDAPL/PLAST/V/8 Unit : per sqm

Description : Pointing to brick masonary


Providing and making flush groove pointing to brick / block / stone masonry in C:M 1:3 including
scaffolding, curing, cleaning complete with all labour and material.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.03 Bags 255.00 7.65
b) Sand 0.01 Cum 1060.00 5.30

2 Labours :
for Pointing 1.00 Sqm 39.00 39.00

3 Centering & Shuttering

Nil

4 Others
Sand screening & scaffolding 1.00 Sqm 7.06 7.06
TOTAL (A) 59.01
5 Tools & Plants Charges 2.00% on total (A) 1.18
6 Water charges 0.50% on total (A) 0.30
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 60.49


8 Over head & Profit 15.00% on total (B) 9.07

TOTAL 69.56

Say Rs. 70 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : P2 Default Date :
Revised on Date : 14-08-06
Item No. : 24 / IV 6 Unit : per sqm

Description : Pointing to Stone masonary


Providing and making sunk pointing to brick or stone masonry in C:M 1:3 including scaffolding, curing,
cleaning etc complete with all labour and material.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.11 Bags 255.00 28.05
b) Sand 0.01 Cum 1060.00 5.30
0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2 Labours :
for Pointing 1.00 Sqm 42.30 42.30
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
3 Centering & Shuttering

Nil

4 Others
Sand screening & scaffolding 1.00 Sqm 7.06 7.06
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 82.71


5 Tools & Plants Charges 2.00% on total (A) 1.65
6 Water charges 0.50% on total (A) 0.41
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 84.78


8 Over head & Profit 15.00% on total (B) 12.72

TOTAL 97.50

Say Rs. 97 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : P4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 26 / IV 10 Unit : per sqm

Description : P/A POP plaster to walls

Providing POP plaster to walls

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) POP 0.13 Bags 0.00 0.00
0.00 Cum 0.00 0.00
0.00 Bags 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2 Labours :
for POP work 1.00 Sqm 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

3 Centering & Shuttering

4 Others
Scaffolding charges 1.00 Sqm 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 0.00


5 Tools & Plants Charges 2.00% on total (A) 0.00
6 Water charges 0.50% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 0.00

TOTAL (B) 0.00


8 Over head & Profit 0.00% on total (B) 0.00

TOTAL 0.00

Say Rs. 0 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________

Rate analysis

Site: 0 Location : 0
Computer Code No. : P4 Default Date : Dec 30, 99
Revised on Date : 14-08-06
Item No. : 26 Unit : per sqm

Description : Back coat for dado work 1:4)


Providing & applying av. 12 cm thick 1:4 C.M. plaster without Neeru finish to concrete and brick surfaces
including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves,
offsets etc. for which which no extra payment will be made.(behind tile dado)

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Cement 0.13 Bags 255.00 33.15
b) Sand 0.01 Cum 1060.00 10.60

2 Labours :
for Plastering work 1.00 Sqm 37.75 37.75

3 Centering & Shuttering

4 Others
Scaffolding charges 1.00 Sqm 7.28 7.28

TOTAL (A) 88.78


5 Tools & Plants Charges 2.00% on total (A) 1.78
6 Water charges 0.50% on total (A) 0.44
7 Electricity Charges 0.00% on total (A) 0.00

TOTAL (B) 91.00


8 Over head & Profit 15.00% on total (B) 13.65

TOTAL 104.64

Say Rs. 105 /- Per per sqm


Rate analysis

Site: Daffodils Location : Somatne


Computer Code No. : P4 Default Date : 15.03.07
Revised on Date : 18.05.07
Item No. : 26 / IV 10 Unit : per sqm

Description : Providing & applying Gypsum Plaster to walls

Providing Gypsum plaster to walls 12 mm thick

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a)Gypsum 0.39 Bags 130.00 50.70
0.00 Cum 0.00 0.00
0.00 Bags 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

2 Labours :
for Plaster work 1.00 Sqm 55.00 55.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

3 Centering & Shuttering

4 Others
Scaffolding charges 1.00 Sqm 12.50 12.50
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 118.20


5 Tools & Plants Charges 2.00% on total (A) 2.36
6 Water charges 1.00% on total (A) 1.18
7 Electricity Charges 1.00% on total (A) 1.18

TOTAL (B) 122.93


TOTAL (B) 122.93
8 Over head & Profit 15.00% on total (B) 18.44

TOTAL 141.37

Say Rs. 141 /- Per per sqm

Prepared by :

Name : _________________________________ Sign: ________________


0.013
0.304
0.00608
0.17024
0.02432

0.1354
0.034
Rate analysis

Site: 0 Location : Pune


Computer Code No. : R1 Default Date :
Revised on Date : 14-08-06
Item No. : FDAPL/RCC/III/22 Unit : MT

Description : Reinforcement works

Providing and laying in position reinforcemnt steel of various diameters incluidng cutting
bending, binding with binding wire for all RCC work like footings, columns, beams, slabs,
paradise staircases, chajjas, walls, etc. as per RCC Specialist's design & drawing details
with necessary bending, laying, binding, with binding wire, etc. complete. Rate to include all
lead & lift.

