Documente Academic
Documente Profesional
Documente Cultură
www.intecsea.com
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
HOLDS List
HOLDS closed during following revision of document to be deleted from the table.
Section No.
HOLD
& Revision Description of HOLD
No.
Inserted
Page 3 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Table of Contents
1 SCOPE ....................................................................................................................................... 8
1.1 Project Overview ..................................................................................................... 8
Page 4 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
5.9 Pre-Heat................................................................................................................... 26
Page 5 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Page 6 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Page 7 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
1 SCOPE
Pipeline and Flowline Welding (rigid and flexible) and shall apply to all onshore and offshore
pipelines as well as Risers, PLEMs, PLETs Manifolds, ILS, ILT, rigid Jumpers and Tie ins for the
automatic and manual welding of girth welds and attachments.
XMT, Tubing Hangers and associated equipment
Pressure Retaining Components Welding (piping, fittings, flanges etc.)
Structural Welding including Subsea Structures
Tubing Welding including, but not limited to, Umbilicals and Flying Leads
All welding and inspection shall be carried out using welding processes and techniques permitted
by the Project referenced Codes and Standards and as listed in COMPANY project specifications.
Page 8 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
CONTRACTOR shall obtain COMPANY written approval for any deviations from the requirements
of this document or specifications, standards and drawings referenced herein or elsewhere in the
Contract.
This document and the codes, specifications and referenced documents listed in section 1.4 and
1.5 below are not intended to be all-inclusive. The requirements set forth do not relieve
CONTRACTOR of his responsibility to perform all services in a safe manner, to meet applicable
codes and standards, to comply with government regulations or to supply a product capable of
performing its intended service.
1.5.1 General
The latest editions of all applicable codes, specifications and references shall define the minimum
requirements applicable to the subject work and no statement contained in this General
Requirements document shall be construed as limiting the work to such minimum requirements.
Wherever conflicts or omissions between codes, specifications and contract occur, the most
onerous condition shall apply. CONTRACTOR is responsible for reviewing the list below and
informing the COMPANY of any omissions. All conflicts shall be formally brought to the attention
of COMPANY.
Page 9 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Page 10 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Page 11 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Page 12 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
1.7 Definitions
For the purpose of this document, the following definitions shall apply:
Term Definition
COMPANY or “Owner” shall mean ONGC, its affiliated companies,
COMPANY partners, co-lessees, co-owners, joint ventures, and their agents, third
party inspectors, officers, and employees.
Where referenced shall mean COMPANY’S written and executed
CONTRACT
contract with the CONTRACTOR.
Also referred to as “Vendor”, “Seller” or “Supplier” shall mean the party
CONTRACTOR to whom COMPANY’S Purchase Order, CONSTRUCTION Order, or other
written CONTRACT is awarded.
Where referenced, shall mean those processes that produce the
CONSTRUCTION
equipment, including manufacture, fabrication, assembly, and testing.
MAY Indicates possible course of action.
Any assembly or sub-assembly deemed to be critical to the safety,
Safety Critical Element
integrity and performance of the subsea production system.
Page 13 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Term Definition
SHALL Indicates mandatory requirement.
SHOULD Indicates preferred course of action.
The person, group or organization who may be employed by
CONTRACTOR (or sub-CONTRACTOR in reference to a supply chain) to
Sub-CONTRACTOR provide services for the design, manufacture, testing and load-out /
shipping of the equipment, or, to provide materials, sub- components
and sub-assemblies for incorporation in the specified equipment.
WILL Indicates an intention of action.
WORK The scope of CONSTRUCTION to be performed per the CONTRACT.
Term Definition
AUT Automatic Ultrasonic Testing
CE Carbon Equivalent
CO2 Carbon Dioxide
CRA Corrosion Resistant Alloy
CVN Charpy V Notch
ECA Engineering Critical Assessment
ECT Eddy Current Testing
FPSO Floating Production Storage and Offloading
GTAW Gas Tungsten Arc Welding
H2S Hydrogen Sulfide
HAZ Heat Affected Zone
HE Hydrogen Embrittlement
HISCC Hydrogen Induced Stress Corrosion Cracking
ILS / ILT Inline Sled / Inline Tee
KOH Potassium Hydroxide
MPI Magnetic Particle Inspection
NDA Northern Discovery Area
NDT Non Destructive Testing
Page 14 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Term Definition
Pcm Critical Metal Parameter
PLEM Pipeline End Manifold
PLET Pipeline End Termination
ppmV Parts per Million by Volume
PQR Procedure Qualification Record
PWHT Post Weld Heat Treatment
QA Quality Assurance
QC Quality Control
RBM Riser Base Manifold
ROL Run Out Length
RPQR Repair Procedure Qualification Record
RT Radiographic Testing
RWPS Repair Welding Procedure Specification
SDA Southern Discovery Area
SDU Subsea Distribution Unit
SPS Subsea Production System
SURF Subsea Umbilicals, Risers and Flowlines
UT Ultrasonic Testing
WPS Welding Procedure Specification
XMT Christmas Tree.