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
a) Reinforcement steel 1.00 MT 43000.00 43000.00
b) Binding wire 12.00 Kg 47.00 564.00

2 Labours :
for reinforcement works including 1.00 MT 3506.25 3506.25
cutting, bending, binding etc.
including T & P etc. complete.

3 Centering & Shuttering


Nil

4 Others

TOTAL (A) 47070.25


5 Tools & Plants Charges 2.00% on total (A) 941.41
6 Water charges 0.00% on total (A) 0.00
7 Electricity Charges 0.50% on total (A) 235.35

TOTAL (B) 48247.01


8 Over head & Profit 15.00% on total (B) 7237.05

TOTAL 55484.06

Say Rs. 55,484 /- Per MT


Prepared by :

Name : _________________________________ Sign: ________________


4025
Site Name : 0
Location : Pune
SINGLE LINE ESTIMATION

Sr.No. Description Unit Quantity Rate


1 Excavation in soil and soft murum upto 1. per cum 0 166
2 #REF! #REF! 0.00 #REF!
3 Excavation in Hard Murum & boulders per cum 0.00 213
4 Excavation in Soft Rock per cum 0.00 357
5 Excavation in Hard Rock by chiselling per cum 0.00 914
6 P.C.C. (1 :2:4 ) per cum 0.00 3439
7 P.C.C. (1 : 4: 8 ) per cum 0.00 2690
8 #REF! #REF! 0.00 #REF!
9 C.C. M20 for Footing, raft per cum 0.00 3393
10 #REF! #REF! 0.00 #REF!
11 C.C. M20 for superstructure Columns per cum 0.00 5304
12 #REF! #REF! 0.00 #REF!
13 C.C. M20 for floor Beams per cum 0.00 4975
14 #REF! #REF! 0.00 #REF!
15 C.C. M20 for slab per cum 0.00 3934
16 C.C. M20 for Staircase per cum 0.00 4742
17 RCC M20 for Pardi, fins per cum 0.00 6065
18 UCR In plinth per cum 0.00 1985
19 Brick masonary 35cm thk. Below plinth per cum 0.00 2440
20 Brick work 35cm thk. In superstructure per cum 0.00 2544
21 Plinth Masonry 23cm thk #REF! 0.00 2086
22 #REF! #REF! 0.00 #REF!
23 Ext. Plaster single coat mortor ratio (1:5) per sqm 0.00 149
24 External Plastering Double coat per sqm 0.00 170
25 Internal Neeru Plaster CM (1:4)-12mm thk. per sqm 0.00 123
26 #REF! #REF! 0.00 #REF!
27 Grey Mosaic Tile Flooring of 25cm x 25cm per sqm 0.00 336
28 #REF! #REF! 0.00 #REF!
29 #REF! #REF! 0.00 #REF!
30 #REF! #REF! 0.00 #REF!
31 #REF! #REF! 0.00 #REF!
32 Brickbat water proofing for toilets per Cum 0.00 2652
33 Brickbat water proofing for terrace per sqm 0.00 348
34 Chemical w/p for terrace, toilets per sqm 0.00 327
35 Reinforcement works MT 0.00 55484
36 Structural steel works per Sqm. 0.00 43578
37 12mm dia. Fan hook per No. 0.00 32
38 Chainlink fencing per Sqm. 0.00 259
39 0 0 0.00 0
40 0.03 0.00 0
41 0 0.005 0
42 0 0.005 0
43
44
45
46
47
48
49
50
Total :
0
Pune
SINGLE LINE ESTIMATION

Amount
0.00
#REF!
0.00
0.00
0.00
0.00
0.00
#REF!
0.00
#REF!
0.00
#REF!
0.00
#REF!
0.00
0.00
0.00
0.00
0.00
0.00
0.00
#REF!
0.00
0.00
0.00
#REF!
0.00
#REF!
#REF!
#REF!
#REF!
0.00
0.00
0.00
0.00
0.00
0.00

#REF!
Rate analysis
Site: 0 Location : Pune
Computer Code No. : Default Date : Dec 30, 99
Revised on Date
Item No. : Unit :

Description :

Sr.No. Particulars Quantity Unit Rate per Amount


1 Materials :
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
2 Labours : 0 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
3 Centering & Shuttering 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
4 Others 0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00

TOTAL (A) 0.00


4 Tools & Plants Charges 5.00% on total (A) 0.00
5 Water charges 1.00% on total (A) 0.00
6 Electricity Charges 1.00% on total (A) 0

TOTAL (B) 0.00


7 Over head & Profit 15.00% on total (B) 0.00

TOTAL 0.00

Say Rs. 0 /- Per