4) Hg content Nil
Page 15 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
2 DESIGN DATA
2.2.1 Welding
The governing standard for welding on the KG-DWN-98/2 project shall be as follows.
Page 16 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
3 DESCRIPTION OF WORK
3.1 Overview
The KG-DWN-98/2 CONSTRUCTION CONTRACTOR is responsible for the Scope of Work under the
CONTRACT in accordance with this specification, including the provision of all labor, materials,
tools, facilities and services required to design, manufacture, test, deliver and load out the specified
equipment. All work shall be performed in accordance with the requirements and provisions of this
specification and CONTRACTOR supplied Project Execution and Quality Plan which shall be
reviewed by COMPANY prior to the start of work.
Page 17 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
4.1 General
The Design Requirements are included in the core specifications, statutory design codes
/regulations and basis of design.
A separate overall and documented philosophy for the prevention of HE and HISSC shall be
established, planned and implemented covering all phases from conceptual development through
to abandonment.
Page 18 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
5.1 General
5.1.1 Welding
All welding on the CONSTRUCTION shall be carried out using a process or combination of
processes that has been fully qualified according to the requirements, referenced codes and
standards and Project specifications.
Within the CONTRACT specified deliverables period, after award, CONTRACTOR shall submit a
matrix showing all welding procedures and procedure qualification records proposed for their
scope of work.
CONTRACTOR shall submit and demonstrate the required examination procedures for COMPANY
review before any welding or procedure qualification welding takes place.
Non-destructive testing shall comply with the specified Codes, Standards and Specifications as
defined in the applicable codes and project specific requirements stated in section 1.6.1 and
relevant to NDT.
RT testing is not allowed for narrow gap configuration welds. Approved AUT methods shall be
used on narrow gap configurations welds.
All NDT technicians shall be qualified as a minimum to ASNT Level NDT II.
All NDT procedures shall be reviewed and endorsed by ASNT NDT Level 3 qualified personnel.
The qualifications of intended NDT personnel shall be submitted to COMPANY for review prior to
the commencement of NDT activities.
CONTRACTOR shall provide a NDT personnel matrix to be reviewed by COMPANY prior to start of
manufacture
Extent of NDT shall be 100% of external surface and volume of weld and their components.
Due to the complexity of flaw assessment and inspection methods of CRA clad materials
considering the dissimilar nature of the materials abutting at any welded joint, CONTRACTOR shall
Page 19 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
develop a reliable inspection technique which allows full assessment of the integrity of any CRA
clad materials following deposition of root and subsequent weld depositions. The inspection shall
demonstrate an absence of root defects and deleterious volumetric defects, and weld shall have a
satisfactory internal root profile. The inspection technique shall be reviewed by COMPANY prior to
any production.
COMPANY reserves the right to proficiency test at no additional cost to COMPANY, any NDT
operative working at any of CONTRACTORs fabrication yards/barges or sub-contractors facilities
irrespective of their current NDT Qualifications. The test will comprise of a practical demonstration
of the NDT operatives abilities on a sample test piece or NDT report relative to the work they will
be carrying out on the project.
Qualifications shall be conducted on production pipe or plate materials unless otherwise agreed by
COMPANY.
Special care to be taken on carbon steel welds to ensure weld metal is not anodic to parent metal.
Preferential weld corrosion shall be avoided by careful choice of consumables with respect to the
parent metal by the CONTRACTOR in conformance with the relevant referenced specifications and
guidelines in section 1.6.1 of this document. CONTRACTOR to demonstrate compliance to this
requirement for pressure containing welds.
If accelerated cooling is to be used during production welding, then this will be qualified during
procedure qualification using identical conditions as the production welds, including cooling
medium, cooling pressure and minimum coolant temperature.
Position and Welding parameters shall be as qualified in the Procedure Qualification Record (PQR)
for pressure containing welds.
The proposed Welding Procedure Specifications shall include, but not be limited to, the following
information:
Page 20 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Pre-qualified welding procedures for pressure retaining and primary structural components shall
not be permitted. If permitted previously qualified PQR shall be endorsed by a third party and a
new project specific WPS generated. This WPS shall reflect applicable Project Specifications and
latest codes and standards.
Structural procedures previously qualified by CONTRACTOR and meeting all the requirements
specified for the Project may be submitted for evaluation by COMPANY.
The qualification testing of the WPS shall be documented in a Procedure Qualification Record
(PQR) with testing performed at a COMPANY agreed laboratory.
CONTRACTOR shall provide sufficient advance notice of PQR testing to allow COMPANY to witness
all of the testing.
Only welding procedures reviewed by COMPANY shall be used for production welding
The allowable range of heat input rates to be applied by the welding process for each bead shall
be clearly specified. The units used shall be kilojoules per mm (kJ/mm).
During weld procedure qualification, weld data logging equipment shall be used that allows
recording of voltage, amperage and travel speed for each weld pass, to enable the heat input to be
calculated. This same equipment, or agreed equivalent, shall also be used during production
welding.
Weld data logging equipment shall have valid calibration at the time of checking/measurement.
The PQR shall also contain a weld map detailing the location of each welding pass placed. PQR
shall contain a record of all examination and test results and shall include copies of all examination
and test reports.
Page 21 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
When Automatic Ultrasonic Testing (AUT) is to be utilized, CONTRACTOR shall provide the AUT
inspection company with the joint designs details for weld procedure qualification and production
welding for use in the manufacture of the calibration blocks for AUT made from project material
specific to the pipeline.
Test pieces for procedure qualification of carbon steel shall be selected from the higher range of
carbon equivalents (CE) and/or Pcm based on the steel purchased for the Project.
For carbon steel an increase in Pcm of more than 0.02, CE of more than 0.03 or C content more
than 0.02% shall require requalification. Pcm and CE are defined as follows;
The Heat Number of the material used for Qualification shall be recorded on the PQR including the
CE and/or Pcm value.
PQR shall record the application of preheat, which may be by electrical resistance method or oxy-
propane torches.
Separate qualification testing is required for repair welding and these repair procedures shall be
subject to COMPANY review cycle and shall be carried out in representative conditions and shall
include a description of defect removal and groove preparation. The RPQR should be similar to a
Procedure Qualification Record and reflect anticipated welding parameters and conditions.
Material test certificates and typical welding consumable test certificates or other background
information shall be provided.
The welding consumables used shall be of a grade which will yield a weld equivalent to or higher
than that of the base metal. Sufficient quantities of welding consumables shall be available for the
entire production program.
Cellulosic electrodes shall not be used for installation welding in deep water (>500m). For other
applications, (e.g. onshore welding and shallow water), use of cellulosic electrodes shall only be
allowed with written consent from COMPANY.
Page 22 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Welding consumables supplied from a different batch than those used in the qualification program
shall be subject to batch testing.
All NDT for welding procedure’s qualifications shall be carried out 48 hours after the completion of
the weld.
Batch testing of consumables shall be performed using COMPANY reviewed WPS (s).
For any sour service environment, the chemical composition of welding consumables shall comply
with ISO 15156 relevant section
For any sour service environment, the WPS/PQR and production welding shall conform to ISO
15156 relevant section.
All non-sour services for the SURF and SPS shall comply to DNV-OS-F101.
The heat number, material number and other tracking identification shall be transferred and
recorded in the PQR test record.
All mechanical testing and examination shall be conducted after any post weld heat treatment that
may be required.
The review of welding procedure qualifications will be based on satisfactory mechanical testing and
non-destructive examination in accordance with the applicable welding Code.
Qualification Certificates shall include the actual results of the tests required by this Specification.
The term 'satisfactory' for tensile, CVN, hardness and corrosion tests is not acceptable
Acceptance criteria for tests relating to weld performance (tensile, hardness, CVN, corrosion tests,
etc.) shall be included with the reported results (as per construction or welding codes, whichever is
the most stringent).
Additional tests required for corrosion resistant alloys (CRA) shall be reported with mechanical
testing. These shall include acceptance criteria (e.g. ASTM G48 – duration, test temperature and
maximum weight loss) with the results of the test. No evidence of pitting at x20 magnification will
be considered as acceptable. In the event of disputed pits, namely occluded or non-occluded, the
ASTM G46 recommendations shall be used to define the morphology of the pit.
Page 23 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
COMPANY reserves the right to witness welder and welding operator qualification testing
including any mechanical testing of qualification test coupons.
Grouping weld procedures for welder qualification purposes shall be per the applicable code,
specification or standard referenced for the project.
Welders / welding operator’s qualification tests shall be subject to the same NDT method and
technique as used for production welding.
Welder qualifications remain valid providing there are no gaps greater than 6 months during which
welding using same process, materials and consumables has not been performed.
Automatic welding equipment used for welder qualification shall be the same type as that
proposed by CONTRACTOR for pipeline/flowline welding.
A list of qualified welders or operators and the procedures they are qualified to use shall be
maintained and posted on the work site. Welder qualification certificates shall include a
photograph of the welder for identification purposes.
5.6.1 General
Production welding shall be carried out in accordance with COMPANY reviewed welding
procedures.
The qualified WPS shall be located in the vicinity of production welding and shall be available to
welders or automatic welding operators.
Page 24 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Welding surfaces shall be thoroughly cleaned so as to be dry and free from paint, oil, rust, scale,
and any other material detrimental to weld quality.
Each bead shall be cleaned of scale, oxides, dirt, slag, silicates, and other impurities before any
succeeding weld passes are made.
Welding and heat treatment of weldments must be protected from weather conditions that would
impair weld quality.
Welds carried out on socket welds or threaded seal welds will have a minimum of two runs
showing, on completion of the final pass.
Low hydrogen electrodes must be adequately stored to limit diffusible hydrogen to a maximum 4.0
ml/100 g deposited metal.
Electrode storage must comply with that used during weld procedure qualification.
Flux for submerged arc welding shall be free from any active weld metal alloying additions.
Consumables shall deposit weld metal having a minimum yield and ultimate tensile strength at
least equal to that specified for the parent material.
For piping weld procedure qualifications, the batches of electrodes used for qualifications shall be
used for production.
Should different batches from those used in qualifications be proposed for production, such
consumables will be subject to individual batch tests using COMPANY reviewed WPS (s).
Vacuum packed Low Hydrogen electrodes shall be protected from damage and be accompanied
by the hydrogen classification certificates.
Page 25 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Low Hydrogen welding consumables capable of depositing weld metal containing less than 4 ml of
hydrogen per 100 grams of deposited weld metal shall be used for carbon steel structures and
pipe work unless specified otherwise in CONTRACT or Project Documentation.
All equipment used for monitoring or measures welding parameters shall be calibrated to ensure
compliance with the variables listed in the approved welding procedures.
Welding machines shall be operated within the approximate voltage and current ranges
recommended for each type of electrode used. Welding Machines shall not be operated beyond
their rated capacity and shall be maintained in good working order.
Welding machine ground leads shall be fastened securely using clamps or other mechanical means
(not welded). Connections shall prevent damage and arcing.
Welding cables with damaged insulation that exposes wire shall be replaced.
Flow meters shall be used for accurate flow rate measurement when shielding gases are used. Gas
analyzers shall be available for checking compositions of gases.
For Non Ferrous Metals, only stainless steel tools or grinding disks dedicated to stainless steel shall
be used. Material supports, internal purge dams, alignment clamps, and other tools may be coated
with a compatible material reviewed by COMPANY.
5.9 Pre-Heat
The minimum preheat temperature for welding shall be in accordance with the temperature
specified in the qualified welding procedure.
Temperature monitoring shall assure the required preheating temperature is obtained before
welding and maintained during the welding operation.
Temperature indicating crayons shall not be marked on weld bevels, weld beads or surfaces to be
welded.
Page 26 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Under no circumstances shall the use of oxy-acetylene welding or cutting torches be permitted for
preheating weld joints.
Preheat shall be supplied in a gradual and uniform manner and shall be maintained throughout the
welding operation.
The minimum preheat temperature shall be established on both sides of the joint preparation for a
minimum distance of 75 mm or three times the material thickness, whichever is greater.
If possible, the preheat temperature shall be measured on the opposite face to that being heated.
Unless specified otherwise, the preheat minimum temperature shall be held for a minimum of one
minute for each 25 mm of material thickness before welding is commenced.
The preheat temperature shall be checked before and during welding by temperature indicating
crayons or contact pyrometers.
Maximum interpass temperature shall be measured within 25 mm of the weld bevel by contact
pyrometer or any method of temperature measurement reviewed by COMPANY.
Weldments which require post weld heat treated shall be indicated by CONTRACTOR on the
fabrication drawings and submitted to COMPANY for review prior to start of fabrication.
For PWHT and/or stress relief procedures, if required, shall be according to the requirements of
applicable code. CONTRACTOR shall submit a PWHT procedure in compliance for COMPANY
review prior to any PWHT being conducted. Only COMPANY reviewed procedures shall be used for
PWHT. These shall include, but not be limited to, the number, location, and method of attachment
of thermocouples to the pipe or location within a furnace.
Exposed machined and threaded surfaces shall be protected from oxidation during heat treatment.
Cleaning of piping after fabrication and heat treatment shall be performed externally and internally
to remove all loose scale, weld spatter, sand and other foreign material.
Page 27 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
The use of manually operated gas torches or gas rings shall not be permitted for post weld heat
treatment.
Wherever possible, post weld heat treatment shall be carried out in an enclosed furnace with a
neutral furnace atmosphere. For site or field welds, particularly "in situ" welds, local post weld heat
treatment shall be conducted.
Local post weld heat treatment shall be conducted in accordance with an approved procedure.
During furnace or local post weld heat treatment a minimum of four (4) thermocouples shall be
used to ensure that a uniform temperature is achieved, and no harmful gradients occur during the
heat treatment cycle.
No welding shall be permitted on any material that has been post weld heat treated.
Pipe ends, flange faces, threads and any other machined surfaces shall be suitably protected
against oxidation during the post weld heat treatment cycle.
Multiple post weld heat treatments shall be subject to agreement with COMPANY.
WPS for XMT, Tubing Hanger and associated components shall meet or exceed the requirements
of relevant specifications, ASME IX, NACE MR 0175/ISO 15156 and any additional requirements of
this specification.
All aspects of the XMT, Tubing Hanger and associated components shall be NDT tested utilising a
COMPANY reviewed procedure as per DNV/ASME/BPVC Section V for Non Destructive Testing.
CONTRACTOR shall implement the requirements of DNVGL RP-0034 –Steel Forgings for subsea
applications.
Additional requirements for all major forgings such as tree spools, blocks and valves shall as a
minimum be NDT tested at the thickest section and the highest utilisation section of the forgings
to ensure minimum mechanical properties required for the CONSTRUCTION are achieved
throughout the forging.
Page 28 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
The Design Code for KG-DWN-98/2 pipelines and flowlines shall be DNV-OS-F101. Welding shall
follow the requirements of Appendix C of DNV-OS-F101 and any other supplementary
requirements of this general welding and NDT document.
Automatic welding processes nominated by CONTRACTOR shall have a proven track record or
have a test program to prove the process capabilities.
CONTRACTOR shall demonstrate that acceptable welds can be reproduced joint to joint utilizing
the process to be used in production.
CONTRACTOR shall establish the production heat input range for each welding pass by completing
a full weld at the Low Heat Input (LHI) and High Heat Input (HHI) values. The maximum/minimum
or range of average for heat inputs for each weld pass shall be measured and documented.
Use of grinders is limited to interpass cleaning only and shall not be used to remove slag or
spatter. Flapper wheels can be used to remove surface slag or spatter.
Low Hydrogen welding consumables capable of depositing weld metal containing less than 4 ml of
hydrogen per 100 grams of deposited weld metal shall be used for carbon steel pipelines/flowlines
unless specified otherwise in CONTRACT or Project Documentation.
Cellulosic electrodes shall not be used for installation welding in deep water (>500m). For other
applications, (e.g. onshore welding and shallow water), use of cellulosic electrodes shall only be
allowed with written consent from Company.
The yield strength of the weld metal should be selected to ensure that the yield strength of the
deposited girth welds overmatches the actual yield strength of the parent pipe material at both
ambient and maximum design temperature.
Consumables shall provide adequate toughness at both the maximum and minimum design
temperatures. Fracture mechanics testing shall as a minimum, but not limited to, be compliant with
the requirements defined in Appendix A, Subsection D (Girth welds under Strain-based Loading
Assessed According to ECA Static – Full) of DNV-OS-F101.
Each batch/lot of welding consumables shall, be purchased from manufacturers operating a quality
system based upon ISO 9001 and shall have a manufacturer’s certificate conforming to the relevant
EN, ISO or AWS filler metal specification.
Page 29 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
All welding consumables shall be individually marked and supplied with an inspection certificate
type 3.1 according to EN 10204.
All welding consumables shall be delivered in accordance with Manufacturer's data sheets, which
shall state the minimum and maximum levels of C, Mn, Si, P, S, micro-alloying elements and any
other intentionally added elements including trace elements.
Filler metals and fluxes classifications shall conform to the appropriate American Welding Society
(AWS) and/or British Standard (BS).
On Pipeline/Flowline welding all welds, weld identification numbers shall be painted on the pipe
using contrasting colors.
A reference between weld numbers and pipe numbers shall be maintained. Each weld number shall
be located on either side of the pipe between clock positions 1:00 and 5:00 and 7:00 to 11:00
adjacent to the weld.
The width of each letter or number shall not be less than 19 mm (3/4 in.).
Weld identification must be legible using sequential numbers and/or combination of English block
letters and numbers.
Procedure qualifications shall be prepared and qualified for each repair procedure that is
proposed. Such specifications shall include a description of defect removal and groove
preparation and NDT method to inspect the excavated area to ensure removal of flaw.
Repairs to Cracks are not permitted. Welds containing cracks shall be cut out.
For Automatic Ultrasonic Testing of Girth Welds CONTRACTOR shall conform to the requirements
of DNV-OS-F101 Appendix E.
Page 30 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Welding Procedures for DSS welding shall conform to the relevant welding specification defined in
section 1.6.1 of this document.
Welding procedures shall be qualified by separate test coupons welded at the lowest and highest
heat input to be used in production.
Welding procedures shall be on representative size specimens. Small diameter test pieces will not
qualify larger diameters. Diameter range for procedure tests shall be reviewed by COMPANY.
The ferrite/austenite phase balance of the weld metal shall be measured by the point count
method ASTM E562 for the root, fill and cap area of the weld cross section. The ferrite content shall
be 30% to 55% in the weld metal. A magnetic ferrite gauge shall be used to measure the ferrite
percentage on the cap of the weld metal and be reported on the PQR for reference.
All single sided welds shall be made with a GTAW root pass and back purged until at least 6mm of
the weld metal thickness has been deposited. Backing gas shall be welding grade 100% argon with
a purity of at least 99.95% argon. The oxygen content of the back-purged volume shall be less than
0.5% (5000ppm). CONTRACTOR shall submit details of the method and equipment to be used for
monitoring oxygen content as part of the welding procedure specification.
All duplex stainless steel welding shall be monitored 100% and heat inputs and welding sequence
agreed with COMPANY prior to welding.
Production welds shall be checked on the cap along the weld with a calibrated ferrite gauge and
shall not exceed 55% ferrite. The measurement spacing along the weld length shall be the lesser of
three equidistant locations or 300mm (12”). A minimum of five measurements shall be taken at
each location. The surface shall be prepared as recommended by the manufacturer of the testing
instrument. Acceptance shall be based on the average of the measurements at each location. Of
the five local measurements, the highest and lowest values may be discarded and the average of
the remaining three reported as the final value.
Page 31 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Selection of filler wire material shall be reviewed by COMPANY and all WPS/PQR qualifications
shall be carried out in representative simulated fabrication/installation conditions and joint
geometries. Fit up, backing gas and welding consumables shall be agreed with COMPANY.
Weld repairs shall only be performed in accordance with the qualified/reviewed repair WPS and
only one attempt at repairing a defect is permitted. Re-repairs shall require Company review and
will only be permitted if a re-repair WPS has been qualified.
Repaired areas shall be examined with the same NDT method used for original weld.
Repairs to cracks are not permitted. Welds containing cracks shall be cut out.
Only low hydrogen processes and consumables may be used for repair welding.
For procedures based on carbon steel groove welding procedures, work piece temperature shall be
a minimum of 50°C higher than the minimum preheat temperature required for the original
reviewed welding procedures.
Grinding shall not reduce the remaining wall thickness to less than the minimum thickness
specified by the applicable design code. UT thickness checks to be used to verify compliance.
Page 32 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Extent of NDT shall be 100% of volume of welds and 100% of exposed surface of welds and
components.
All aspects of the flexible flowline components shall be NDT tested utilising a COMPANY reviewed
procedure as per DNV/ASME/BPVC Section V for Non Destructive Testing.
End Fittings:
CONTRACTOR shall implement the requirements of DNVGL RP-0034 –Steel Forgings for subsea
applications. Additional requirements for all end fitting forged components shall as a minimum be
NDT tested at the thickest section and the highest utilisation section of the forgings to ensure
minimum mechanical properties required for the CONSTRUCTION are achieved throughout the
forging
Automatic welding shall be held within the minimum and maximum parameters recorded in the
PQR.
Production heat input range shall be as qualified in the WPS. The maximum/minimum or range of
average heat inputs for each weld pass shall be measured and recorded.
Only groove full penetration welds shall be used in pressure containing envelopes. Fillet welds only
allowed with agreement of COMPANY.
Circumferential girth welds shall be separated by the maximum possible distance and at least one
diameter of pipe utilized.
All welds shall be fully traceable between the structure location, weld number and adjoining pipe
or fitting.
Pipe with seam welds shall have their longitudinal seams offset by at least 150mm, preferably
located in the top half of pipe section.
COMPANY shall be notified prior to any repair activities being carried out on jumper spools. Repair
welding shall only be performed in accordance with a qualified and reviewed repair WPS. Only one
Page 33 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
attempt at repairing a defect is allowed. Repairs are not allowed on welds containing cracks. Welds
containing cracks shall be cut out.
The full section of pipe shall be removed if laminations, split ends or longitudinal seam defects are
discovered in any jumper pipe material.
Arc burns shall be prevented. If COMPANY does allow repair, then arc strike shall be removed by
grinding and ground area subject to MPI and UT thickness check. Remedial work shall not reduce
the wall thickness to less than the minimum thickness stipulated in the applicable design
requirements.
Electrical continuity straps shall be attached in accordance with COMPANY reviewed drawings.
Prior to applying surface coating, electrical continuity shall be checked across the interfaces of
structural frames and piping as well as any clamps for piping, top and bottom halves.
Anodes shall not be directly welded to the jumper pipework but shall be attached by doubler plate
connections welded to the pipe utilising a reviewed procedure and connected to the jumper pipe
with continuity straps. Electrical impedance shall not be greater than 0.1 ohm.
Weld overlay where required shall conform to ASME IX/NACE MR0175/ISO 15156 and
requirements of this specification.
Extent of NDT shall be 100% of volume of welds and 100% of exposed surface of welds and
components.
All aspects of the flexible flowline components shall be NDT tested utilising a COMPANY reviewed
procedure as per DNV/ASME/BPVC Section V for Non Destructive Testing.
Extent of NDT shall be 100% of volume of welds and 100% of exposed surface of welds and
components.
Sub-Sea Valves shall be NDT tested utilising a COMPANY reviewed procedure as per ASME/BPVC
Section V for Non Destructive Testing.
Page 34 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
The NDT of overlay welding shall conform to the relevant requirements of API 6A and API 5LC and
include:
Extent of NDT shall be 100% of volume of welds and 100% of exposed surface of welds and
components.
Flanges to connecting pipework shall be NDT tested utilising a COMPANY reviewed procedure as
per DNV/ASME/BPVC Section V for Non Destructive Testing.
Structural Welding shall conform to AWS D1.1 as well as additional requirements of this
specification.
Page 35 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Extent of NDT shall be 100% of volume of welds and 100% of exposed surface of welds and
components.
Each consumable lot shall require a separate procedure qualification(s). A lot includes changes
within the manufacturer’s brand and type of consumable. Such changes shall include material heat,
and batch etc.
Welding procedures shall be qualified by separate test coupons welded at the lowest and highest
heat input to be used in production.
Autogenous welding is not allowed on CRA material without COMPANY written approval.
Autogenous welding may be permitted on some classes of Stainless Steels. Autogenous welding
on Duplex Stainless Steel is prohibited.
Welding procedures shall be on representative size specimens. Small diameter test pieces shall not
qualify larger diameters and vice versa. Diameter range for procedure test shall be reviewed by
COMPANY.
The ferrite/austenite phase balance of the weld metal shall be measured by the point count
method ASTM E 562 for the root, fill, and cap area of the weld cross section. The ferrite content
shall be 30 to 55% in the weld metal. A magnetic ferrite gauge shall be used to measure the
percent ferrite on the cap of weld metal and be reported on the PQR for reference.
The minimum number of mechanical test specimens required for a welding procedure qualification
test weld shall be in accordance with ASME Section IX, with the addition of requirements in Section
5.25.
Page 36 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Test Quantity
Charpy V- Notch at -40°C
Weld Centreline 3
Fusion Line 3
Fusion Line +2.3mm 3
Fusion Line +4.5mm 3
Cross Section for macro-examination, photomicrographs and 1
ferrite measurements.
Charpy impact testing shall be in accordance with ASME Section VIII, UG-84.
Charpy Tests
Lateral expansion measurements shall be reported for information. In the event of failure of Charpy
tests, re-test requirements shall be agreed with COMPANY.
For ferrite assessment during procedure qualification tests, metallurgical sections shall be polished
and electrolytically etched at 7-8 V in 40% KOH to clearly reveal the two-phase austenite/ferrite
microstructure. The area being point counted, either parent material, weld metal or HAZ, should be
examined and photographed under a microscope at a sufficient magnification to fill the field of
view and to be able to clearly discriminate between the constituent phases. A magnification of
400X minimum is required.
The photographs shall be overlaid with a grid of at least 100 points and the percentage ferrite shall
be calculated from the number of points that fall on the ferrite phase and the total number of
points used.
The ferrite content shall be measured on one of the metallurgical sections using the point counting
technique at the following locations:
In the parent metal, one measurement on each side of the weld at mid thickness (total of 2).
In the heat affected zone on each side of the weld, in the region of the root pass (total of 2).
In the weld metal, 3 measurements near to the vertical centre line of the weld, one in the cap, one
in the root, and one at mid thickness (total of 3).
Page 37 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Photomicrographs at 400X minimum shall be provided to the COMPANY for each of the locations
where a phase balance assessment is performed.
The macro-examination shall provide evidence that the weld is sound and free from cracks and
other defects with full penetration and fusion between weld passes and parent metal.
A full chemical composition shall be performed on the weld deposit and the following elements
shall be measured and reported: C-Cr-Ni-Mo-Si-Ti-Al-Mg-N-Cu-Nb.
The maximum interpass temperature shall not exceed that of the PQR. Measurements shall be
taken on the parent metal surface, directly adjacent to the weld groove, using a contact
thermometer with an instant digital display. Temperature indicating crayons shall not be used.
Backing gas shall be welding grade 100% argon with a purity of at least 99.95% argon. The oxygen
content of the back-purged volume shall be less than 0.5% (5000 ppm). CONTRACTOR shall
submit details of the method and equipment to be used for monitoring oxygen content as part of
the welding procedure specification. Where mixed gases are used these will be agreed with
COMPANY.
Production welds shall be checked on the cap along the weld with a calibrated ferrite gauge or
other reviewed method and shall not exceed 55% ferrite. A minimum of three (3) measurements
shall be taken at each location. The surface shall be prepared as recommended by the
manufacturer of the testing instrument. Acceptance shall be based on the average of the
measurements at each location. Of the five (5) local measurements, the highest and lowest values
may be discarded and the average of the remaining three reported as the final value.
The welding of tubes shall be completed in accordance with COMPANY reviewed procedures and
shall only be conducted by qualified personnel certified by an approved third party inspection
body.
Each production butt weld made on all tubes shall be uniquely identified to allow for full
traceability. This may be done by numbering the welds and recording the tube numbers on each
side of the weld. In addition, each weld shall be NDT inspected in accordance with the latest
edition of the relevant ASTM and ASME codes. X-ray sensitivity shall allow for close scrutiny of
welds such that any indication from a radiograph of a weld defect that exceeds the acceptable
allowable shall be cause for rejection.
Page 38 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Tube repair on individual tube sections or welds is not acceptable. The section of damaged tube
or unacceptable weld shall be cut out and a new section of tubing welded in. All damaged,
rejected or unacceptable tube shall be destroyed.
Radiographic testing of welds shall be performed on 100% of the welds in accordance with the
requirements of ASME Section V. Any personnel making evaluations of images must be certified as
ASNT SNT-TC-1A Level II under the direction of Level III personnel or to ISO 9712. The
examination should be performed using low voltage x-ray equipment with either film-based
radiography or digital radioscopy. All images shall be stored on CD-ROM to be made available for
inspection and to be included in Manufacturing Data Books.
A minimum of two elliptical images per orbital weld shall be taken. Any relevant indication in the
orbital weld is cause for rejection and the weld shall be removed. An indication is taken to include:
Lack of penetration
Lack of fusion
Cracks
Pinholes
Undercut
Tungsten inclusions or porosity
Production welds shall be tested in accordance with a frequency schedule of five welds per first lot
at the start of production of each tube size and then at regular intervals (1%) of each lot/heat of
tubes during production.
Failure of any test will require that the failed tube coil is spooled back to the last approved weld
and the unwound material removed. Alternatively, if the reason for the problem is clearly
understood and accepted by COMPANY, the tube SUBCONTRACTOR may use the ‘one fail, two
pass’ methodology (to exclude failure due to incorrect sample preparation only) by taking two
additional test samples. Failure of either of the two extra samples (or absence of such additional
samples) shall require spooling back to the last approved weld and all intermediate material shall
be removed. The isolated material may be returned to the production line only if it has been
successfully reworked in accordance with SUBCONTRACTOR’s procedures and subject to
COMPANY’s written consent.
Weld repairs are not allowed. Any weld failing to meet the requirements shall be cut out and the
tubing re-welded. Any tube or weld sections that have been rejected shall be obviously marked
and destroyed to preclude from being used erroneously. A log of rejected radiography images
shall be maintained.
Page 39 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
Sample welds for each welded line shall be cut and destructively evaluated for tensile strength,
corrosion pitting, microstructure (ferrite count and inter-metallic compound analyses), and bend
tested in accordance with the relevant codes and/or procedures.
All tubes shall be examined visually during manufacturing for defects or damage.
X-ray inspection on 100% of the tube welds shall be performed prior to bundling and results shall
be reported to COMPANY.
Dimensional inspection on 100% of the tubes shall be performed prior to bundling and results
shall be reported to COMPANY.
All aspects of the SDUs shall be NDT tested utilising a COMPANY reviewed procedure as per
DNV/ASME/BPVC Section V for Non Destructive Testing. Extent of NDT testing to be determined
and reviewed by COMPANY. All pressure retaining welds shall be examined by NDT.
Welding requirements for Subsea Diverless Connectors shall be as per connecting pipework and
shall be NDT tested utilising a COMPANY reviewed procedure as per ASME/BPVC Section V for
Non Destructive Testing.
Page 40 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
6.1 General
CONTRACTOR shall ensure all documentation produced by CONTRACTOR or their suppliers in
relation to welding and NDT activities complies with the requirements stipulated in the CONTRACT.
6.2 Documentation
The final as built welding related documentation of the completed CONSTRUCTION shall include,
as a minimum, the following:
CONTRACTOR shall retain the radiographic film, a copy of the examination procedures and
personnel qualifications used for the contracted work for 5 years or according to the CONTRACT
requirements.
Page 41 of 42
KG-DWN-98/2 PRE-FEED
General Requirements for Welding and Non-Destructive Testing -
SURF & SPS
402020-01391-01-SY-CRT-0001
Revision 0A
7.1 General
For pipelines exposed to global yielding (Strain ≥0.4%) it shall be required to perform an ECA
according to DNV-OS-F101 Appendix A.
The yield strength of the weld metal should be selected to ensure that the yield strength of the
deposited girth welds overmatches the actual yield strength of the parent pipe material at both
ambient and maximum design temperature.
Consumables shall provide adequate toughness at both the maximum and minimum design
temperatures. Fracture mechanics testing shall as a minimum, but not limited to, be compliant with
the requirements defined in Appendix A, Subsection D (Girth welds under Strain-based Loading
Assessed According to ECA Static – Full) of DNV-OS-F101.
Page 42 of 42